ITEM 4. 16
CITY MANAGER' S REPORT
DECEMBER 11, 2023 CITY COUNCIL REGULAR MEETING
ITEM: ACCEPT PUBLIC IMPROVEMENTS CONSTRUCTED BY
NOR- CAL CONCRETE COMPANY FOR TEMPORARY
ANIMAL CENTER CONCRETE, CIP GG 23- 06
RECOMMENDATION: Adopt Resolution Accepting Public Improvements Constructed by Nor- Cal Concrete Company for
Temporary Animal Center Concrete, CIP GG 23- 06,
Authorizing the Filing of a Notice of Completion,
Release of Contract Retention, and Release of
Performance and Payment Bonds
SUMMARY:
Nor- Cal Concrete Company ( Nor- Cal) has completed the construction of Temporary Animal Center Concrete, CIP GG 23- 06 ( Project). Staff inspected the improvements and they have been deemed complete and in accordance with the approved plans and specifications by the City Engineer.
Nor- Cal has submitted lien releases confirming all subcontractors and suppliers have been paid in full and provided a one- year warranty bond ( based on 10% of the construction contract) for the improvements to be accepted.
Staff requests City Council accept the completed improvements constructed by NorCal for the Project. Staff also requests City Council authorize the filing of a Notice of Completion with the San Joaquin County Clerk, the release of contract retention to Nor- Cal of$ 4, 190 within forty- five ( 45) days after recording the Notice of Completion, and the release of performance and payment bonds.
BACKGROU N D:
On April 10, 2023, City Council ratified the City Manager' s award of a construction contract on March 1, 2023 to Nor- Cal for the construction of the Project in the amount of $ 76, 590, with a 20% construction contingency of $ 15, 318 for staff to use as necessary to achieve the goals of the Project. The Project scope included pouring concrete slabs for foundations for modular animal kennels.
During construction, contract change orders ( CCO) were issued for a final contract amount of $ 83, 790. The Project' s costs referenced below capture all construction expenditures:
CITY MANAGER' S REPORT PAGE 2
DECEMBER 11, 2023 CITY COUNCIL REGULAR MEETING
ACCEPT PUBLIC IMPROVEMENTS CONSTRUCTED BY NOR- CAL CONCRETE COMPANY FOR TEMPORARY ANIMAL CENTER CONCRETE, CIP GG 23- 06 A. Construction Contract 76, 590
B. Contract Change Orders 7, 200
Total Construction Contract Costs 83, 790
Upon acceptance of the improvements, the performance bond ( Bond No.
WCN7443975, $ 76, 590) and payment bond ( Bond No. WCN7443975, $ 76, 590) will be released and replaced with a one- year warranty bond ( Bond No. WCN7443975, 8, 379). The one- year warranty bond covers any repairs or replacements that may become necessary during the one- year period beginning with this acceptance due to any defective materials or workmanship in connection with the completed improvements. Nor- Cal has also provided the necessary lien releases for the materials supplied and completed work.
Staff requests City Council accept the improvements constructed by Nor- Cal Concrete Company for Temporary Animal Center Concrete, CIP GG 23- 06. Staff also requests City Council authorize the filing of a Notice of Completion with the San Joaquin County Clerk, the release of contract retention to Nor- Cal of $ 4, 190 within forty- five ( 45) days after the recording of the Notice of Completion, and the release of performance and payment bonds.
REASON FOR RECOMMENDATION:
Nor- Cal has completed the project pursuant to the contract documents dated March 1, 2023. Staff inspected the improvements and they have been deemed complete and in accordance with the plans and specifications approved by the City Engineer.
Nor- Cal has submitted a one- year warranty bond for the improvements to be accepted ( based on 10% of the construction contract) and lien releases confirming all sub- contractors and suppliers have been paid in full. The warranty bond covers any repairs or replacements that become necessary during the one- year period, beginning with this acceptance, due to defective materials or workmanship in connection with the completed improvements.
