ITEM 4. 14
CITY MANAGER' SREPORT
FEBRUARY 12, 2024 CITY COUNCIL REGULAR MEETING
ITEM: CREATE CIP PS 24- 31, YOSEMITE AVENUE
PAVEMENT REHABILITATION, APPROVE
REIMBURSEMENT AGREEMENT WITH YOSEMITE
LATHROP 2, LLC, AND APPROVE BUDGET
AMENDMENT
RECOMMENDATION: Adopt Resolution Creating CIP PS 24- 31, Yosemite Avenue Pavement Rehabilitation, Approving
Reimbursement Agreement with Yosemite Lathrop
2, LLC, and Approving Budget Amendment
SUMMARY:
Staff is proposing City Council approve the creation of Capital Improvement Project CIP) PS 24- 31 for Yosemite Avenue Pavement Rehabilitation ( Project) to address and repair the deteriorating pavement surface on Yosemite Avenue. Yosemite Avenue is an east -west arterial road with significant traffic due to the City' s rapid growth.
The project limits will be from SR120 to the eastern City limits, as depicted in Attachment " C".
The Gateway Specific Plan area developer, Yosemite Lathrop 2, LLC ( Phelan), is currently repaving and expanding the south side of Yosemite Avenue along the entire frontage of the development as required by the Subdivision Improvement Agreement. Staff recognizes that improvements on the north side of Yosemite Avenue are also necessary in order to maintain safe road conditions. Phelan has agreed, contingent on Council approval of the proposed reimbursement agreement, to repave a portion of Yosemite Avenue to the extent shown in Attachment " D" Portion of Yosemite Avenue), concurrently with the improvements on the south side of Yosemite Avenue.
The cost to improve the Portion of Yosemite Avenue is equal to or less than quotes City has received for similar work and Phelan has agreed to reduce or waive mobilization costs for the City since Phelan is already required to pay mobilization costs for the required improvements on the south side of Yosemite Avenue fronting the development. The remaining unpaved section of Yosemite Avenue will be improved as a City project at a later date.
Staff recommends City Council approve the creation of CIP PS 24- 31, approve Public Infrastructure Reimbursement Agreement Between City of Lathrop and Yosemite Lathrop 2, LLC Relating to Capital Improvement Project ( CIP) PS 24- 31 Yosemite Avenue Pavement Rehabilitation ( Reimbursement Agreement) and approve a budget amendment transferring $ 799, 551 from the General Fund Street Repair Reserves 1010).
CITY MANAGER' SREPORT PAGE 2
FEBRUARY 12, 2024 CITY COUNCIL REGULAR MEETING
CREATE CIP PS 24- 31, YOSEMITE AVENUE PAVEMENT REHABILITATION, APPROVE REIMBURSEMENT AGREEMENT WITH YOSEMITE LATHROP 2, LLC,
AND APPROVE BUDGET AMENDMENT
BACKGROUND:
Yosemite Avenue is an east -west arterial that has seen significant traffic due to the rapid growth of the City and the increase in warehouse facilities fronting the road.
The road is bound by commercial and industrial zoning, and is utilized for access to SR120.
Through field observations, staff assessed the condition of Yosemite Avenue from SR120 to the eastern City limits and determined that it requires rehabilitation. Staff proposes to create CIP PS 24- 31 for Yosemite Avenue Pavement Rehabilitation to repair the deteriorated pavement surface.
Currently, the developers of the Gateway development, Phelan, are repaving and expanding the south side of Yosemite Avenue along the entire frontage of their development, as required by their Subdivision Improvement Agreement. Phelan has agreed, contingent on Council approval of the proposed Reimbursement Agreement, to repave the Portion of Yosemite Avenue to the extent shown in Attachment " D", concurrently with the improvements on the south side of Yosemite Avenue.
The cost to improve the Portion of Yosemite Avenue is equal to or less than the quotes the City received for similar work and Phelan has agreed to reduce or waive mobilization costs for the City since Phelan is already required to pay mobilization costs for the required improvements on the south side of Yosemite Avenue fronting the development. The remaining unpaved section of Yosemite Avenue will be improved as a City project at a later date.
After completing the construction work, Phelan will fund the entire cost of the improvements and provide the City proof of payment. City staff will then inspect the work, and if deemed complete to City specification by the City Engineer, staff will return to City Council to request Council' s acceptance of the completed public improvements.
