1 16-5195/City Funded Construction Contract.docx – revised 04/2016
CITY FUNDED CONSTRUCTION CONTRACT BETWEEN
THE CITY OF HUNTINGTON BEACH AND
FOR
THIS AGREEMENT ("Agreement") is made and entered into by and between the City of Huntington Beach, a municipal corporation of the State of California, hereinafter referred to as "CITY," and _________________________________________________________________, a _______________________________ corporation, hereinafter referred to as "CONTRACTOR." WHEREAS, CITY has solicited bids for a public works project, hereinafter referred to as "PROJECT," more fully described as _______________________________________________ _______________________________________________ in the City of Huntington Beach; and CONTRACTOR has been selected to perform said services,
NOW, THEREFORE, in consideration of the promises and agreements hereinafter made and exchanged the parties covenant and agree as follows:
1. STATEMENT OF WORK; ACCEPTANCE OF RISK
CONTRACTOR shall complete and construct the PROJECT pursuant to this Agreement and the Contract Documents (as hereinaf ter defined) and furnish, at its own cost and expense, all labor, plans, tools, equipment, suppl ies, transportation, utilities and all other items, services and facilities necessary to comple te and construct the PROJECT in a good and workmanlike manner.
CONTRACTOR agrees to fully assume the risk of all loss or damage arising out of the nature of the PROJECT, during its progress or prior to acceptance by CITY, from the action of the elements, from any unforeseen difficult ies which may arise or be encountered in the NEWBUILD CONSTRUCTION AND RESTORATION, INC.
NEWLAND HOUSE & MUSEUM, EXTERIOR RESTORATION, CC1788
NEWBUILD CONSTRUCTION AND RESTORATION, INC.
NEWLAND HOUSE & MUSEUM, EXTERIOR
RESTORATION, CC1788
4 16-5195/City Funded Construction Contract.docx – revised 04/2016
3. COMPENSATION
CITY agrees to pay and CONTRACTOR agrees to accept as full compensation for the faithful performance of this Agreement, subject to any additions or deductions made under the provisions of this Agreement or the Contract Documents, a sum not to exceed _______________________________________________________________________ Dollars ($___________________), as set forth in the Contract Docu ments, to be paid as provided in this Agreement.
4. COMMENCEMENT OF PROJECT
CONTRACTOR agrees to commence the PROJECT within ten (10) working days after the Notice To Proceed is issued and diligently prosecute the PROJECT to completion within __________________________________ (_______) consecutive Working days from the day the Notice to Proceed is issued by DPW, excluding delays provided for in this Agreement.
5. TIME OF THE ESSENCE
The parties hereto recognize and agree th at time is of the essence in the performance of this Agreement and each and every provision of the Contract Documents.
CONTRACTOR shall prepare and obtain approval as required by the Contract Documents for all shop drawings, details and sa mples, and do all other things necessary and incidental to the prosecution of its work in conformance with the progress schedule set forth in the Contract Documents. CONTRACTOR shall coordinate its work with the work of all other contractors, subcontractors, and CITY forces working on the PROJECT in a manner that will facilitate the efficient completion of the PROJE CT and in accordance with the terms and provisions of this Agreement. CITY shall have complete control of the premises on which the work is to be performed and shall have the right to decide the time and order in which the various portions of the work shall be performed and the priority of the work of other contractors,
SIX-HUNDRED TWENTY-EIGHT THOUSAND SIX-HUNDRED
628,600
ONE-HUNDRED TEN 110