1 TO: City Council
FROM: Ryan Smoot, City Manager
REVIEWED BY: Carla Dillon, P.E., Public Works Director
MEETING DATE: September 19, 2023
SUBJECT: Discussion and Consideration to Authorize the Release of a Bid Package for the 247th Street Area Water Main Replacement Project

RECOMMENDATIONS
Authorize staff to release the bid package for the 247th Street Area Water Main Replacement Project; and find the project categorically exempt from CEQA.

BACKGROUND
The 247th Street Area Water Main Replacement Project consists of replacing pipelines.

The existing water main around 247th Street area runs north and south within private properties crossing 246th Street, 247th Street, 247th Place, and 248th Street. This existing water main includes a 4-inch diameter pipe for approximately 955 feet and a 6-inch diameter pipe for the rest of the area. The water mains were constructed in 1928 and have exceeded their useful life. The age of these water mains makes them particularly at risk for main breaks and leaks, especially as a result of an earthquake.

The proposed new water main will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right-of-way and along Western Avenue (which is Caltrans right-of-way), and connecting back to the City of Lomita along 247th Street, 247th Place, 248th Street and Lomita Blvd. This project consists of constructing approximately 3,300 linear feet of 6-inch PVC water pipeline and appurtenances (fire hydrants, valves, services, and fittings). The existing pipeline located in private property will be abandoned.

This project aims to improve fire flow in the project area by replacing the existing 4-inch and 6-inch diameter pipes, which allows emergency responders to more effectively fight fires in this area. This project will also reduce the risk of water damage to private properties in the event of a main break or earthquake.

In November 2021, the City Council awarded a Professional Services Agreement to Item No. Sch 8b

CITY OF LOMITA

CITY COUNCIL REPORT
2 Onward Engineering for engineering design services in the amount of $133,119.50 plus a 20% contingency in the amount of $26,623.90. The design phase encountered several delays due to approvals by outside parties (CalTrans and City of Los Angeles), as well as the identification of unmarked utilities during the potholing. The design of the water main replacement is completed, and the project is ready to be released for bid.

Staff is requesting approval of the project and authorization to release it for bid as soon as possible.

CEQA
It is recommended that the City Council find this project is not subject to CEQA pursuant to CEQA Guidelines, Section 15302 Replacement or Reconstruction of existing structures and facilities. This project installation can be found to be exempt from the requirements of CEQA. The proposed project consists of replacement pipes to supply water to residences with no increase in capacity.

FISCAL IMPACT
There is no fiscal impact of this action.

The City has Hazard Mitigation Grant Program (HMGP) funds for the 247th Street Area Water Main Replacement project which provides for the $1,125,000 in funding toward the project. The City is required to contribute at least 25% of the total project cost.

OPTIONS

1. Approve staff’s recommendation.

2. Provide alternative direction.

ATTACHMENTS

1. Design Plans and Bid Documents

2. CEQA Notice of Exemption
Reviewed by: Approved by:
___________________________
Gary Y. Sugano Ryan Smoot
Assistant City Manager City Manager
Reviewed by:
_______________________
Carla Dillon, P.E.

Public Works Director

WATER MAIN REPLACEMENT
247TH STREET AREA
PROJECT NO. 2021-1-WA

VICINITY MAP

NOT TO SCALE

STANDARD SYMBOLS

CITY STANDARD PLANS
W-100: WATER MAIN TRENCH DETAIL
W-101: 1 " WATER SERVICE INSTALLATION
W-102: 2" WATER SERVICE INSTALLATION
W-103: 1" & 2" SERVICE CONNECTION TO MAIN LINE
W-110: FIRE HYDRANT INSTALLATION
W-130: DI CONNECTION TO MAIN
W-140: CONCRETE THRUST BLOCK (4" TO 16" DIA FITTING)
W-142: THRUST BLOCK AREA REQUIREMENTS
W-150: VALVE BOX ASSEMBLY

