ITEM 4. 21

CITY MANAGER' SREPORT
APRIL 14, 2025 CITY COUNCIL REGULAR MEETING
ITEM: CREATE CIP WW 25-3 MCKINLEY AVENUE FORCE

MAIN INTERTIE, APPROVE PROFESSIONAL

SERVICES AGREEMENT WITH BLACK WATER

CONSULTING ENGINEERS, AND APPROVE BUDGET

AMENDMENT
RECOMMENDATION: Adopt Resolution to Create CIP WW 25-3 McKinley Avenue Force Main Intertie, Approve a Professional
Services Agreement with Black Water Consulting
Engineers, and Approve Budget Amendment
SUMMARY:

City staff request that City Council create a new Capital Improvement Project ( CIP) WW 25-3 McKinley Avenue Force Main Intertie. This project is needed to establish a connection between the Manteca Wastewater Quality Control Facility ( MWQCF) and the Lathrop Consolidated Treatment Facility ( LCTF) to allow for the efficient transfer of wastewater based on demand and system resiliency.

Staff also requests City Council approve an initial budget allocation for the project engineering design by transferring $ 925, 200 from the Wastewater Connection Fee Fund 6030 to the new CIP WW 25-3 through the approval of a budget amendment.

Furthermore, staff requests the City Council approve the attached Professional Services Agreement ( PSA) with Black Water Consulting Engineers in the amount of 771, 001 for Tasks 1-6 under their proposal to complete the engineering design, permitting and bidding assistance tasks needed to award the construction contract.

This agreement is for professional engineering services to conduct a feasibility assessment, basis of design report and design of the force main intertie between the two wastewater treatment systems.

BACKGROUND:

The City treats its wastewater at two facilities: the MWQCF provides treatment for areas located primarily east of I-5, excluding the Crossroads, Gateway and South Lathrop development areas, and the LCTF provides treatment for Crossroads, Gateway, South Lathrop and areas located west of I-5.

An intertie connecting the two wastewater treatment systems is recommended to provide numerous benefits, including increased system reliability, enhanced operational flexibility and efficiency. The proposed intertie would be located between the existing sanitary sewer force main located at the intersection of Vierra Road and McKinley Avenue and would proceed west on Vierra Road and D' Arcy Parkway to the CITY MANAGER' SREPORT PAGE 2
APRIL 14, 2025, CITY COUNCIL REGULAR MEETING
CREATE CIP WW 25-3 MCKINLEY AVENUE FORCE MAIN INTERTIE,

APPROVE PROFESSIONAL SERVICES AGREEMENT WITH BLACK WATER

CONSULTING ENGINEERS AND APPROVE BUDGET AMENDMENT
southeast corner of LCTF. Additional pipelines and pumping facilities are anticipated to manage the wastewater flow between the connected systems.

On March 6, 2025, staff issued a Request for Proposals for engineering consulting services for the McKinley Intertie project and received a proposal from one ( 1) qualified engineering consultant, Black Water Consulting Engineers.

REASON FOR RECOMMENDATION:

Staff requests that the City Council create CIP WW 25-3 McKinley Avenue Force Main Intertie with an initial budget of $ 925, 200 through transfer of funds from Fund 6030 to the new CIP WW 25-3. Additionally, staff requests approval of a PSA with Black Water Consulting Engineers in the amount of $ 771, 001 to complete Tasks 1-6 needed to complete the project design, permitting and bidding assistance.

FISCAL IMPACT:

The cost of the Professional Services Agreement with Black Water Consulting Engineers is $ 771, 001 for Tasks 1-6 under their proposal. Staff requests that City Council approve the following proposed budget amendment to transfer $ 925, 200 from the Wastewater Connection Fee Fund 6030 into the new CIP WW 25-3:

Increase Transfer Out
6030- 9900-90- 9- 1 $ 925, 200
Increase Transfer In
6090- 900- 393- 00- CIP WW 25-3 $ 925, 200
Increase Appropriation
6090- 8- 00- 420- 84- 00 CIP WW 25-3 $ 925, 200
ATTACHMENTS:

A. Resolution to Create CIP WW 25-3 McKinley Avenue Force Main Intertie, Approve a Professional Services Agreement with Black Water Consulting Engineers, and Approve Budget Amendment
B. Professional Services Agreement with Black Water Consulting Engineers for Engineering Design Services for the WW 25-3 McKinley Avenue Force Main Intertie
CITY MANAGER' S REPORT PAGE 3
APRIL 14, 2025, CITY COUNCIL REGULAR MEETING
CREATE CIP WW 25-3 MCKINLEY AVENUE FORCE MAIN INTERTIE,

APPROVE PROFESSIONAL SERVICES AGREEMENT WITH BLACK WATER

CONSULTING ENGINEERS AND APPROVE BUDGET AMENDMENT

APPROVALS
Greg Gijon Date
Senior Civil Engineer
FOR
Brad Taylor
City Engineer
Cari J es
Finan Director
ON/ o3/ x' z
y • 3 • 2ozS
Date
v/ 3/.? 0, 2.5-
Date
f • 3 2o2S
Michael King Date
Assistant City Manager
Salvador Navarrete Date
City Attorney

3.* Z4?)
1t• L?• ZS
Stephen J. Salvatore Date
City Manager
RESOLUTION NO. 25 -

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LATHROP TO CREATE CIP WW 25-3 MCKINLEY AVENUE FORCE MAIN INTERTIE, APPROVE A

PROFESSIONAL SERVICES AGREEMENT WITH BLACK WATER CONSULTING

ENGINEERS, AND APPROVE BUDGET AMENDMENT
WHEREAS, the City of Lathrop treats its wastewater at two facilities: the Manteca Water Quality Control Facility ( MWQCF) provides treatment for areas located primarily east of I-5, excluding the Crossroads, Gateway and South Lathrop development areas, and the Lathrop Consolidated Treatment Facility ( LCTF) serves the Crossroads, Gateway, South Lathrop and areas located west of I-5; and WHEREAS, an intertie connecting the two wastewater treatment systems is recommended to provide numerous benefits, including increased system reliability, enhanced operational flexibility and efficiency; and
WHEREAS, on March 6, 2025, staff issued a Request for Proposals for engineering consulting services for the McKinley Intertie project and received a proposal from one ( 1) qualified engineering consultant, Black Water Consulting Engineers; and
WHEREAS, staff requests that City Council create a new Capital Improvement Project ( CIP) for the WW 25-3 McKinley Avenue Force Main Intertie; and WHEREAS, staff requests City Council approve a Professional Services Agreement ( PSA) with Black Water Consulting Engineers in the amount of $ 771, 001 for Tasks 1-6 under their proposal to complete the engineering design, permitting and bidding assistance tasks for the McKinley Avenue Force Main Intertie project CIP WW 25-3 and
WHEREAS, staff is seeking an initial budget allocation for engineering design, permitting and bidding assistance services by transferring $ 925, 200 from the Wastewater Connection Fee Fund 6030 to the new CIP WW 25-3 through the approval of a budget amendment as detailed below.

NOW, THEREFORE, BE IT RESOLVED, the City Council of the City of Lathrop does hereby create McKinley Avenue Force Main Intertie, CIP WW 25-3; and NOW, THEREFORE, BE IT FURTHER RESOLVED, that the City Council of the City of Lathrop does hereby approve a Professional Services Agreement with Black Water Consulting Engineers in the amount of $ 771, 001 for Tasks 1-6 to complete the engineering design, permitting and bidding assistance tasks for the McKinley Avenue Force Main Intertie project CIP WW 25-3 ; and NOW, THEREFORE, BE IT FURTHER RESOLVED, that the City Council of the City of Lathrop does hereby approve a budget amendment to transfer $ 925, 200 from the Wastewater Connection Fee Fund 6030 into the new CIP WW 25-3 as follows:

Increase Transfer Out
6030- 9900-90- 9- 1 $ 925, 200
Increase Transfer In
6090- 900- 393- 00- CIP WW 25-3 $ 925, 200
Increase Appropriation
6090- 8- 00- 420- 84- 00 CIP WW 25-3 $ 925, 200
The foregoing resolution was passed and adopted this 14th day of April 2025, by the following vote of the City Council, to wit:

AYES:

NOES:

ABSENT:

ABSTAIN:

Paul Akinjo, Mayor
ATTEST:

Teresa Vargas, City Clerk Salvador Navarrete, City Attorney APPROVED AS TO FORM:

ATTACHMENT' E

CITY OF LATHROP

AGREEMENT FOR PROFESSIONAL SERVICES WITH BLACK WATER CONSULTING

ENGINEERS

TO PROVIDE ENGINEERING DESIGN SERVICES FOR THE MCKINLEY AVENUE FORCE MAIN INTERTIE, CIP WW 25-3
THIS AGREEMENT, dated for convenience this 14th day of April 2025, is by and between the City of Lathrop, a California municipal corporation (" CITY"), and Black Water Consulting Engineers (" CONSULTANT");
RECITALS:

WHEREAS, CONSULTANT is specially trained, experienced, and competent to perform Engineering Design Services, which are required by this agreement; and WHEREAS, CITY selected the CONSULTANT pursuant to said qualifications; and WHEREAS, CONSULTANT is willing to render such Engineering Design Services, as hereinafter defined, on the following terms and conditions; NOW, THEREFORE, CONSULTANT and the CITY agree as follows:

AGREEMENT
1) Scope of Service
CONSULTANT agrees to perform Engineering Design Services in accordance with the scope of work and fee proposal provided by CONSULTANT, attached hereto as Exhibit "A" and incorporated herein by reference. CONSULTANT represents it is prepared to and can diligently perform these services in accordance with the upmost standards of its profession and to CITY' Ssatisfaction. The fee proposal shall include all reimbursable costs required for the performance of the Scope of Services. Payment of additional reimbursable costs considered to be over and above those inherent in the original Scope of Services shall be approved of in advance and in writing, by the CITY.
2) Compensation
CITY hereby agrees to pay CONSULTANT a sum not to exceed $ 771, 001 for the Engineering Design Services for Tasks 1-6 set forth in Exhibit "A",. CONSULTANT shall be paid any uncontested sum due and payable within thirty ( 30) days of receipt of billings containing all information pursuant to Paragraph 5 below. Compensation for any task must be equal to or less than the percentage of task complete. In no event shall CONSULTANT be entitled to compensation for work not included in Exhibit " A", unless a written change order or authorization describing the extra work and payment terms has been executed by CITY' sauthorized representative prior to the commencement of the work. Payment is made based on a time and materials basis.

