Consor Page 1 3/11/2026
Design Proposal Task Descriptions
for
12-Inch Diameter Water Main for South Main Street
City of Lakeport
Approach and Work Plan
This scope of work is based on original plans & specifications prepared for the 14” Water Main Loop Project completed in 2019. The design team proposes completing the Project based on the following work plan with tasks and subtasks as provided by the City to help with tracking the budget for the project. Additional clarifications and assumptions have been added to the tasks and subtasks to help further define the scope of work.
Task 1 – Project Management and Coordination
Project Management within this task refers to the Consor duties for administration of the project. Coordination includes all e-orts to coordinate the design process for the City, the design team, and stakeholders.
1.1 Project Management
Consor project management duties include project administration, scheduling of sta-, monitoring of budget and schedule, and administrative correspondence with City sta-. The Project Coordinator and Project Manager will prepare monthly progress reports and cost summaries, which will be included with each invoice.
Assume a span of 12 months for design and bidding the project and 4 months for initial Construction Services = 16 months.
Assume 1 hour per month for the Water Project Manager. Assume 3 hours per month for Project Coordinator.
1.2 Design Meetings
Design meetings are anticipated to be weekly throughout the design period to provide rapid feedback and answers to design questions to expedite the design process. Budget 12 meetings.
Assume 12 meetings: 11 virtual meetings and 1 in-person meeting. Assume each meeting is 1 hour.
Assume each meeting includes some preparation before meeting and follow-up correspondence after each meeting: additional 1/2 hour per meeting Assume 18 hours for the Water Project Engineer.
Consor Page 2 3/11/2026
Assume as needed or 6 hours for the Water Project Manager.
1.3 Project Meetings
The project meetings will be scheduled to provide coordination and updates with the other project stakeholders including Lake County Public Works and Lake County Special Districts. Budget 4 meetings.
Assume 4 meetings; 3 virtual and 1 in-person, as needed. Assume each meeting is 1 hour.
Assume each meeting includes some preparation before meeting and follow-up correspondence after each meeting: additional 1 hour per meeting. Assume 8 hours per Principal Engineer.
1.4 On-Site Meeting Costs
This item includes all related costs associated with attending in-person meetings. This item includes sta- travel time but not meeting times, which are to be included in 1.1 and 1.2 above.
Assume 1 design meeting and 1 project meeting.
Assume each meeting includes 6 hours round trip of travel time plus mileage, and lodging, as necessary.
Assume 1 Roadway or Water Project Manager at each site visit. Assume 1 Water or Roadway Project Engineer at each site visit.
Task 2 – Preliminary Design – 12-Inch Diameter Water Main with Services and Hydrants For the original 14” Water Main Loop Project, the water main was located in the southbound lane of the roadway to align with the existing water main that deadends just north of the City boundary limits in South Main Street. At the City’s request, the extension of the water main will now be designed as a12-inch diameter water main located in the northbound lane with adequate distance from the joint trench and sewer main. The anticipated location is approximately on the northbound lane fog line. The City is performing the preliminary design to layout the water main and services to clear conflicts with utilities and facilities both existing and already designed for the County’s Soda Bay Roadway Project. The alignment will also be modified as needed to avoid conflicts with culturally sensitive areas as previously identified. The design depth for the water main and services shall be 36- inches of cover over the pipe.
The water main design also assumes replacement and lowering of the existing sanitary sewer laterals (20) to provide adequate clearance between the water main and sewer laterals. The scope of work for the design of the sewer laterals is provided in Task 3 – Design – Sewer Laterals.
Consor Page 3 3/11/2026
2.1 Prepare Base Drawings
This task includes the preparation of base drawings derived from the current roadway design drawings for inclusion in the final bid package as separate Water Utility sheets. Topographic base maps with existing and proposed utilities for the Soda Bay Roadway Project will be prepared as plan and profile sheets for the design of the new alignment of the water main, services, and hydrants.
Assume preparation of 8 plan and profile sheets.
Assume CAD time to set up each sheet is 8 hours.
2.2 Preliminary Vertical and Horizontal Plans for Water Main A preliminary design submittal will be delivered to the City with the new water main shown in plan and profile for acceptance of the proposed alignment. Profile includes features such as saddles under storm drains or joint trenches, and other features included on the original design. Stationing o-set from new to old plans will be provided to the City for reference. Assume design of water main alignment in plan and profile by the Water Project Engineer is 8 hours per sheet.
Assume oversight/review by Water Project Manager is 2 hours total. Additional CAD hours to complete/clean-up design are 2 hours per sheet. Assume QC review by Senior Consor Principal Engineer for water main alignment prior to submittal to the City is 2 hours total.
