TASK ORDER NO. 6
UNDER

AGREEMENT FOR PROFESSIONAL CONSULTANT SERVICES – RFQ 769-22 SERVICE GROUP CATEGORY 2 – TRAFFIC ENGINEERING

DATED DECEMBER 6, 2022

BETWEEN

THE CITY OF LANCASTER, "OWNER"
AND
KIMLEY-HORN AND ASSOCIATES, INC., "CONSULTANT"

PROJECT TITLE: SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (PWCP 13-020)

PROJECT DESCRIPTION: Provide updated traffic forecasts, reassess the preferred alternative design, and prepare an updated concept drawing and overall project cost estimate.

Additionally, evaluate the economic impacts associated with the recent logistics and industrial development within the project area to support the City’s preparation of competitive discretionary grant applications.

SCOPE OF WORK: Per Attached Exhibit "1", Scope of Services

PERIOD OF SERVICES: Per Attached Exhibit "2", Schedule

COMPENSATION
FOR SERVICES: Per Fee Schedule - Not to Exceed $221,054.50

"OWNER" "CONSULTANT"

CITY OF LANCASTER KIMLEY-HORN AND
ASSOCIATES, INC.

By: By:

Trolis Niebla Sri Chakravarthy, P.E., T.E.

City Manager Senior Vice President

Date: Date:

Approved by Dept. Head:

APPROVED AS TO FORM:

Allison E. Burns, Esq., City Attorney
Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 1 of 9

EXHIBIT 1: SCOPE OF SERVICES

PROJECT DESCRIPTION
Consultant shall provide professional engineering and planning services to assess the SR-14 (SR- 138)/Avenue G Interchange Improvements Project (Project) and prepare the Project for grant funding applications.

The scope includes traffic forecasting, project scope validation, design and cost estimate validation, economic analysis, and project management. The work will support the City of Lancaster in confirming project improvements and developing competitive grant applications.

PROJECT LOCATIONS
Generally, the SR -14 (SR -138)/Avenue G Interchange Project (PWCP 13 -020), see attached Vicinity Map. Specific study locations include the following.

Avenue D Study Locations

1. SR-14 NB Ramps and Ave D

2. SR-14 SB Ramps and Ave D

3. 20th St W and Ave D

4. Sierra Hwy and Ave D

5. 30th St W and Ave D

Avenue E Study Locations

6. 30th St W and Ave E

7. 20th St W and Ave E

8. Sierra Hwy and Ave E

9. Division St and Ave E
Avenue F Study Locations

10. SR-14 NB Ramps and Ave F

11. SR-14 SB Ramps and Ave F
Avenue G Study Locations

12. SR-14 NB Ramps and Ave G

13. SR-14 SB Ramps and Ave G

14. 20th St W and Ave G

15. 10th St W and Ave G

16. Sierra Hwy and Ave G

17. Division St and Ave G

18. 30th St W and Aven G

19. 50th St W and Ave G
Avenue H Study Locations

20. SR-14 NB Ramps and Avenue H

21. SR-14 SB Ramps and Avenue H

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 2 of 9

ADDITIONAL INFORMATION
Consultant shall provide professional engineering and planning services per the Detailed Scope of Work herein.

The Consultant shall submit a consolidated monthly invoice in a format acceptable to the City.

The Consultant shall include with the monthly invoice a progress report that reflects the work completed within the invoice period. Payments to the Consultant ar e to be in arrears.

The Consultant must have actually incurred and paid the costs prior to invoicing the City.

The City shall make progress payments per the completed units detailed in Exhibit 3.

The Consultant shall generate an invoice that:
− Details the specific units completed with a cost breakdown with hourly rates for each field function
− Provides sufficient back up to verify expenditures claimed − Is consistent with fee grids submitted in the cost proposal − Includes a brief progress report describing work completed during the invoicing period − Includes delay details if schedule is slipping and how the Consultant will recover the schedule to meet the contract completion date
− Describes work to be completed in the next invoicing period The invoice must include a summary table that details the total contract price, previously paid, current invoice amount and remaining balance.

Consultant shall not start work prior to receiving Notice to Proceed. The Notice to Proceed shall be issued in writing once the insurance documents are submitted and approved and a Task Order has been executed.

Consultant shall not perform additional work without written authorization from the City of Lancaster P roject Manager. Written Authorization shall come in the form of an Additional Authorization to the Task Order.

