STAFF REPORT
City of Lancaster
CC 7
1/9/2024
JC
Date: January 9, 2024
To: Mayor Parris and City Council Members
From: Marissa Diaz, Director – Public Works
Sheila Niebla, Senior Engineer – PW City Engineering
Subject: Task Order for Multi-Year Professional Services (Service Group Category 1 – Roadway and Structures Engineering) for 2024 Pavement Management Program (PMP) Road Rehabilitation Project (Reference: PWCP 24-005) Recommendation:

Approve Task Order No. 1 with Pavement Engineering, Inc., in accordance with the Multi-Year Professional Services Agreement, Service Group Category (SGC) 1 - Roadway and Structures Engineering, to provide Design Services for pavement resurfacing on approximately 14.2 lane miles in the amount of $369,935.00 plus a 10% contingency; and authorize the City Manager, or his designee, to sign all documents.

Fiscal Impact:
$406,928.50 (including 10% contingency); sufficient funds are available in the Capital Improvement Budget in project string CP15ST085.CONST from GL Codes 21149900.8000, 21549900.8000, 22049900.8000, and 41449900.8000.

Background:

The 2024 Pavement Management Program (PMP) will include the design and improvement of

14.2 lane miles of streets including:
•Avenue K from Challenger Way to 20 th Street East
•Avenue J from 25 th Street West to 30th Street West
•Business Center Parkway from Avenue K-8 to Avenue L
•20 th Street West from Avenue J-8 to Avenue K
•Challenger Way from Avenue K to Avenue L
On November 7, 2022, the City Council approved Multi-Year Professional Service Agreements with the consulting firms recommended by staff to be pre-qualified service providers through December 31, 2026. The Multi-Year Agreement permits City staff to issue Task Orders for individual projects.
1 4
8 5
City staff requested proposals for design from nine (9) firms on the Multi-Year Professional Services Agreement List of Pre-Qualified Firms under SGC 1 - Roadway and Structures Engineering. On November 30, 2023, at 9:00 a.m., the City received proposals from four (4) firms for review.

Responsibilities, under this Task Order, include project management; research and geotechnical services; mapping and surveying services; and preparation of plans, specifications, and estimates (PS&E) bid package for construction.

With approval of this contract, the vendor cumulative total for all contracts with the City will increase from $0.00 to $369,935.00.

SN/km