RECEIVE UPDATEAND PROVIDE DIRECTION FOR
CIP PS 22-41 MOSSDALE ROUNDABOUTS IMPROVEMENTS
ITEM 5.5

CITY COUNCIL SPECIAL MEETING
MAY 16, 2022
1 TIMELINE
2 Dec 13, 2021
• City Council
provided
direction to
evaluate
improvements
to Mossdale
roundabouts
Jan 10, 2022
• Council
elected the
construction
of splitter
islands
• Estimated cost
$200K per
roundabout
• Future
consideration
of Rectangular
Rapid Flashing
Beacons
March 14, 2022 • Proposed CIP
PS 22-41
Mossdale
Roundabouts
Improvements • construct new
splitter islands
• install new
curb ramps
• resurface both
intersections
• restripe all
crosswalks
• enhance
signage
April 15, 2022 • Plans &
Specs were
advertised
for formal
bidding
May 5, 2022 • The lowest
responsive &
responsible
bidder was
determined
to be FBD
Vanguard
Construction,
Inc.
• Bid amount:
$971,442
EXISTING CONDITIONS:
3 1 Towne Centre Drive and McKee Blvd 2 Brookhurst Blvd and Golden SpikeTrail CIP PS 22-41 MOSSDALE ROUNDABOUTS IMPROVEMENTS
Brookhurst Blvd and Golden SpikeTrail 4 1 Towne Centre Drive and McKee Blvd 2 RECOMMENDATION:
 Staff is requesting that City Council:
• Approve the creation of CIP PS 22-41 Mossdale Roundabouts Improvements • Award a construction contract to FBDVanguard Construction, Inc. • Approve a related budget amendment transferring $1,105,000 from the TDALTF Street & Roads Fund (2140) to the CIP Project Fund (3310) to support the construction costs including any additional construction inspection services
5