2026-10-12_item_4.12_approve_emerg._change_order_no._1_with_hale_construction_inc._and_task_orders_1-4_with_engeo_inc._for_cip_gg_23-11

Lathrop City Council
October 12, 2026

Document
2026-10-12_item_4.12_approve_emerg._change_order_no._1_with_hale_construction_inc._and_task_orders_1-4_with_engeo_inc._for_cip_gg_23-11
Meeting
October 12, 2026
Body
Lathrop City Council
Pages
3
Original file
1.7 MB
Text extracted from the city's file for reading and search. Open the original on www.ci.lathrop.ca.us. That file is the official record.

ITEM 4. 12

CITY MANAGER' S REPORT
OCTOBER 12, 2026 CITY COUNCIL REGULAR MEETING
ITEM: APPROVE EMERGENCY CHANGE ORDER NO. 1 WITH
HALE CONSTRUCTION, INC. AND TASK ORDER NO. 1-
4 WITH ENGEO, INC. FOR LATHROP ANIMAL CENTER,
CIP GG 23- 11 AND ASSOCIATED BUDGET

AMENDMENT
RECOMMENDATION: Adopt a Resolution to Approve Emergency Change Order No. 1 with Hale -Construction, Inc. and Task
Order No. 1-4 with ENGEO, Inc. for the Lathrop
Animal Center, CIP GG 23- 11 and Associated Budget
Amendment
SUMMARY:

On August 10, 2026, the City Council approved a construction contract with Hale Construction, Inc. ( Hale) for the Lathrop Animal Center, CIP GG 23- 11 (Project).

Construction began in late September 2026.

In preparation for construction, staff identified a conflict between the proposed temporary sewer and storm drain connections and future Pacific Gas and Electric Company ( PG& E) infrastructure. The temporary connections must be eliminated and the permanent infrastructure constructed to maintain essential public services to the Project. Staff requested a proposal from Hale to construct the revised sewer and storm drain facilities for an amount not to exceed $ 1, 061, 715 plus a 15% contingency of $ 159, 258.

The Project also requires specialized construction engineering services, including Stormwater Pollution Prevention Plan ( SWPPP) services and inspection of topside and underground construction. Staff requested proposals from ENGEO, Inc. (ENGEO), under the City' smaster agreement for construction engineering services approved on August 5, 2025.

Staff recommend that the City Council approve Emergency Change Order No. 1 ( ECO No. 1) with Hale in an amount not to exceed $ 1, 220, 973 and approve the associated budget amendment. Staff also recommend that the City Council approve Task Orders No. 1-4 with ENGEO in a combined amount not to exceed $ 368, 500 to provide construction engineering services for the Project.

BACKGROUND:

On January 9, 2023, the City Council approved the creation of the Project. LDA Partners prepared the plans and specifications, and the Project was advertised for CITY MANAGER' SREPORT PAGE 2
OCTOBER 12, 2026 CITY COUNCIL REGULAR MEETING
APPROVE EMERGENCY CHANGE ORDER NO. 1 WITH HALE CONSTRUCTION, INC. AND TASK ORDER NO. 1-4 WITH ENGEO, INC. FOR LATHROP ANIMAL CENTER, CIP GG 23- 11 AND ASSOCIATED BUDGET AMENDMENT
bids on June 26, 2026. On August 10, 2026, the City Council approved a construction contract with Hale, and construction began in late September 2026.

The Project design included temporary sewer and storm drain connections behind the westerly sidewalk instead of installing the permanent, larger pipes in Stanford Crossing Drive. Those larger pipes are intended to serve future development in the Central Lathrop Phase 2 Specific Plan area ( CLSP Phase 2), north of Dos Reis Road.

As staff coordinated the Project' s electrical connections with PG& E, staff identified a spatial conflict between the proposed temporary sewer and storm drain connections and future PG& E service infrastructure. Accordingly, ECO No. 1 will replace the temporary connections with permanent, larger sewer and storm drain pipes in Stanford Crossing Drive to maintain essential public services to the Project.

Hale proposed to construct the revised sewer and storm drain facilities for an amount not to exceed $ 1, 220, 973. Because the facilities in Stanford Crossing Drive will also benefit future development in CLSP Phase 2, staff anticipates that the City will be reimbursed for the costs associated with ECO No. 1 when that area develops.

The Project requires specialized construction engineering services, including SWPPP services and inspection of topside and underground construction. The City maintains a master agreement with ENGEO for construction engineering services on City capital improvement projects. Staff requested proposals from ENGEO for the services needed to support this Project.

The proposed task orders and associated costs are:

Task Order Scope of Services
No. 1 SWPPP Services
No. 2 Topside Inspection Services
No. 3 General Underground Inspection
No. 4 Stanford Crossing Underground Insp.

Total Construction Engineering Services
Amount
68, 500
80, 000
70, 000
150, 00
368, 500
Staff recommend that the City Council approve ECO No. 1 with Hale in an amount not to exceed $ 1, 220, 973, approve the associated budget amendment, and approve Task Orders 1-4 with ENGEO in a combined amount not to exceed $ 368, 500.

REASON FOR RECOMMENDATION:

ECO No. 1 is necessary to avoid conflicts with future PG& Einfrastructure and maintain essential public services to the Project. The proposed ENGEO task orders will provide SWPPP management and special inspectionsneeded to support ongoing construction.

CITY MANAGER' SREPORT PAGE 3
OCTOBER 12, 2026 CITY COUNCIL REGULAR MEETING
APPROVE EMERGENCY CHANGE ORDER NO. 1 WITH HALE CONSTRUCTION, INC. AND TASK ORDER NO. 1-4 WITH ENGEO, INC. FOR LATHROP ANIMAL CENTER, CIP GG 23- 11 AND ASSOCIATED BUDGET AMENDMENT
FISCAL IMPACT:

Staff is requesting that the City Council approve a budget amendment totaling 1, 220, 973 for ECO No. 1, which includes the construction of the required infrastructure to maintain essential public services to the Project including water, sewer, and storm drain services. The costs are as follows:

Water:

Sewer:

Storm Drain:

Total:
113, 629
441, 856
665, 488
1, 220, 973
Future development will reimburse the City for its proportionate share of these infrastructure costs as development occurs.

Sufficient funds are available in the Water Operating Fund ( 5620) and Sewer Connection Fee Fund ( 6030) to cover their respective costs. However, the Storm Drain Connection Fee Fund ( 2280) does not have sufficient funds to cover the $ 665, 488 storm drain cost. Staff is therefore recommending that the General Fund ( 1010) temporarily fund the storm drain shortfall, with the understanding that future development will reimburse the City for its proportionate share.

Additionally, on January 9, 2023, the City Council approved Resolution 23- 5205, authorizing $ 7, 498, 000 for the Lathrop Animal Center. The Municipal Services Fund currently has sufficient funds to reduce the outstanding interfund loan by $ 665, 488.

This reduction will offset the amount of General Fund funding needed for the storm drain shortfall.