Page 1 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEY AVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 3) Effective Date and Term
The effective date of this Agreement is April 14, 2025 and it shall terminate no later than June 30, 2027.
4) Independent Contractor Status
It is expressly understood and agreed by both parties that CONSULTANT, while engaged in carrying out and complying with any of the terms and conditions of this Agreement, is an independent contractor and not an employee of the CITY. As an independent contractor, CONSULTANT is responsible for controlling the means and methods to complete the scope of work described in Exhibit "A" to City' ssatisfaction. CONSULTANT expressly warrants not to represent, at any time or in any manner, that CONSULTANT is an employee of the CITY. 5) Billin s
CONSULTANT shall submit invoices for completed work on a monthly basis, or as otherwise agreed, providing without limitation, details as to amount of hours, individual performing said work, hourly rate, and indicating to what aspect of the Scope of Services said work is attributable. CONSULTANT' Sbills shall include a list of all tasks, a total amount due, the amounts previously billed, and the net amount due on the invoice. Except as specifically authorized by CITY, CONSULTANT shall not bill CITY for duplicate services performed by more than one person. In no event shall CONSULTANT submit any billing for an amount in excess of the rates or the maximum amount of compensation provided in section ( 2) for either task or for the entire Agreement, unless modified by a properly executed change order.
6) Advice and Status Reporting
CONSULTANT shall provide the CITY with timely reports, orally or in writing, of all significant developments arising during performance of its services hereunder, and shall furnish to CITY such information as is necessary to enable CITY to monitor the performance of this Agreement. CONSULTANT shall submit to CITY such reports, diagrams, drawings and other work products developed pursuant to the Scope of Services. 7) Auditing
CITY reserves the right to periodically audit all charges made by CONSULTANT to CITY for services under this Agreement. Upon request, CONSULTANT agrees to furnish CITY, or a designated representative, with necessary information and assistance needed to conduct such an audit. CONSULTANT agrees that CITY or its delegate will have the right to review, obtain and copy all records pertaining to performance of this Agreement. CONSULTANT agrees to provide CITY or its delegate with any relevant information requested and shall permit CITY or its delegate access to its premises, upon reasonable notice, during normal business hours for the purpose of interviewing employees and inspecting and copying such books, records, accounts, and other material that may be relevant to a matter under investigation for the purpose of determining compliance with the requirement.

CONSULTANT further agrees to maintain such records for a period of three (3) years after final payment under this agreement.

Page 2 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEYAVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 8) Assignment of Personnel
CONSULTANT acknowledges that the CITY has relied on CONSULTANT' scapabilities and on the qualifications of CONSULTANT' s
principals and staff as identified in its proposal to
CITY. The services shall be performed by, or under the direct supervision, of CONSULTANT' sAuthorized Representative: Edgar Torres. CITY shall be notified by CONSULTANT of any change of its Authorized Representative, and CITY is granted the right of approval of all original, additional, and replacement personnel at CITY' ssole discretion,
project staff
and
prior
shall
to any
be
change.
notified by CONSULTANT of any changes of CONSULTANT' s
CONSULTANT shall assign only competent personnel to perform services pursuant to this Agreement. If CITY asks CONSULTANT to remove a person assigned to the work called for under this Agreement, CONSULTANT agrees to do so immediately, without requiring the City to process a reason or explanation for its request. 9) Assignment and Subcontracting
It is recognized by the parties hereto that a substantial inducement to CITY for entering into this Agreement was, and is, the professional reputation and competence of CONSULTANT.

Neither this Agreement nor any interest therein may be assigned by CONSULTANT without the prior written approval of CITY' Sauthorized representative. CONSULTANT shall not subcontract any portion of the performance contemplated and provided for herein, other than the subcontractors noted in the proposal, without prior written approval of the CITY' S authorized representative.
10) Insurance
On or before beginning any of the services or work called for by any term of this Agreement, CONSULTANT, at its own cost and expense, shall carry, maintain for the duration of the Agreement, and provide proof thereof that is acceptable to the CITY the insurance specified in subsections (a) through (c) below with insurers and under forms of insurance satisfactory in all respects to the CITY. CONSULTANT shall not allow any subcontractor to commence work on any subcontract until all insurance required of the CONSULTANT has also been obtained for the subcontractor. Verification of this insurance shall be submitted and made part of this Agreement prior to execution.
a) Workers' Compensation. CONSULTANT shall, at CONSULTANT' Ssole cost and expense, maintain Statutory Workers' Compensation Insurance and Employer' sLiability Insurance for any and all persons employed directly or indirectly by CONSULTANT. Said Statutory Workers' Compensation Insurance and Employer' sLiability Insurance shall be provided with limits of not less than one million dollars ($ 1, 000,0). In the alternative, CONSULTANT may rely on a self- insurance program to meet these requirements provided that the program of self- insurance complies fully with the provisions of the California Labor Code. The insurer, if insurance is provided, or the CONSULTANT, if a program of self- insurance is provided, shall waive all rights of subrogation against the CITY for loss arising from work performed under this Agreement.

Page 3 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEYAVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 b) Commercial General and Automobile Liability Insurance. CONSULTANT, at CONSULTANT' Sown cost and expense, shall maintain commercial general and automobile liability insurance for the period covered by this Agreement in an amount not less than two million dollars ($ 2, 000,0) per occurrence, combined single limit coverage for risks associated with the work contemplated by this Agreement. If Commercial General Liability Insurance or an Automobile Liability form or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to the work to be performed under this Agreement or the general aggregate limit shall be at least twice the required occurrence limit. Such coverage shall include but shall not be limited to, protection against claims arising from bodily and personal injury, including death resulting therefrom, and damage to property resulting from activities contemplated under this Agreement, including the use of owned and non -owned automobiles.

Coverage shall be at least as broad as Insurance Services Office Commercial General Liability occurrence form CG 0001 ( ed. 11/ 88) and Insurance Services Office Automobile Liability form CA 0001 ( ed. 12/ 90) Code 1 ( any auto).

Each of the following shall be included in the insurance coverage or added as an endorsement to the policy:
i) CITY, its officers, employees, agents, and volunteers are to be covered as insured with respect to each of the following: liability arising out of activities performed by or on behalf of CONSULTANT, including the insider' s general supervision of CONSULTANT; products and completed operations of CONSULTANT; premises owned, occupied or used by CONSULTANT. The coverage shall contain no special limitations on the scope of protection afforded to CITY, its officers, employees, agents, or volunteers.
ii) The insurance shall cover on an occurrence or an accident basis, and not on a claim made basis.
iii) An endorsement must state that coverage is primary insurance and that no other insurance affected by the CITY will be called upon to contribute to a loss under the coverage.
iv) Any failure of CONSULTANT to comply with reporting provisions of the policy shall not affect coverage provided to CITY and its officers, employees, agents, and volunteers.
v) Insurance is to be placed with California -admitted insurers with a Best' srating of no less than A: VII.
vi) Notice of cancellation or non -renewal must be received by CITY at least thirty days prior to such change.

Page 4 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEYAVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 c) Professional Liability. CONSULTANT, at CONSULTANT' Sown cost and expense, shall maintain for the period covered by this Agreement professional liability insurance for licensed professionals performing work pursuant to this Agreement in an amount not less than Two Million Dollars ($ 2, 000,00) per claim made and per policy aggregate covering the licensed professionals' errors and omissions, as follows:
i) Any deductible or self -insured retention shall not exceed $ 150, 00 per claim.
ii) Notice of cancellation, material change, or non -renewal must be received by the CITY at least thirty days prior to such change shall be included in the coverage or added as an endorsement to the policy.
iii) The policy must contain a cross liability or severability of interest clause.
iv) The following provisions shall apply if the professional liability coverages are written on a claims made form:

1. The retroactive date of the policy must be shown and must be before the date of the Agreement.

2. Insurance must be maintained and evidence of insurance must be provided for at least five years after completion of the Agreement or the work, so long as commercially
available at reasonable rates.

3. If coverage is canceled or not renewed and it is not replaced with another claims made policy form with a retroactive date that precedes the date of this Agreement, CONSULTANT
must provide extended reporting coverage for a minimum of five years after completion of the Agreement or the work.

The CITY shall have the right to exercise at the
CONSULTANT' Scost, any extended reporting provisions of the policy should the CONSULTANT cancel or not renew the coverage.

4. A copy of the claim reporting requirements must be
submitted to the CITY prior to the commencement of any
work under this Agreement.
d) Deductibles and Self -Insured Retentions. CONSULTANT shall disclose the self -insured retentions and deductibles before beginning any of the services or work called for by any term of this Agreement. During the period covered by this Agreement, upon express written authorization of the CITY' s authorized representative, CONSULTANT may increase such deductibles or self -insured retentions with respect to CITY, its officers, employees, agents, and volunteers. The CITY' s authorized representative may condition approval of an increase in deductible or self -insured retention levels upon a requirement that CONSULTANT procure a bond guaranteeing payment of losses and related investigations,

Page 5 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEYAVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 claim administration, and defense expenses that is satisfactory in all respects to each of them.
e) Notice of Reduction in Coverage. In the event that any coverage required under subsections ( a), (b), or (c) of this section of the Agreement is reduced, limited, or materially affected in any other manner, CONSULTANT shall provide written notice to CITY at CONSULTANT' Searliest possible opportunity and in no case later than five days after CONSULTANT is notified of the change in coverage.
f)In addition to any other remedies CITY may have if CONSULTANT fails to provide or maintain any insurance policies or policy endorsements to the extent and within the time herein required, CITY may, at its sole option:
i) Obtain such insurance and deduct and retain the amount of the premiums for such insurance from any sums due under the Agreement;
ii) Order CONSULTANT to stop work under this Agreement or withhold any payment which becomes due to CONSULTANT hereunder, or both stop work and withhold any payment, until CONSULTANT demonstrates compliance with the requirements hereof;
iii) Terminate this Agreement.

