Attachment 1
Submittal Report
LSR-C19-FY25/26-5469-001
FY 25/26
Submittal Details
Program
Local Streets and Roads
Agency
City of Lake Forest
Date Created
05/05/2025
Date
05/16/2025
Date
Address
100 Civic Center Dr
City
Lake Forest
State
CA
Zip Code
92630
Contact
Naz Mokarram
Contact Title
Principal Civil Engineer
Contact Phone
(949) 461-3490
Contact Email
[email protected]
Avg. Network PCI
77 Measurement Date
11/2024
Support Documentation
Draft Resolution and Project List - Will be brought to City Council June 17th, 2025 meeting for action.
Additional Information
N/A
Project Details
Title Description Location Component
Priority
Status
Est. Schedule Useful
Life
Assem SenateStart Complete Min Max
Street
Resurfacing:
portions of
Lake Forest
from Bake
Pkwy to I-5
Fwy
This project will include: Cost Estimating,
Document Preparation, Preliminary Design |
Resurfacing Design for Lake Forest Drive from
Bake Pkwy to I-5 Fwy
Portions of Lake Forest
from Bake Pkwy to I-5 Fyw
Pre-
Constructio
n
In Progress
23/24
02/2023 12/2027
10 15 68 37
Street
Resurfacing:
portions of
Bake Pkwy
from Rancho
Parkway
South to
South Pointe
Drive
This project will include: ADA Curb Ramp
Rehab/Repair (Existing), Bicycle Lane
Rehab/Repair (Existing), Pavement Rehab/Repair
(Existing), Paving and/or Striping Rehab/Repair
(Existing Safety), Sidewalk and/or Crosswalk
Rehab/Repair (Existing), Traffic Signals,
Lights, and/or Signage Rehab/Repair (Existing
Safety)
Bake Parkway from Rancho
Parkway South to South
Pointe Drive
Constructio
n
In Progress
23/24
08/2025 10/2027
10 15 68 37
Street
Resurfacing:
El Toro from
Jeronimo to
Trabuco
This project will include: ADA Curb Ramp
Rehab/Repair (Existing), Pavement Rehab/Repair
(Existing), Paving and/or Striping Rehab/Repair
(Existing Safety), Sidewalk and/or Crosswalk
Rehab/Repair (Existing), Traffic Signals,
Lights, and/or Signage Rehab/Repair (Existing
Safety)
El Toro Road from Jeronimo
to Trabuco
Constructio
n
In Progress
23/24
09/2025 09/2026
10 15 68 37
Annual
Slurry Seal,
Zone D
This project will include: Pavement Rehab/Repair
(Existing), Paving and/or Striping Rehab/Repair
(Existing Safety), Sidewalk and/or Crosswalk
Rehab/Repair (Existing) | Design started in
November 2023
Neighborhood between
Trabuco Rd. and Portola
Parkway, North of Lake
Forest Drive.
Constructio
n
In Progress
23/24
08/2025 03/2026
7 10 68 37
Street
Resurfacing:
portions of
El Toro Rd
from Glenn
Ranch Rd to
I-5
This project will include: Cost Estimating,
Document Preparation, Preliminary Design
Portions of El Toro Rd from
Glenn Ranch Rd to I-5 Fwy
Pre-
Constructio
n
In Progress
23/24
04/2023 12/2028
10 15 68 37
Annual
Slurry Seal,
Zone E
This project will include: Cost Estimating,
Document Preparation, Project Scope Development
The neighborhood between
Trabuco Rd. and Portola
Parkway, South of Lake
Forest Drive.
Pre-
Constructio
n
Carried
Over 24/25
06/2026 03/2027
7 10 68 37