The following budget and accounting entries are required:

Decrease Interfund Loan Receivable
1010-41- 00-0
Decrease Interfund Loan Payable
2270-05- 00-0
Increase Due from Others
1010-31- 0-0
Increase Due to Others
2280-03- 01-0
665, 488
665, 488
665, 488
665, 488
CITY MANAGER' SREPORT PAGE 4
OCTOBER 12, 2026 CITY COUNCIL REGULAR MEETING
APPROVE EMERGENCY CHANGE ORDER NO. 1 WITH HALE CONSTRUCTION, INC. AND TASK ORDER NO. 1-4 WITH ENGEO, INC. FOR LATHROP ANIMAL CENTER, CIP GG 23- 11 AND ASSOCIATED BUDGET AMENDMENT
Increase Revenue - CFF - North Central Lathrop - Dos Reis 2280- 5- 90- 318- 04- 73 $ 665, 488
Increase Transfer Out
6030- 9900-90- 9010
5620- 9900-90- 9010
2280- 9900-90- 9010
441, 856
113, 629
665, 488
Increase Transfer In
3010- 9900- 393- 0000 GG 23- 11 $ 1, 220, 973
Increase Expenditures
3010- 8000- 420- 10 GG 23- 11 $ 1, 220, 973
ATTACHMENTS:

A. Resolution to Approve Emergency Change Order No. 1 with Hale Construction, Inc. and Task Order No. 1-4 with ENGEO, Inc. for the Lathrop Animal Center, CIP GG 23- 11 and Associated Budget Amendment
B. Emergency Change Order No. 1
C. Task Order No. 1 - SWPPP Services
D. Task Order No. 2 - Topside Inspection Services
E. Task Order No. 3 - Underground Inspection Services
F. Task Order No. 4 - Stanford Crossing Underground Inspection Services CITY MANAGER' SREPORT ! PAGE 5
OCTOBER 12, 2026 CITY COUNCIL REGULAR MEETING
APPROVE EMERGENCY CHANGE ORDER NO. 1 WITH HALE CONSTRUCTION, INC. AND TASK ORDER NO. 1-4 WITH ENGEO, INC. FOR LATHROP ANIMAL CENTER, CIP GG 23- 11 AND ASSOCIATED BUDGET AMENDMENT
APPROVALS:
064,
BraciTaylor Date
Public Works Director/ City Engineer
iVJ40laoalp Cari Jam
Finance ctor
Thomas Hedegard
Deputy City Manager
Date
Date
10 • Co • 2OZCo
Michael King Date
Assistant City Manager
o • a 2.6
Salvador Navarrete Date
City Attorney
Stephen J. Salvatore Date
City Manager
RESOLUTION NO. 26-

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LATHROP TO APPROVE EMERGENCY CHANGE ORDER NO. 1 WITH HALE CONSTRUCTION, INC. AND TASK ORDER NO. 1-4 WITH ENGEO, INC. FOR THE LATHROP ANIMAL CENTER, CIP GG 23- 11 AND ASSOCIATED BUDGET AMENDMENT WHEREAS, on January 9, 2023, the City Council approved the creation of CIP GG 23- 11, Lathrop Animal Center ( Project). LDA Partners prepared the plans and specifications, and the Project was advertised for bids on June 26, 2026. On August 10, 2026, the City Council approved a construction contract with Hale Construction, Inc. (Hale), and construction began in late September 2026; and WHEREAS, the Project design included temporary sewer and storm drain connections behind the westerly sidewalk instead of installing the permanent, .larger pipes in Stanford Crossing Drive. Those larger pipes are intended to serve future development in the Central Lathrop Phase 2 Specific Plan area ( CLSP Phase 2), north of Dos Reis Road; and
WHEREAS, as staff coordinated the Project' selectrical connections with Pacific Gas & Electric ( PG& E), staff identified a spatial conflict between the proposed temporary sewer and storm drain connections and future PG& Eservice infrastructure.

Accordingly, Emergency Change Order No. 1 ( ECO No. 1) will replace the temporary connections with permanent, larger sewer and storm drain pipes in Stanford Crossing Drive to maintain essential public services to the Project; and WHEREAS, Hale proposed to construct the revised sewer and storm drain facilities for an amount not to exceed $ 1, 061, 715 plus a 15% contingency of 159, 258 for a total cost of $ 1, 220, 973. Because the facilities in Stanford Crossing Drive will also benefit future development in CLSP Phase 2, staff anticipates that the City will be reimbursed for the costs associated with ECO No. 1 when that area develops; and
WHEREAS, the Project requires specialized construction engineering services, including SWPPP services and inspection of topside and underground construction.

The City maintains a master agreement with ENGEO for construction engineering services approved on August 5, 2025. Staff requested proposals from ENGEO for the services needed to support this Project. The proposed task orders and associated costs are:

Task Order Scope of Services Amount
No. 1 SWPPP Services
No. 2 Topside Inspection Services
No. 3 General Underground Inspection
No. 4 Stanford Crossing Underground Insp.

Total Construction Engineering Services
and
68, 500
80, 000
70, 000
150, 00
368, 500
WHEREAS, sufficient funds for ENGEO' sservices have been included in the adopted Fiscal Year 2026/7 budget for CIP GG 23- 11; therefore, no budget amendment is required for special inspections, only approval of the task orders; and WHEREAS, staff is requesting that the City Council approve a budget amendment totaling $ 1, 220, 973 for ECO No. 1, which includes the construction of the required infrastructure to maintain essential public services to the Project including water, sewer, and storm drain services. The costs areas follows:

Water: $ 113, 629
Sewer: $ 441, 856
Storm Drain: $ 665, 488
Total: $ 1, 220, 973
and
WHEREAS, sufficient funds are available in the Water Operating Fund ( 5620) and Sewer Connection Fee Fund ( 6030) to cover their respective costs. However, the Storm Drain Connection Fee Fund ( 2280) does not have sufficient funds to cover the 665, 488 storm drain cost. Staff is therefore recommending that the General Fund 1010) temporarily fund the storm drain shortfall, with the understanding that future development will reimburse the City for its proportionate share; and WHEREAS, on January 9, 2023, the City Council approved Resolution 23- 5205, authorizing $ 7, 498, 000for the Lathrop Animal Center. The Municipal Services Fund currently has sufficient funds to reduce the outstanding interfund loan by $ 665, 488.

This reduction will offset the amount of General Fund funding needed for the storm drain shortfall; and
WHEREAS, the following budget and accounting entries are required:

Decrease Interfund Loan Receivable
1010-41- 00-0
Decrease Interfund Loan Payable
2270-05- 00-0
Increase Due from Others
1010-31- 0-0
Increase Due to Others
2280-03- 01-0
665, 488
665, 488
665, 488
665, 488
Increase Revenue - CFF - North Central Lathrop - Dos Reis 2280- 5- 90- 318- 04- 73 $ 665, 488
Increase Transfer Out
6030- 9900-90- 9010
5620- 9900-90- 9010
2280- 9900-90- 9010
Increase Transfer In
3010- 9900- 393- 0000
Increase Expenditures
3010- 8000- 420- 10
441, 856
113, 629
665, 488
GG23- 11 $1, 220, 973
GG23- 11 $1, 220, 973
NOW, THEREFORE, BE IT RESOLVED, the City Council of the City of Lathrop does hereby approve Emergency Change Order No. 1 with Hale Construction, Inc. included as Attachment B to the City Manager' sReport and the associated budget amendment; and
NOW, THEREFORE, BE IT FURTHER RESOLVED, the City Council of the City of Lathrop does hereby approve Task Orders 1 through 4 with ENGEO, Inc.

The foregoing resolution was passed and adopted this 12h day of October, 2026, by the following vote of the City Council, to wit:

AYES:

NOES:

ABSENT:

ABSTAIN:

ATTEST:

Teresa Vargas, City Clerk
Paul Akinjo, Mayor
APPROVED AS TO FORM:

Salvador Navarrete, City Attorney

ATTACHMENT
CHANGE ORDER. JUSTIFICATION • .

LATH_ ROP ANIMAL. CEN• TER; CIP,
E OR
GG 2•3- 11
CHANGE NO. 1
DATE: October 12, 2026.

On August 10, 2026, the Lathrop City Council adopted Resolution 26- 6086, awarding a 12, 750, 859 construction contract for the Lathrop Animal Center ( CIP GG 23- 11) to Hale Construction,
authorization.

Inc., and establishing a $ 1, 912, 629project contingency under the City Manager' s On October 12, 2026, city Council adopted Resolution 26- , approving an additional 1, 220, 973 in supplementalcontingency funds to cover Change Order No. 1 and other unforeseen items that may arise. This increased the City Manager' stotal change order authorization to $3, 133, 6O2 to complete project construction.

Change Order No: 1 Details::

PCO- 1 ($1, 061, 75): Prior to construction,_ staff identified a conflict between proposed temporary utility connections and future Pacific Gas and Electric Company ( PG& E) infrastructure. To maintain essential public services to the facility, staff requested a proposal from Hale Construction, Inc: to construct the permanentsewer and storm drain facilities instead of temporary connections, for an amount not to exceed'$ 1, 061, 715.

