1 TO: City Council
FROM: Ryan Smoot, City Manager
PREPARED BY: Carla Dillon, P.E., Director of Public Works MEETING DATE: July 18, 2023
SUBJECT: Monthly Report for the Public Works Department RECOMMENDATION:

Receive and file the monthly report for the Public Works Department.

BACKGROUND:

Water Division Updates
Cypress Water Production Facility (CWPF) and Distribution System Update Well No. 5 remains offline due to the detection of benzene and the construction project to upgrade the CWPF. The State’s Division of Drinking Water (DDW) and the Los Angeles Regional Water Quality Control Board (RWQCB) have been investigating possible sources of benzene, and information is available at https://www.lomitawater.com/news/.

In June 2023, the City pumped 0.0 acre-feet of groundwater from Well No. 5. All drinking water was supplied with imported water from West Basin MWD. In June 2023, the City imported 159.5 acre-feet from West Basin MWD. Monthly water reports can be found at www.lomitawater.com/oversight/water-quality-reports/.

The City has been offering monthly tours of the Cypress Water Production Facility. A tour was hosted on June 13th for 3 community members. Residents who are interested in touring the facility may sign up for a tour at https://www.lomitawater.com/water-tours/.

The Annual Water Supply and Demand Assessment (AWSDA) is an annual assessment required of water systems through an on-line portal. The assessment is a projection for the upcoming fiscal year regarding estimated water supply and demand. The City’s assessment anticipates adequate water supply to meet water demands. The AWSDA was completed by staff and submitted by the July 1 deadline.

Item No. 7h

CITY OF LOMITA

CITY COUNCIL REPORT
2 Water Division Performance Measures:

Main Breaks/Leak Repairs 0
Service Connection Breaks/Leaks 2
Water Outages 0
Water Service Requests 42
USA Dig-Alert Tickets 72
Dead-end Fire Hydrant Flushing 20
Meter Maintenance 10
Inspection of Water Facilities Daily
Water Quality Complaints 0
Engineering/PW Administration Division Updates
CIP Update
Cypress Water Production Facility (CWPF) Upgrade Project The City’s contractor RC Foster, with the oversight of the contract manager, AKM Consulting Engineers, is progressing on construction. Hazen and Sawyer continue to provide submittal and request for information (RFI) review as well as documentation and support for the permitting with the Division of Drinking Water (DDW).

Progress As of June 30, 2023
Percent Project completion 98%
Overall Project, invoiced/approved $4,324,971
Overall Project budget (approved contracts) $4,835,131
The City shares project updates on https://www.lomitawater.com/ as new information is available. In addition, a short video describing the GAC project and treatment process is available here: https://www.lomitawater.com/infrastructure/granular-activated-carbon/.

Street Reconstruction – Zone G
This project consists of overlaying and reconstructing certain streets in Zones G (just north and south of Lomita Boulevard and east of Eshelman Avenue), as detailed in the Pavement Management Program (PMP). This project includes significant repairs and resurfacing of streets where slurry seal would not be sufficient to extend the life of the street.

The design of the project was awarded to David Evans and Associates (DEA) in July 2022, and design is scheduled to be completed in 2023. Construction is programmed for Spring-Summer 2024. Extensive field investigation and sampling have taken place to evaluate the road condition on the 17 streets included in this project, and the City has received related technical reports. In addition, DEA has identified and provided 3 preliminary cost estimates for curb ramps that require upgrades in the project zone. DEA is preparing the 60% detailed design drawings, which are expected in August 2023.

Progress As of June 30, 2023
Percent Project completion 35% (of design)
Overall Project, invoiced/approved $86,254.81
Overall Project budget $1,200,000
247th Street Area Watermain Project
This project consists of abandoning a watermain that runs north and south within private properties crossing 246th Street, 247th Street, 247th Place, and 248th Street. The proposed new water main will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right of way and along Western Avenue (which is Caltrans right of way), and connecting back to the City of Lomita along 247th Street, 247th Place, 248th Street and Lomita Blvd. This project consists of constructing approximately 3,300 linear feet of PVC water pipeline and appurtenances (fire hydrants, valves, services, and fittings). The existing pipeline located in private property will be abandoned.

Design of the project was awarded to Onward Engineering in November 2021. The permit from Caltrans was approved in September 2022. The encroachment permit and traffic control plans were approved by the City of Los Angeles in December 2022. The permit fees for Lomita to work in the City of Los Angeles’ Right-of-Way is approximately $316,000.

Onward Engineering has completed two rounds of potholing. The first round identified an unknown pipe requiring a new alignment and additional potholing. The second round of potholing has shown elevated levels of Lead in the area. Onward Engineering is working on an alternate alignment and is planning for further potholes to avoid contaminated soil.

Following this, the final design will be resubmitted to the City for review.

Progress As of June 30, 2023
Percent Project completion 95% (of design)
Overall Project, invoiced/approved $119,821.50
Overall Project budget $1,499,916
Emergency Generator
This project consists of the selection and design of an emergency generator that will be capable of servicing the Appian Way Pump Station as needed. The design of this project was awarded to AEPC Group in July 2022 and was completed in June 2023. City Council approved the design in June 2023, and authorized release for bidding.