ITEMS TO BE PROVIDED BY THE CITY
The following items shall be provided by the City:
− Existing reports and prior studies (including TOAR documentation) − Available traffic count data
− Planned land use and development information
Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 3 of 9

− GIS data and mapping resources
− Relevant planning documents and projections.

DETAILED SCOPE OF WORK
TASK 1 TRAFFIC FORECASTS DEVELOPMENT
Consultant shall develop the traffic forecasts along Avenue G and in the northern portion of Lancaster using Southern California Association of Governments (SCAG)’s 2024 Regional Transportation Plan/Sustainable Community Strategy (RTP/SCS) travel demand model.

Traffic forecasts for study locations will be developed through application of a post-processing methodology that uses the difference method, consistent with the National Cooperative Highway Research Program Report (NCHRP) 765: Analytical Travel Forecasting Approaches for Project Level Planning and Design (Transportation Research Board, 2014) methodologies.

The SCAG 2024 RTP/SCS model has a 2019 Base Year and a 2050 Future Year. The model roadway network in the study area will be reviewed to confirm that the base and future year models reflect the existing roadway network, and any improvements planned by the City of Lancaster and in SCAG’s 2024 financially constrained RTP. The Consultant shall review land uses in the study area and coordinate with the City to ensure that the planned industrial and warehouse land use developments are included in SCAG future year model. The Consultant shall re-run the SCAG future year model to account for identified transportation and land use projects.

The AM and PM peak hour and daily traffic volume forecasts will be developed at the study intersections listed below. The cost estimate includes 21 study locations.

The traffic forecasts will be developed for both personal auto and heavy- duty truck vehicles.

The Consultant shall collect existing turning movement volumes for both autos and trucks at the study intersections to have an accurate baseline count. The Consultant will already have traffic counts at six of the study intersections on Avenue F and Avenue G that the Consultant collected for nearby projects in 2023 and 2024, and the Consultant shall collect new traffic counts at the remaining 15 study intersections during the AM peak period (7:00-9:00AM) and PM peak period (4:00-6:00PM) as part of this study. The Future Year (2050) forecasts will be developed by applying the growth calculated from the Base Year and Future Year models to the existing traffic volumes. Interim year forecasts (e.g., Year 2030) will also be developed by interpolating between the existing and Future Year volumes, if needed.

Task 1.2 – Additional Freight Forecasting
In addition to the peak hour intersection forecasts in Task 1, the Consultant shall provide daily traffic volume forecasts and additional freight related data as described below:

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 4 of 9

• Consultant shall forecast daily heavy duty truck volumes on Avenue G and on the adjacent corridors of Avenue D, Avenue E, Avenue F, Avenue H, and SR-14 for Year 2050 using the SCAG model.
• Consultant shall collect existing daily roadway classification counts for the five corridors listed above (24-hour count on a weekday).
• Consultant shall estimate the growth in truck trips with an origin/destination in the Antelope Valley between 2019 and 2050 conditions using the SCAG model. • Consultant shall use socio-economic data from the SCAG model to report the number of jobs associated with industrial land uses in the Antelope Valley for 2019 and 2050.

This data will reflect recently approved and pending projects in the City of Lancaster (Task 1 includes updating the model to reflect these projects). • Consultant shall utilize other big data sources to obtain data on truck origins - destinations in the broader study area. Since the SCAG model ends at the Los Angeles County line, this data will be helpful to understand truck activity associated with Kern County.
• Consultant shall coordinate internally on SCAG model assumptions and factors relating truck payloads and truck trips to the employment types and groups used in the SCAG model to help provide estimates of potential commodity flow/freight volumes for the Avenue G study area.

Task 1.3 Technical Memorandum
The methodology and traffic forecasts results outlined above will be documented in a technical memorandum that will be provided to the project team for review. The Consultant shall respond to one round of comments and submit the final memorandum.

Task 1 Deliverables
• One (1) Draft Traffic Forecast Technical Memorandum
• One (1) Final Traffic Forecast Technical Memorandum
Task 1 Critical Path
Caltrans is currently constructing improvements along SR-14, which have ramps and mainline lanes closed. This task cannot begin until traffic control and lane closures are cleared from all intersections listed in Task 1.1 so that accurate count data can be obtained.

Task 1 Payment
Payment for Task 1 shall be at the lump sum price as shown on Exhibit 3. Such payment shall be considered full compensation for furnishing all labor, equipment, materials and incidentals for performing Task 1 as required in this Scope of Work.

