Proposal To: License Number: 958561
hereinafter referred to as "OWNER";
Site Development
Tensar TXF Fabric, 3 Layers
1' of CL II Base, Between 2 Layers of Tensar
Payment & Performance Bonds
Misc T&M Grading, as Required for Grading
**This is a T&M Quote, Not to Exceed Amount**
Notes:

All Work Completed in 1 Move-In.

No Off-Site Work Included.

Prevailing Wage Rates, Acknowledged.

No Export of other trades spoils included.

No removal, relocation & or adjustment of any utilities. No removal of any hazardous materials.

No removal of any buried objects. All area's must be accessible with heavy equipment.

Plans by ERSC dated 8-26-24. Soils by Inland Foundation dated 7-9-24.

Existing topo does not reflect import from City Hall Construction, Estimated at 2,000 CY's.

ACCEPTED:

Company:

By: Date: By:

Title: Title:

Pad Total $197,900.00
LS $10,000.00 $10,000.001
City of Lake Elsinore
130 S Main St

QUANTITY
and materials to construct and complete in a good and workmanlike manner upon the following described real property, only the items indicated below:

UNIT PRICE
October 8, 2025
New City LibraryTRACT NUMBER:

ITEM DESCRIPTION
Job # 6115B
PROJECT LOCATION:

Contractors State License Board, 1020 North St., Sacramento, CA 95814 Chance Edmondson
30 days from completion of above work.

Contractors are required by law to be licensed by the Contractors' State License Board. Any questions EDMONDSON CONSTRUCTION CO.
18135 Grand Ave - Lake Elsinore, California 92530 - (951) 678-0800 - Fax (951) 678-0884 P.O. BOX 101 - LAKE ELSINORE, CALIFORNIA 92531
President
billings are due on the 10th of the month following. All retention's are due and payable payments upon receipt of invoice(s) covering work completed to date of invoice. Progressive The above prices are firm until: November 1, 2025 Total:
concerning the responsibilities of a contractor may be referred to the Registrar of the Board whose address is:
calendar days be required to complete the above items, owner will make progressive Owner to supply water meter (On-Site), soils testing, survey, SWPPP, permits & traffic control. $230,000.00
Terms: Net cash, due and payable upon completion. Should more that 30 consecutive Pad Stabilization
www.wemovedirt.com
124 W Sumner Ave Lake Elsinore, CA
EDMONDSON CONSTRUCTION CO. proposes to furnish all supervision, labor, equipment Lake Elsinore, CA 92530

ITEM TOTAL
Attn: Gus Papagolos
1 LS $22,100.00 $22,100.00