For the reasons outlined above, the Engineering Department requests that the City Manager approve Change Order No. 1to ensurethe project proceeds as planned., Submitted by:

Project Manager
Approved by:

Brad Taylor, PE., Public Works Director / City Engineer For Internal Use Only)
ORIGINAL CONTINGENCY AMOUNT 1, 912, 629
SUPPLEMENTAL CONTINGENCY 1, 220, 973.

CONTINGENCY TO DATE 3, 133, 602
TOTAL COST FOR CHANGE ORDER # 1 1, 061, 715
REMAINING CONTINGENCY AFTER CHANGE ORDER #1 2, 071, 887 City of Lathrop
390 Towne Centre Dr
Lathrop, California 95330
Phone: ( 209) 941- 7200
CCO # 001
Project: GG 23- 11 - Lathrop Animal Center
15005 Stanford Crossing
Lathrop, California 95330
Contract Change Order #001: CE #001 - Stanford Crossing Extension CONTRACT COMPANY:

DATE CREATED:

CONTRACT STATUS:

DESIGNATED REVIEWER:

DUE DATE:

INVOICED DATE:

SCHEDULE IMPACT:

Hale Construction Inc.
13791 Castle Rd.

Manteca, California 95336
10/ 01/ 2026
Approved

SIGNED CHANGE ORDER
RECEIVED DATE:

DESCRIPTION:

CE #001 - Stanford Crossing Extension
ATTACHMENTS:

Final Stanford crossing E tgnsio0_ C, O__ Regu_ est Rayised; pdf CONTRACT FOR:

CREATED BY:

REVISION:

REVIEWED BY:

REVIEW DATE:

PAID DATE:

EXECUTED:

SC- GG 23- 11- 001 :Prime
Tyler Milton ( City of Lathrop - HQ)
0 10/ 01/ 2026
No
TOTAL AMOUNT: 1, 061, 714. 50
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:

PCO # Title Schedule Impact Amount
001 CE # 001 - Stanford Crossing Extension 1, 061, 714. 50 Total: 1, 061, 714. 50
CHANGE ORDER LINE ITEMS:

PCO # 001: CE # 001 - Stanford Crossing Extension
Budget Code Description Qty Units Unit Cost . Subtotal
1 PC. MCO Cost 20" C900 470. 0 265. 00 124, 550. 0
2 PC. MCO Cost SS Manhole 2. 0 28, 000. 56, 000.
3 PC. M CO Cost 72" RCP 202. 0 610. 00 123, 220. 0
4 PC. M CO Cost 60" HDPP 276. 0 325. 00 89, 700. 0
5 PC. M CO Cost Storm Drain Manhole ( Custom Build) 3. 0 49, 000. 147, 000, 6 PC. M CO Cost Drain Inlets 2. 0 18, 500. 0 37, 000.
7 PC. M CO Cost 20" C900 Reclaim 78. 0 124. 00 9, 672. 00 8 PC. M CO Cost 20" Gate Valve 4. 0 12, 900. 0 51, 600. 0 9 PC. M CO Cost 20" x 20" Cross 1. 0 6, 500. 0 6, 500. 0 10 PC. M CO Cost 12" C900 Domestic 78. 0 146: 00 11, 388. 00 11 PC. M CO Cost 12" Gate Valve 2. 0 5, 900. 0 11, 800. 0 12 PC. M CO Cost 12" Tee 1. 0 4, 800. 0 4, 800. 0
13 PC. MCO Cost Fire Hydrant 2. 0 14, 000. 28, 000.
14 PC. MCO Cost Blow Off 3. 0 9, 000. 27, 000.

City of Lathrop Page 1 of 2 Printed On: 10// 2026 02 :35 PM CCO # 001
Budget Code Description Qty Units Unit Cost Subtotal
15 PC. HC CO Cost De -watering 1. 0 195, 000. 195, 000.

Subtotal: 923, 20. 0
Contractor Fee ( 10. 00% ):92, 323. 00
Overhead and Bond Premium (5. 00% ): 46, 161. 50
Grand Total: 1, 061, 714. 50
The original ( Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be increased by this Change Order in the amount of The. nw contract sum including this Change Order will be The contract time will not be changed by this Change Order.

City of Lathrop
390 Towne Centre Dr
Lathrop, California 95330

SIGNATURE DATE
12, 743, 850. 95

0.0 12, 743, 850. 95
1, 061, 714. 50
13, 805, 565. 4
Hale Construction Inc.
13791 Castle Rd. .

Manteca, Califomia 95336

SIGNATURE DATE
City of Lathrop Page 2 of 2 Printed On: 10// 2026 02 :35 PM Unit Unit Price Total
Sewer
20" C900
SS Manhole
Subtotal
Dewatering, Fee, Overhead
Total
470 $ 265. 00 $124, 550. 0
2 $ 28, 000. $56, 000.
180, 550. 0
82, 680. 78
Storm
72" RCP
60" HDPP
SD Manhole
Inlets
Subtotal
Dewatering, Fee, Overhead
Total
202 $ 610. 00 $123, 220. 0
276. $ 325. 00 $ 89, 700. 0
3 $ 49, 000.. $147, 000.
2 $ 18, 500. 0 $37, 000.
396, 920. 0
181, 764. 92
Water
20" C900
20" valve
20x20 cross
Subtotal
Dewatering, Fee, Overhead
Total
78 $ 124. 00 $ 9, 672. 00
4 $ 12, 900. 0 $51, 600. 0
1 $ 6, 500. 0 $ 6, 500. 0
67, 772. 00
31, 035. 40
Recycled Water
12" C900
12" valve
12" tee
Hydrant
Blow off
Subtotal
Dewatering, Fee, Overhead
Total
78 $ 146. 00 $ 11, 388. 00
2 $ 5, 900. 0 $11, 800. 0
1 $ 4, 800. 0 $ 4, 800. 0
2 $ 14, 000. $28, 000.
3 $ 9, 000.0 $27, 000.
82, 988. 00
38, 003. 39
mug
Subtotal ( less dewat, fee, over)
Dewatering
Contractor Fee
Overhead
728, 230. 0
Total $ 1, 061, 714. 50
1 $ 195, 000. $195, 000.

10. 00%

5. 00%

0. 1 $ 92, 323. 00

0.5 $ 46, 161. 50
City of Lathrop
390 Towne Centre Dr
Lathrop, California 95330
P: (209) 941- 7200
CHANGE EVENT# 001 Stanford Crossing Extension
Project: GG 23. 11 - Lathrop Animal Center
15005 Stanford Crossing
Lathrop, California 95330
Origin:

Date Created: 10// 2026 Created By: Tyler Milton
Status: Open Scope: Out ofScope
Type: I Allowance Change Reason: Existing Condition
Description: This work is required to extend the roadway and underground utility network beyond the footprint of the active Animal Center construction site. Executing this scope at this time avoids future service disruptions to the Animal Center and adjacent municipal facilities, which would inevitably occur tithe roadway and utility work were deferred until a future commercial or residential developer assumed construction responsibility. Extending these critical • utilities concurrently with ongoing regional operations prevents costly retrofit operations and traffic/ utility downtime.

Attachments: Final Stanford crossing Extension C. O. Request Revised. pdf.

CHANGE EVENT LINE ITEMS
Budget: Code Vendor /. Contract
Funding . Cost
Latest ._
UOM: QTY Unit Cost ROM Funding CCO PriceQTY Unit Cost . ROM RFQ Commit. Latest Cost Over/ Budget
Under Mod.

PC. M.

CO. Cost.

Description:
20" C900
PC. M
CO Cost
Hale Construction Inc.

SC- GG23- 11- 001

0. $ 265. 00 $0.0 0.0 470. 0 $265. 00 $124, 550. 0 $ 124, 550. 0 $124, 550. 0 Description:.

SS Manhole
Hale Construction. Inc.

SC- GG 23- 11- 001

0. $28, 000. $0.0 0.0 2. 0 $28, 000. $56, 000. $ 56, 000. $56, 000.

