CITY OF LAKE ELSINORE CITY HALL - REQUEST FOR ADDITIONAL AUTHORIZATION NO. 7
GRADING, DRAINAGE AND UTILITY PLAN MODIFICATIONS
Dear Gus,
Per recent conversations, we have revised grading, drainage and utility plans for the new City Hall to reflect the relocation of the existing alley access (driveway) and relocate the fire department connection from Main Street to Graham Avenue. Further, we have provided coordination and plan revisions related to potholing activities and upcoming video of the sewer lines in Main Street and Graham Avenue required by the Elsinore Valley Municipal Water District. And, finally, we have coordinated the preparation and provided processing of a Water Rights Grant Deed (WRGD) for parcel (APN 373-151- 024) supporting the alley.
As part of the work, the following services are necessary to modify plans for the City and Elsinore Valley Municipal Water District (EVMWD) and provide supporting calculations and documentation.
1. Revise grading, drainage and street design and associated plans
2. Revise EVMWD plans to reflect new location of the fire department connection.
3. Coordinate potholing activities and add pothole data to plans.
4. Coordinate video survey of existing sewers on Main Street and Graham Avenue.
5. Coordinate preparation and approval of a WRGD for APN 373-151-024.
The Scope of Work outlined below provides further information into the plan modifications/additions result from the proposed work. Required revisions include the design of the following plan modifications:
Scope of Work
Grading, Drainage and Street Design – Modify the current plan set to account for the relocation of the existing access to the alley to the easterly edge of the city hall property. oModification of the street design along the south side of Graham Street including curb and gutter, sidewalk, and a new commercial driveway approach including an accessible path of travel.
Confirm the design of the proposed grind and overlay on Graham Street. oRedesign grading in the alley to provide access to the existing traveled way in the alley including grading and paving south of Graham Avenue and revised grading along the alley at the rear of the new building.
oModify drainage design at the northeast corner of the proposed building and along the alley reconstruction to accommodate the modular wetland and ensure adequate treatment of site runoff.
Page | 21861 W. Redlands Blvd., Redlands, CA 92373
T: (909) 890-1255 | F: (909) 890-0995 | erscinc.com
Fire Department Connection – Design related to the relocation of the fire department connection to Graham Street east of the proposed driveway. Move the fire department connection from its current location on Main Street to the new location Graham Avenue. Provide design of the proposed waterline connection, piping, DCDA, post indicator valve, fire department connection, various check valves, and a new fire hydrant. Route piping from the fire department connection to the point of connection at the building. Prepare fire flow calculations for multiple scenarios based on the new design and previously acquired fire flow data from EVMWD.
Potholing – Coordinate potholing activities with USI, review and interpret pothole reports, and add tabulated pothole data the plans for EVMWD. Potholing will occur on Main Street and Graham Avnenu to identify points of connection on existing water lines, gas line crossings, and portions of the waterline being replaced.
Sewer Video – Provide coordination, video review, and data interpretation for video footage of the existing sewers in Main Street and Graham Avenue necessary to locate three sewer laterals serving the three buildings that previously occupied the city hall site. Add sewer lateral locations to the EVMWD plans and coordinate abandonment thereof with District staff.
Water Rights Grant Deed – Relocating the DCDA/FDC to the Graham Avenue will result in the need for a Water Rights Grant Deed (WRGD) in favor of the Elsinore Valley Municipal Water District (EVMWD).
ERSC will coordinate the preparation and response to any plan check comments with the City’s survey consultant, Dennis Janda, Inc. ERSC will process the WRGD through EVMWD to approval. When approved, ERSC will acquire a wet signed copy of the WRGD and provide the same to EVMWD for signature and recording.
Reimbursable Expenses – ERSC will pay plan check fees for the review of the WRGD on behalf of the city.
Deliverables
Modified Grading, Drainage and Street Plans.
Modified Water and Sewer Plans with Fire Flow Calculations (EVMWD). Additions to EVWMD plans showing tabulated pothole data. Sewer video and addition of sewer laterals to EVMWD plans. Approved Water Rights Grant Deed.
Fee Estimate
Fees and charges associated with the design services outlined above are provided below.
Grading, Drainage, and Street Plans $ 3,655
Fire Department Connection $ 14,175
Potholing $ 4,200
Sewer Video $ 2,520
Water Rights Grant Deed $ 4,630
Reimbursable Expenses $ 4,225
Total $ 33,405
If you have any questions regarding this request, please give me a call at (909) 890-1255, x103.
Page | 41861 W. Redlands Blvd., Redlands, CA 92373
T: (909) 890-1255 | F: (909) 890-0995 | erscinc.com
Respectfully,
Matt Brudin
Signed electronically 11.07.2025.