C6 SC1 Channel Improvements(PHASE I)
June 16, 2026
Project Location
Scope of Work
Removal of damaged sections of concrete channel wall
Install 3-inch geocomposite drainage layer
Construct new 6-inch reinforced concrete channel wall
Project Budget
Construction – Base Bid
$329,095.07
Contingency (15%)
$ 49,364.26
Supplemental Services (5%)
$ 16,454.75
Total Project Cost
$ 394,914.08
C6-SC1 Channel P1
Acct.
21188011.82500
Sufficient funds are available in the current fiscal year budget in Account No. 21188011.82500 (C6-SC1 Channel P1).