PC. M Hale Construction Inc.

CO Cost SC- GG 23- 11- 001
Description:
72" RCP
PC. M
CO Cost
Description:
60 HDPP

0. $ 0.0 $ 0.0 0.0 202. 0 $610. 00 $123, 220. 0 $ 123, 220. 0 $123, 220. 0, City of Lathrop
Hale Construction Inc.

SC- GG23- 11- 001

0. $ 0.0 $0.0 0.0 276. 0 $325. 00. $89, 700. 0 $ 89, 700. 0 $89, 700. 0

Page 1 of 3 ends

Funding Cost
Budget Code
PC, M
CO Cost
Description:

Storm Drain Manhole
PC. M
CO Cost
Description:

Drain Inlets
PC. M
CO Cost
Description:
20" C900 Reclaim
Vendor ! Contract
Hale Construction Inc.

SC- GG23- 11- 001
Custom Build)
UOM QTY Unit Cost ROM Funding CCO
Latest
Price
QTY Unit Cost ROM RFQ Commit. Latest Cost.

0. $ 0.0 $0.0
Hale Construction Inc.

SC- GG 23- 11- 001
PC. M
CO Cost
Description:
20" Gate Valve
Hale Construction Inc.

SC- GG 23- 11- 001

0. $ 0.0 $0.0

0. $ 0.0 $0.0

0.0 3. 0 $49, 000. $147, 000. $ 147, 000. $147, 000.

Over/ Budget
Under Mod.

0.0 2. 0 $18, 500. 0 $37, 000..

0.0 ' 78. 0 $ 124. 00 $ 9, 672. 00
37, 000. $37, 000.
9, 672. 00 $9, 672. 00
Hale Construction Inc.

SC- GG 23- 11- 001
PC. M
CO Cost
Hale Construction Inc.

SC- GG 23- 11- 001
Description:
20" x 20" Cross
PC. M Hale Construction Inc.

CO Cost SC- GG 23- 11- 001
Description:
12" C900 Domestic
PC. M
CO Cost
Description:
12" Gate Valve
Hale Construction Inc.

SC- GG 23- 11- 001

0. $ 0.0 $0.0

0. $ 0.0 $0.0

0.0 4. 0 $12, 900. 0 $51, 600. 0 51, 600. 0 $51, 600. 0

0.0 1. 0 $ 6, 500. 0 $6, 500. 0 $ 6, 500. 0 $6, 500. 0

0. $ 0.0 $0.0

0. $ 0.0 $ 0.0

0.0 78. 0 $ 146. 00 $11, 388. 00 $ 11, 388. 00 $11, 388. 00

0.0 2. 0 $ 5, 900. 0 $11, 800. 0 11, 800. 0 $11, 800. 0 PC. M
CO Cost
Description:
12" Tee
PC. M
CO Cost
Description:

Fire Hydrant
Hale Construction Inc.

SC- GG 23- 11- 001

0. $ 0.0 $0.0
Hale Construction Inc. 0.

SC- GG 23- 11- 001
PC. M Hale Construction Inc.

CO Cost SC- GG 23- 11- 001
Description:

Blow Off

0.0 $0.0

0.0 1. 0 $ 4, 800. 0 $4, 800. 0

0.0 2M $ 14, 000. $28, 000.
4, 800. 0 $4, 800. 00.
28, 000. $28, 000.

0. $ 0.0 $ 0.0 0.0 3. 0 $ 9, 000. $27, 000. 27, 000. $27, 000.

City of Lathrop Page 2 of 3 Printed on: 10// 2026 at 03:7PM PDT Funding Cost
Budget Code
PC. HC
CO Cost
Description:

De -watering
Grand Totals
City of Lathrop
Vendor I Contract
Hale Construction Inc.

SC- GG 23- 11- 001
UOM QTY Unit Cost ROM Funding CCO
Latest
Price
QTY Unit Cost ROM RFQ Commit Latest Cost

0. $ 0.0 $0.0 0.0 1. 0 $195, 000. $195, 000. $ 195, 000. $195, 000.

Over! Budget
Under Mod.

0.0 $ 0.0 $ 0.0 $ 923, 20. 0 $0.0 $923, 20. 0 $923, 20. 0 ($923, 20. 0) $0.0

Page 3 of 3 ends

ATTACHMENT
C;
NGEO
Expect Excellence

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
DATE: September 3, 2026
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 I info@engeo. com
ENGEO Project No.: 16218. 000.16
Phase: 003
ENGEO Contact: Kenneth Hamilton
PROJECT NAME: City of Lathrop Animal Center
ORIGINAL CONTRACT: City of Lathrop Master Agreement:( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope of Services: As requested, we have prepared this Request for Task Order ( RFTO) for stormwater pollution prevention plan ( SWPPP) services for the City of Lathrop Animal Center project The purpose of our SWPPP services is to satisfy State Water Resources Control Board (SWRCI3) Order WQ 2022. 0057- DWQ (General Permit) for stormwater discharges from sites with a disturbed area greater than tacre.

We will provide the required SWPPP monitoring and reporting services, including QSD and QSP site inspections, weekly delegate inspections, and storm -related delegate inspections, in accordance with the CGP. Our estimated number of site inspections is based on an approximately 60 -week construction schedule, from September 2026 to November 2027.

The actual number of inspections will be .determined by the forecasted precipitation events, project schedule, and Notice of Termination ( NOT) approval timeframe.

Based on the estimated construction schedule and a preliminary risk level assessment, we assume this project SWPPP will be designated as Risk Level 1. This proposal is based on the requirements of Order WQ 2022- 0057- DWQ and includes the following minimum SWPPP tasks:

TABLE 1: Scope of SWPPP Services
TASK 1 SWPPP DEVELOPMENT

1. SWPPP
Development
A final Risk Level Determination will be performed based on the sediment and receiving water risk using the SWRCB- provided GIS Maps and Environmental Protection Agency ( EPA) rainfall erosivity calculations. Once the final Risk Level has been determined; a project -specific SWPPP will be preparedin accordance with the General Permit requirements by an ENGEO Qualified SWPPP Developer. (QSD): Our project -specific SWPPP will include an Erosion and Sediment Control Plan ESCP).

We assume that the project is not subject to Total Maximum Daily Load ( TMDL) requirements specified in the General Permit. We assume that construction dewatering discharge, active treatment systems.

ATS), and passive treatment systems ( PTS) will not be required for this project. If construction dewatering discharge, ATS, or PTS are required, a revision to our scope and fee may be needed.

Following completion of the SWPPP and other Permit Registration Documents ( PRDs), we will file the Notice of Intent ( NOI) to the SWRCB' s SMARTS website for Owner certification. Following NOI approval, we will prepare one hard copy of the SWPPP document for field use.

City of Lathrop
City of Lathrop Animal Center

REQUEST FOR TASK ORDER
16218. 000.16
September 3, 2026

Page 2 ends

TASKS 2 AND' 3 • SITE INSPECTIONS

2. QSD
Inspections.

Our QSD will perform the following on -site visual inspections.

Within 30 days of construction activities beginning
Twice annually ( once between August - October, and once between January - March) Inspections will occur during daylight hours of a normal business work week ( Monday through Friday).

3. QSP and
Delegate
Inspections
Our Qualified SWPPP Practitioner (QSP) will perform the following on -site visual inspections.

Monthly ( routine) inspections
Pre -precipitation event inspections within 72 hours prior to a forecasted qualifying precipitation event ( QPE)
An ENGEO QSP, or an appropriately trained QSP Delegate, will performthe following additional site inspections.

Weekly ( routine) inspections
During- and post -precipitation event inspections:
o During- QPE inspections will be conducted at least once every. 24 -hour period during extended QPEs.
o Post -storm event inspections will be conducted within 96 hours after QPEs with at least

0. 5 inch of measured precipitation.

Inspections will occur during daylight hours of a normal business work week ( Monday through Friday).

