CONSTRUCTION CONTRACT

CHANGE ORDER
Date 06/24/2025 C.C.O No. 1 951-674-3124
130 S. MAIN STREET
LAKE ELSINORE, CA 92530
WWW.LAKE-ELSINORE.ORG
CONTRACTOR:

Aneen Construction Inc.

In conformance with and as part of the existing Agreement for this project the City of Lake Elsinore authorizes and directs changes to the Agreement as described below. 1) EXTRA WORK ORDER (EWO) (Unknown or Unforeseen Work not covered by Contract) a) Extra Work Item: Correct EVMWD design error to the new revised plans to accommodate the increased depth of two manholes to 25 feet.
•Pipe Grade and Alignment – Upgrade to DR18
•Manhole Depth – must be constructed deeper to adjust to the increased depth. •Coating Requirement change due to depth.
•Additional Excavation Volume and use of larger shoring equipment TOTAL Lump Sum = $432,246.00
2) CHANGED WORK ORDER (CWO) (Significant increases in quantity of Unit-Price items; greater than 25%):
a) Changed Work Item A
i) Time impact is (+) 40 additional Working Days.
3) CLOSING SUMMARY ORDER (CSO) (Final adjustment of original estimated contract quantities based on final measured quantities):
a) Closing Summary Order:
i) Payment for this work is paid as follows:

Total = $432,246.00
AGREEMENT AMOUNT: Compensation as set
forth in the Agreement and as amended by
this and prior Contract Change Order(s) is:
$1,284,026.00
Original Contract Amount: $851,780.00
Amount All Previous CCOs (+-): $0.00
Amount This CCO (+-): $432,246.00
Total Contract Amount: $1,284,026.00
CITY’S ACCEPTANCE: The above described
work is hereby approved and directed to be
completed in accordance with the Contract
Documents.

City of Lake Elsinore
Rec.: _______________________________
City Engineer Date
App.: _______________________________
City Manager Date
CONTRACTOR’S ACCEPTANCE: Contractor agrees to perform
the above work as directed, in accordance with the
Contract Documents, and accept payment described above
as full compensation for work described subject to
additions and reductions of the quantities of various items.

Contractor: Aneen Construction, Inc.

By __________________________________________
Title: ________________________________________
Date: ________________________________________

← All documents from this meeting