Exercise of any of the above remedies, however, is an alternative to other remedies CITY may have and is not the exclusive remedy for CONSULTANT' Sbreach.
11) Indemnification - CONSULTANT' SResponsibility
As to the CONSULTANT' Swork hereunder, it is understood and agreed that ( a) CONSULTANT has the professional skills necessary to perform the work, (b) CITY relies upon the professional skills of CONSULTANT to perform the work in a skillful and professional manner, and ( c) CONSULTANT thus agrees to so perform. Acceptance by CITY of the work performed under this Agreement does not operate as a release of said CONSULTANT from such professional responsibility for the work performed. It is further understood and agreed that CONSULTANT is apprised of the scope of the work to be performed under this Agreement and CONSULTANT agrees that said work can and shall be performed in afully competent manner in accordance with the standard of care applicable to CONSULTANT' Sprofession. CONSULTANT shall indemnify, defend, and hold CITY, its officers, employees, agents, and volunteers harmless from and against any and all liability, claims, suits, actions, damages, and causes of action arising out of any personal injury, bodily injury, loss of life, or damage to property, or any violation of any federal, state, or municipal law or ordinance, to the extent caused by the willful misconduct or negligent acts or omissions of CONSULTANT, its employees, subcontractors, or agents, or on account of the performance or character of this work, except for any such claim arising out of the negligence or willful misconduct of the CITY, its officers, employees, agents, or volunteers.

It is understood that the duty of CONSULTANT to indemnify and hold harmless includes the duty to defend as set forth in Section 2778 of the California Civil Code. Acceptance of insurance certificates and endorsements required under this Agreement does not relieve

Page 6 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEYAVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 CONSULTANT from liability under this indemnification and hold harmless clause. This indemnification and hold harmless clause shall apply whether or not such insurance policies shall have been determined to be applicable to any of such damages or claims for damages.
12) Licenses
If a license of any kind, which term is intended to include evidence of registration, is required of CONSULTANT, its employees, agents, or subcontractors by federal or state law, CONSULTANT warrants that such license has been obtained, is valid and in good standing, and CONSULTANT shall keep it in effect at all times during the term of this Agreement, and that any applicable bond has been posted in accordance with all applicable laws and regulations.
13) Business Licenses
CONSULTANT shall obtain and maintain a CITY of Lathrop Business License until all Agreement services are rendered and accepted by the CITY. 14) Termination
Either CITY or CONSULTANT may cancel this Agreement upon 30 days written notification to the other party. Upon termination, or completion of services under this Agreement, all information collected, work product and documents shall be delivered by CONSULTANT to CITY within ten ( 10) calendar days.
15) Funding
CONSULTANT agrees and understands that renewal of this agreement in subsequent years is contingent upon action by the City Council consistent with the appropriations limits of Article XIII ( B) of the California Constitution and that the Council may determine not to fund this agreement in subsequent years.
16) Notices
All contracts, appointments, approvals, authorizations, claims, demands, Change Orders, consents, designations, notices, offers, requests and statements given by either party to the other shall be in writing and shall be sufficiently given and served upon the other party if (1) personally served, (2) sent by the United States mail, postage prepaid, (3) sent by private express delivery service, or (4) in the case of a facsimile transmission, if sent to the telephone FAX number set forth below during regular business hours of the receiving party and followed with two ( 2) Days by delivery of a hard copy of the material sent by facsimile transmission. Personal service shall include, without limitation, service by delivery and service by facsimile transmission.

To City: City of Lathrop
City Clerk
390 Towne Centre
Lathrop, CA 95330

Page 7 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEYAVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 Copy to:

To Consultant:
17) Miscellaneous
City of Lathrop
Department of Public Works
390 Towne Centre
Lathrop, CA 95330
MAIN: ( 209) 941- 7430
FAX: ( 209) 941- 7449
Black Water Consulting Engineers
602 Lyell Drive
Modesto, CA 95356
Phone: ( 209) 322- 1820
a) Consent. Whenever in this Agreement the approval or consent of a party is required, such approval or consent shall be in writing and shall be executed by a person having the express authority to grant such approval or consent. b) Contract Terms Prevail. All exhibits and this Agreement are intended to be construed as a single document. Should any inconsistency occur between the specific terms of this Agreement and attached exhibits, the terms of this Agreement shall prevail.
c) Controlling Law. The parties agree that this Agreement shall be governed and construed by and in accordance with the Laws of the State of California. d) Definitions. The definitions and terms are as defined in these specifications. e) Force Majeure. Neither party shall be deemed to be in default on account of any delay or failure to perform its obligations under this Agreement, which directly results from an Act of God or an act of a superior governmental authority. f) Headings. The paragraph headings are not a part of this Agreement and shall have no effect upon the construction or interpretation of any part of this Agreement. g) Incorporation of Documents. All documents constituting the Agreement documents described in Section 1 hereof and all documents which may, from time to time, be referred to in any duly executed amendment hereto are by such reference incorporated in the Agreement and shall be deemed to be part of this Agreement. h) Integration. This Agreement and any amendments hereto between the parties constitute the entire Agreement between the parties concerning the Project and Work, and there are no other prior oral or written agreements between the parties that are not incorporated in this Agreement.
i) Modification of Agreement. This Agreement shall not be modified or be binding upon the parties unless such modification is agreed to in writing and signed by the parties.

Page 8 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEY AVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 j) Ownership of Documents. All documents, photographs, reports, analyses, audits, computer media, or other material documents or data, and working papers, whether or not in final form, which have been obtained or prepared under this Agreement, shall be deemed the property of the CITY. Upon CITY' srequest, CONSULTANT shall allow CITY to inspect all such documents during the CONSULTANT' sregular business hours.
k) Provision. Any agreement, covenant, condition, clause, qualification, restriction, reservation, term or other stipulation in the Agreement shall define or otherwise control, establish or limit the performance required or permitted or to be required of or permitted by either party. All provisions, whether covenants or conditions, shall be deemed to be both covenants and conditions.

I) Severability. The invalidity in whole or part of any provision of this Agreement shall not void or affect the validity of any other provision of this agreement. If a court of competent jurisdiction finds or rules that any provision of this Agreement is void or unenforceable, the provisions of this Agreement not so affected shall remain in full force and effect.
m) Status of CONSULTANT. In the exercise of rights and obligations under this Agreement, CONSULTANT acts as an independent contractor and not as an agent or employee of CITY. CONSULTANT shall not be entitled to any rights and benefits accorded or accruing to the City Council members, officers or employees of CITY, and CONSULTANT expressly waives any and all claims to such right and benefits. n) Successors and Assigns. The provisions of this Agreement shall inure to the benefit of, and shall apply to and bind, the successors and assigns of the parties. o) Time of the Essence. Time is of the essence of this Agreement and each of its provisions. In the calculation of time hereunder, the time in which an act is to be performed shall be computed by excluding the first Day and including the last. If the time in which an act is to be performed falls on a Saturday, Sunday or any Day observed as a legal holiday by CITY, the time for performance shall be extended to the following Business Day.

P)
q)
Venue. In the event that suit is brought by either party hereunder, the parties agree that trial of such action shall be vested exclusively in the state courts of California in the County of San Joaquin or in the United States District Court for the Eastern District of California.

Recovery of Costs. The prevailing party in any action brought to enforce the terms of this Agreement or arising out of this Agreement may recover its reasonable costs, including reasonable attorney' sfees, incurred or expended in connection with such action against the non -prevailing party.

Page 9 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEY AVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 18) Notice to Proceed
Prior to commencing work under this agreement, CONSULTANT shall receive a written Notice to Proceed" from CITY. A Notice to Proceed shall not be issued until all necessary bonds and insurances have been received. City shall not be obligated to pay CONSULTANT for any services prior to issuance of the Notice to Proceed. 19) Signatures
The individuals executing this Agreement represent and warrant that they have the right, power, legal capacity, and authority to enter into and to execute this Agreement on behalf of the respective legal entities of the CONSULTANT and the CITY. This agreement shall inure to the benefit of and be binding upon the parties hereto and their respective successors and assigns.

Page 10 of 11 ends

CITY OF LATHROP - BLACK WATER CONSULTING ENGINEERS
ENGINEERING DESIGN SERVICES FOR THE MCKINLEY AVENUE FORCE MAIN INTERTIE, CIP WW 25- 23 Approved as to Form:

Recommended for Approval:

Approved by:

Resolution No. 25 -
Consultant:

City of Lathrop
City Attorney
Salvador Navarrete
City of Lathrop
Assistant City Manager
j-7- LoL
Date
Michael King
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
Date
Stephen J. Salvatore Date
City Manager
Black Water Consulting Engineers
602 Lyell Drive
Modesto, CA 95356
Fed ID #
Lathrop Business License #
Signature Date
Print Name and Title
Signature Date
Print Name and Title

Page 11 of 11 ends

CITY OF LATHROP

REQUEST FOR PROPOSAL
McKinley
Avenue
Forcemain
Intertie Project
MARCH 25, 2025

BLACK CR) WATER

CONSULTING ENGINEERS
SUBMITTED BY:

Black Water Consulting Engineers
602 Lyell Drive, Modesto, CA 95356
209. 322. 1820 I www. blackwater- eng. com

BLACK WATER
March 25, 2025
Greg Gibson, Project Engineer
City of Lathrop
Subject: Proposal Submission for Design of McKinley Avenue Forcemain Intertie Project Dear Mr. Gibson,
On behalf of Black Water Consulting Engineers ( Black Water), I am pleased to submit our proposal for professional engineering services for the McKinley Avenue Forcemain Intertie Project. We appreciate the opportunity to partner with the City of Lathrop ( City) on this critical infrastructure project that will support the City' s ongoing growth and enhance wastewater system resilience, reliability, and operational flexibility.

Black Water brings extensive experience in wastewater infrastructure design, permitting, and construction management, with a proven track record of delivering innovative, cost- effective, and timely solutions for municipalities across California. Our multidisciplinary team of professional engineers, technical experts, and qualified subconsultants are fully committed to the successful delivery of this project.

Our approach integrates a deep understanding of the City' sobjectives, collaboration, and a comprehensive review of existing infrastructure conditions. We will deliver a full basis - of -design report, detailed PS& E documents, and provide construction support to ensure seamless execution. We are confident that our hands- on methodology, familiarity with regional permitting agencies, and history of delivering similar forcemain and wastewater treatment projects will add measurable value to this endeavor.

Should we be awarded this contract, we are prepared to begin immediately upon receipt of Notice to Proceed. We affirm our commitment to executing the scope of work as outlined in the RFP within the required timeframe, and in full compliance with all contract requirements.

Please do not hesitate to contact me at ( 209) 753- 0078 or aja@blackwater- eng. com, for any additional information or clarification regarding this proposal.