TASKS 4 AND 5 REPORTING

4. Annual Reports
By September 1, and continuing annually every year the permit is active, we will prepare an Annual Compliance Report ( ACR) and upload it to SMARTS. The ACR will contain the minimum required elements described in the General Order. We will prepare and upload the ACR for the applicable reporting years ( 2026-027 and 2027-028) for LRP certification.

5. Notice of.

Termination
After construction is complete and disturbed areas have been stabilized, we will prepare a Notice of Termination ( NOT) and submit to SMARTS for LRP certification. The NOT will include a description of the' basis of termination, final QSP inspection report, and photographs documenting the post -construction stabilization, if applicable.

TASK 6 CONSULTATION
Consultation
We will provide additional as -needed consultation for specific requests, such as performing non -routine site inspections, attending meetings, preparing SWPPP Amendments and Changes of Information, sampling for non -visible pollutants and/ or construction dewatering discharges, and other SWPPP needs on a time -and -expense basis.

Estimated Additional Fees: $68, 500

SCOPE OF SERVICES

ADDITIONAL
FEE
FEE
TYPE*
Phase 003: SWPPP
Task 001: SWPPP Development
Includes one hard copy of the SWPPP document.

Task 002: Routine QSD Inspections
Estimated four inspections at $750 each.

Task 003: Routine QSP and Delegate Inspections
Estimated 70 inspections at $ 600 each
10, 500
3, 000
42, 000
LS
U
u
PRINTED NAME:

TITLE:

Steve Harris
City of Lathrop
City of Lathrop Animal Center

REQUEST FOR TASK ORDER
16218. 000.16
September 3, 2026

Page 3 ends

SCOPE OF SERVICES

ADDITIONAL FEE
FEE TYPE*
Task 004: Annual Compliance Reporting
Estimated two reports at $1, 750 each
Task 005: Notice of Termination
Task 006: Consultation
Time -and -expense, as -needed
3, 500
3, 500.
6, 000
U
LS
T&E
LS = lump sum, U = unit cost,. T&E time -and -expense
If you are in agreement with the. scope of services and fees' outlined in this request, please forward a task order to the above -referenced original contract as authorization, for: us to _proceed. All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
DATE:
vkd/ kah/ sdh/ cb
Principal
September 3, 2026

ATTACHMENT
EllGEQ
Expect Excellence

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330.

DATE: September 29, 2026
2633 Camino Ramon, Suite 250,
San Ramon, CA 94583
925) 866- 9000 I info@engeo. com
ENGEO Project No:: 16218. 000.16
Phase: 007
ENGEO Contact: Ken Hamilton
PROJECT NAME: City of Lathrop Animal Shelter - Stanford Crossing Extension CIP Number GG 23-. 11
ORIGINAL CONTRACT: City of Lathrop Master Agreement (ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope -of Services:

We propose to provide construction testing and observation services during construction of topside improvements for the Stanford Crossing Extension on an on -call, as -needed basis as directed by the City of Lathrop. This fee estimate is based on our review of the project plans and specifications and discussions with the City of Lathrop and the project contractor.

We estimate that our services will be required on a part- time basis for a total of approximately 3 months.

Estimated Additional Fees:,
We propose to perform the above -described testing and observation services for topside improvements on a time -and -expense basis estimated at $80, 000.

If you are in agreement with the scope of services and feesoutlined in this request, please forward a task order to the above -referenced original contract as authorization for us to proceed. All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
BY:

PRINTED NAME:. ac Crawford
TITLE:

DATE:
aj/ zac/ ss
Principal
September 29, 2026

ATTACHMENT
E
Expect Excellence —

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne. Centre Drive
Lathrop, CA, 95330
DATE: : September 10,. 2026,
Revised September 29, 2026
PROJECT NAME: City of Lathrop Animal Shelter
CIP Number: GG 23- 11
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 Iinfo@engeo. com
ENGEO Project No.: 16218. 000.16
Phase: 004
ENGEO Contact: Ken Hamilton
ORIGINAL CONTRACT: City of Lathrop Master Agreement ( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope ofServices:

We propose to provide construction testing and" observation services during construction of underground improvements on an on -call, as -needed basis as directed by the City of Lathrop. This fee estimate is based on our review of the project plans and specifications, and discussions with the City of Lathrop and the project contractor. We estimate that our services will be required on a full- time basis for total of approximately 6 weeks.

Estimated Additional Fees:

We propose to perform the above -described testing and observation services for underground improvements on a time -and -expense basis estimated at $ 70, 000
If you are in agreement with the scope of services and fees outlined in this request, please forward a task order to the above -referenced original contract as authorization for us to proceed. All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
BY:

PRINTED NAME:

TITLE:

DATE:
aj/ zac/ ca
Zac Crawford
Principal
September 29, 2026

ATTACHMEN
a, .F- u
GEO
Expect Excellence ;

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA, 95330
DATE: September 29; 2026
PROJECT NAME: City of Lathrop Animal Shelter -. Stanford Crossing Extension CIP Number: GG 23- 11
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 I info@engeo. com
ENGEO Project No.: 16218. 000.16
Phase: 006
ENGEO Contact: Ken Hamilton
ORIGINAL CONTRACT: City of Lathrop Master Agreement ( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope of Services: .

We propose to provide construction testing and observation services during construction of underground improvements for the Stanford Crossing Extension on an on -call, as -needed basis as directed by the City of Lathrop. This fee estimate is based on our review of the project plans and specifications, and discussions with the City of Lathrop and the project contractor. We estimate that our services will be required on a full- time basis for a total of approximately 3 months.

Estimated Additional Fees:.

We propose to perform the above -described testing and observation services for underground . improvementson a time -and -expense basis estimated at $150, 00.

If you are in agreement with the scope of services and fees outlined in this request, please forward a task order to the above -referenced originalcontract as authorization for us to proceed. All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
BY:

PRINTED NAME: Zac Crawford
TITLE:

DATE:
ajlzacica
Principal
September 29, 2026
ATTAC 1HMENT V
a

CITY OF LATHROP
TASK ORDER NO. 1 PURSUANT TO MASTER CONSULTING AGREEMENT WITH ENGEO INC. DATED AUGUST 5, 2025

TO PROVIDE STORMWATER POLLUTION PREVENTION PLAN ( SWPPP) SERVICES FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 THIS TASK ORDER NO. 1, dated for convenience this 12th day of October 2026, is by and made and entered into by and between ENGEO Inc. ("CONSULTANT"), and the City of Lathrop, a California municipal corporation of the State of California C ITY");
RECITALS:

WHEREAS, on August 5, 2025, CONSULTANT entered into a Master Agreement (" AGREEMENT") with the CITY, by which the CONSULTANT has agreed to provide engineering services, testing and observation services, special inspection services, and laboratory testing on an on -call, as -needed basis; and WHEREAS, CONSULTANT is specially trained, experienced, and competent to perform engineering services, testing and observation services, special inspection services, and laboratory testing, which are required by this agreement; and WHEREAS, CONSULTANT is willing to render such engineering services, testing and observation services, special inspection services, and laboratory testing, as hereinafter defined, on the following terms and conditions.

NOW, THEREFORE, CONSULTANT and the CITY agree as follows:

AGREEMENT
1) Incorporation of Master Agreement
This Task Order No. 1 hereby incorporates by reference all terms and conditions set forth in the Master Agreement for Geotechnical Investigations and Engineering Services dated August 5, 2025, unless specifically modified by this Task Order. 2) Scope of Service
CONSULTANT agrees to perform services in accordance with the scope of work and fee proposal provided by CONSULTANT, attached hereto as Exhibit " A" and incorporated herein by reference. CONSULTANT agrees to diligently perform these services in, accordance with the upmost standards of its profession and to CITY' ssatisfaction.

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 1 FOR STORMWATER POLLUTION PREVENTION PLAN ( SWPPP) SERVICES FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11
3) Effective Date and Term
The effective date of Task Order No. 1 is October 12, 2026, and it shall terminate no later than June 30, 2027.
4) Compensation
CITY hereby agrees to pay CONSULTANT hourly rates and other charges not to exceed $ 68, 500 for provide SWPPP Services, described in Exhibit " A" of Task Order No. 1 pursuant to the Master Agreement dated August 5, 2025.

