CONSOLIDATED TREATMENT FACILITY (CTF)
PHASE 3 EXPANSION UPDATE
CITY COUNCIL REGULAR MEETING | SEPTEMBER 8, 2025 | ITEM: 2.4 1 2

BACKGROUND
Roth Rd
Manila Rd
• Phase 3 Expansion: Add 2 Million
Gallons per Day (MGD) to the existing 2
MGD of wastewater treatment capacity.
• Need: Ensure sufficient wastewater
treatment capacity to keep new
development moving.
• Cost/Funding: $42,283,240; 20% City /
80% River Islands
3 PROJECT MILESTONES
Project Milestone Milestone Date
Project Creation June 2021
Bid Advertisement June 2024
Award Construction Contract August 2024
Begin Construction September 2024
Complete Construction Spring 2026
4 PROJECT VIDEOS
• Drone Timelapse
• Static Timelapse