Thank you for considering our submission. We look forward to the opportunity to support the City of Lathrop in advancing this vital project.

Sincerely,
Aja Verburg, P. E.

Vice President
MODESTO 1602 Lyell Drive, Modesto, CA 95356 1209. 322. 1820 I blackwater- eng. com Table of Contents
Approach to Project 1
Design Team & Resumes 3
Subconsultants 12
References & Experience 14
Fee Proposal 15
2025 Rate Schedule 16
Claims & Suits & Exclusions 17
Appendix A
Project Understanding Al
Scope of Work Al

APPROACH TO PROJECT
Black Water Consulting Engineers ( Black Water) is incorporated in California, with our main office in Modesto, CA. We provide professional engineering services in water, wastewater, drainage, and construction management. Black Water was formed in 2012 and is comprised of talented local professionals who endeavor to maintain an outstanding reputation for delivering responsive service, technical expertise, and value to our clients.

Project Understanding
The City of Lathrop ( City) is requesting design proposals for an intertie connecting two wastewater treatment facilities: the Manteca Wastewater Quality Control Facility (MWQCF) and the City of Lathrop Consolidated Treatment Facility (LCTF). This intertie will improve wastewater flow management, enhance system resilience, and increase operational flexibility while reducing reliance on a single facility. Black Water is responding to the City' srequest with this proposal, which includes a detailed response and description of tasks to be completed to deliver a successful project. A full project understanding and Scope of Work can be found in Appendix A.

Project Approach

OUR CAPABILITIES & SERVICES

RELATING TO THIS PROJECT
Pump Station & Force Main Design
Wastewater Treatment & Process Design
Collection System Evaluation & Design
Pipeline Rehabilitation
Regulatory Compliance & Permitting
Sewer Master Planning & Asset
Management
Corrosion & Odor Control
Collection System Modeling
Trenchless Construction
Financing Alternatives
Construction Management
Ask any of our clients, the first step of our approach is to understand their needs by getting to know the operations staff and their procedures. Black Water' s
approach to the Project will begin with a staff/ operations/ engineering meeting to understand, organize, and prioritize the elements of the project in a way that addresses project constraints, like schedule and budget, and incorporates the institutional and operational knowledge of the staff who works with the existing sewer infrastructure daily. Black Water has extensive experience with determining and establishing necessary design criteria through basis of design reports, preparation of preliminary and final design plans, specifications, and estimates, and providing engineering assistance during construction. The success of this project will depend on achieving and exceeding the City' s goals.

We have reviewed the information provided with the RFP and during the pre -proposal meeting and have a solid understanding of the existing site constraints, the potential issues and challenges, and the overall need for the Project. From our review, we have identified the following goals and components for a successful Project:

Equipment and Operation:

Provide a new reliable diversion piping and intertie
system to connect the two wastewater treatment
facilities.

Integrate the existing Super Store Industries ( SSI)
and LIP lift stations to the LCTF Headworks.

Inclusion of SCADA monitoring equipment.

Jack and boring underneath the Union Pacific
Railroad and D' Arcy Parkway.

Reliability, Redundancy, and Safety:

Provide a redundant system in case of pump station
failures.

Allow optimized routing based on flow demands.

Evaluation of the existing system and infrastructure
condition.

Evaluation of and verification of the existing and
required capacity.

Rehabilitation of the LCTF headworks.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN 1 To successfully deliver this project, critical work components are establishing the City' s objectives, concerns, and preferences at or before the kickoff meeting. These criteria will serve as the baseline for the development and evaluation of alternative scenarios. Black Water must also be focused and responsive by promptly developing alternative scenarios and early follow- through with subconsultants and outside agencies.

Key risk factors which should be considered in the development of alternative scenarios and design of the project are anticipated to include:

Cost
Construction sequencing
Connections to existing infrastructure
Electrical service reliability
Construction schedule
Community impacts
Right- of- wayconstraints at McKinley Road and Vierra
Road intersection
Safety ( during construction and during operation and
maintenance of the facility)
Reliability and redundancy for LCTF operation
Environmental requirements
Obtaining permits for governing agencies for
proposed force main ( FM) alignment
Coordination with Union Pacific Railroad
Mitigation of these risk factors will be approached based on the City' sobjectives, concerns, and preferences established at the beginning of the Project. Mitigation measures will be presented by Black Water, discussed with the City, and collaboratively decided together. As the project develops, additional risk factors may emerge and will be discussed, with proposed options for mitigation presented to the City.

At this early stage, we understand that City and operations staff may have additional design suggestions. We look forward to having productive conversations if Black Water is selected for this project.

Timeline for completion
Notice to Proceed / Anticipated Award Date April 14, 2025 Information Collection and Review April 14, 2025 - October 6, 2025 Technical Memorandum April 14, 2025 - May 26, 2025
Plans, Specifications, and Estimates May 12, 2025 - October 6, 2025 Permitting and Environmental Continuous
Bidding Assistance October 6, 2025 - December 2, 2025
Construction Management Assistance
Scheduling assumes only pipeline work is involved.

December 2, 2025 - June 1, 2026
A full project understanding and Scope of Work can be found in Appendix A.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN 2

DESIGN TEAM & RESUMES
The organization chart shows the key professional staff at Black Water and subconsultants that will be dedicated to the City of Lathrop McKinley Intertie Project. Black Water staff meets weekly to review and schedule our workload so that we can be most responsive to our client' sneeds. Black Water and all assigned key professional staff are properly licensed to practice in the state of California.

Principal -In -Charge
Aja Verburg, P. E.

Time commitment for
this project: 5%
Technical Advisor/ QC
Alison Furuya, P. E.

Project Manager/ Primary Contact
Edgar Torres
Time commitment for
this project: 5%
Time commitment for
this project: 20%
Design Team
Associate Engineer
Angel Mariscal, P. E.

Assistant Engineer
Ernesto Meza, E. I.T.

Assistant Engineer
Andrew Ruiz, E. I.T.

Assistant Engineer
Christian Camacho, E. I.T.

Engineer Technician/
Construction Inspector
Ulises Yepez
Time commitment for
this project: 70%
Subconsultants
Survey
North Star Engineering
Geotech
Crawford & Associates
Structural
Pelton Wylie + Fahrney
Environmental
BaseCamp Environmental
Potholing
Mozingo Construction
Electrical
HCS Engineering
Ground Penetrating Radar
CSR Locating
CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 3

BLACK WATER
B. S., Civil Engineering, California
Polytechnic State University, San
Luis Obispo
years with Black Water
11 years with others
11 registrations
Professional Engineer:

Arizona # 72561
California # 73020
Nevada # 028296
affiliations
Modesto Engineers Club,
Past President
Aja J. Verburg, P. E.

VICE PRESIDENT
Aja Verburg has 22 years of experience in public infrastructure and water/ wastewater project management and design. Ms. Verburg has a strong understanding of delivering projects from a public agency' sperspective.

She is experienced with of all aspects of project management, which includes application for funding, public outreach, preliminary engineering, environmental approval, right- of- way acquisition, utility coordination, permitting, project approval and design, and project advertisement, for federal, state, and locally -funded projects. This broad range of experience is a benefit to clients, as her approach for each project is to act as an extension of the agency staff and deliver the most cost efficient and innovative design, on schedule, from the planning stage through construction, to serve the client and public. Throughout her career she has served as a project manager and engineering designer for various public and private water and wastewater projects. Ms. Verburg also has extensive experience using Geographical Information System (GIS) software and Innovyze InfoWater and InfoSewer hydraulic network modeling software.

Project Experience
Sanitary Sewer Management Plan Update and Audit, City of Pittsburg CA. Principal -In -Charge. Assisted in the audit and currently updating the City' s
SSMP to ensure compliance with SWRCB Order No. 2O22- O1O3- DWQ. The project involves reviewing existing policies, evaluating sanitary sewer overflow ( SSO) data, updating regulatory compliance measures, and preparing the final SSMP report to support the City' s wastewater management program.

Sewer Pipeline Rehabilitation/ Replacement Project, Phase 2, Jamestown Sanitary District - Jamestown, CA. Project Engineer. Replacement and rehabilitation of approximately 5,00 LF of 6 and 8 -inch sanitary sewers located in the public right- of- way and within sewer easements on private property.

Wastewater Collection and Treatment Systems Evaluation and Planning Improvements - CWSRF, Westley Community Services District - Westley, CA. Project Manager. This project consisted of the evaluation and planning of improvements to the District' swastewater collection and treatment systems. Black Water prepared and submitted the CWSRF planning application for Westley CSD that included preparation of the general, technical, environmental, and financial packages for evaluation of the wastewater treatment plant. Black Water coordinated with SWRCB staff during the application review process and development of the funding agreement. In coordination with California Rural Water Association, a rate study was completed and Proposition 218 process was conducted to evaluate and increase sewer rates in order for Westley CSD to qualify for funding under the program' seligibility requirements.

Church Street Sewer Improvements, Murphys Sanitary District - Murphys, CA. Principal - in -Charge. Preparation of the plans, specifications, and cost estimates for the sewer replacement of 478 LF of sewer piping and replacement of four sewer manholes between Church Street and Gold Street.

Wastewater Treatment Plant Upgrade, City of Escalon - CA. Principal -in -Charge. Validating a preliminary design for a combined domestic and industrial wastewater treatment process to construct improvements to address deficiencies and upgrade the existing plant to produce recycled water.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 4

BLACK WATER
M. S., Civil and Environmental
Engineering, University of
California, Berkeley
B. S., Environmental Engineering
Science, Massachusetts Institute
of Technology
years with Black Water
11 years with others
17 registrations
Professional Engineer:

California # 58943
trainings
National Association of Sewer
Service Companies Pipeline
Assessment Certification
Program/ Lateral Assessment
Certification Program, and
Manhole Assessment
Certification Program
affiliations
California Water Environment
Association ( CWEA)
Alison K. Furuya, P. E.

VICE PRESIDENT
Alison Furuya has 28 years of experience, specializing in water and wastewater projects. Ms. Furuya has been involved in projects from the planning stage through to construction, and operation and maintenance.

Her range of projects and experience is a benefit to clients by providing perspective in how to plan and design better projects. Ms. Furuya has served as the project engineer or project manager for studies, master plans, and designs of pump stations, pipelines, and treatment plant improvements.

