CIP Project Summary Report
CC177 FY23/24 Sewer Lining Project
January 20, 2026
Project Summary
Lining 23,500 lineal feet of sewer main
Rehabilitation of 86 Manholes
Work Included:
Cleaning and removal of calcium deposits
Trenchless lining utilizing UV Lighting and C.I.P.P.
Project Benefits and Schedule
Benefits:
Improved sewer flows
Reduced level of maintenance
Increased system integrity reducing the chance of SSO’s Schedule:
Start Date: July 14, 2025
Substantial Completion: December 10, 2026
Final Completion: January 15, 2026
Financial ProjectSummary
Original Contract Amount
1,599,942.70
Approved Change Orders (Total)
$21,969.00
Final Contract Amount
$1,621,911.70
Contingency Budget
$159,994.27
Remaining Balance
$138,025.27
Conclusion/Photos
Key Outcomes:
Critical investment in Sewer Infrastructure
50-year service life
Delivered with:
Minimal disruption to residents and services.
On time and within budget.
First use of UV Light curing liner in HB.