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 5 of 9

TASK 2 PROJECT SCOPE VALIDATION
Consultant shall validate the Project design based on updated traffic forecasts and current standards.

Task 2.1 Traffic Validation
Consultant shall use the updated traffic forecasts completed in Task 1 to assess and validate the design of the preferred alternative.

A Synchro model will be developed to evaluate the 2050 traffic operations at all study intersections in the build scenario only. Existing and 2050 No-build analysis will not be conducted. The AM/PM peak hour analysis in Synchro will be used to assess whether the proposed improvements will still provide satisfactory operations (LOS D or better). If operations with the new 2050 forecasts show any operational deficiencies in the intersection analysis, the analysis will also evaluate what additional improvements are needed to operate at LOS D or better.

The findings will be documented in a brief technical memorandum. It is assumed that no revisions to the analysis or technical memorandum will be required.

Task 2.2 Design Validation
Consultant shall use the traffic validation completed in Task 2.1, along with the freight forecasting completed in Task 1.2, to validate the design of the preferred alternative. It is assumed that the updated traffic analysis will inform at a high level if there is a need to incorporate additional improvements to address any design deficiencies due to the updated traffic forecasts.

Additionally, the preferred design approved in the Project Report will be compared to the latest version of the 7th Edition of the Highway Design Manual (HDM), last updated on 8/8/2025. Any design revisions required due to changes in the HDM will be noted for discussion with the City.

Because the extent of required design revisions will be determined at this time, the scope of work and associated fee required for this effort will be reassessed during this discussion.

A concept drawing will be prepared for review by the City. It is assumed that a fully developed Caltrans Geometric Approval Drawing (GAD) will not be required at this time. One round of consolidated comments will be incorporated into a final concept drawing.

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 6 of 9

Task 2.3 – Cost Estimate Validation
The Consultant shall use the updated concept drawing prepared as stated in Task 2.2 to update the Project cost estimate. The Project cost estimate will also be updated to reflect today’s dollars, including escalation to the anticipated mid-point of construction.

The Consultant shall also provide an estimated cost to complete the PS&E design for inclusion in the grant application.

Task 2 Deliverables
• One (1) Traffic Validation Memorandum (Task 2.1)
• One (1) Draft Concept Drawing (Task 2.2)
• One (1) Final Concept Drawings (Task 2.2)
• One (1) Construction Opinion of Probable Cost (Task 2.3) • One (1) PS&E Fee Estimate (Task 2.3)
Task 2 Critical Path
This task cannot begin until Tasks 1.1 Traffic Forecasts is completed.

Task 2 Payment
Payment for Task 2 shall be at the lump sum price as shown on Exhibit 3. Such payment shall be considered full compensation for furnishing all labor, equipment, materials and incidentals for performing Task 2 as required in this Scope of Work.

TASK 3 ECONOMIC ANALYSIS
Task 3.1 Review of Existing Plans & Projections
The Consultant shall review projections for new industrial and logistics development around the Avenue G Corridor/Fox Field Industrial Corridor, including information from the City on any proposed projects and the zoning allowances for the Corridor. These projections will be informed by the traffic forecasts developed in Task 1.

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 7 of 9

Task 3.2 Economic Impacts Estimation
The Consultant shall evaluate a range of potential economic impacts related to new logistics and industrial development in the Avenue G Corridor/Fox Field Industrial Corridor. These will include:
• Job creation by industry and occupation
• Wages associated with new jobs
• Municipal tax revenue (e.g., property tax, sales tax) generated by new uses The Consultant shall rely on public and proprietary data sources to estimate the above impacts and will build on its previous analysis of employment dynamics in the City to demonstrate the capacity for the City’s existing resident workforce to fill new jobs, and any projected growth in in- commuting associated with these jobs.

The additional freight forecasting completed in Task 1.2 will be utilized to analyze the growth in heavy duty truck traffic and associated volume of goods generated by new logistics and industrial development in the Corridor as it pertains to economic impacts.

The Consultant shall apply gathered data on site location criteria for new industrial and logistics development, including physical site characteristics that developers and operators prefer, to the parcels in the Avenue G Corridor/Fox Field Industrial Corridor to comment on the relative appropriateness and attractiveness of the sites for this new development. Relevant GIS data will be requested from the City to facilitate this review.