Project Experience
Thornton Sewer System Evaluation, Housing Authority of the County of San Joaquin - Thornton, CA. Project Manager. Prepared a comprehensive evaluation of the existing facilities, including a condition assessment of 4, 000 feet of sewer collection system, influent pump station, Imhoff tank, evaporation and percolation ponds, backup power, and electrical controls systems.

Wastewater Treatment Plant Upgrade Project - CWSRF, Murphys Sanitary District - Murphys, CA. QA/C for the preparation of preliminary and final design improvements to the wastewater treatment plant to improve process efficiency, capacity and effluent quality. Preliminary design included a review of the existing facility and analysis of the existing aerated pond treatment capacity. Improvements include new influent pumps, 1 mile of sewer force main replacement, new headworks screening, sub -surface aeration system, sludge removal, and increasing storage capacity.

Manteca North Trunk Sewer Design - Manteca, CA. Project Engineer.

Assisted with the preparation of plans, specifications, and cost estimates for approximately 3, 500 LF of 60 -inch PVC -lined reinforced concrete pipe and 1, 300 LF of 36 -inch. The design included coordination with the City, local utilities, and the South San Joaquin Irrigation District. Project included a bore and jack section beneath a high traffic area and design modifications to address conflicts with current and future City projects.

Riverbank Pond T- 4 Improvements Project - Riverbank, CA. Project Engineer. Prepared plans and specifications for the installation and replacement of gates in existing structures, improvements to existing structures, replacement of a 30 -inch pipeline, and a vactor truck receiving station. Improvements were a phase of an overall plan to address maintenance and operations issues at the treatment plant.

Wastewater Treatment Plant Upgrade, City of Escalon - CA. Project Manager. Validating a preliminary design for a combined domestic and industrial wastewater treatment process to construct improvements and upgrade the existing plant to produce recycled water.

Oakdale Wastewater Capital Improvement Plan Update, City of Oakdale - CA. Project Manager. Preparation of an update to the Wastewater Capital Improvement Plan to be used in the Capital Facilities Fee Nexus Study.

Additionally, assisting in the assessment of the feasibility of implementing a recycled water disposal strategy.

Oakdale Wastewater River Crossing Project, City of Oakdale - CA. Project Manager. Prepared preliminary and final design documents for the replacement of the existing 18 - inch sewer crossing over the Stanislaus River with a multi -barrel siphon located below the River.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN 5

BLACK WATER
B. S., Civil and Environmental
Engineering, University of
California - Davis
years with Black Water
1 years with others
5 registrations
Professional Engineer:

California # 94930
affiliations
Modesto Engineers Club
Edgar Torres, P. E.

PROJECT MANAGER
Edgar Torres has six years of engineering experience of various public and private design projects. He is proficient in utilizing AutoCAD for a diverse range of projects, including dry/ wet utilities, drainage systems, erosion control, striping, typography, demolition, and grading. Mr. Torres has a strong background in the design and preparation of drawings, technical specifications, and cost estimates for municipal projects, specifically with water, sewer, and storm drain systems. He has a proven track record of consistently delivering high -quality work and preparing detailed technical reports that offer expertise and recommendations. With four years of experience working for a public agency, Mr. Torres has a thorough understanding of local, state, and federal regulatory requirements and guidelines governing engineering projects. Excelling in project management, Mr. Torres oversees projects from inception to completion while ensuring adherence to timelines, budgets, and regulatory requirements.

Project Experience
Thornton Wastewater Improvements Project - CWSRF, Housing Authority of the County of San Joaquin - Thornton, CA. Project Engineer. This project consisted of the preparation of a wastewater planning project engineering report, environmental documents for the recommended alternative, sewer rate study, and CWSRF construction application for the Thornton wastewater treatment and disposal facilities owned by the HACSJ. Black Water was also retained to complete the planning and design for the Thornton Wastewater Improvements Project. The project involves closure of the existing Thornton WWTF and construction of a pump station and 2. 3 -mile force main.

Responsibilities include design review and edits during the construction phase.

Public Safety Center Wastewater Screenings Facility, Stanislaus County Modesto, CA. Project Engineer. Preparation of plans, specifications, and estimates for several wastewater screening facilities. The screening facilities will include a vertical auger/ spiral screen system. The design will also include an aeration system for the existing lift station.

Wastewater Treatment Plant Upgrade, City of Escalon - CA. Project Engineer. Validated a preliminary design for a combined domestic and industrial wastewater treatment process to construct improvements to address deficiencies and upgrade the existing plant to produce recycled water. Black Water' sValidation Report recommended modifications to the existing preliminary design to reduce the capital and operating costs for the upgrades. Responsibilities include engineering design on the 90% design submittal.

Sewer Bypass Hydraulic Evaluation, Town of Los Altos Hills - CA. Project Engineer. This project involved preparation of a technical memorandum summarizing the assumptions and results of the hydraulic evaluation for a proposed sewer bypass line that is intended to prevent overflowing at an existing pump station wet well during prolonged periods of power outage. Responsibilities included preparing the engineering design calculations.

Water System Improvements - Phase I, New Auberry Water Association - Auberry, CA. Project Engineer. Providing engineering services for the construction design package to include contract documents, plans, and technical specifications for project improvements to the existing water system. Improvements include replacing transmission pipelines, upgrading well pumps, increasing water storage volume, and assisting with CEQA studies and reports.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 6

BLACK WATER
B. S., Civil Engineering, California
State University - Fresno
years with Black Water
1 years with others
4 registrations
Professional Engineer:

California # 96883
Angel Mariscal, P. E.

ASSOCIATE ENGINEER
Angel Mariscal has over five years of comprehensive engineering experience in various design projects. He is proficient in utilizing AutoCAD and sanitary and septic analysis software for a wide range of applications, including land development, utility design, grading, project layout, storm drain systems, and water and wastewater management. Mr. Mariscal' stechnical expertise includes the preparation of detailed technical reports for potable and non -potable water applications, permit amendments, and municipal utility projects. He has a strong background in the design and preparation of engineering drawings, technical specifications, and cost estimates. Dedicated to providing high -quality deliverables, Mr. Mariscal is adept at understanding and addressing client needs to ensure optimal project solutions.

Project Experience
Thornton Wastewater Improvements Project - CWSRF, Housing Authority of the County of San Joaquin - Thornton, CA. Assistant Engineer. Black Water was retained to complete the planning and design for the Thornton Wastewater Improvements Project. The project involves closure of the existing Thornton WWTF and construction of a pump station and 2. 3 -mile force main. Additionally, providing engineering services during construction and assisting with the construction inspection. Responsibilities include assistance with the project permitting.

River Trunk Realignment Project, City of Modesto - CA. Project Engineer.

This project consists of the design of a portion of the River Trunk Realignment project which will divert flow from the existing River Trunk, located at the E J Gallo facility, to the proposed River Trunk Pump Station, located near B Street and between 7th and 9th Streets. Assisting with the development of the plans, specifications, and estimate for the project.

Bert Crane Regional Wastewater Treatment Plant Discharge Study, City of Atwater - CA. Project Engineer.

Preparation of a discharge study evaluating feasible alternatives for the discharge of effluent to Merced Irrigation District via Black Rascal Creek. The project would allow sustainable use of existing water resources for the community in compliance with the Sustainable Groundwater Management Act.

Crows Landing CSD Sewer Improvement Planning Project, Self -Help Enterprises - Crows Landing, CA.

Assistant Engineer. This project consists of the preparation of an engineering report and 30 -percent plans, specifications, and estimates for the recommended project. The report evaluates alternatives to eliminate the potential for community exposure to surfacing septic system effluent as well as reduce the potential for groundwater degradation, which is the sole source of potable water for the community. 10 -Year Capital Improvement Plan, Murphys Sanitary District - Murphys, CA. Assistant Engineer. Prepared a CIP for wastewater projects and overall District improvements over a 10 -year planning horizon.

WWTP Upgrades Phase II, Tuolumne City Sanitary District - CA. Assistant Engineer. This project consisted of the design and construction of WWTP site improvements including of aeration basin paving, effluent line relocation, and installation of a new SCADA system. Assisted with the contract documents and specifications for the bidding of the project.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN 7

BLACK WATER
B. S., Civil Engineering, University
of California - Davis
years with Black Water
1 years with others
1 registrations
Engineer -in -Training:

California # 179868
Ernesto Meza, E. I.T.

ASSISTANT ENGINEER
Ernesto Meza is a recent civil engineer graduate with a Bachelor' s degree
from the University of California, Davis. Over the course of his career, he has gained extensive experience in both technical and field -based aspects of civil engineering. His expertise includes reviewing and analyzing construction documents, conducting thorough project inspections, and performing detailed plan reviews. Mr. Meza is also proficient in utilizing GIS applications for project planning and management, enhancing his ability to contribute to complex infrastructure projects. Additionally, Mr. Meza has a strong background in working on capital improvement projects, collaborating with various stakeholders, and ensuring projects are executed efficiently and within regulatory standards. His well- rounded experience enables him to navigate both the design and implementation phases of civil engineering projects.

Project Experience
Paradise - Grimes - Ohio Area Strengthen and Replace Water Mains, City of Modesto - CA. Assistant Engineer. This project involves the replacement of approximately 19, 350- LFof aging water distribution pipes with new water mains in a primarily rural residential area with numerous agricultural parcels fronting the project alignments. Responsibilities include assistance with the preparation of the design documents.

Crows Landing CSD Sewer Improvement Planning Project, Self -Help Enterprises - Crows Landing, CA. Assistant Engineer. This project consists of the preparation of an engineering report and 30 -percent plans, specifications, and estimates for the recommended project. The report evaluates alternatives to eliminate the potential for community exposure to surfacing septic system effluent as well as reduce the potential for groundwater degradation, which is the sole source of potable water for the community.

Wastewater Facility Upgrades No. 1 - CWSRF, Jamestown Sanitary District - Jamestown, CA. Assistant Engineer. This project involves preparation of planning and design documents, bidding support, construction management, and construction of recommended improvements for the JSD WWTF to meet new discharge requirements as the Tuolumne Utilities District improves its treatment plant. Planned upgrades include increasing capacity, improving chlorine tanks, and building emergency storage. Responsibilities include preparation assistance with the construction funding application, including planning and design documents.

Church Street Sewer Improvements, Murphys Sanitary District - Murphys, CA. Assistant Engineer. Preparation of the plans, specifications, and cost estimates for the sewer replacement of 478 LF of sewer piping and replacement of four sewer manholes between Church Street and Gold Street. Responsibilities included assistance with the plan set and contract documents for bidding.