The performance bond and payment bond will be released and replaced with the oneyear warranty bond upon City Council' s acceptance of the improvements.
FISCAL IMPACT:
The final construction contract amount with Nor- Cal for the Project is for $ 83, 790.
Adequate funds have been allocated in the FY 2023- 24 budget to close out CIP GG 23- 06. With the completion of the Project, staff requests that unused funds be transferred back to the original funding sources.
CITY MANAGER' S REPORT PAGE 3
DECEMBER 11, 2023 CITY COUNCIL REGULAR MEETING
ACCEPT PUBLIC IMPROVEMENTS CONSTRUCTED BY NOR- CAL CONCRETE COMPANY FOR TEMPORARY ANIMAL CENTER CONCRETE, CIP GG 23- 06 ATTACH M ENTS:
A. Resolution Accepting Public Improvements Constructed by Nor- Cal Concrete Company for Temporary Animal Center Concrete, CIP GG 23- 06, Authorizing the Filing of a Notice of Completion, Release of Contract Retention, and Release of Performance and Payment Bonds
B. Notice of Completion - Temporary Animal Center Concrete, CIP GG 23- 06 CITY MANAGER' S REPORT PAGE 4
DECEMBER 11, 2023 CITY COUNCIL REGULAR MEETING
ACCEPT PUBLIC IMPROVEMENTS CONSTRUCTED BY NOR- CAL CONCRETE COMPANY FOR TEMPORARY ANIMAL CENTER CONCRETE, CIP GG 23- 06 APPROVALS:
r `•.- e i: i l. Z 7. 2
Steven Hollenbeak Date
Assistant Engineer
ll- 7- 23
Ken Reed Date
Senior Construction Manager
I 1 i'i/ 2o23
Brad ylor Date
City gineer
I 3
Cari Jam s Date
Finance D ctor
I l • Zg • Zo 23
Michael King Date
Assistant City Manager
l , 2, • 2.0 'z
Salvador Navarrete Date
City Attorney
r _.—
Z '' Z3
Stephen J. Salvatore Date
City Manager
RESOLUTION NO. 23-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LATHROP ACCEPTING
PUBLIC IMPROVEMENTS CONSTRUCTED BY NOR- CAL CONCRETE COMPANY FOR TEMPORARY ANIMAL CENTER CONCRETE, CIP GG 23- 06, AUTHORIZING
THE FILING OF A NOTICE OF COMPLETION, RELEASE OF CONTRACT
RETENTION, AND RELEASE OF PERFORMANCE AND PAYMENT BONDS WHEREAS, on April 10, 2023, City Council ratified the City Manager' s award of a construction contract to Nor- Cal Concrete Company ( Nor- Cal) on March 1, 2023 for the construction of Temporary Animal Center Concrete, CIP GG 23- 06 ( Project) in the amount of $ 76, 590 with a 20% construction contingency of $ 15, 318 for staff to use as necessary to achieve the goals of the Project; and WHEREAS, the scope of work consisted of pouring concrete slabs for foundations for modular animal kennels; and
WHEREAS, during construction, contract change orders were issued for a final contract amount of$ 83, 790, the cost of which captures all construction expenditures; and
WHEREAS, staff inspected the improvements and the City Engineer deemed the improvements complete and in accordance with the approved plans and specifications; and
WHEREAS, Nor- Cal has provided the necessary lien releases for the materials supplied and completed work and a one- year warranty bond ( based on 10% of total Project cost) for the improvements being accepted; and
WHEREAS, the performance bond ( Bond No. WCN7443975, $ 76, 590) and payment bond ( Bond No. WCN7443975, $ 76, 590) will be released and replaced with a one- year warranty bond ( Bond No. WCN7443975, $ 8, 379) upon City Council' s acceptance of the improvements; and
WHEREAS, the one- year warranty bond covers any repairs or replacements that may become necessary during the one- year period beginning with this acceptance, due to defective materials or workmanship in connection with the completed improvements; and
WHEREAS, adequate funds have been allocated in the FY 2023- 24 budget to close out the Project. With the completion of the Project, staff requests that unused funds be transferred back to the source Fund; and
WHEREAS, staff requests City Council accept the public improvements constructed by Nor- Cal for Temporary Animal Center Concrete, CIP GG 23- 06; and WHEREAS, staff also requests City Council authorize the filing of a Notice of Completion with the San Joaquin County Clerk, the release of contract retention to Nor- Cal in the amount of $ 4, 190 within forty- five ( 45) days after the recording of the Notice of Completion, and the release of performance and payment bonds.
