Review and Consider Modifications to
Spartan Way Design and Approval of
Change Order No. 2 with United Pavement
Maintenance, Inc and Budget Amendment
for CIP PS 26-20, Spartan Way Traffic
Safety Enhancements
CITY COUNCIL REGULAR MEETING
MAY 11, 2026 | ITEM: 5.9
1 1
Background
• October 13, 2025: Council approved creation of
CIP PS 26-20 for the installation of a raised
crosswalk, median fencing, restriping and bike lane
barriers to reduce vehicle speeds and improve
pedestrian safety
• December 8, 2025: Council approved a
construction contract with Cervantes Landscape
Services, Inc for the installation of the median
fence
• December 8, 2025: Council approved the
purchase of the bike lane barriers
• January 12, 2026: Council approved a
construction contract with United Pavement
Maintenance, Inc for the installation of the raised
crosswalk, restriping, and bike lane barriers
• March 13, 2026: Work began and was
substantially completed on March 23, 2026
2 /
Vehicle Speed
3 Direction
85th
Percentile
Before
Project (mph)
85th
Percentile
After Project
(mph)
Change
(mph)
Eastbound 38 30 -8
Westbound 42 34 -8
Average Speed After Project: 25 mph for Eastbound and 29 mph for Westbound Anticipated
Collisions
◦ FHWA Crash Modification Factor (CMF)
◦ 1.694 for lane narrowing from 11 feet to 9 feet
and addition of physical barriers
◦ Pre-project collision rate was two collisions per
year
◦ Post-project collision rate is expected to be
1.694 x 2 = 3.39
◦ Collision rate expected to decrease with time
as drivers become familiar with the changes
◦ Collision type is expected to change since
vehicle speeds have been reduced.
4 PostProject
Collisions
◦ 4 total reported collisions since completion
◦ Collision type and severity changed as
expected
◦ Pre-project: ½ of the collisions resulted in
minor injuries
◦ Post-project: No reported injuries
◦ Primary cause of post-project collisions is
distracted driving and drivers not staying in
the travel lane
5 Collision Timeline
6 24 Mar.
Unsafe Movement
31 Mar.
Unsafe Movement
7 Apr.
Distracted Driving
14 Apr.
Unsafe Movement
No reported collisions between April 14th and May 11th
Option to
Modify
Spartan Way
Design
◦ Move barriers one foot to change lane width from 9
feet to 10 feet
◦ Additional recovery zone before vehicles hit the barrier ◦ Vehicle speed may increase
◦ Cost for United Pavement Maintenance Change Order
#2 is $40,832
7 City Staff Request Council to:
Review the updated speed data and traffic collision analysis and provide direction regarding potential modifications to the Spartan Way design. If City Council elects to proceed with the modifications, staff request City Council approve City Manager to execute a Change Order with United Pavement Maintenance for $40,832 to move the barriers and a budget amendment of $50,000 from the Measure C Fund to the Project.