Water System Improvements - Phase I, New Auberry Water Association - Auberry, CA. Assistant Engineer.

Providing engineering services for the construction design package to include contract documents, plans, and technical specifications for project improvements to the existing water system. Improvements include replacing transmission pipelines, upgrading well pumps, increasing water storage volume, and assisting with CEQA studies and reports. Responsibilities included bidding support assistance and development of cost estimates.

Wastewater Treatment Plant Upgrade, City of Escalon - CA. Assistant Engineer. Validation of a preliminary design for a combined domestic and industrial wastewater treatment process to construct improvements to address deficiencies and upgrade the existing plant to produce recycled water.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN 8

BLACK WATER
B. S., Civil Engineering,
Environmental, and Sustainable
Engineering, Santa Clara
University
years with Black Water
Joined in 2024
years with others
0 registrations
Engineer -in -Training:

California # 181498
Andrew Ruiz, E. I.T.

ASSISTANT ENGINEER
Andrew Ruiz is a recent graduate of Santa Clara University with a Bachelor of Science in Civil, Environmental, and Sustainable Engineering. His academic foundation includes coursework in structural analysis, wastewater treatment, reinforced concrete design, and land surveying. Prior to joining Black Water, Mr. Ruiz gained experience in construction project management at a general contracting and design -build firm, where he worked as a Field Engineer. His work included project scheduling, cost estimation, contract management, and site logistics planning, providing him with valuable insight into largescale civil projects.

At Black Water, Mr. Ruiz has contributed to various water and wastewater projects, including hydraulic modeling, infrastructure assessments, and technical feasibility studies. He has assisted with preparing engineering reports, system improvement plans, and cost estimates to support municipal and private - sector projects. His work includes pipeline evaluations, stormwater management planning, and regulatory compliance support, ensuring projects meet state and federal requirements. Additionally, Mr. Ruiz has played a key role in drafting technical memoranda, reviewing project specifications, and assisting with contract document development. With hands- onexperience in both construction and water resources engineering, Mr. Ruiz brings a wellrounded skill set to water and wastewater infrastructure projects.

Project Experience
Mission Lift Station Replacement Project - CWSRF, Santa Nella County Water District - Santa Nella, CA. Assistant Engineer. The project involves the design of the replacement of the Mission Lift Station and force mains to accommodate startup and 25 -year build -out scenarios. Responsibilities included preparing engineering calculations.

River Trunk Realignment Project, City of Modesto, CA. Assistant Engineer. This project consists of the design of a portion of the River Trunk Realignment project, which will divert flow from the existing River Trunk, located at the E & J Gallo facility, to the proposed River Trunk Pump Station, located near B Street and between 7th and 9th Streets. Assisted with the project utility coordination. 2022 Water Main and Service Replacement, City of Ceres, CA. Assistant Engineer. Design of 6, 400 LF water main replacement, including new service laterals, hydrants, and system appurtenances to improve distribution system performance and reliability. The project involves pipeline design, stakeholder coordination, preparation of bid documents, and construction services. Assisted with the preparation of the plan set and cost estimate analysis.

Church Street Sewer Improvements, Murphys Sanitary District — Calaveras County, CA. Assistant Engineer.

Preparation of plans and specifications for the replacement of approximately 478 linear feet of 8 -inch diameter sewer pipeline, and associated manholes and connections. Black Water provided bidding assistance for the construction of the project and will provide engineering services during construction. Responsibilities included assisting with the preparation of the contract documents and reviewing the bids.

Sika French Camp Water and Sewer Evaluation Project, Sika Corporation — French Camp, CA. Assistant Engineer.

Engineering support, including assessing water and wastewater system expansion options. Evaluated the feasibility of connecting to a neighboring system, analyzed the reliability of the existing well, and assessed the long- term capacity of the sewer system. Delivered technical recommendations to support infrastructure planning and compliance.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN 9 BLACK 6 WATER
B. S., Civil Engineering, University
of California — Berkeley
years with Black Water
Joined in 2024
years with others
0 registrations
Engineer - in -Training:

California # Pending
Christian Camacho, E. I.T.

ASSISTANT ENGINEER
Christian Camacho is a recent graduate from the University of California - Berkeley, with a strong foundation in engineering principles and analytical problem -solving. At Black Water, he has been involved in various water, wastewater, and stormwater projects. His responsibilities include assisting in hydraulic modeling, water distribution system analysis, and the development of technical reports. Mr. Camacho has supported the design and evaluation of infrastructure improvements, helping ensure compliance with state and federal regulations. His contributions also extend to drafting plans and specifications, cost estimating, and assisting with permitting and funding applications for public utility projects. Mr. Camacho has engaged in diverse projects, including working on technical feasibility studies, pipeline replacement projects, and water supply system improvements. His experience also includes stormwater management assessments and wastewater system evaluations. In addition to his engineering work, he has applied data science and computational modeling to support design and planning efforts.

Project Experience
Wastewater Treatment Plant Upgrades, Phase II - CWSRF, Tuolumne City Sanitary District - CA. Assistant Engineer. Black Water was tasked with evaluating the existing wastewater treatment facilities to determine optimum strategies to improve efficiency of operations and treatment methods. Phase II consists of the design, specifications, and contract documents for constructing improvements at the WWTP which include site paving, retailing walls, grit chamber dump station, drainage improvements, and outfall pipeline. Assisted with submittal and RFI review and engineering services during construction.

Wastewater Treatment Facility Corrective Action Assistance, City of Escalon - CA. Assistant Engineer.

Identified the corrective actions necessary and prepared a Corrective Action Report to respond to the Tentative Cease and Desist Order issued to the City' s WWTF by the Regional Board. Responsible for the preparation and updating of the monthly odor monitoring reports.

Atwater Wastewater Treatment Plant Discharge Study, City of Atwater - CA. Assistant Engineer. Preparation of discharge study to identify alternatives for discharging treated wastewater effluent from the treatment plant to a nearby river, ensuring compliance with the Sustainable Groundwater Management Act (SGMA). The report evaluated and scored three alternatives, ultimately recommending a single project based on cost, constructability, and land acquisition requirements. A schedule and total cost estimate were developed for the selected project. The report will support project justification and funding efforts to complete the recommended solution.

Water System Improvements, New Auberry Water Association - Auberry, CA. Assistant Engineer. Providing engineering services for the construction design package to include contract documents, plans, and technical specifications for project improvements to the existing water system. Improvements include replacing transmission pipelines, upgrading well pumps, increasing water storage volume, and assisting with CEQA studies and reports. Assisted with the cost estimate.

Santa Nella/ Volta Water Quality Improvement Project — DWSRF, Santa Nella County Water District — Merced County, CA. Assistant Engineer. Design of approximately 5 miles of 8 -inch water transmission main to provide groundwater to SNCWD and consolidate with VCSD. Secured funding for the District for the design and construction of the project through the SWRCB DWSRF program. Provided bidding and advertisement support for the project. Responsibilities included assistance with the preparation of the contract documents and calculations.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 10

BLACK WATER
B. S., Earth System Science,
University of California - Merced
years with Black Water
2 years with others
2 certifications
Pipeline Assessment Certification
Program ( PACP), NASSCO
Lateral Assessment Certification
Program ( LACP), NASSCO
Manhole Assessment Certification
Program ( MACP), NASSCO
affiliations
Modesto Engineers Club
Ulises Yepez

ENGINEER TECHNICIAN /

CONSTRUCTION INSPECTOR
Ulises Yepez is a graduate from the University of California - Merced where he received his Bachelor' sin Environmental Science. During his studies, he worked as a research assistant where he assisted in conducting water cost analyses of 30 water districts in Kern County, CA. Mr. Yepez gained a solid understanding of CEQA related documents, and state and local guidelines and protocols for environmental - related concerns through his internship at a water district in the southern San Francisco Bay Area. Since joining Black Water, he has gained extensive construction related experience including project inspection, RFI and submittal reviews, managing budgets, interpreting design drawings, materials organization, and coordinating with multiple teams. He is proficient in collecting, organizing, and analyzing data and familiar using GIS.

Project Experience
Thornton Wastewater Improvements Project - CWSRF, Housing Authority of the County of San Joaquin - Thornton, CA. Construction Inspector. Black Water was retained to complete the planning and design for the Thornton Wastewater Improvements Project. The project involves closure of the existing Thornton WWTF and construction of a pump station and 2. 3 -mile force main. Responsibilities include providing engineering services during construction and assisting with the construction inspection.

Oakdale Wastewater River Crossing Project, City of Oakdale - CA.

Construction Inspector. The project consisted of preliminary and final design documents for the replacement of the existing 18 - inch sewer crossing over the Stanislaus River with a multi -barrel siphon located below the River.

Responsibilities include construction observation of the project during the construction phase.

Collection System - CWSRF, Tuolumne City Sanitary District - Tuolumne, CA. Engineer Technician. Black Water provided improvement design documents for construction of the replacement of aging pipes and manholes of the District' ssewer system.

Responsible for reviewing submittals during the construction phase of the project.

Wastewater Treatment Plant Upgrade, City of Escalon - CA. Engineer Technician. Validating a preliminary design for a combined domestic and industrial wastewater treatment process to construct improvements to address deficiencies and upgrade the existing plant to produce recycled water. Assisted with the planset details and drawings.

Oakdale Wastewater Capital Improvement Plan Update, City of Oakdale - CA. Engineer Technician. Preparation of an update to the Wastewater Capital Improvement Plan to be used in the Capital Facilities Fee Nexus Study.

Additionally, assisting in the assessment of the feasibility of implementing a recycled water disposal strategy.

Assisting with the development of GIS figures.

Colorado Water Main Project, City of Modesto - CA. Engineer Technician. Project consists of engineering, design, bid assistance, and engineering services during construction for a new water main line in Colorado Avenue.

The water main provides water service to the lots fronting Colorado Avenue and connects to existing water mains along the alignment. Assisted with the engineering services during construction including submittal reviews.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 11

SUBCONSULTANTS
SURVEY
NorthStar Engineering Group ( NorthStar) was founded in 2002 and employs a staff of 45 full- time professionals under the direction of three working principals. A California corporation and a California Registered Small Business, NorthStar performs all services out of one office located in downtown Modesto.