Task 3.3 Evaluation of Additional Impacts
The Consultant shall consider other economic impacts related to the proposed improvements at the Avenue G and SR-14 interchange. This evaluation will build on the previous work completed for the City reviewing commute patterns and industry growth trends. Specifically, the following evaluations will be completed:
• Commute Patterns: Data will be collected on the number of residents commuting out from the areas surrounding the Avenue G Corridor, as well as the number of workers commuting into the area, using Census sources. This information will indicate the volume of commuters using the Avenue G/SR-14 interchange who would be positively impacted by the interchange improvements.
• Impacts on Other Industries and Related Job Growth: Data will be collected on industries projected to grow in the City and neighboring communities, as well as the County, over the next ten years. Building on the review of existing plans and projects completed in Task Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 8 of 9

3.1, industries that might be likely to locate in the Avenue G Corridor given its zoning and other characteristics will be identified. The development capacity for these other industries in the Avenue G Corridor will be estimated along with estimated job g rowth associated with that potential new development. This evaluation will be iterative with Task 3.2, so there is no “double-counting” of new economic activity.

Task 3.4 Summary of Findings
The Consultant shall prepare a PowerPoint presentation summarizing findings from Tasks 3.1 to

3.3 and will present the findings at a meeting with City staff and other stakeholders as appropriate.

Based on feedback provided during this meeting, the Consultant shall make any requested revisions to its findings and prepare a technical memorandum for City use.

Task 3 Deliverables
• One (1) PowerPoint Presentation
• One (1) Economic Analysis Technical Memorandum
Task 3 Critical Path
This task cannot begin until Task 1.1 Traffic Forecasts and 1.2 Additional Freight Forecasting are completed.

Task 3 Payment
Payment for Task 3 shall be at the lump sum price as shown on Exhibit 3. Such payment shall be considered full compensation for furnishing all labor, equipment, materials and incidentals for performing Task 3 as required in this Scope of Work.

TASK 4 PROJECT MANAGEMENT
The Consultant shall attend up to four (4) meetings with the City to discuss upcoming tasks and actions. The Consultant shall prepare monthly invoices with a bullet summary of the tasks performed each month.

Task 4 Deliverables
• Monthly invoices with progress summaries
Task 4 Payment
Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 1, Page 9 of 9

Payment for Task 4 shall be at the lump sum price as shown on Exhibit 3. Such payment shall be considered full compensation for furnishing all labor, equipment, materials and incidentals for performing Task 4 as required in this Scope of Work.

TASK 5 PROJECT PHOTO SIMULATION RENDERING
The Consultant shall provide visualization services to produce one (1) photo-realistic 3D design overlay on a high-resolution aerial drone perspective.

Task 5 Deliverables
• One (1) Photo-realistic 3D design overlay on a high-resolution aerial drone perspective Task 5 Critical Path
This task cannot begin until Task 2.2 Design Validation is completed.

Task 5 Payment
Payment for Task 5 shall be at the lump sum price as shown on Exhibit 3. Such payment shall be considered full compensation for furnishing all labor, equipment, materials and incidentals for performing Task 5 as required in this Scope of Work.

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 2, Page 1 of 1

EXHIBIT 2: SCHEDULE
Task Order will be processed and executed as soon as possible, and shall be in place prior to Notice to Proceed.

TASKS COMPLETE BY
Anticipated NTP 05/29/2026
Traffic Counts Collection 06/12/2026
City to Provide Land Use Data 06/12/2026
Initial Ave G Traffic Forecasts 07/17/2026
Traffic Forecast Technical & Traffic Validation Memos 08/18/2026 Concept Drawing & Estimate 08/28/2026
Economic Analysis Technical Memo 09/18/2026
Photo Simulation Rendering 10/02/2026
City review periods, as noted in Exhibit 1, are included in this schedule; no additional time will be awarded for allowable time with City.

With submittal of a Proposal, the Consultant acknowledges understanding and awareness of the proposed schedule. No price adjustments will be permitted for acceleration.

