CIP Project Summary Report
CC 1634: Humboldt Sewer L.S.
January 20, 2026
Project Summary
Abandonment and demolition of an existing Sewer Lift Station, and installation of a new Station.
Increase in storage capacity, efficient pumps, enhanced lift station control system.
Work included:
Three 185 GPM Pump
Force main
Gravity main
Curb and gutter
Paving
Project Benefits and Schedule
Project Benefits:
System reliability
Efficient Pumps and equipment
State of the art Communication systems
System storage
Schedule:
Start Date: 8/5/2024
Substantial Completion: 7/31/2025
Final Completion: 9/25/2025
Financial ProjectSummary
Approved Project Budget
$4,193,450.00
Approved Change Orders
$211,911.65
Contingency used
$211,911.65
Remaining Budget Balance
$176,801.85
Conclusion/Photos
Improved system reliability
Coordinated with:
Community and stakeholders
Public Utilities Companies
Other HB Departments/Divisions
Delivered on time and under budget
Sets a strong model for future sewer projects