Procurement of a short-term rental generator has been initiated, and construction bidding will take place in July 2023.

Progress As of June 30, 2023
4 Percent Project completion 95% (of design)
Overall Project, invoiced/approved $52,030
Overall Project budget $76,365
Narbonne Avenue Water Replacement and Street Rehabilitation Project This project consists of constructing approximately 1,600 linear feet of PVC water pipeline on Narbonne Avenue from PCH to the southern end of the City of Lomita. The proposed watermain will be a new 8-inch PVC water main to provide improved flow, pressure, and fire protection. This new water main will replace the existing 1928 6-inch and 8-inch water main.

Design of the project was awarded to David Evans and Associates (DEA) in December 2022. DEA has performed a pavement analysis of the current conditions, and the 60% preliminary design package is expected in July 2023. They plan to pothole at various locations to determine depth of possible conflicting utilities. The final design is scheduled to be completed in the third quarter of 2023.

Progress As of June 30, 2023
Percent Project completion 10% (of design)
Overall Project, invoiced/approved $25,626.66
Overall Project budget $199,940
New Groundwater Well Feasibility Study
The purpose of this study is to identify preliminary locations where construction of a new groundwater well is feasible. The installation of a new well would minimize the City’s longterm reliance on imported water and provide a contingency well in case of future adverse impacts to Lomita Well No. 5. The City currently has groundwater rights of 1,352-acre feet (ac-ft) in the West Coast Basin, and in its last year of normal operations, CY 2018, Well No. 5 only pumped 561 ac-ft of groundwater.

In February 2023, this study was awarded to Stetson Engineering, Inc, who is currently acquiring and reviewing data. In June, the preliminary report was received, and staff have begun the review. The study and final report are scheduled to be completed in July 2023.

Progress As of June 30, 2023
Percent Project completion 75%
Overall Project, invoiced/approved $29,682.75
Overall Project budget $63,135
Appian Way Pump Station Roof Project
This project consists of designing and constructing a new roof for the Appian Way Pump Station. The design contract has been awarded to Tetra Tech, Inc. and they have submitted 60% design drawings. Lomita staff is reviewing the drawings. 5 Stephenson Center Maintenance Project
This project consists of design and construction for upgrades to the restroom facilities as well as restoration/replacement of the three-level roof at the Stephenson Center in Lomita Park. The Project design has been awarded to BOA Architecture; they have visited the site and provided preliminary drawings for the restroom layout to meet accessibility design requirements. Lomita staff are reviewing the drawings.

Engineering/Regulatory Updates
Encroachment Permit Review/Approval
For the month of June 2023, staff received and reviewed 11 encroachment permit applications from various utility companies, contractors, and residents. Permits were issued to 5 applicants. Public Works now has an on-line portal for encroachment permitting, available at https://lomitaca.viewpointcloud.com/categories/1081.

Stormwater
In June, the Dominguez Channel Watershed Group submitted the required semi-annual Report for the period July – December 2022 for MS4 NPDES Permit Order No. R4-2021- 0105, NPDES No. CAS004004. In addition, City staff provided stormwater outreach in conjunction with the city booth at Founder’s Day.

Sewer System
In June, several items were required for reissued Order WQ 2022-0103-DWQ, including request for continued coverage, current Sewer System Management Plan (SSMP), submittal of the Legally Responsible Officer (LRO), latest Audit, and a revised Emergency Response Plan. The City completed these requirements. The reissued order changes the cycle for the SSMP revisions, audit, and LRO requirements.

Public Safety and Traffic
Public Safety and Traffic Commission (PS&TC) met in June. The PS&TC heard presentation on changes to the Fleming Middle School bus zones and restriping of Narbonne Ave, south of PCH. The PS&TC recommended these changes to City Council.

The PS&TC also discussed the “Follow Me, I’m Drug and Gang-Free” Walk.

All new requests for traffic issue investigations are accepted through the on-line OpenGov portal and may be submitted here: https://lomitaca.viewpointcloud.com/categories/1081. 6 Public Works Field Operations Division (Parks/Street/Trees) Updates Parks Division:

Mowed Park Grounds, number of times 19
Playground Safety Inspections 7
Raised Median/Planter Weeding 29
Park Grounds Fertilize 0
Museum/City Hall Grounds Maintenance 7
Sprinkler Repair/Replacement 44
Trimmed Hedges/Trees (City grounds) 40
Streets and Trees Division:

Trees Trimmed (by Crew) 35
Trees Trimmed (by Contractor) 0
Trees/Stumps Removed 6
Graffiti Locations Cleaned 72
Sidewalk Maintenance 268
Curb/Gutter Maintenance 9
City Drains Cleaned 35
Street Signs Replaced or Repaired 24
Potholes Filled / Patches 75
New work order requests 14
Backlog of work orders 11
Total Trees Planted 0
Reviewed by: Approved by:

Gary Y. Sugano Ryan Smoot
Assistant City Manager City Manager
Prepared by:

Carla Dillon, PE
Public Works Director