2.3 Preliminary Vertical and Horizontal Plans for Services and Hydrants Services and hydrants were not included in the original design of the 14-inch Water Main Loop Project. After the water main alignment has been confirmed in Task 2.2, the City will provide locations for the 34 new services and 8 new fire hydrants. The water main alignment submittal plans will be marked up by the City showing location of future meter or hydrant with dimensions shown from R/W and property lines. The City will provide size and standard details for the services and hydrants.
Assume services are installed from the water main to a meter box with meter setter located at back of curb.
Assume design of services and hydrants in plan and profile by Project Engineer is 6 hours per sheet.
Assume oversight/review by Water Project Manager is 2 hours total. Assume additional CAD hours to complete/clean-up design is 1 hour per each service and hydrant.
Assume QC review by Senior Consor Principal Engineer for the service and hydrant locations prior to submittal to the City at 2 hours.
Consor Page 4 3/11/2026
2.4 Large Water Services and Hydrant Lines Crossing Joint Trench Large water services and hydrant line that will cross the joint trench will need special coordination with the joint trench designers. Time to coordinate plans and design solutions for these crossings will be tracked separately from other services and hydrants.
Assume 6 large services and hydrant crossings.
Assume design by Project Engineer is 4 hours per crossing. Assume coordination with Joint Trench Project Engineer is 2 hours per crossing. Assume additional CAD hours to complete/clean-up design is 1 hour per crossing.
Deliverables
Plan and profile sheets will be drawn at 1”= 20’.
A preliminary submittal will be delivered to the City to confirm the vertical and horizontal alignment of the water main.
After receipt of the City’s marked-up plans with the location of the new services and hydrants, the plan and profile drawings will be updated and returned to the City for review. QC will be provided prior to each submittal to the City.
Task 3 – Preliminary Design - Sewer Laterals
The base plans prepared in Task 2 will be modified to include the replacement of 20 existing sewer laterals. The City has performed field investigations and will mark up the plans with cleanout locations and connection points to the existing sewer main.
3.1 Prepare Cross Sections at Sewer Laterals
A cross section profile will be prepared at each lateral location to show other underground utilities and features. Cross sections will be included on a custom sewer detail sheet.
3.2 Preliminary Plan and Profile of Sewer Laterals
Design of sewer laterals includes abandonment of existing lateral, new cleanout and connection to existing sewer main per Special District Standards. Required clearances from the potable water main and services will be maintained.
Because the joint trench will be constructed in advance, it can be assumed that the joint trench design will accommodate sewer laterals in their existing locations and elevations.
Assume that sewer laterals will be added to the Utility plan and profile sheets prepared in Task 2.
Consor Page 5 3/11/2026
Assume preparation of cross sections by Roadway Project Engineer is 2 hours per section.
Assume additional CAD hours to prepare 5 custom detail sheets for cross sections and complete/clean-up design are 2 hours per sheet.
Assume design of sewer lateral by Project Engineer is 8 hours per plan and profile sheet.
Assume oversight/review by Water Project Manager is 2 hours total. Assume QC review by Senior Consor Principal Engineer for the service and hydrant locations prior to submittal to the City is 2 hours.
Deliverables
Plan and profile sheets will be drawn at 1”= 20’.
The sewer and water utilities will be shown on the same plan and profile sheets (8 sheets). Assume 4 sewer lateral cross sections per sheet = 5 new custom detail sheets.
Task 4 - Preliminary Design Reviews
This task includes coordinating all review of the preliminary design.
4.1 City Review
Provide 14 calendar days in schedule for City review. No anticipated cost to submit.
4.2 Design Review by Roadway and Joint Trench Designers Task includes review by other design team members to identify potential conflicts with other design elements.
Assume Roadway Review by Roadway Project Engineer = 20 hours. Assume Joint Trench Review by Roadway Project Engineer = 20 hours.
4.3 Lake County Public Works, Special District Reviews and Utility Companies Coordinate reviews for design concept approval from associated agencies and a-ected utilities.
Assume Roadway Principal Engineer Coordinates with agencies = 8 hours. Assume Roadway Project Engineer Coordinates with a>ected utilities = 8 hours.
4.4 Consolidate all design review comments
Consolidate all design review comments into a single document organized by station on plans, including a narrative for each item to be resolved. Provide a list for design and/or project meetings to resolve all conflicts. Assume Water Project Engineer oversees and reviews all comments for distribution = 40 hours.
Assume Engineering Designer prepares and updates document = 12 hours.