REASON FOR RECOMMENDATION:
The Project is needed to bolster the structure and improve the wearing course of Yosemite Avenue. The proposed creation of CIP PS 24- 31, the budget amendment, and Reimbursement Agreement would allow the Project to move forward and the City to fund the improvements for the portion of Yosemite Avenue.
FISCAL IMPACT:
Sufficient funds were not allocated in the approved FY 23-4 budget, therefore, staff is requesting the approval of budget amendment transferring $ 799, 551 from the General Fund Street Repair Reserves ( 1010) to the CIP Project Fund ( 3310) as follows:
CITY MANAGER' S REPORT PAGE 3
FEBRUARY 12, 2024 CITY COUNCIL REGULAR MEETING
CREATE CIP PS 24- 31, YOSEMITE AVENUE PAVEMENT REHABILITATION, APPROVE REIMBURSEMENT AGREEMENT WITH YOSEMITE LATHROP 2, LLC,
AND APPROVE BUDGET AMENDMENT
Decrease Street Repair Reserves
1010- 251- 03-0
Increase Transfer Out
1010- 9900-90- 9010
Increase Transfer In
3310- 9900- 393- 0000
Increase Appropriation
3310- 8000- 420- 10
Increase Appropriation
3310- 8000- 420- 840
ATTACHMENTS:
799, 551
799, 551
PS 24- 31 $ 799, 551
PS 24- 31 $ 749, 551
PS 24- 31 $ 50, 000
A. Resolution Creating CIP PS 24- 31, Yosemite Avenue Pavement Rehabilitation, Approve Reimbursement Agreement with Yosemite Lathrop 2, LLC, and Approve Budget Amendment
B. Public Infrastructure Reimbursement Agreement with Yosemite Lathrop 2, LLC CIP PS 24- 31
C. CIP PS 24- 31 Limits Map - Yosemite Avenue Pavement Rehabilitation D. Improvement Location Map - Gateway Frontage - Yosemite Avenue CITY MANAGER' S REPORT PAGE 4
FEBRUARY 12, 2024 CITY COUNCIL REGULAR MEETING
CREATE CIP PS 24- 31, YOSEMITE AVENUE PAVEMENT REHABILITATION, APPROVE REIMBURSEMENT AGREEMENT WITH YOSEMITE LATHROP 2, LLC,
AND APPROVE BUDGET AMENDMENT
APPROVALS:
5 - 2 4
B IaI Nabizadah Date
Assistant Engineer
Brad ylor
City Engi eer
Can Jame
Director o'\ inance
2./ s /2 mai
Date
Q,\ 6) Al/ t
Date
Michael King Date
Assistant City Manager
Salvador Navarrete Date
City Attorney
0,/- z4
Stephen J. Salvatore Date
City Manager
RESOLUTION NO. 24-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LATHROP CREATING CIP PS 24- 31, YOSEMITE AVENUE PAVEMENT REHABILITATION, APPROVING REIMBURSEMENT AGREEMENT WITH YOSEMITE LATHROP 2,
LLC, AND APPROVING BUDGET AMENDMENT
WHEREAS, Yosemite Avenue is an east - west arterial that has seen significant traffic due to the rapid growth of the City and the increase in warehouse facilities fronting the road. The road is bound by commercial and industrial zoning, and is utilized for access to SR120; and
WHEREAS, through field observations, staff has assessed the condition of Yosemite Avenue from SR120 to the eastern City limits and determined that it requires rehabilitation; and
WHEREAS, Staff proposes to create CIP PS 24- 31 for Yosemite Avenue Pavement Rehabilitation to maintain and repair the deteriorated pavement surface; and
WHEREAS, currently, the developers of the Gateway development, Phelan, is repaving and expanding the south side of Yosemite Avenue along the entire frontage of their development as is required by their Subdivision Improvement Agreement; and
WHEREAS, Phelan has agreed, contingent on Council approval of proposed Public Infrastructure Reimbursement Agreement Between City of Lathrop and Yosemite Lathrop 2, LLC Relating to Capital Improvement Project ( CIP) PS 24- 31 Yosemite Avenue Pavement Rehabilitation ( Reimbursement Agreement), to repave the Portion of Yosemite Avenue to the extent shown in Attachment " D" of the City Manager' s Report that accompanies this Resolution ( Portion of Yosemite Avenue), concurrently with the improvements on the south side of Yosemite Avenue; and WHEREAS, the cost to improve the Portion of Yosemite Avenue is equal to or less than quotes City has received for similar work and Phelan has agreed to reduce or waive mobilization costs for the City since Phelan is already required to pay mobilization costs for the required improvements on the south side of Yosemite Avenue fronting the development; and