Service Group Category 2 (Reference RFQ 769-22)
Traffic Engineering for
SR-14 (SR-138)/Avenue G Interchange Project Readiness Studies (Reference: PWCP 13-020)
Exhibit 3, Page 1 of 1
TASK
NO. DESCRIPTION PRICE

1. 71,504.00$

2. Project Scope Validation 56,018.00$

3. Economic Analysis 67,648.50$

4. Project Management & Expenses 16,002.00$

5. Project Photo Simulation Rendering 9,882.00$

221,054.50$
a. Hours** and Personnel
b. Rate and Personnel
** Hours are for progress tracking purposes only. This is a time and materials not to exceed contract to provide services as described in Exhibit 1, complete. Additional hours and associated costs will only be considered for change in scope and must be authorized in writing prior to expenditure. * In support of Exhibit 3, Consultant shall provide two fee grids (in table format), with an itemized EXHIBIT 3: PAYMENT AND FEES*
and fifty cents
TOTAL COST AMOUNT WRITTEN IN WORDS Two hundred twenty one thousand fifty four dollars Traffic Forecast Development
TOTAL COST*

TIME AND MATERIALS NOT TO EXCEED
1 Category/Title
Billing Rate $399.00 $289.00 $246.00 $208.00 $180.00 $147.00 $137.00 Task 1 8 8 0 0 0 0 0 16 $ 5,504.00 $ 66,000.00 71,504.00$

1.1 2 2 4 $ 1,376.00 $ 1,376.00

1.2 2 2 4 $ 1,376.00 $ 1,376.00

1.3 4 4 8 $ 2,752.00 $ 2,752.00 Task 2 14 16 88 40 88 0 0 246 $ 56,018.00 $ - $ 56,018.00

2.1 6 2 8 40 56 $ 13,260.00 $ 13,260.00

2.2 6 8 64 48 126 $ 29,090.00 $ 29,090.00

2.3 2 6 16 40 64 $ 13,668.00 $ 13,668.00 Task 3 16 8 0 24 0 0 0 48 $ 13,688.00 $ 53,960.50 $ 67,648.50

3.1 2 2 4 8 $ 2,208.00 $ 8,030.00 $ 10,238.00

3.2 4 2 8 14 $ 3,838.00 $ 24,420.00 $ 28,258.00

3.3 4 2 4 10 $ 3,006.00 $ 12,710.50 $ 15,716.50

3.4 6 2 8 16 $ 4,636.00 $ 8,800.00 $ 13,436.00 Task 4 6 22 18 0 0 0 6 52 $ 14,002.00 $ - $ 14,002.00

4.1 4 8 4 16 $ 4,892.00 $ 4,892.00

4.2 8 8 4 20 $ 4,828.00 $ 4,828.00

4.3 2 6 6 2 16 $ 4,282.00 $ 4,282.00 44 54 106 64 88 0 6 362
$17,556.00 $15,606.00 $26,076.00 $13,312.00 $15,840.00 $0.00 $822.00 $ 89,212.00 $ 119,960.50 $ 209,172.50 $ - $ - $ 2,000.00 Task 4 $ 2,000.00
$ 89,212.00 $ 119,960.50 $ 211,172.50 Task O
O.1 2 2 12 16 $ 3,566.00 $ 3,566.00 O.2 2 4 24 30 $ 6,554.00 $ 6,554.00 O.3 2 4 40 46 $ 9,882.00 $ 9,882.00 OPTIONAL TASKS TOTAL HOURS 6 10 76 0 0 0 0 92
Optional Tasks Subtotal Labor: 2,394.00$ 2,890.00$ 18,696.00$ - $ -$ -$ -$ TOTAL COST with Optional Tasks included:
3/16/2026

TOTAL HOURS
Subtotal Labor:

Other Direct Costs
Misc Expenses
Optional Tasks
Project Photo Simulation Rendering
Illustrative Sketch
Photo-Realistic 2D Overlay
Photo-Realistic 3D Overlay
Project Scope Validation
Traffic Validation
Design Validation
Review of Existing Plan & Projections
Economic Impacts Estimation
Contract Preparation
City of Lancaster
Avenue G - Scope Validation & Grant Readiness
Kimley-Horn and Associates, Inc.

Support
Staff

TOTAL HOURS TOTAL PROJECT
COST
Traffic Forecast Development
Traffic Forecasts
Additional Freight Forecasting
Technical Memorandum
Sr.

Professional II

TOTAL SUB COSTTOTAL KH COST
TOTAL COST:

Analyst ISr.

Professional I
Economic Analysis
Meetings (up to 4)
Invoices (assumed 4)
Evaluation of Other Interchange Related Impacts
Economic Analysis Summary of Findings
Project Management
Professional Analyst IISenior Technical
Support
Cost Estimate Validation
Rate Schedule Used