Cities Index.
item_5.4_create_seventh_st._parking_rehabilitation_cip_ps_26-31

Lathrop City Council
April 13, 2026

Document
item_5.4_create_seventh_st._parking_rehabilitation_cip_ps_26-31
Meeting
April 13, 2026
Body
Lathrop City Council
Original file
1.1 MB
Text extracted from the city's file for reading and search. Open the original on www.ci.lathrop.ca.us. That file is the official record.

1 REVIEW AND CONSIDER CREATION OF SEVENTH STREET PARKING REHABILITATION, CIP PS 26-31, APPROVE MASTER AGREEMENT AND TASK ORDER NO.1 WITH GDR ENGINEERING FOR DESIGN SERVICES

AND APPROVE A BUDGET AMENDMENT

CITY COUNCIL REGULAR MEETING
APRIL 13, 2026 | ITEM 5.4
1 BACKGROUND
 On February 9, 2026, City Council approved the inclusion of asphalt parking and sidewalk reconstruction at the
southwest corner of Seventh Street and K Street into FY 2023-2024 Pavement Maintenance, Capital Improvement
Project (CIP) PS 24-05.
 Council also expanded the scope of asphalt and sidewalk work to K Street with a crosswalk on K Street and
approved a budget amendment of $200,000 to fund the
work.
2 EXISTING CONDITIONS
3 UPDATED PROJECT SCOPE
4 ENGINEER’S ESTIMATE
5 ITEM # BID ITEM QUANTITY UNITS UNIT PRICE ITEM PRICE
1 Mobilization, Bonds & Insurance 1 LS $40,000.00 $50,000.00 2 Traffic Control 1 LS $32,000.00 $38,000.00
3 Remove/Offhaul/Dispose 3" Depth of Existing Asphalt 5,300 SF $11.00 $58,300.00 4 Remove/Offhaul/Dispose 2"Depth of AB / Soil 5,300 SF $4.30 $22,790.00 5 Remove/Offhaul/Dispose of Existing PCC Sidewalk 1,260 SF $22.50 $28,350.00 6 Install Glass Grid for Hot Mix Asphalt 4,700 SF $9.50 $44,650.00 7 Install Storm Drain Catch Basin 2 EA $6,000.00 $12,000.00 8 Connect Storm Drain Catch Basin to Existing Storm Line 2 EA $1,500.00 $3,000.00 9 Clean Existing Storm Drain Line 1 LS $800.00 $800.00
10 Construct Concrete Pedestrian Bulbout w/ ADA Ramp & Truncated Domes 1 EA $26,000.00 $26,000.00 11 Construct Concrete Valley Gutter 230 LF $31.00 $7,130.00 12 Supply/Install/Compact Aggregate Base @ 5" Depth 4,700 SF $16.50 $77,550.00 13 Place Hot Mix Asphalt - 3" Single Lift 89 TON $250.00 $22,250.00 14 Construct 5' Wide Concrete Sidewalk w/ Vertical Curb 1,260 SF $29.00 $36,540.00 15 Construct ADA Curb Ramp 2 EA $7,300.00 $14,600.00
16 Thermoplastic Crosswalk - 12" White Line 70 LF $8.00 $560.00 17 Thermoplastic White Line Hatching 240 LF $6.00 $1,440.00 18 Thermoplastic Striping Parking Spaces 12 EA $300.00 $3,600.00 19 Thermoplastic Striping Parking Space - ADA 1 EA $400.00 $400.00 SUB TOTAL: $447,960.00
10% CONTINGENCY: $44,796.00
TOTAL: $492,756.00

RECOMMENDATION
6 Staff request that City Council review and consider the updated Project scope and cost.

If Council elects to approve the Project, staff request that City Council create Seventh Street Parking
Rehabilitation, CIP PS 26-31, approve a Master
Agreement and Task Order No. 1 with GDR for $48,250
for design and construction support services, and
approve a budget amendment of $350,000 from Street
Reserves to the Project.

NEXT STEPS
Upon completion of the design, staff will formally solicit bids for the Project’s construction. Based upon the schedule submitted by GDR, staff anticipates bringing a construction contract and budget amendment request to Council for
approval at the September 14, 2026 City Council Regular Meeting.
7

← All documents from this meeting