Consor Page 6 3/11/2026
Task 5 – 95% Design-Water
This task includes incorporating all of the resolved design review comments into the preliminary plans and completing the plans ready for incorporation into the larger project set but not the actual incorporation.
5.1 Incorporating Resolved Comments.
Assume 8 plan and profile sheets.
Assume Water Project Engineer reviews and incorporates all comments: 6 hours per sheet.
Assume CAD updates notes, comments, and cleanup: 6 hours per sheet.
5.2 Prepare Detail Sheets
Incorporate City of Lakeport Standard Plans and customized details. Plan for one full sheet of custom details (primarily for crossing joint trench and box culverts), connection detail, and end/blow o- detail. City standard drawings will be included on detail sheets. Any changes necessary for City of Lakeport Standard plans will be performed by the City.
Assume preparation of 1 custom detail sheet by Water Project Engineer is 6 hours total.
Assume preparation of 1 custom detail sheet is 6 CAD hours. Assume preparation of 2 standard detail sheets is 4 CAD hours. Assume QC review by Senior Consor Principal Engineer prior to submittal to the City is 2 hours.
Task 6 – 95% Design – Sewer Laterals
This task includes incorporating all of the resolved design review comments into the preliminary plans and completing the plans ready for incorporation into the larger project set but not the actual incorporation. The existing sewer laterals will have minimal changes in replacement. The City will resolve any conflicts during Task 3.
6.1 Incorporating resolved comments
Assume 8 plan and profile sheets and 5 section sheets. Assume Water Project Engineer reviews and incorporates all comments: 1.5 hours per plan and profile sheet.
Assume CAD updates notes, comments, and cleanup: 4 hours per sheet.
6.2 Prepare Detail Sheets
Incorporate City of Lakeport Standard Plans and customized details. Plan for 1/4 sheet of custom details (primarily for crossing joint trench). Any changes necessary for City of Lakeport Standard plans will be performed by the City. Assume that sewer custom details will be added to the lateral cross sections sheets that were prepared in Task 2.
Consor Page 7 3/11/2026
Assume preparation of cross sections by Roadway Project Engineer is included in Task 2.
Assume design modifications of sewer lateral by Water Project Engineer is 4 hours. Assume additional CAD hours to complete/clean-up design and incorporate on previously prepared detail sheets are 4 hours total.
Assume preparation of 1 sewer standard detail sheet is 3 CAD hours. Assume QC review by Senior Consor Principal Engineer for the service and hydrant locations prior to submittal to the City is 2 hours.
Task 7 - 95% Design Reviews
This task includes coordinating all review of the 95% design. This includes providing a detailed description of resolved conflicts with specific references to plan changes with indicated locations. Organize this list by commenting organization/agency. City to provide a template for preferred comment log. Consor can provide, if requested.
7.1 City Review
Provide 14 calendar days in schedule for City review. No anticipated cost to submit.
7.2 Design Review by Roadway and Joint Trench Designers Task includes review by other design team members to ensure that all previous comments have been addressed.
Assume Roadway Review by Roadway Project Engineer = 15 hours. Assume Joint Trench Review by Roadway Project Engineer = 15 hours.
7.3 Lake County Public Works, Special District Reviews, and Utility Companies Task includes review using the resolved conflict list for each agency to assure that they are in agreement with implementation/solutions provided. Assume Roadway Principal Engineer Coordinates with agencies = 8 hours. Assume Roadway Project Engineer Coordinates with a>ected utilities = 4hours.
7.4 Consolidate Design Reviews Comments
All design review comments will be consolidated into a single document, or comment log. This will Identify any outstanding unresolved issues. Assume Water Project Engineer oversees and reviews all comments for incorporation into the Comment Log for tracking = 8 hours. Assume Water Engineering Designer prepares and updates document = 8 hours.
Consor Page 8 3/11/2026
7.5 Coordinate Meeting(s)
Coordinate meeting(s) with each agency to solve any outstanding issues. Assume Roadway Project Manager coordinates any meetings with agencies and stakeholders = 8 hours.
Assume Water Project Engineer assists in coordination/communication = 4 hours.
Task 8 – 100% Design Review
This task includes finalization of the water and sewer lateral plans, review of the City prepared technical specifications, and estimating quantities based on City provided bid items.
8.1 Finalize Plans
Based on Task 7 above, incorporate all comments and provide City with final plans to prepare quantity estimates based on City prepared bid items. Assume Water Project Engineer = 8 hours.
Assume CAD = 8 hours.
Assume Water Engineering Designer = 8 hours.
