Zone 3 Residential Overlay Project
Zone 3
Residential Zone Maintenance Program
Residential Paving
Phases within program
Tree Maintenance - Fall
Concrete Rehabilitation/ADA Ramps – Fall/Winter
Street Paving – Spring/Early Summer
Slurry Seal – Early Summer
Zone 3 Residential Overlay Project
This project will rehabilitate the pavement for approximately 75 of the worst residential street segments in Maintenance Zone 3. Work will include limited localized pavement repairs, crack sealing, cold milling, striping, and an asphalt overlay.
Zone 3 Residential Overlay Project
Street Construction