NorthStar is a full services local firm which provides civil engineering, land planning, and land surveying. The members of their team have an average of 30 years of experience in the civil engineering and land surveying profession. This experience is heavily weighted with projects for public agencies.

NorthStar has been providing professional land surveying services since its inception. Their team members include California registered land surveyors and technicians who are experienced at performing boundary, topographic, and construction surveys. Their experienced field and office staff manage a full range of projects and are consistently prepared for heavy workloads and critical deadlines. NorthStar' s surveying services
include, but are not limited to, right- of- way surveys, topographic surveys and mapping, construction staking, boundary surveys, legal descriptions and plats, final maps, parcel maps, ALTA surveys, technical support, cross - training of agency staff, record of surveys, monumentation, and aerial control surveys.

GEOTECH
Crawford & Associates, Inc. (Crawford) was established in 2012 and is a registered small business
geotechnical engineering firm ( Certification ID: 1744908) that specializes in large- scale public works projects.

In 2016, Crawford merged with Taber Consultants, one of the nation' s oldest geotechnical engineering companies. The principals of both firms bring significant geotechnical engineering experience on a wide variety of projects throughout Northern California. Crawford has provided geotechnical engineering services on hundreds of water and wastewater projects, including pipelines, roadways, storm drain, sanitary sewer lift stations, water well pump stations, water tanks, drainage basins, buildings, and water/astewater treatment facilities. Their staff has experience working with various state and federal agencies including USACE, DF& G, RWQCB, DSOD, NMFS, NOAA Fisheries, and US Fish & Wildlife Services.

STRUCTURAL
Pelton Wylie + Fahrney Engineering, Inc. (PW+ F) is a full - service structural engineering firm in Modesto, CA where 100% of their work is completed. Principals Jamey Wylie and Nick Fahrney bring a combined 45+ years of experience in a wide variety of commercial, retail, industrial, educational, health care, residential and rehabilitation projects.

The team at Pelton Wylie + Fahrney consists of two California - licensed Structural Engineers, a California - licensed Professional Engineer, an Engineer - In -Training, three drafters, and a supporting administration staff.

The firm is also licensed to practice in Arizona, Oregon and Nevada. PW + F has extensive experience with timber, masonry, reinforced concrete and steel ( structural and light gage) construction with an emphasis on 1 to 4 story wood framed structures, and the resources to provide quality structural analysis, structural design, and computer -aided drafting for all types of projects. The broad range of experience enables PW + F to reliably provide clients with efficient and quality structural solutions while respecting project timelines and budgets.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 12

ENVIRONMENTAL
BaseCamp Environmental, Inc. (BaseCamp) specializes in the preparation of environmental impact assessment documents under the California Environmental Quality Act (CEQA) and the National Environmental Policy Act ( NEPA) and the often intensive environmental planning and problem -solving needed to successfully complete the environmental review process. BaseCamp is dedicated to finding resolve for the multi -faceted environmental challenges that face government, energy, water and urban development interests one project at a time.

BaseCamp is dedicated to high -quality environmental products and services and to promoting effective communication between agencies, proponents, consultants and decision - makers. BaseCamp draws from an experience base that extends to virtually every community and environmental setting in central and northern California. Having handled numerous complex and controversial projects, BaseCamp is comfortable navigating new and dynamic project circumstances. The BaseCamp professional team has been responsible for environmental processing of hundreds of major residential, commercial, industrial, mining, recreation/ resort, energy, water, transportation, and communication systems projects.

POTHOLING
Mozingo Construction, Inc. (Mozingo) was founded in 1990. As Mozingo has grown, they have maintained the highest standards of quality, and integrity. Mozingo specializes in underground construction. Their work consists of installing wet utilities which include sewer, storm drain, domestic water, recycled water and major irrigation pipelines. They also construct pump stations and other related mechanical work, storm water vaults, minor structures and appurtenances involved with pipeline construction. Mozingo aims to be the most proficient, specialized, up- to- date contractors in this rapidly evolving field.

ELECTRICAL
HCS Engineering ( HCS) is the Central Valley' spremier electrical engineering consulting firm and has been for the past 50 years. Richard Smith, HCS Engineering' sPrincipal Electrical Engineer, began his tenure in 1990 and brings extensive experience across all facets of electrical engineering. With an Honors Bachelor of Science in Electrical Engineering from California State University, Sacramento, complementing a Bachelor of Science in Computer Science from California State University, Chico, his academic foundation is robust. Over the past 35 years, Richard has developed expertise in various domains, including commercial, medical, office, and school design, industrial electrical engineering, and distribution systems. His skill set extends to water/astewater pump station design, power distribution and control systems, substation design, and computer network design.

GROUND PENETRATING RADAR
CSR Locating Inc. (CSR) is an underground utility locating company located in Central California. The company was founded in 2018 and is comprised of talented professionals to help locate underground utilities safely. They use ground penetrating radar ( GPR) and radio detection equipment to locate underground mains, including telecommunication, electricity distribution, natural gas, cable television, fiber optics, storm drains, water mains, wastewater pipes, traffic lights and streetlights.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 13

PROJECT EXPERIENCE & REFERENCES
Housing Authority of the County of San Joaquin
Thornton Wastewater Improvements Project
REFERENCE: Gerald " Chip" Jones - Project Manager
P: 209. 460. 5042 I E: gjones@hacsj. com I 2575 Grand Canal Boulevard, PROJECT DATES: Apr 2019 - Ongoing CONTRACT VALUE: $968, 200. 0 Black Water completed a project engineering report which evaluated five wastewater treatment and disposal alternatives for the Housing Authority' sdevelopments in Thornton. An alternative was selected to decommission the existing WWTF and construct a new pipeline to convey wastewater to an existing Sacramento Area Sewer District (SASD) booster pump station, where the wastewater is eventually transported to a Sacramento Regional County Sanitation District ( Regional San) interceptor system, which then conveys the wastewater to the Regional San treatment plant. Black Water also provided the design of a new lift station, including a wet well with a duplex submersible pump system, an emergency storage tank, 2. 3 -mile long force main, tie- in to existing SASD pump station and decommission/ demolition of the old Thornton WWTF. Black Water is currently providing engineering services during construction and construction inspection services for the project.

CWSRF
Stockton, CA 95207
Previously, Black Water completed a
detailed alternative analysis to evaluate
wastewater treatment and disposal for
HACSJ' s
properties within Thornton, CA.

Murphys Sanitary District
Wastewater Treatment Plant Upgrade Project - CWSRF
REFERENCE: Kristina Fillmore - Administrative Manager
P: 209. 728. 3094 I E: kristina@murphyssd. org I 15 Ernest St, Ste. A, Murphys, CA 95247 PROJECT DATES: Mar 2015 - Apr 2021 CONTRACT VALUE: $574, 280 CONSTRUCTION COST: $4, 247, 900 Black Water provided engineering design and construction services to correct wastewater treatment plant deficiencies while keeping user rates and annual operation and maintenance costs as low as feasible. Improvements included relocating the headworks facilities to the WWTP and installing a flex rake bar screen with washer and compactor; replacing the influent pump station; replacing 1 mile of the sewer force main; replacing the emergency generator: replacing the aeration system with a fine bubble aeration system in Ponds 1 and 2; adding solar mixers to Pond 4; removing accumulated biosolids from Pond 1; constructing a new concrete disinfection basin; and adding a reinforced composite geomembrane liner throughout the entire finishing basin to prevent seepage.

The power supply at the WWTP was
improved by transitioning from overhead
to buried service. There was constant
groundwater seepage and intrusion at the
Influent Pump Station (IPS). Despite this
challenge, the contractor managed the
water effectively to keep the construction
on schedule. Additionally, a new, larger
power service was provided by PG& Eat
the IPS.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 14 CRY

LATHROF OP
B
LAC
K
WATER

MCKINLEY AVENUE FORCEMAIN

INTERTIE

PROJECT
c
cn .,* ,
e1.
rvc,. caC 4/ 2/025 Fee sal
Propo
Level
of
Effo
rt
BLACK! )
WATER
S
ubs
BillinRag
tesVII, 288. :
282
528
184 .
115..
178
183 TASKTask
Activity
P1
alp $ l,
Pnljadt Manager
Asao848t
90 AfalaMt88r 2
pt[ Bit[e
0as1yN
TIApNNsH OAQCI AAn81s
NaN* 0888 TM
NbYt
a
NBaBYWtef: fM
Togo
Survey NorthSlar)
E
nelro Basamp) ec
GPR (
CSR
L
ocating)
Poth
oli ng
laminae)
DMYn,
inae) eotechnlool
Inv
estigatio n
CAl
Inc.)
ProjecI
tManagement
and
Administration

1. Kickoff
M
eeting
2 2
2 4
10 2,008

1. 2
Draft
Technical
Memo
Review
Mee
tingANorkshop
2 2
2 4
10 2
008

1. 3 Tec hn
Final
ical Memo
Mee
Review
ting/Workshop
2 2
2 4
10 2
008

51. 50%
PS& E
Review
M
eeting
2 2
4 2
10 942 1,

1. 6
75%
PS& E
R
eview
M
eeting
2 2
4 2
10 1,942

1. Fin7
al
PSBE
Mee
Review
ting
2 2
2 4
2 12
518 2,

1. 8
Agency
Coordination
4 8
14 4
38 8,100
Pro gre1. 9
ss Reports
Scheduleand
4 12
12 8
8 44
9,408

1. 10
Budget
and
Invoicing
8 4
12 24
4 364
Task
Tole ( 1
16 40
36 34
0 0
42 168
34, 296
0 0
0 0
0 Infolma2
tion
Collection
Rev i
and
w Bac2
Informa
kground
tionCollection
and Review
4 16
24 30
12 86
18 472

2. Site
Visits
10 10
20 4, 900

2. 3
Utility
an
Research
dCoordination
8 16
40 16
80 15, 952
To2. 4
pographic
Survey
8 24
12 20
64 13, 336
10049,

2. 5
Geotechnica'
inves tigation
8 24
12 44
9,776

2. 6
GPR
8 16
20 16 60$1,12312, 272
21 ,
100
27Potholing (
Assume potho30
les)
8 24
12 16
60 62072,
5,800
72, 500
Tota
Task
l
4 66
138
126
0 80
0 414
087, 332
854, 900
0 821, 100
72, 500
861, 123
Tec hnicaMel
morandum

