CONSENT OF ASSIGNMENT
Professional Services Agreement
Assignment by the City of Laguna Beach to the Laguna Beach Community Land Trust This Consent of Assignment is entered into by and between the City of Laguna Beach (“City”) and, Laguna Beach Community Land Trust (“Land Trust”) with the acknowledgment and consent of the Harris and Associates Inc (“Harris”), collectively the Parties.
Whereas the City of Laguna Beach City and Harris and Associates Inc Harris entered into that certain Professional Services Agreement dated ____________ for professional services related to the establishment of the Laguna Beach Community Land Trust and; Whereas the City intends to assign and transfer all of its rights duties responsibilities and obligations under the Agreement to the Land Trust including but not limited to oversight performance requirements deliverables reporting and all contractual responsibilities identified in the Agreement; and
Whereas the Land Trust is willing to accept such assignment and assume full responsibility for performance of all obligations under the Agreement as though it were the original contracting party; and
Whereas Harris agrees to such assignment and accepts the Land Trust as the substituted contracting party provided that all terms obligations and standards under the Agreement remain unchanged; and
Now therefore in consideration of the foregoing and the mutual promises contained herein the Parties agree as follows:
1. Assignment by the City
The City hereby assigns transfers and conveys to the Land Trust all of the City’s rights obligations interests and responsibilities under the Agreement. Upon execution of this Consent the Land Trust shall stand in the place of the City with respect to all contractual duties.
2. Assumption by the Land Trust
The Land Trust accepts the assignment and assumes all obligations duties responsibilities and liabilities of the City under the Agreement including but not limited to administration oversight performance compliance insurance obligations indemnity obligations and all other terms contained in the Agreement.
Attachment 3
212
3. Consent of Harris
Harris hereby consents to the assignment and agrees to recognize the Land Trust as the contracting entity in place of the City. Harris further agrees to perform all services under the Agreement for the benefit of the Land Trust consistent with all terms conditions and standards set forth therein.
4. No Modification of Agreement
Except for the substitution of the Land Trust for the City all terms of the Agreement remain in full force and effect. No amendment or modification is intended or created by this Consent.
5. Effective Date
This Consent shall be effective upon full execution by all Parties.
6. Counterparts
This Consent may be executed in multiple counterparts each of which shall be deemed an original and all of which together constitute one instrument.
CITY OF LAGUNA BEACH HARRIS AND ASSOCIATES
INC
LAGUNA BEACH
COMMUNITY LAND TRUST
By:
______________________
_________
Name:
Title:
Date:
By:
______________________
_________
Name:
Title:
Date:
By:
______________________
_________
Name:
Title:
Date:
213
22 Executive Park, Suite 200, Irvine, CA 92614 p: 949.655.3900 f: 949.655.3995 www.WeAreHarris.com
MEMORANDUM
To: City of Laguna Beach, Jeremy Frimond and Louie Lacasella From: Harris & Associates
RE: Amendment Memo– Laguna Beach Community Land Trust Project Date: Friday, November 7, 2025
CC: Mark Asturias Consulting and Redwood Public Law
Harris & Associates (Harris) was engaged by the City of Laguna Beach in March 2025 to support establishment of a Community Land Trust (CLT). The original contract amount was $94,681, and included tasks related to community engagement, feasibility analysis, organizational structuring, and regulatory compliance tasks.
On November 3, 2025, the City directed Harris to pause all other work and limit remaining efforts to the following:
1. Founding Board appointments
2. Founding Board orientation
3. IRS 1023 filing completion
Under this revised direction, remaining tasks/deliverables in the original scope that fall outside these three priorities will be paused and are not expected to be completed under the updated scope. A deliverable tracker/list is provided here to document which tasks have been completed to date under the original scope, and which tasks have been paused based on the revised direction. Any remaining balance after the three priorities are completed will be reserved for the Founding Board to determine how best to allocate at a later time.
Based on these revised priorities, and the increased need for subconsultant support, Harris proposes restructuring the remaining budget of $ 34,210.50 as follows:
• $4,500 (approximately 15 hours) added to Mark Asturias Consulting subconsultant agreement contract to assist with board appointments, orientation, and IRS application. • $3,000 (approximately 4.5 hours) added to Redwood Public Law subconsultant agreement for legal counsel during onboarding and as needed.
• $5,000 allocated to a new Task 7: Project Management for coordination, contract administration, invoicing, documentation, amendments/reallocations, etc. • $21,710.50 remaining to be held for future project needs / Founding Board direction/ additional project management (if needed).
The budget amounts above are proposed on a Time & Materials (T&M) not-to-exceed basis. The figures reflect current assumptions only and they are not a guarantee that the work associated with these three 214
2 priorities can be fully completed within these amounts, as actual support needs may vary depending on final direction and level of effort required.
The contract term remains unchanged, through March 31, 2026.
Once the City confirms agreement with the revised scope, budget allocations, and assumptions outlined above, Harris will proceed under this revised direction. 215