CONSULTANT shall be paid any uncontested sum due and payable within thirty 30) days of receipt of billings containing all information pursuant to Paragraph 5 below. Compensation for any task must be equal to or less than the percentage of task complete. In no event shall CONSULTANT be entitled to compensation beyond what is expressed in this agreement and Exhibit " A", unless a CITY authorized representative has executed a written change order or authorization describing the extra work and payment terms prior to the commencement of the work.
5) Notice to Proceed
Prior to commencing work under this agreement, CONSULTANT shall receive a written " Notice to Proceed" from CITY. A Notice to Proceed shall not be issued until all necessary documents and insurance have been received. CITY shall not be obligated to pay CONSULTANT for any services prior to issuance of the Notice to Proceed.
6) Signatures
The individuals executing this Agreement represent and warrant that they have the right, power, legal capacity, and authority to enter into and to execute this Agreement on behalf of the respective legal entities of the CONSULTANT and the CITY. This agreement shall inure to the benefit of and be binding upon the parties hereto and their respective successors and assigns.

Page 2 of 3 ends

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 1 FOR STORMWATER POLLUTION PREVENTION PLAN ( SWPPP) SERVICES FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11
Approved as to Form: City of Lathrop
City Attorney
Salvador Navarrete Date
Recommended for Approval: City of Lathrop
Public Works Director/ City Engineer
Brad Taylor Date
Approved by: City of Lathrop
Resolution No. 26- 390 Towne Centre Drive
Lathrop, CA 95330
Stephen J. Salvatore Date
City Manager
Consultant: ENGEO, Inc.
17278 Golden Valley Parkway
Lathrop, CA 95330
Fed ID # 94- 1748418
Lathrop Business License # LB -001373- 2025
Signature Date
Print Name and Title
Signature Date
Print Name and Title

Page 3 of 3 ends

EXHIBIT A
EM3EO
Expect Excellence -- —

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
DATE: September 3, 2026
PROJECT NAME: City of Lathrop Animal Center
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 I info@engeo. com
ENGEO Project No.: 16218. 000.16
Phase: 003
ENGEO Contact: Kenneth Hamilton
ORIGINAL CONTRACT: City of Lathrop Master Agreement ( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope of Services: As requested, we have prepared this Request for Task Order ( RFTO) for stormwater pollution prevention plan ( SWPPP) services for the City of Lathrop Animal Center project The purpose of our SWPPP services is to satisfy State Water Resources Control Board ( SWRCB) Order WQ 2022- 0057- DWQ (General Permit) for stormwater discharges from sites with a disturbed area greater than 1 acre.

We will provide the required SWPPP monitoring and reporting services, including QSD and QSP site inspections, weekly delegate inspections, and storm -related delegate inspections, in accordance with the CGP. Our estimated number of site inspections is based on an approximately 60 -week construction schedule, from September 2026 to November 2027.

The actual number of inspections will be determined by the forecasted precipitation events, project schedule, and Notice of Termination ( NOT) approval timeframe.

Based on the estimated construction schedule and a preliminary risk level assessment, we assume this project SWPPP will be designated as Risk Level 1. This proposal is based on the requirements of Order WQ 2022- 0057- DWQ and includes the following minimum SWPPP tasks.

TABLE 1: Scope of SWPPP Services
TASK 1 SWPPP DEVELOPMENT

1. SWPPP
Development
A final Risk Level Determination will be performed based on the sediment and receiving water risk using the SWRCB- provided GIS Maps and Environmental Protection Agency (EPA) rainfall erosivity calculations. Once the final Risk Level has been determined, a project -specific SWPPP will be prepared in accordance with the General Permit requirements by an ENGEO Qualified SWPPP Developer ( QSD). Our project -specific SWPPP will include an Erosion and Sediment Control Plan ESCP).

We assume that the project is not subject to Total Maximum Daily Load ( TMDL) requirements specified in the General Permit. We assume that construction dewatering discharge, active treatment systems ATS), and passive treatment systems ( PTS) will not be required for this project. If construction dewatering discharge, ATS, or PTS are required, a revision to our scope and fee may be needed.

Following completion of the SWPPP and other Permit Registration Documents ( PRDs), we will file the Notice of Intent ( NOI) to the SWRCB' sSMARTS website for Owner certification. Following NOI approval, we will prepare -one hard copy of the SWPPP document for field use.

City of Lathrop
City of Lathrop Animal Center

REQUEST FOR TASK ORDER
16218. 000.16
September 3, 2026

Page 2 ends

TASKS 2 AND 3 SITE. INSPECTIONS

2. QSD
Inspections
Our QSD will perform the following on -site visual inspections.

Within 30 days of construction activities beginning
Twice annually ( once between August - October, and once between January - March) Inspections will occur during daylight hours of a normal business work week ( Monday through Friday).

3. QSP and
Delegate
Inspections
Our Qualified SWPPP Practitioner ( QSP) will perform the following on -site visual inspections.

Monthly (routine) inspections
Pre -precipitation event inspections within 72 hours prior to a forecasted qualifying precipitation event ( QPE)
An ENGEO QSP, or an appropriately trained QSP Delegate, will perform the following additional site inspections.

Weekly ( routine) inspections
During- and post -precipitation event inspections:
o During- QPE inspections will be conducted at least once every 24 -hour period during extended QPEs.
o Post -storm event inspections will be conducted within 96 hours after QPEs with at least

0. 5 inch of measured precipitation.

Inspections will occur during daylight hours of a normal business work week ( Monday through Friday).

TASKS 4 AND 5 REPORTING

4. Annual Reports
By September 1, and continuing annually every year the permit is active, we will prepare an Annual Compliance Report ( ACR) and upload it to SMARTS. The ACR will contain the minimum required elements described in the General Order. We will prepare and upload the ACR for the applicable reporting years ( 2026-027 and 2027-028) for LRP certification.

After construction is complete and disturbed areas have been stabilized, we will prepare a Notice of

5. Notice of Termination ( NOT) and submit to SMARTS for LRP certification. The NOT will include a description of Termination the basis of termination, final QSP inspection report, and photographs documenting the post -construction stabilization, if applicable.

TASK 6 CONSULTATION

6. Consultation
We will provide additional as -needed consultation for specific requests, such as performing non -routine site inspections, attending meetings, preparing SWPPP Amendments and Changes of Information, sampling for non -visible pollutants and/ or construction dewatering discharges, and other SWPPP needs on a time -and -expense basis.

Estimated Additional Fees: $ 68, 500

SCOPE OF SERVICES

ADDITIONAL FEE
FEE TYPE*
Phase 003: SWPPP
Task 001: SWPPP Development
Includes one hard copy of the SWPPP document.

Task 002: Routine QSD Inspections
Estimated four inspections at $ 750 each.

Task 003: Routine QSP and Delegate Inspections
Estimated 70 inspections at $600 each
10, 500 LS
3, 000 U
42, 000 U
City of Lathrop
City of Lathrop Animal Center

REQUEST FOR TASK ORDER
16218. 000.16
September 3, 2026

Page 3 ends

SCOPE OF SERVICES ADDITIONAL FEE
FEE TYPE*
Task 004: Annual Compliance Reporting
Estimated two reports at $1, 750 each
Task 005: Notice of Termination
Task 006: Consultation
Time -and -expense, as -needed
3, 500
3, 500
6, 000
U
LS
T&E
LS = lump sum, U = unit cost, T&E= time -and -expense
If you are in agreement with the scope of services and fees outlined in this request, please forward a task order to the above -referenced original contract as authorization for us to proceed: All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
PRINTED NAME:

TITLE:

Steve Harris
DATE:
vkd/ kah/ sdh/ cb
Principal
September 3, 2026

ATTACHMENT
w

CITY OF LATHROP
TASK ORDER NO. 2 PURSUANT TO MASTER CONSULTING AGREEMENT WITH ENGEO INC. DATED AUGUST 5, 2025

TO PROVIDE CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR

TOPSIDE IMPROVEMENTS FOR THE STANFORD CROSSING EXTENSION, RELATED TO THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 THIS TASK ORDER NO. 2, dated for convenience this 12th day of October 2026, is by and made and entered into by and between ENGEO Inc. ("CONSULTANT"), and the City of Lathrop, a California municipal corporation of the State of California (" CITY"); RECITALS:

WHEREAS, on August 5, 2025, CONSULTANT entered into a Master Agreement AGREEMENT") with the CITY, by which the CONSULTANT has agreed to provide engineering services, testing and observation services, special inspection services, and laboratory testing on an on -call, as -needed basis; and WHEREAS, CONSULTANT is specially trained, experienced, and competent to perform engineering services, testing and observation services, special inspection services, and laboratory testing, which are required by this agreement; and WHEREAS, CONSULTANT is willing to render such engineering services, testing and observation services, special inspection services, and laboratory testing, as hereinafter defined, on the following terms and conditions.

