PPT - Public Works Projects Update

City Council/Public Financing Authority
October 21, 2025

Document
PPT - Public Works Projects Update
Meeting
October 21, 2025
Body
City Council/Public Financing Authority
Original file
1.8 MB
Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

CIP
Project Summary
Report
Zone 2 Overlay
October 21, 2025

Project Summary
• Rehabilitated over 100 of theresidential street
segments in poorest condition inZone 2
• Zone 2 boundaries:

Warner Ave (N), Beach Blvd (E), Ellis Ave (S),
Springdale St (W)
• Work included:
• Spot pavement repairs
• Crack sealing
• Cold milling
• Asphalt overlay
• New striping

Project Benefits
and Schedule
• Project Benefits:
• Streets now have12 or more yearsof useful life
• Part of the City’s12-zone pavement plan
• Treatments based on pavement condition
• Schedule:

Start Date: 3/3/25
Substantial Completion: 7/9/25
Final Completion: 7/16/25
Financial Project
Summary
Approved Project Budget $4,551,907.00
Final Construction Contract Amount $4,133,721.02
Construction Inspection and
Survey Monumentation Services
$245,344.00
Remaining Budget Balance $172,841.98
Conclusion/Photos
• Improved street quality withminimal disruption
• Coordinated with:
• Schools
• Trash collection and Street Sweeping
• Deliveries
• Delivered on time and under budget
• Sets a strong model for future paving projects

CIP Project
Summary
Report
17th Street Arterial Rehabilitation
October 21, 2025

Project Summary
17th Street Arterial Rehabilitation
• Project Manager
Eduardo Okamoto-Cerda
• Project Scope:

Rehabilitated 17th Street from Main to Palm
Poor PCI of 42
• Work Included:
• Asphalt Concrete Paving
• Traffic Loops
• Curb, gutter, sidewalk repairs
• Striping
• New trees

Project Benefits and
Schedule
• Benefits:
• Extended pavement life by approximately 20 years
• Improved visibility for pedestrians and bicyclists
• Nearby schools: HBHS, Dwyer MS, Smith ES.
• Schedule:

Start Date: June 23, 2025
Substantial Completion: Sept 17, 2025
Final Completion: Pending Close-out
Financial Project
Summary
Approved Project Budget $1,952,522.10
Final Construction Contract Amount $1,595,404.26
Geotechnical Pavement T esting Services $10,162.00
Remaining Budget Balance $346,955.84
Conclusion/Photos
• Key Outcomes:
• Critical investment in local street infrastructure
• Delivered with:
• Minimal disruption to schools, trash, and deliveries
• Strong contractor collaboration
• On time and within budget
• Community Impact:
• Long-lasting improvements for residents
• Model for future CIP paving projects

CIP Project
Summary
Report
Traffic Signal Improvements at Warner Ave. & Ash
Ln. / Millstream Ln. and Main St & Delaware St.

October 21, 2025

Project Summary
Traffic Signal Improvements at
1) Warner Ave. & Ash Ln.
2) Main St & Delaware St.
• Purpose
Improvements aim to enhance traffic safety,
accessibility, andoverall intersection
functionality.
• Scope of Work:
• Removed and replaced traffic signal poles and
foundations
• Installed new electrical conduit and pull boxes
• Constructed ADA-compliant curb ramps and
sidewalk improvements
• Installed new signage and striping

Project Benefits and
Schedule
• Project Benefits
• Traffic Signal Upgrades: Replaced existing signal poles and foundations; installed new electrical conduit and pull boxes.
• ADA and Sidewalk Enhancements: Constructed ADA-compliant curb ramps and improved sidewalks.
• Signage and Striping: Installed new roadway signs and pavement markings. • Safety Enhancements:
• Introduced protected left-turn phasing at both intersections. • This eliminates conflicts between left-turning vehicles, through traffic, and crossing pedestrians—significantly improving intersection safety. • Project Schedule
Start Date: June 12, 2025
Substantial Completion: August 15, 2025
Final Completion / Close-Out Status: August 31, 2025
Financial Project
Summary
Approved Project Budget $1,320,000.00
Final Construction Contract Amount $1,161,687.08
Construction Management and Inspection Services $152,558.02 Remaining Budget Balance $5,754.90
Conclusion/Photos
• Key Outcomes:
• Improved traffic and pedestrian safety
• Delivered with:
• Minimal schedule disruption
• Strong contractor collaboration
• Within budget
• Community Impact:
• Long-term operational improvements
Before
Questions?