Bluff Top
Slope Repair
Project
December 16, 2025

BACKGROUND
• The existing Bluff Top slope is beginning to fail in certain areas and exhibits signs of surface erosion
• Erosion caused by rainfall runoff
• Project opened bids publicly on October 21, 2025

• Public safety
• Reconstruct and reinforce Blufftop slope
• Provide stability and prevent further erosion
• Improve slope durability
• Enhance slope appearance

NEEDS/WHY/BENEFITS

FUNDING
• Infrastructure Fund $402,236

SCHEDULE
• Construction to commence in January 2026
• Complete project in 30 working days

RECOMMENDATION
• Accept the lowest responsive and responsible bid
submitted by Wright Construction Engineering Corp. in
the amount of $293,249
• Authorize the Mayor and City Clerk to execute a
construction contract in a form approved by the City
Attorney.