WHEREAS, the remaining unpaved section of Yosemite Avenue will be improved as a City project at a later date; and
WHEREAS, after completing the construction work, Phelan will fund the entire cost of the improvements and provide the City proof of payment. City staff will then inspect the work, and if deemed complete to City specifications by the City Engineer, staff will return to City Council to request Council' s acceptance of the completed
public improvements; and
WHEREAS, staff requests City Council approve the creation of CIP PS 24- 31, Yosemite Avenue Pavement Rehabilitation; and
WHEREAS, staff also requests the approval of a budget amendment transferring $ 799, 551 from the General Fund Street Repair Reserves to the CIP Project Fund to create the project and fund the design and construction as follows; and
Decrease Street Repair Reserves
1010- 251- 03-0
Increase Transfer Out
1010- 9900-90- 9010
Increase Transfer In
3310- 9900- 393- 0000
Increase Appropriation
3310- 8000- 420- 100
Increase Appropriation
3310- 8000- 420- 840
799, 551
799, 551
PS 24- 31 $ 799, 551
PS 24- 31 $ 749, 551
PS 24- 31 $ 50, 000
WHEREAS, staff further requests City Council approve the execution of a Reimbursement Agreement with Yosemite Lathrop 2, LLC for a reimbursement amount not to exceed $ 749, 551.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Lathrop hereby approves the creation of Capital Improvement Project ( CIP) PS 24- 31, Yosemite Avenue Pavement Rehabilitation; and
BE IT FURTHER RESOLVED, that the City Council of the City of Lathrop also approves a budget amendment transferring $ 799, 551 from the General Fund Street Repair Reserves ( 1010) to the CIP Project Fund ( 3310) as detailed above; and BE IT FURTHER RESOLVED, that the City Council of the City of Lathrop also approves a Reimbursement Agreement with Yosemite Lathrop 2, LLC for a total reimbursement amount not -to -exceed $ 749, 551.
The foregoing resolution was passed and adopted this 12th day of February, 2024 by the following vote of the City Council, to wit:
AYES:
NOES:
ABSTAIN:
ABSENT:
Sonny Dhaliwal, Mayor
ATTEST: APPROVED AS TO FORM:
Teresa Vargas, City Clerk Salvador Navarrete, City Attorney
ATTACHMENT
CITY OF LATHROP
PUBLIC INFRASTRUCTURE REIMBURSEMENT AGREEMENT
BETWEEN THE CITY OF LATHROP AND YOSEMITE LATHROP 2,
LLC RELATING TO CAPITAL IMPROVEMENT PROJECT ( CIP) PS 24- 31 YOSEMITE AVENUE PAVEMENT REHABILITATION
This Public Infrastructure Reimbursement Agreement Relating to CIP PS 24- 31, Yosemite Avenue Pavement Rehabilitation, Lathrop, CA (" Agreement") is made and entered into this 12th day of February 2024 (" Effective Date") by and between the City of Lathrop, a municipal corporation of the State of California (" City"), and Yosemite Lathrop 2, LLC ("Developer"). City and Developer may be collectively referred to herein as the " Parties" or individually as a " Party".
RECITALS
A. Lathrop Municipal Code ( LMC) 3. 22 provides a mechanism to reimburse developers for certain public improvements as detailed therein.
B. The " Project," as referenced in this Agreement, consists of ( 1) removal and replacement of 3 inch asphalt with glass grid for portions of roadway with concrete panels under the existing asphalt ( 2) removal and replacement of 3 inch asphalt and removal and replacement of 12 inch aggregate base for portions of the roadway with no concrete panels under the existing asphalt, centerline and edgeline striping, and markers on the North side of Yosemite Avenue which includes two 12' travel lanes and 1' of shoulder, as shown in Exhibit A.
C. Developer will pay expenses for the Project and is entitled to a reimbursement from the City of Lathrop (" Reimbursement") as outlined herein. The purpose of this Agreement is to detail the mechanisms for the payment of Reimbursement to Developer only for those items set forth in Exhibit B to this Agreement.
D. As detailed below, upon completion of the Project, the City agrees to reimburse Project expenses paid by Developer, with total Reimbursement not to exceed $ 749, 551.
