City Council/Public Financing Authority
January 20, 2026

Document
1/20 Sup Com - C.Vu Memo & PPT
Meeting
January 20, 2026
Body
City Council/Public Financing Authority
Original file
764 KB
Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

Office: (714) 536 – 5200 | 2000 Main Street, Huntington Beach, CA 92648 | www.huntingtonbeachca.gov To: Honorable Mayor and City Council Members
From: Chau Vu, Director of Public Works
Date: January 16, 2026
Subject: Supplemental Communication for Item 12 Capital Improvement Project (CIP) Updates Please see the attached updated PowerPoint presentation included with this supplemental communication, which replaces the original presentation previously published with the staff report.
01/20/2026
12 (26-064)
CIP Project
Summary
Report
CC1777 FY23/24 Sewer Lining
Project
January 20, 2026

Project Summary
• Lining 23,500 lineal feet of sewer main
• Rehabilitation of 86 Manholes
• Work Included:
• Cleaning and removal of calcium
deposits
• Trenchless lining utilizing UV Lighting
and C.I.P .P .

Project Benefits and
Schedule
• Benefits:
• Improved sewer flows
• Reduced level of maintenance
• Increased system integrity reducing the chance of SSO’s • Schedule:
• Start Date: July 14, 2025
• Substantial Completion: December 10, 2026
• Final Completion: January 15, 2026
Financial Project
Summary
Original Contract Amount 1,599,942.70
Approved Change Orders (Total) $21,969.00
Final Contract Amount $1,621,911.70
Contingency Budget $159,994.27
Remaining
Balance

$138,025.27
Conclusion/Photos
• Key Outcomes:
• Critical investment in Sewer Infrastructure
• 50-year service life
• Delivered with:
• Minimal disruption to residents and services.
• On time and within budget.
• First use of UV Light curing liner in HB.