McFadden Sewer Lift Station, Wet Well Phase 2 CC1610
March 17, 2026 City Council Meeting
Project Location Map
McFadden Sewer Lift Station, Wet Well Location
McFadden Sewer Lift Station, Wet Well CC1610
Wet Well
Valve vault
Gravity Sewer
Force Main
Infrastructure Investment
Originally constructed in 1972
Scope of Work
Construct new valve vault, wet well, gravity sewer, force main, emergency gas generator & enclosure, and associated site improvements Utility Coordination
Environmental documentation and regulatory agency permits Construction engineering and environmental monitoring
Funding and Schedule
Schedule:
Design – Complete FY 24/25
Construction – To Begin Spring FY 25/26
Current Funding
Sewer Service Fund (511)
$1,462,325.01
Reappropriation
Sewer Service Fund (511)
$3,705,260.35
New Appropriation
Sewer Service Fund (511)
$651,039.74
Total Funding:
$5,818,625.10