NOW, THEREFORE, CONSULTANT and the CITY agree as follows:

AGREEMENT
1) Incorporation of Master Agreement
This Task Order No. 2 hereby incorporates by reference all terms and conditions set forth in the Master Agreement for Geotechnical Investigations and Engineering Services dated August 5, 2025, unless specifically modified by this Task Order. 2) Scope of Service
CONSULTANT agrees to perform services in accordance with the scope of work and fee proposal provided by CONSULTANT, attached hereto. as Exhibit " A" and incorporated herein by reference. CONSULTANT agrees to diligently perform these services in accordance with theupmost standards of its profession and to CITY' ssatisfaction.

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 2 FOR CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR TOPSIDE IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 3) Effective Date and Term
The effective date of Task Order No. 2 is October 12, 2026, and it shall terminate no later than June 30, 2027.
4) Compensation
CITY hereby agrees to pay CONSULTANT hourly rates and other charges not to exceed $ 80, 000 for provide construction testing and observation services described in Exhibit " A" of Task Order No. 2 pursuant to the Master Agreement dated August 5, 2025. CONSULTANT shall be paid any uncontested sum due and payable within thirty ( 30) days of receipt of billings containing all information pursuant to Paragraph 5 below. Compensation for any task must beequal to or less than the percentage of task complete. In no event shaIICONSULTANT be entitled to compensation beyond what is expressed in this agreement and Exhibit A", unless a CITY authorized representative hasexecuted a written change order or authorization describing the extra work and payment terms prior to the commencement of the work.
5) Notice to Proceed
Prior to commencing work under this agreement, CONSULTANT shall receive a written " Notice to Proceed" from CITY. A Notice to Proceed shall not be issued until all necessary documents and insurance have been received. CITY shall not be obligatedto pay CONSULTANT for any services prior to issuance of the Notice to Proceed.
6) Signatures
The individuals executing this Agreement represent and warrant that they have the right, power, legal capacity, and authority to enter into and to execute this Agreement on behalf of the respective legal entities of the CONSULTANT and the CITY. This agreement shall inure to the benefit of and be binding upon the parties hereto and their respective successors and assigns.

Page2of3
CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 2 FOR CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR TOPSIDE IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 Approved as to Form: City of Lathrop
City Attorney
Salvador Navarrete
Recommended for Approval: City of Lathrop
Public Works Director/ City Engineer
Approved by:

Resolution No. 26 -
Consultant:

Date
Brad Taylor
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
Date
Stephen J. Salvatore Date
City Manager
ENGEO, Inc.
17278 Golden Valley Parkway
Lathrop, CA 95330
Fed ID # 94- 1748418
Lathrop Business License # LB -001373- 2025
Signature Date
Print Name and Title
Signature Date
Print Name and Title

Page 3 of 3 ends

Expect Excellence

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
DATE: September 29, 2026
PROJECT NAME: City of Lathrop Animal Shelter - Stanford Crossing Extension CIP Number: GG 23- 11

EXHIBIT A
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 I . info@engeo. com
ENGEO Project No.: 16218. 000.16
Phase: 007
ENGEO Contact: Ken Hamilton
ORIGINAL CONTRACT: City of Lathrop Master Agreement ( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope of Services:

We propose to provide construction testing and observation services during construction of topside improvements for the Stanford Crossing Extension on an on -call, as -needed basis as directed by the City of Lathrop. This fee estimate is based on our review of the project plans and specifications and discussions with the City of Lathrop and the project contractor.

We estimate that our services will be required on a part- time basis for a total of approximately 3 months.

Estimated Additional Fees:

We propose to perform the above -described testing and observation services for topside improvements on a time -and -expense basis estimated at $80, 000.

If you are in agreement with, the scope of services and fees outlined in this request, please fonivard a task order to the above -referenced original contract as authorization for us to proceed. All: other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
BY:

PRINTED NAME: Zac Crawford
TITLE:

DATE:
aj/ zac/ ss
Principal
September 29, 2026

ATTACHMENT
a
e

CITY OF LATHROP
TASK ORDER NO. 3 PURSUANT TO MASTER CONSULTING AGREEMENT WITH ENGEO INC. DATED AUGUST 5, 2025

TO PROVIDE CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR

UNDERGROUND IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER
PROJECT, CIP GG 23- 11
THIS TASK ORDER NO. 3, dated for convenience this 12th day of October 2026, is by and made and entered into by and between ENGEO Inc. ("CONSULTANT"), and the City of Lathrop, a California municipal corporation of the State of California (" CITY"); RECITALS:

WHEREAS, on August 5, 2025, CONSULTANT entered into a Master Agreement AGREEMENT") with the CITY, by which the CONSULTANT has agreed to provide engineering services, testing and observation services, special inspection services, and laboratory testing on an on -call, as -needed basis; and WHEREAS, CONSULTANT is specially trained, experienced, and competent to perform engineering services, testing and observation services, special inspection services, and laboratory testing, which are required by this agreement; and WHEREAS, CONSULTANT is willing to render such engineering services, testing and observation services, special inspection services, and laboratory testing, as hereinafter defined, on the following terms and conditions.

NOW, THEREFORE, CONSULTANT and the CITY agree as follows:

AGREEMENT
1) Incorporation of Master Agreement
This Task Order No. 3 hereby incorporates by reference all terms and conditions set forth in the Master Agreement for Geotechnical Investigations and Engineering Services dated August 5, 2025, unless specifically modified by this Task Order. 2) Scope of Service
CONSULTANT agrees to perform services in accordance with the scope of work and fee proposal provided by CONSULTANT, attached hereto as Exhibit " A" and incorporated herein by reference. CONSULTANT agrees to diligently perform these services in accordance with theupmost standards of its profession and to CITY' ssatisfaction.

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 3 FOR CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR UNDERGROUND IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 3) Effective Date and Term
The effective date of Task Order No. 3 is October 12, 2026, and it shall terminate no later than June 30, 2027.
4) Compensation
CITY hereby agrees to pay CONSULTANT hourly rates and other charges not to exceed $ 70, 000 for provide construction testing and observation services described in Exhibit " A" of Task Order No. 3 pursuant to the Master Agreement dated August 5, 2025. CONSULTANT shall be paid any uncontested sum due and. payable within thirty ( 30)' days of receipt of billings containing all information pursuant to Paragraph 5 below. Compensation for any task must beequal to or less than the percentage of task complete. In no event shaIICONSULTANT be entitled to compensation beyond what is expressed in this agreement and Exhibit A", unless a CITY authorized representative hasexecuted a written change order or authorization describing the extra work and payment terms prior to the commencement of the work.
5) Notice to Proceed
Prior to commencing work under this agreement, CONSULTANT shall receive a written " Notice to Proceed" from CITY. A Notice to Proceed shall not be issued until all necessary documents and insurance have been received. CITY shall not be obligatedto pay CONSULTANT for any services prior to issuance of the Notice to Proceed.
6) Signatures
The individuals executing this Agreement represent and warrant that they have the right, power, legal capacity, and authority to enter into and to execute this Agreement on behalf of the respective legal entities of the CONSULTANT and the CITY. This agreement shall inure to the benefit of and be binding upon' the parties hereto and their respective successors and assigns.

