Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

0 40’ 80’ 160’
02/26/2026

EDISON PARK CONCEPTUAL PLAN

CITY OF HUNTINGTON BEACH, CALIFORNIA
THIS DOCUMENT IS THE PROPERTY OF RJM DESIGN GROUP , INC., AND NO PART THEREOF SHALL BE USED, REUSED, OR MODIFIED WITHOUT THE WRITTEN CONSENT OF RJM DESIGN GROUP , INC. © 2026 RJM Design Group, Inc. All rights reserved.

OPTION 2 CONCEPTUAL PLAN

EDISON PARK CONCEPTUAL PLAN LEGEND

1. Reconfigured parking lot. (Total parking spaces ± 245)

2. New parking lot entry at Poston Lane.

3. New sport court plaza with seating and shade.

4. New full court basketball court (6).

5. New tennis courts (2).

6. New practice hitting wall at tennis court.

7. New pickleball courts (8).

8. Existing tennis courts (#3 and #4) with 8 pickleball overlays.

9. Existing trees.

10. New trees.

11. New shade shelter.

12. Existing softball fields.

13. New turf community open space.

14. New (50 yds x 70 yds) soccer field overlay in SCE Corridor (pending SCE review and approval).

15. Enlarged all-wheel plaza.

16. New tot lot with rubber surfacing, equipment and shade.

17. Expanded exterior restrooms at Community Center.

18. Existing SCE Towers and overhead utility lines.

19. Existing walkways.

20. Landfill monitoring station.

21. Oil Well #1.

22. Oil Well #2.

23. New mounded lawn for spectator seating.

24. New bocce ball courts (4).

Existing Healthy Trees to Remain ~ 95
(Per 2022 Arborist Report)

Existing Healthy Trees to be Removed
Based on Plan Improvements ~ 50
New Trees 200+

New Parking Stalls ~ 44