STAFF REPORT
City of Lancaster
CC 11
12/12/2023
JC
Date: December 12, 2023
To: Mayor Parris and City Council Members
From: Marissa Diaz, Director – Public Works
Stephen Carrillo, Senior Engineer – PW City Engineering Subject: Antelope Valley College: Campus Infrastructure Phase 1, Avenue J-12 and 30th Street West Intersection Bid #AVC2019/2020-20 – Acceptance of Improvements (Streets)
Recommendation:
Approve the developer-constructed streets on the following project. In addition, accept the streets for maintenance by the City and for public use.
Project Location/Owner Campus Infrastructure Phase 1, Avenue J-12 and 30th Street West Avenue J-12 and 30th Street West Owner: Antelope Valley Community College District Intersection Bid #AVC2019/2020-20
Fiscal Impact:
Estimated value of Capital assets accepted is $846,867.36.
Background:
The streets have been constructed and completed by the developer according to the approved plans and specifications. The work has been inspected and found to be satisfactory to the Director – Public Works.
SC:TL/km
Attachment:
Vicinity Map