Page 2 of 3 ends

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 3 FOR CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR UNDERGROUND IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 Approved as to Form: City of Lathrop
City Attorney
d •7 •-tot(
Salvador Navarrete Date
Recommended for Approval: City of Lathrop
Public Works Director/ City Engineer
Brad Taylor Date
Approved by: City of Lathrop
Resolution No. 26- 390 Towne Centre Drive
Lathrop, CA 95330
Stephen J. Salvatore Date
City Manager
Consultant: ENGEO, Inc.
17278 Golden Valley Parkway
Lathrop, CA 95330
Fed ID # 94- 1748418
Lathrop Business License # LB -001373- 2025
Signature Date
Print Name and Title
Signature Date
Print Name and Title

Page 3 of 3 ends

Expect Excellence

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA, 95330
DATE: September 10, 2026,
Revised September 29, 2026
PROJECT NAME: City of Lathrop Animal Shelter
CIP Number: GG 23- 11

EXHIBIT A
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 I info@engeo. com
ENGEO Project No.: 16218. 000.16
Phase: 004
ENGEO Contact: Ken Hamilton
ORIGINAL CONTRACT: City of Lathrop Master Agreement ( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope of Services:

We propose to provide construction testing and observation services during construction of underground improvements on an on -call, as -needed basis as directed by the City of Lathrop. This fee estimate is based on our review of the project plans and specifications, and discussions with the City of Lathrop and the project contractor. We estimate that our services will be required on a full- time basis for a total of approximately 6 weeks.

Estimated Additional Fees:

We propose to perform the above -described testing and observation services for underground improvements on a time -and -expense basis estimated at $70, 000.

If you are in agreement with the scope of services and fees outlined in this request, please forward a task order to the above - referenced original contract as authorization for us to proceed. All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
BY:

PRINTED NAME:

TITLE:

DATE:

Zac Crawford
Principal
September 29, 2026
aj/ zac/ ca

ATTACHMENT
f ..

CITY OF LATHROP
TASK ORDER NO. 4 PURSUANT TO MASTER CONSULTING AGREEMENT WITH ENGEO INC. DATED AUGUST 5, 2025

TO PROVIDE CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR

UNDERGROUND IMPROVEMENTS FOR THE STANFORD CROSSING EXTENSION, RELATED TO THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11 THIS TASK ORDER NO. 4, dated for convenience this 12th day of October 2026, is by and made and entered into by and between ENGEO Inc. ("CONSULTANT"), and the City of Lathrop, a California municipal corporation of the State of California (" CITY"); RECITALS:

WHEREAS, on August 5, 2025, CONSULTANT entered into a Master Agreement AGREEMENT") with the CITY, by which the CONSULTANT has agreed to provide engineering services, testing and observation services, special inspection services, and laboratory testing on an on -call, as -needed basis; and WHEREAS, CONSULTANT is specially trained, experienced, and competent to perform engineering services, testing and observation services, special inspection services, and laboratory testing, which are required by this agreement; and WHEREAS, CONSULTANT is willing to render such engineering services, testing and observation services, special inspection services, and laboratory testing, as hereinafter defined, on the following terms and conditions.

NOW, THEREFORE, CONSULTANT and the CITY agree as follows:

AGREEMENT
1) Incorporation of Master Agreement
This Task Order No. 4 hereby incorporates by reference all terms and conditions set forth in the Master Agreement for Geotechnical Investigations and Engineering Services dated August 5, 2025, unless specifically modified by this Task Order. 2) Scope of Service
CONSULTANT agrees to perform services in accordance with the scope of work and fee proposal provided by CONSULTANT, attached hereto as Exhibit " A" and incorporated herein by reference. CONSULTANT agrees to diligently perform these services in accordance with theupmost standards of its profession and to CITY' ssatisfaction.

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 4 FOR CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR

STANFORD CROSSING EXTENSION UNDERGROUND IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11
3) Effective Date and Term
The effective date of Task Order No. 4 is October 12, 2026, and it shall terminate no later than June 30, 2027.
4) Compensation
CITY hereby agrees to pay CONSULTANT hourly rates and other ch` arges not to exceed $ 150, 00 for provide construction testing and observation services described in Exhibit " A" of Task Order No. 4 pursuant to the Master Agreement dated August 5, 2025. CONSULTANT shall be paid any uncontested sum due and payable within thirty ( 30) days of receipt of billings containing all information pursuant to Paragraph 5 below. Compensation for any task must beequal to or less than the percentage of task complete. In no event shaIICONSULTANT be entitled to compensation beyond what is expressed in this agreement and Exhibit A", unless a CITY authorized representative hasexecuted a written change order or authorization describing the extra work and payment terms prior to the commencement of the work.
5) Notice to Proceed
Prior to commencing work under this agreement, CONSULTANT shall receive a written " Notice to Proceed" from CITY. A Notice to Proceed shall not be issued until all necessary documents and insurance have been received. CITY shall not be obligatedto pay CONSULTANT for any services prior to issuance of the Notice to Proceed.
6) Signatures
The individuals executing this Agreement represent and warrant that they have the right, power, legal capacity, and authority to enter into and to execute this Agreement on behalf of the respective legal entities of the CONSULTANT and the CITY. This agreement shall inure to the benefit of and be binding upon the parties hereto and their respective successors and assigns.

Page 2 of 3 ends

CITY OF LATHROP - ENGEO, INC.

TASK ORDER NO. 4 FOR CONSTRUCTION TESTING AND OBSERVATION SERVICES FOR

STANFORD CROSSING EXTENSION UNDERGROUND IMPROVEMENTS FOR THE LATHROP ANIMAL CENTER PROJECT, CIP GG 23- 11
Approved as to Form:

Recommended for Approval:

Approved by:

Resolution No. 26 -
Consultant:

City of Lathrop
City Attorney
o, 7- Uzb
Salvador Navarrete Date
City of Lathrop
Public Works Director/ City Engineer
Brad Taylor Date
City of Lathrop
390 Towne Centre Drive
Lathrop, CA 95330
Stephen J. Salvatore Date
City Manager
ENGEO, Inc.
17278 Golden Valley Parkway
Lathrop, CA 95330
Fed ID # 94- 1748418
Lathrop Business License # LB -001373- 2025
Signature Date
Print Name and Title
Signature Date
Print Name and Title

Page 3 of 3 ends

GEO
Expect Excellence

REQUEST FOR TASK ORDER
TO: Ms. Leisser Mazariegos
City of Lathrop
390 Towne Centre Drive
Lathrop, CA, 95330
DATE:. September 29, 2026
PROJECT NAME: City of Lathrop Animal Shelter - Stanford Crossing Extension CIP Number: GG 23- 11

EXHIBIT A
2633 Camino Ramon, Suite 250
San Ramon, CA 94583
925) 866- 9000 I info@engeo. com
ENGEO Project No:: 16218. 000.16
Phase: 006
ENGEO Contact: Ken Hamilton
ORIGINAL CONTRACT: City of Lathrop Master Agreement ( ENGEO Project No. 16218. 000.00) ORIGINAL CONTRACT DATE: August 5, 2025
Additional Scope of Services:

We propose to provide construction testing and observation services during construction of underground improvements for the Stanford Crossing Extension on an on -call, as -needed basis as directed by the City of Lathrop. This fee estimate is based on our review of the project plans and specifications, and discussions with the City of Lathrop and the project contractor. We estimate that our services will, be required on a full- time basis for a total of approximately 3 months.

Estimated Additional Fees:

We propose to perform the above -described testing and observation services for underground improvements on a time -and -expense basis estimated at $ 150; 00.

If you are in agreement with the scope of services and fees outlined in this request, please forward a task order to the above -referenced original contract as authorization for us to proceed. All other terms and conditions of the original contract shall remain in effect.

ENGEO INCORPORATED
BY:

PRINTED NAME: Zac Crawford
TITLE:

DATE:
aj/ zacica
Principal
September 29, 2026