STAFF REPORT
City of Lancaster
CC 9
03/25/25
TN
Date: March 25, 2025
To: Mayor Parris and City Council Members
From: Sonya Patterson, Parks, Arts, Recreation, and Community Services Director Subject:Mariposa Park Outdoor Fitness Equipment Project Notice of Completion (NOC) Recommendation:
Accept the Capital Improvement Project No. CP11ZZ014.CONST – Mariposa Park Outdoor Fitness Equipment Project as complete and direct the City Clerk to file the Notice of Completion for the project.
G.C. Section 84308: No
Fiscal Impact:
$123,294 was awarded to Capital Improvement Project CP11ZZ014.CONST, which had sufficient funds.
Background:
On December 10, 2010, City Council adopted Resolution No.19-59 authorizing the submittal of grant applications for Proposition 68 Per Capita Grant Funds. The California Department of Parks and Recreation Office of Grants and Local Services awarded grant funds in the amount of $123.294 for the installation of concrete pads and the purchase of outdoor exercise equipment from the Greenfields Outdoor Fitness, which was installed in-house by City of Lancaster Staff with oversite by a Greenfields Outdoor Fitness supervisor on February 5, 2025. The concrete pads were designed and built in accordance with the equipment manufacturer’s requirements.
The grant and the improvements it provided has created a dedicated fitness area for the community.
Construction of the project has been completed to the satisfaction of the Director of Parks, Arts, Recreation, and Community Services. The project was substantially completed on February 5,2025, which is within the time permitted by grantor.
Attachment:
1 3
9 2
Notice of Completion
Vicinity Map
SP:NF