From:Marissa Diaz, Director – Public Works
Nicholas Godin, Assistant Director – PW City Engineering Subject:Site Plan Review (SPR) 22-01 - Acceptance of Improvements (Water) Recommendation:
Approve the completed water system installed by the developer for the following project:
Project Location/Owner SPR No. 22-01 20th Street West and Avenue K (APN: 3129-016-066) Owner: FRE Lancaster SS, LLC
G.C. Section 84308: No
Fiscal Impact:
None. These improvements are not maintained by the City.
Background:
Water system improvements are approved by the City in order to exonerate the Developer’s Undertaking Agreement and release improvement securities. The water system for this project has been constructed and completed to the satisfaction of the local water purveyor, Los Angeles County Waterworks District 40-04, Antelope Valley, and was constructed according to the approved plans and specifications. Additionally, the work has been inspected and found to be satisfactory by the Director of Public Works.