Street Light Modifications
Orange Avenue: 11th St. to 18th St.
12th Street: PCH to Orange Avenue
Walnut Avenue: 11th Street to 17th Street
13th Street: PCH to Palm Avenue
6/16/2026

Project Scope
Replace street lighting circuits, poles and conduits on Orange Avenue, Walnut Avenue, 12th Street and 13th Street Existing circuits operate at 6000 volts, current practice is 240 volts Existing system is approximately 100 years old with deteriorated poles, conduits and conductors

Project Budget
Bids opened on May 7, 2026
Low Apparent Bid is $1,389,738.46
Project Cost Estimate is $1,760,000 including construction contingency and contract administration Available Funds: $1,760,000 budgeted in Infrastructure Fund, Account No. 31440030.82800 Staff recommendation is to award contract to Asplundh Construction, LLC, the lowest responsive and responsible bidder