8.2 City Prepared Bid Item Descriptions
Review City prepared bid item descriptions and prepare detailed quantity estimates based on the bid item descriptions. Provide City with sample format for Caltrans Bid Items to reduce review time and formatting. Assume Water Project Engineer = 12 hours total.
Assume Project Coordinator = 2 hours total.
Assume Water Project Manager = 2 hours total.
8.3 City Provided Technical Specifications
Review City provided technical specifications. Provide the City with sample water and sewer technical specifications in Caltrans format to reduce review time and formatting. Front-end specifications are part of County’s scope of work and will not be included in this scope of work.
Assume combined water and sewer technical specifications in Microsoft Word document for tracking changes.
Assume Water Project Engineer provides technical review = 12 hours total. Assume Project Coordinator provides editing and formatting = 2 hours total. Assume Water Project Manager = 2 hours total.
Consor Page 9 3/11/2026
8.4 Revise Drawings
Drawings will be revised and updated to incorporate any items discovered in the above process. Anticipate 2 cycles to complete, with minor comments on each cycle.
Assume a total of 18 water and sewer sheets
Assume Water Project Engineer = 4 hours per cycle1, 2 hours per cycle 2 Assume CAD time for updates = 4 hours per cycle 1, 4 hours per cycle 2 Assume Water Engineering Designer = 6 hours per cycle 1, 2 hours per cycle 2
8.5 Review Finalized Items
Review finalized bid items, bid item descriptions and technical specifications.
Assume Water Project Engineer = 2 hours total.
Task 9 – Incorporation into Roadway Package
This item includes incorporating the water and sewer plan sheets into the full set of construction documents. This will require modification of the Title Sheet, Table of Contents, Sheet Numbering, review and incorporation of General Notes, and other legends, abbreviations, and symbols on General Sheets.
Water and sewer bid items shall be incorporated into the Project bid schedule and bid item descriptions. Technical specifications shall be formatted and incorporated into the Project bid package.
Assume Water Project Engineer = 8 hours total.
Assume Roadway/Joint Trench Project Engineer = 40 hours total. Assume CAD = 8 hours total.
Assume Project Coordinator = 16 hours total.
Task 10 – Bid Support
This item includes providing bid support in the form of answering contractor questions during the bid period and preparing and drawing modifications needed therefore. It is assumed that the City will respond to the majority of the questions regarding the water and sewer design.
Assume response to 5 requests for clarifications.
o Assume 2 hours each request for a Water Project Engineer. o Assume 1 hour each request for a Water Project Manager. Assume assistance in preparation of 1 Addendum.
o Assume 5 hours total for a Water Project Engineer.
o Assume 4 hours total for Project Coordinator.
Assume preparation of Record Drawings.
Consor Page 10 3/11/2026
o Assume 8 hours total for a Project Engineer.
o Assume 12 hours total for CAD.
Task 11 – Construction Support
This item includes providing support during construction to address and resolve construction related issues. It is assumed that the City will review and respond to the majority of the submittals for water and sewer design items. Our water and sewer design sta- will assist, as requested.
Assume review and respond to no more than 10 submittals. o Assume 2 hours each submittal by the Project Engineer. Assume assistance with review and response to no more than five (5) requests for information/clarification
o Assume 2 hours per request for a Project Engineer.
o Assume Water Project Manager = 2 hours total.
o Assume Engineering Designer = 4 hours total.
It is estimated that the plan sheets will include the following:
Abbreviation, Symbols, and Legend (1/2)
General Notes (1/2)
Standard Details (3) (1 sewer; 2 water)
Sewer Lateral Cross Section Sheets (5)
Pipeline Custom Details (1)
Potable Water Main Plan and Profile (8)
TOTAL = 18
All improvement plans will be prepared to a scale of 1”= 20’.
S
M
ain
St
Manning
Creek
S
M
ain
St
State
Highway 29
Manning Creek
29 Ackley
Rd
Vista
Point
Rd
Parallel Dr
Sylva Ln
S
M
ain
St
Soda
Bay
Rd
Soda Bay Rd
Highway
175
State Highway
175
State
Highway 29
175
Vista
Point
Rd
Dixon Dr
Highway 175
Manning Creek
281
1 2 3
4 5
6 Water Systems
1 - Mendo Mill CA 1700739
2 - Rotten Robbie CA 1700727
3 - Jitter Bean CA 1700733
4 - Thomas Water System CA 1700730
5 - Jack in the Box CA 1700715
6 - Lakeport Cinemas CA 1700712
Pipe - 7,902'
Services - 58
Hydrants - 16