NOW, THEREFORE, for good and valuable consideration, City and Developer agree as follows:
AGREEMENT
1. Recitals. The recitals set forth above are true and correct and made a part of this Agreement.
2. City and Developer Obligations.
a) City Obligations:
1 i) City shall accept the subject public improvements from the Developer following Developer' ssatisfaction of all obligations as listed in Section 2(b) of this Agreement.
ii) Subject to the limitation herein, City shall reimburse Developer for the Project cost of construction, with Reimbursement not to exceed 749, 551 following City' s acceptance of the Public Improvements contemplated by this Agreement.
b) Developer Obligations:
i) Developer has submitted an exhibit and specifications to the City pursuant to LMC 3. 22. 010E.
ii) Developer will complete all construction of the Project in compliance with the Subdivision Improvement Agreement for Parcel Map 21- 02. iii) Developer shall provide reasonable documentation of the actual costs incurred for Project ( which may include, among others, unconditional lien releases, invoices, proof of payment, confirmation on letterhead from relevant contractor( s)/ubcontractor( s) of payment, and/ or any other reasonable documentation similar in detail and content as has been previously provided to City); City shall then have the right, but not the obligation, to reasonably review and audit said documentation, to the extent it determines reasonably appropriate, with any such audit being completed within thirty ( 30) days. No later than thirty (30) days of either ( a) the receipt of said documentation, or (b) the completion of any audit.
3. Reimbursement.
a) Timing of Reimbursement.
i) Timing of Reimbursement to Developer shall occur within a reasonable time after City Engineer' s approval of the Project pursuant to LMC
3. 22. 010 and acceptance of the Public by City Council. City shall deliver such Reimbursement to the address set forth in Section 10 below.
4. Term of Agreement; Termination.
a) This Agreement shall commence on the Effective Date and shall terminate on the sooner of (i) one year after the date of execution or ( ii) when Developer has received Reimbursement.
2 5. Indemnification. Developer agrees to protect, defend, indemnify and hold City, its City Council members, officers, employees, engineer, and construction manager harmless from and against any and all claims, demands, liabilities, losses, damages, costs, expenses, liens, penalties, suits, or judgments, arising in whole or in part, directly or indirectly, at any time from any injury to or death of persons or damage to property as a result of the willful or negligent act or omission of Developer or its Contractors, or which results from Developer' snoncompliance with any Law respecting the condition, use, occupation or safety of the Project site, or any part thereof, or which arises from conduct in the performance of or failure to perform the terms and conditions of this Agreement, except as may arise from the sole willful or negligent act or omission of City or any ofits City Council members, officers, employees. This indemnification shall extend to any and all claims, demands, or liens made or filed by reason of any construction, renovation, or remodeling work performed by Developer under this Agreement at any time during the term of this Agreement, or arising thereafter.
6. Governing Law. This Agreement shall be governed by the laws of the State of California.
7. Binding Effect. This Agreement is for the benefit of and shall be binding upon both Parties and their respective successors, heirs, executors, administrators, permitted assigns and successors in interest.
8. Assignment. Not Applicable.
9. Notices. For purposes of this Agreement, " notice" means any notice, demand, request, or other communication to be provided under this Agreement. All notices shall be in writing and shall be sent to the below addresses or at such other addresses as either Party may later specify for that purpose. All notices required or permitted under this Agreement shall be personally delivered or sent by registered or certified mail, return receipt requested, postage prepaid or by a nationally recognized overnight courier, such as FedEx or UPS, with charges prepaid for next business day delivery, addressed to the Parties as follows:
If to City:
With a concurrent copy to:
If to Developer:
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
Attn: City Clerk
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
Attn: Salvador Navarrete, City Attorney
Email: snavarrete@ci. lathrop. ca. us
Yosemite Lathrop 2, LLC
220 Montgomery Street, Suite 315
San Francisco, CA 94104
Attn: David Haugen
Email: dhaugen@phelandevco. com
3 The date of any notice shall be the date of receipt, provided that rejection or other refusal to accept or the inability to deliver because of a change in address of which no notice was given shall be deemed to constitute receipt of the notice sent. Either Party may change its address for notice by giving notice to the other Party in accordance with this Section 9.
10. Payments to Developer. All reimbursement payments due to Developer hereunder shall be sent to the following address or at such other address ( or wiring instructions) as Developer shall from time to time specify in writing to City:
Yosemite Lathrop 2, LLC
220 Montgomery Street, Suite 315
San Francisco, CA 94104
Attn: David Haugen
11. Amendments. Any modifications to this Agreement shall be in writing and signed by authorized representatives of both Parties.
