Amendment No. 2 to the On-Call Professional Services Agreement with AESCO, Inc., February 3, 2026 City Council Meeting

SUMMARY
Staff is requesting Contract Authority NOT Budget Authority Projects are fully funded
to Increase the Not-to-Exceed Amount by $300,000 and Extend the Contract Term by One Year.

AESCO is ENGINEER OF RECORD for 2 Major Projects: Admiralty Bridge & McFadden Sewer Lift Station

Project Location Map
McFadden Sewer Lift Station, Wet Well Location

McFadden Sewer Lift Station, Wet Well CC1610
Wet Well
Valve vault
Gravity Sewer
Force Main
Infrastructure Investment
Originally constructed in 1972

Scope of Work
Install new valve vault, wet well, gravity sewer, force main, and emergency gas generator & enclosure, and associated site improvements Utility Coordination
Develop plans, specifications, material testing and estimate Environmental documentation and regulatory agency permits Construction engineering and environmental monitoring

Funding and Schedule
Current Funding:

Sewer Service Fund (511): $3,900,000
Sewer Development Fee (210): $1,500,000
Schedule:

Design – Complete FY 23/24
Construction – To Begin Spring FY 25/26

Project Location Map
Admiralty Bridge Rehabilitation Location

Admiralty Bridge Rehabilitation CC1450
Concrete deck
Steel Guard Railing
Barrier Wall
Street Lighting
Utility Coordination
Traffic Infrastructure
Originally constructed in 1961

Scope of Work
Install new deck, barrier walls, guardrails, refurbish existing steel beams, steel lighting, traffic infrastructure, pedestrian sidewalk, and other associated bridge repairs or improvements Utility Coordination
Develop plans, specifications, material testing and estimate Environmental documentation and regulatory agency permits Construction engineering and environmental monitoring

Funding and Schedule
Current Funding:

Federal HBRR (Highway Bridge Replacement & Rehabilitation) Grant Fund: $3,280,000 Infrastructure Fund: $500,000
Measure M Fund: $2,100,000
Department of Transportation HBP Grant Fund (Caltrans): $1,916,490 Schedule:

Design – Complete FY 22/23
Construction – In Progress, Mid-March