FY 2025/26 Sewer Lining ProjectConstruction Contract CC1845 June 2, 2026 City Council Meeting

Background
The City’s Utility Division implements an annual sewer lining program to rehabilitate ageing sewer mains identified through CCCTV inspections and maintenance history.

This project includes lining approximately 29,850 linear feet of sewer main using UV CIPP technology across multiple pipe diameters (8”–15”). Work also includes rehabilitation of 66 manholes and restoration of service laterals.

Project locations are shown in the accompanying maps.

The Sewer Lining Project is essential to public health and safety, in addition to preserving the life of the City’s existing sewer infrastructure. This project helps prevent sewer overflows, tree root intrusion, groundwater seepage, and calcium build-up.

FY 2025/26 Sewer Lining Project CC1845
New UV Sewer Lining Cure-in-Place Pipe
(CIPP) Technology
Estimated 29,850 linear feet of existing
sewer main to be lined
Long Term Sewer Main Infrastructure
Protection from groundwater seepage
through minor cracks and from tree root
intrusion.

Total of 66 manhole’s to be rehabilitated
Projects

FY 2025/26 Sewer Lining Project CC1845
City Sewer Mainline Zones
to receive New UV Lined
CIPP & Manhole Rehabilitation:

District 146
District 128
District 199
District 424
District 426
Projects

Funding and Schedule
Current Funding:

The FY 2025-26 Sewer Lining Project is fully funded through the Sewer Improvement Fund, Account No. 51189028.82600
No additional appropriations will be required
Schedule:

Design Phase completed 24/25
Construction to begin early summer 2026

Bid / Recommendation
Lowest Responsive & Responsible Bid:

Performance Pipeline Technologies, Inc.

Huntington Beach, California
Bid amount: $1,970,231.60
15% Contingency: $295,534.74
Supplemental: $100,000.00
Total Construction Cost: $2,365,766.34
Staff recommends awarding the Construction Contract to Performance Pipeline Technologies, Inc.