NOW THEREFORE, BE IT RESOLVED, that the City Council of the City of Lathrop does hereby accept the completed public improvements constructed by NorCal Concrete Company for Temporary Animal Center Concrete, CIP GG 23- 06, pursuant to the contract documents dated March 1, 2023; and BE IT FURTHER RESOLVED, that the City Council of the City of Lathrop authorizes the filing of the Notice of Completion with the San Joaquin County Clerk and the release of the contract retention to Nor- Cal Concrete Company, in the amount of $ 4, 190, within forty-five ( 45) days after the recording of the Notice of Completion, and authorizes the release of the performance and payment bonds; and BE IT FURTHER RESOLVED, that the City Council of the City of Lathrop approves the transfer of unused funds back to the original funding source.
The foregoing resolution was passed and adopted this 11th day of December, 2023 by the following vote of the City Council, to wit:
AYES:
NOES:
ABSENT:
ABSTAIN:
Sonny Dhaliwal, Mayor
ATTEST: APPROVED AS TO FORM:
Teresa Vargas, City Clerk Salvador Navarrete, City Attorney
ATTACHMENT
RECORDING REQUESTED BY, AND
WHEN RECORDED MAIL TO:
CITY OF LATHROP
ATTN: CITY CLERK
390 TOWNE CENTRE DRIVE
LATHROP, CA 95330
Exempt from payment ofrecording fees( GC 11922)
SPACE ABOVE THIS LINE FOR RECORDER' S USE
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN:
1. That the interest or estate stated in paragraph 3 herein in the real property herein described is owned by:
NAME STREET AND NO. CITY STATE
City of Lathrop 390 Towne Centre Drive Lathrop CA 95330 If more than one owner of the interest stated, the name and address of each must be stated)
2. That the full name and address of the owner of said interest or estate, if there is only one owner, and that the full names and addresses of all the co- owners who own said interest or estate as tenants in common, as joint tenants, or otherwise, if there is mare than one owner, are set forth in the preceding paragraph.
3. That the nature of the title of stated owner, or if more than one owner, then of the stated owner and co- owners is fee title( e. g. fee title, leasehold, joint tenancy, etc.).
4. That on the 11 th day of December, 2023 a work of improvement on the real property herein described was completed.
5. That the name of the original contractor, if any, for said work of improvement was: Nor- Cal Concrete Companv
6. That the name and address of the transferor is:
NAME STREET AND NO. CITY STATE
Nor- Cal Concrete ComQany P. O. Box 521 Suisun Citv CA 94585
7. That the real property herein referred to is situated in the Citv of Lathrop Counry of San Joaquin, State of California, and is described as follows:
CIP GG 23- 06 Temparary Animal Center Concrete
That the undersigned has lrnowledge ofthe contents herein and states under penalty ofperjury that the foregoing is true and correct.
CITY OF LATHROP
By.
Stephen J. Salvatore, City Manager Date
By:
Teresa Vargas, City Clerk Date
CERTIFICATE OF ACCEPTANCE
This is to certify that the interest in real property conveyed by the NOTICE OF COMPLETION dated December 11, 2023 by Nor-Cal Concrete Company to the City of Lathrop, a political corporation and/ or governmental agency, is hereby accepted by the undersigned officer or agent on behalf of the City Council pursuant to authority conferred by minute action of the City Council adopted on December 11, 2023, and the grantee consents to recordation thereof by its duly authorized officer.
Dated By
Stephen J. Salvatore, City Manager