12. Attorney' sFees and Venue. In the event of a dispute arising under this Agreement between the Parties, the prevailing Party shall be entitled to an award against the other Party of reasonable and actual attorney' sfees and costs incurred in connection with the dispute. The venue for any litigation shall be in San Joaquin County, California.
13. Cumulative Rights; Waiver. The failure by either Party to exercise, or delay in exercising any rights under this Agreement, shall not be construed or deemed a waiver thereof, nor shall any single or partial exercise by either Party preclude any other or future exercise thereof or the exercise of any other right. Any waiver of any provision or any waiver of any breach of any provision of this Agreement must be in writing, and any waiver by either Party of any breach of any provision of this Agreement shall not operate as or be construed as a waiver of any other breach of that provision or of any breach of any other provision of this Agreement.
14. Severability. If any provision of this Agreement is deemed by a court of competent jurisdiction to be invalid, illegal or unenforceable, such provision shall be deemed to be severed or deleted from this Agreement and the balance of this Agreement shall remain in full force and effect notwithstanding such invalidity, illegality or unenforceability.
15. Headings. All headings herein are inserted only for convenience and ease of reference and are not considered in the construction or interpretation of any provision of this Agreement.
16. Signing Authority. The individuals signing this Agreement represent and agree that they have full and actual authority to bind their respective Parties to this Agreement.
17. Entire Agreement. This Agreement constitutes the entire agreement between the Parties regarding its subject. This Agreement supersede all proposals, oral and written, and all negotiations, conversations or discussions heretofore and between the Parties related to the subject matter of this Agreement.
4 18. No Third -Party Beneficiaries. There are no intended third -party beneficiaries of any right or obligation assumed by the Parties. In particular, and without limitation, no merchant builder or other purchaser of land from Developer shall have any right to enforce this Agreement.
19. Minor Modifications. Not applicable.
20. Counterparts; Electronic Signatures. This Agreement may be signed in counterparts, each of which shall constitute an original and which collectively shall constitute one instrument. Signatures may be given by facsimile, emailed PDF, or other electronic means with the same force and effect as signed, wet originals.
Signatures to follow on next page]
5 IN WITNESS WHEREOF, City and Developer have executed this Agreement as of the Effective Date.
CITY:
CITY OF LATHROP,
A California municipal corporation
By:
Stephen J. Salvatore
City Manager
ATTEST:
City Clerk of and for the City
of Lathrop, State of California
By:
Teresa Vargas, City Clerk
APPROVED AS TO FORM:
By:
Salvador Navarrete
City Attorney
DEVELOPER:
YOSEMITE LATHROP 2, LLC,
A Delaware limited liability company
By: Phelan- Haugen, LLC,
a California limited liability company,
Its Managing Member
By: Haugen Investments, LLC,
a California limited liability company,
Its Manager
By:
David M. Haugen, Manager
6 EXHIBIT A
DEPICTION OF PROJECT SITE
7 Exhibit
A
Improvement
Limits
Per
Reimbursement
With
Yosemite
Lathrop
2,
LLC
Two
12 fo
ot
lanes
a
nd
1 fo
ot
of
North
side
of
Y
osemite Avenue
Scope
of
Work:
1. Removal replaand ofcement
3 inch
asphalt
with
glass
grid
for
portions
of
ro
adway
with
con
crete
pan
els
u
nder
the
existing
asphalt
2. Remova
l
and repla ofcement
3 inch
asphalt
and
remo
val
and replacement
of
12 inch
aggregate
base
fo
r
portions
of
the
roadway
with
no
concrete
3. a Centerline
nd
edgeline
striping,
a
nd
markers
on
the
North
side
of
Yo
semite
Avenu
e
EXHIBIT B
CONTRACTOR' SESTIMATE
8 Priority 1 & 2 - Yosemite Ave Partial Reconstruct, 10" Digout & 3" Overlay
Lathrop Gateway Ph2
a II
iE1CHERI'
Quote To:
Phone:
E- mail:
Contact:
Phone:
E- mail:
City of Lathrop
See exclusions listed below.
Andrew Cumpian/ Eric Buriel
209- 689- 9445/ 69- 1461
Job Name: Lathrop Gateway Ph2
Date of Plans: N/ A working off Narrative/ Email to
Reconstruct portions & Overlay portions
Revision Date: 2024- 02-7
Revison 1
Estimate No: 210169I
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
TRAFFIC CONTROL
1100 Traffic Control Plan ( Engineer to Amend) 1. 00 LS 1,00. 0 1,00. 0 1200 CMS Boards ( Public Notification)- 1 month each 3. 00 EA 2, 900. 0 8, 700. 0 1300 Construction Area Signs 5. 00 EA 350. 00 1, 750. 0 1325 NOT BID K -Rail LF
1700 Traffic Control Materials 1. 00 LS 9, 500. 0 9, 500. 0 1750 Flagging, Lane Closures, & Detour 1. 00 LS 26, 700. 0 26, 700. 0 1800 Temporary Striping 1. 00 LS 11, 000. 11, 000.
