Magnolia Street
Corridor Streets
Improvements
August 19, 2025

BACKGROUND
• Magnolia Street (Adams Avenue to Pacific Coast Highway) • 2 street miles of construction

• New slurry coat or asphalt overlay required to existing paveme nt for extending life of street
• Reconstruct damaged and uneven concrete sidewalk
• Reconstruct driveway approaches and ramps to be ADA compliant • Landscape enhancement with street-friendly tree replacement • Striping and signage improvements including enhance bike lines and pedestrian crosswalks
• Construct new landscaped medians

NEEDS/WHY/BENEFITS

FUNDING
Proposed Project Costs $5.3M
o Orange County Transportation Grant (OCTA )
Total OCTA Funding $4,687,000
o Local Funds: AES/Measure M/RMRA
o $640,000

SCHEDULE
• Design in FY 2025/2026
• Construction in 2026/2027
Questions?