REPORT TO CITY COUNCIL
To:Honorable Mayor and Members of the City Council
From:Jason Simpson, City Manager
Prepared by:Remon Habib, City Engineer
Date:July 22, 2025
Subject:Tract Map No. 34249, Canyon Hills Estates
Recommendation
Approve Final Tract Map No. 34249, subject to the City Engineer’s acceptance as being true and correct, authorize the City Clerk to sign the map and arrange for recordation of Final Tract Map No. 34249, and approve and authorize the City Manager to execute the Construction of Improvements Agreement for Monumentation.

Background
Canyon Hills Estates (Project) is located south of Canyon Hills Road and west of Cottonwood Canyon Road. With Tract Map No. 34249, the Project proposes to subdivide a 81.33 acre site to construct 133 single-family homes, two (2) lots for water quality basins, one (1) lot for public park, one (1) lot for HOA Community Center, four (4) lots for open space, two (2) lots for private street purposes, and five (5) lots dedicated to City for public street and utility purposes. All future public improvements have been secured.

Discussion
Per Subdivision Map Act 66474.1, Tract Map No. 34249 has been reviewed and has been determined that it is in substantial conformance to the previously approved Tentative Tract Map No. 34249. All Conditions of Approval relative to the final tract map approval have been satisfied.

Fiscal Impact
Public improvements are to be constructed by the developer. The security posted is sufficient for the City to complete the construction if needed. Staff time was utilized to prepare the documents.

Final Tract Map No. 34249

Page 2 of 2 ends

1 9
9 1
Attachments
Attachment 1 - Final Index Map
Attachment 2 - Vicinity Map
Attachment 3 - Construction Agreement