1850 Private Driveways - Maintain Access 1. 00 LS 4,00. 0 4,00. 0 1999 SUBTOTAL TRAFFIC CONTROL 63, 150. 0
GENERAL/ EARTHWORK/ STAGING
2150 Potholing Ex. Utilities 1. 00 LS 10, 500. 0 10, 500. 0 2200 Sawcut, Remove & Dispose of Existing AC - YOS 64, 748. 00 SF 1.0 71, 222. 80 2250 Concrete Panel Removal x 16" YOS 8, 096.0 SF 4. 00 32,84. 00 2275 NOT BID Clearing & Grubbing LS
2350 Erosion Control - SEE Bid Group Below LS
2550 Roadway Ex & Offhaul Excess to On -Site Stockpile 1. 00 LS 43, 000. 43, 000. 2600 NOT BID Fill/inish Planter/ Contours - None Shown SF 2625 NOT BID Subgrade& Fine Grade Sidewalk - None
Shown
SF
2700 Subgrade & Fine Grade AC Pavement - YOS 8, 096.0 SF 1. 90 15, 382. 40 2775 NOT BID Subgrade for 10" Digout Areas SF
2999 SUBTOTAL
GENERAL/ EARTHWORK/ STAGING
172, 489. 20
SURFACE IMPROVEMENTS
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
3100 Grind 2" Conforms @ Ends Only 750. 00 SF 4. 00 3, 000. 3150 Glass Grid 8502 for Lap Joint & 3" Overlay 51, 078.0 SF 2. 05 104, 709. 90 3200 19" AB under 10" AC for Full Depth Portion ONLY 8, 096.0 SF 6. 45 52, 219.0 3225 10" AC Pavement 20, 922. 00 SF 8. 30 173, 652.0
3235 3" AC Pavement Overlay 45, 326. 00 SF 2. 70 122, 380. 2 3250 NOT BID Shoulder Backing - None Shown LF
3300 NOT BID AC Dike/ Berm None Shown LF
3500 Tack Oil - Final Lift of 10", Overlay & Conforms 67, 748. 00 SF 0. 20 13, 549. 60 3600 NOT BID Driveway Repairs or Conforms SF
3999 SUBTOTAL SURFACE IMPROVEMENTS 469, 511.0
WATER
4400 Raise Exisitng Water Valves 6. 00 EA 1,00. 0 6,00. 0 4999 SUBTOTAL WATER 6,00. 0
STRIPING AND SIGNAGE
5300 NOT BID Additional Roadside Signs- None Shown LS
5350 Striping & Markings ROM 1. 00 LS 30, 000. 30, 000. 5999 SUBTOTAL STRIPING AND SIGNAGE ITEMS 30, 000.
SIGNALS AND LIGHTING/ J
6200 NOT BID Detector Loop Replacement - None Shown LS
6300 NOT BID additional Signal Work - None Shown LS
6400 NOT BID additional Lighting or JT work - Non
Shown
LS
6999 SUBTOTAL SIGNALS & LIGHTING/ J
LANDSCAPE & IRRIGATION
7200 NOT BID additional Landscape & Irrig - None
shown
LS
7999 SUBTOTAL LANDSCAPE & IRRIGATION
EROSION CONTROL AND SWPPP
22100 Construction Entrances ( or Sweeping) 2. 00 EA 3, 900. 0 7, 800. 0 22150 NOT BID Straw Fiber Rolls LF
22300 NOT BID Hydroseed - None Shown AC
22400 NOT BID Temp Inlet Protection - None Shown EA
22450 NOT BID QSP/SD Sevrices MO
22999 SUBTOTAL EROSION CONTROL AND
SWPPP ITEMS
LS 7, 800. 0
GRAND TOTAL
NOTES:
Exclusions:
Qunatities and Scope based on Teichert provided Exhibit.
Adjusting of dry utility boxes.
Inspection, Permits, Fees, Testing.
749, 550. 7
Design, Engineering and Surveying/ staking. SWPPP.
PAGE LEFT
INTENTIONALLY
BLANK