3. 1
Draft
Memo
6 12
26 60
20 4
128
25 852

3. 2
Final
Memo
4 10
22 36
10 6
88 017, 870
Task3
Total
10 22
48 96
0 30
10 216
543, 722
0 SO
0 0
0 4
Plans,
Sped$ catians,
and
Estimates

4. 2
50%
POSE
4 48
94 104
52 178
34 514
98 ,
818

4. 3
75%
PS& E
4 48
94 84
52 168
10 460
90, 646

4. 4
Final
PS& E
4 48
64 44
32 118
6 316
63,34

4. 5
BidSchedule
and
Front SpecEnd
ific atonReview
2 4
6 10
10 32
6 ,
562
Task4
Total
14 148
258
242
146
464
50 1322
259, 660
0 0
0 00
00 5
P
ermitting
arta 5. Environmental
1 Building
Permit
4 4
8 4
20 3 ,
884
Encroa5. 2
chment
Permit
4 4
8 4
20 884 3,

5. 3 Pe
Other
rmits
4 16
16 36
7, 640

5. 4
CEQA
4 4
8 4
20 3 ,
884
6 000

5. Initia5
l
Study/
Mitigated
Negative
Declaration
8 8
8 24
4, 824
35, 000
Task
Total
0 24
36 40
0 0
20 120
824, 116
0 000 41,
SO
0 0
6 Bidding
Assistance

6.1 AsBid
sistance
2 6
8 8
8 8
40 7,32

6. 2
Attend
Pre -
Bidmeeting
4 4
2 10
2 ,
186
Co nf6. 3
rmed
Documents
2 4
8 8
8 12
42 8, 440
Task
6 Total
4 14
20 16
16 12
10 92
018, 35
0 0
0 0
S0
7 Construction
Ma
naAssistance
gement Constru7.1
ction
M
eetings
10 30
80 10
130
30, 110

7. 2
Monument
Preservation
0 0
18, 920

7. 3
to
Respond
RFI' s
40 80
80 8
208 51,
624

7. 4
Submittals
40 80
80 20
220
52,
980

7. 5
PrepaASI/ E
rations
20 50
50 8
128
31 164

7. 6 Builts /AsDrawin
Record
gs
6 12
12 60
90 18, 288

7. Pro7
jec Closeot
ut (
final Walkihrough
Punand
ch
List)
8 8
16 32
8,
048
Task
Total
124
260
318
0 0
60 46
808
192, 214
18,920
0 0
0 0
TOTALS
172
574
854
554
162
T
646
I
178
r
3,140
8659,
700 $
73, 820 $
41, 000 $
21, 100 $
72, 500 $
61, 123 $
N

1. otes:
scopeAlt
Mors
ase
and
oaaMd
lees baare on
sed
Iha
East
a ppro ximatio
n
we
can
crake
gtven
the
current
level
of
inform
ation
we ha
ve.

Blac 2.
kWater MS
en
discuss
d/ or
n
egoaele
with
the
Client
any
scope
or
fee
item shove
l
on
this

3. S Proposal.
0600reultanl
work
is
charge
d
at
c
ost
plus
pe
10 rcen t
2025 RATE SCHEDULE
ENGINEERING: HOURLY RATE
Engineering Intern $ 113. 00
Engineer Technician $ 173. 00
Assistant Engineer $ 184. 00
Associate Engineer/ Assistant Project Manager $ 228. 00 Project Manager $ 262. 00
Principal $ 288. 00
TECHNICAL STAFF:

CAD Technician $ 155. 00
Senior CAD Technician $ 178. 00
Senior CAD Designer $ 213. 00
FIELD SERVICES:

Construction Intern $ 113. 00
Construction Inspector $ 212. 00
Construction Manager $ 262. 00
ADMINISTRATION:

Administration $ 113. 00
EXPERT WITNESS: $ 374. 00
DIRECT COSTS• Cost plus 10 percent
SUBCONSULTANTS: Cost plus 10 percent
MILEAGE: IRS rate
The above rate schedule is subject to adjustment July 1, 2025.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 16

CLAIMS AND SUITS
In 2020, Black Water and our Client (Agency) were defendants in a claim made by a developer stemming from a memo written in 2014. The claim was settled through mediation.

EXCLUSIONS
Black Water Consulting Engineers has reviewed the City' s Scope of Work and addressed all assumptions in the Full Scope of Services shown in Appendix A.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I 17

APPENDIX A

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN A

PROJECT UNDERSTANDING
The construction and operation of the intertie and proposed force main are essential to support Lathrop' songoing growth and the corresponding demand for improved wastewater infrastructure. Currently, the City sends an average of 1. million gallons per day ( MGD) to the MWQCF, approaching its allocated capacity of 1. 45 MGD. This project will establish a diversion system that enables wastewater flows to be redirected between the MWQCF and Lathrop' s own
CTF, enhancing system redundancy and operational flexibility.

The proposed force main intertie is planned at the intersection of McKinley Road and Vierra Road. The new main will extend west along Vierra Road within the City' sright- of- way, requiring a jack and bore crossing beneath the Union
Pacific Railroad and D' Arcy Parkway before ultimately connecting to the header at the LCTF headworks. In addition to this intertie, the existing SSI Lift Station is expected to be connected to the 16 -inch SSFM along McKinley Avenue by extending a 6 -inch SSFM south of Super Store Industries at 2400 W Louise Avenue. Furthermore, a new force main may be extended from the 6 -inch SSFM along Shideler Parkway to the proposed 6 -inch SSFM along Yosemite Avenue to facilitate flow diversion from the LIP Lift Station as needed. The total length of the proposed force main, covering all three connections, is approximately 2, 400 linear feet.

Along with the proposed force mains and connections, a
thorough evaluation of the existing infrastructure, including force mains, pump stations, and connecting to the LCTF, is anticipated. The project will also include installing automated systems to enable remote monitoring and control of intertie operations through the City' s SCADA system.

SCOPE OF WORK
Task 1- Project Management and Administration
This task includes management of our staff and resources, providing and maintaining the project schedule and milestone timelines, reporting and monthly invoicing, ongoing coordination efforts between the design team and the City, meetings, and other work within this scope to ensure a successful project. Meetings budgeted under this task include: Kickoff meeting, Project review meeting to discuss the results of Task 3 - Basis of Design Report, Review meetings to discuss the 30%, 60%, 90% and 100% submittals.

Deliverables: Meeting agendas and minutes, assuming seven meetings, Project Schedule and milestones timeline, Invoices with Progress Reports, and Public Outreach Documents.

Task 2 — Information Collection and Review
Thorough research to obtain all available utility documents within the project area for all applicable agency and utility companies shall be conducted. A field site visit will be conducted to collect visible information of the project site. A list and map of all underground and aboveground utilities and facilities in the project areas will be prepared and utility requests will be initiated and information obtained before any field investigations are done. City data and information regarding site topography and soils will be reviewed. Topographic survey, geotechnical investigations, utility investigations through potholing and Ground Penetrating Radar ( GPR).

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I Al Deliverables: Electronic (AutoCAD Format) of topographic survey, utility data and maps. Electronic format of KMZ file/ report of GPR utility locations and potholing report. Electronic format of the Draft and Final Geotechnical Report.

Assumptions: The City will obtain necessary rights - of -entry to complete field investigations and will waive or pay required encroachment permit fees.

Task 3 — Basis of Design Report
A Basis of Design Report will be prepared. The report will summarize the findings from preliminary meetings, background research, and field investigations and provide recommendations for the design of the intertie and force mains. The report aims to define the overall project goals, design intent, and the detailed design criteria for all project components, systems, and subsystems. The report will include relevant field collection data, an assessment of the physical attributes of the existing system and infrastructure, provide limitations/ obstacles, existing capacity, design flow rate, surge pressure needs and velocity for design flow, pump and system curves for operating pressures and velocity, potential sources of connection for SSI and Shideler Parkway Development, a site layout determination, an opinion of probable construction cost, and identification of permit requirements for implementing the Project.

Deliverables: Draft Basis of Design Report, Final Basis of Design Report in PDF format.

Task 4 — Plans, Specifications, and Estimates
Black Water will prepare improvement plans, specifications, and cost estimates for the Project. The improvement plans will provide all information required to construct the project, including mitigation measures to address the key risk factors identified in the Basis of Design Report. Black Water will submit 30-, 60-, 90-, and 100 -percent for review and comment by the City. Specifications and estimates will be included with each submittal. A final set of bid documents will be provided to the City.

Deliverables: 30-, 60-, 90-, 100 -percent engineer stamped and signed PS& Eto scale ( 24" x36") in PDF format.

Project bid schedule.

Assumptions: The City will provide the front end sections including the Notice Inviting Bids and the City' sstandard construction contract specifications and insurance requirements.

Task 5 - Permitting and Environmental
During the development of the Basis of Design Report, Black Water will identify permits, such as building and encroachment permits, that will be required for the construction of the project. Black Water will confirm the environmental requirements that apply to this project. Requirements for additional permits from Union Pacific Railroad and other regulatory agencies will be researched, and permit applications will be prepared if required. The City will be responsible for paying permit fees.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I A2 Task 6 — Bidding Assistance
During bidding of the project, Black Water will provide responses to inquiries from prospective bidders and prepare addenda as required and provide conformed documents, including a set of plans incorporating any changes addressed in addendums. Black Water shall produce a digital copy of the construction package, signed and stamped as " Conformed Set." Black Water will attend the pre -bid meeting as well.

Deliverables: Conformed documents ( electronic copy), RFI responses, and addenda.

Task 7 — Construction Management Assistance
Black Water will attend the pre -construction meeting and present the technical engineering information to the contractor. During construction, Black Water will review and respond to contractor submittals, respond to Requests for Information ( RFIs) that arise during construction, prepare ASI' sand/ or ESI' s as required. Black Water will attend construction meetings as needed and attend a final walk- through meeting and prepare a final punch list. Black Water will also provide As- Builts/ Record Drawings showing appropriate record information based on project annotated record documents received from Contractor and furnish such Record Drawings to Owner.

Deliverables: RFI responses, submittal review documents, ASI/ ESI' s, final punch list, final as- built/ record drawings in AutoCAD and PDF format. Monument Record of Survey.

Schedule
A timeline for completion is shown on page 2. A detailed schedule will be provided upon project award.

CITY OF LATHROP I MCKINLEY AVENUE FORCEMAIN INTERTIE PROJECT DESIGN I A3