SHEET INDEX
1 TITLE SHEET, VICINITY MAP, LOCATION MAP, STANDARD SYMBOLS,

UTILITY INFORMATION
2 STANDARD NOTES FOR WATER CONSTRUCTION, SPECIAL NOTES

TO CONTRACTOR, AND NPDES GENERAL NOTES
3 WATER PLAN - LOMITA BLVD TO WESTERN AVE
4 WATER PLAN - WESTERN AVE FROM LOMITA BLVD TO 248TH ST 5 WATER PLAN - 248TH STREET TO WESTERN AVENUE
6 WATER PLAN - 247TH PLACE TO WESTERN AVENUE
7 WATER PLAN - 247TH STREET TO WESTERN AVENUE
8 WATER PLAN - 246TH STREET TO WESTERN AVENUE
9 TYPICAL TRENCH SECTIONS
10 BUS PAD DETAILS
11 TRAFFIC CONTROL PLAN - GENERAL NOTES
12 TRAFFIC CONTROL PLAN - WESTERN AVENUE WORK AREA
13 TRAFFIC CONTROL PLAN - LOMITA BOULEVARD WORK AREA
14 TRAFFIC CONTROL PLAN - 248TH STREET WORK AREA
15 TRAFFIC CONTROL PLAN - 247TH PLACE WORK AREA
16 TRAFFIC CONTROL PLAN - 247TH STREET WORK AREA
17 TRAFFIC CONTROL PLAN - 246TH STREET WORK AREA
18 TRAFFIC CONTROL PLAN - WESTERN AVENUE FRONTAGE ROAD
WORK AREAS 1 AND 3
19 TRAFFIC CONTROL PLAN - WESTERN AVENUE FRONTAGE ROAD
WORK AREAS 2 AND 4
20 TRAFFIC CONTROL PLAN - WESTERN AVENUE AND 247TH STREET

DETOUR PLAN
21 EROSION CONTROL PLAN LOCATION MAP

NOT TO SCALE

DISSIMILAR PIPE CONNECTIONS

CONTRACTOR SHALL FIELD VERIFY DIMENSIONS OF EXISTING CAST IRON (CI), DUCTILE

IRON (DI), ASBESTOS CEMENT (AC), OR OTHER PIPES, AT POINTS OF CONNECTION, CONSTRUCTION WORK. THE USE OF MODIFIED MECHANICAL JOINT BELLS, WITH OVERSIZE

GLANDS, TO CONNECT EXISTING PIPES TO NEW MECHANICAL JOINT (MJ) PIPE AND FITTINGS IS ALLOWED, PER MANUFACTURER'S RECOMMENDATIONS. APPROVED TRANSITION COUPLINGS OR OTHER CAST ADAPTERS MAY

ALSO BE USED BY THE CONTRACTOR AS AN OPTION TO CONNECT EXISTING DISSIMILAR PIPE TO NEW PIPE OR FITTINGS WHEN NECESSARY, WHETHER SHOWN OR NOT SHOWN ON THE PLANS.

NOTE TO CONTRACTOR

UTILITY CONTACTS

CONTRACTOR SHALL NOTIFY ALL UTILITY AGENCIES CONCERNED A MINIMUM OF 48 HOURS PRIOR TO CONSTRUCTION INCLUDING BUT NOT LIMITED TO:

AT&T (510) 645-2929
CALTRANS (213) 897-0954
CHARTER (714) 591-4870
CITY OF LOMITA (310) 325-7110
CITY OF LOMITA- WATER DIVISION (EMERGENCY PHONE) (310) 597-6428 LOS ANGELES COUNTY FIRE DEPARTMENT (310) 326-2461
LOS ANGELES COUNTY SHERIFF DEPARTMENT (310) 539-1661
LOS ANGELES COUNTY SANITATION DISTRICT (562) 699-7411
LOS ANGELES COUNTY FLOOD CONTROL DISTRICT (562) 861-0316 SOUTHERN CALIFORNIA EDISON (714) 796-9932
SOUTHERN CALIFORNIA GAS (310) 687-2032
TIME WARNER CABLE (714) 903-8446
UNDERGROUND SERVICE ALERT 811
VERIZON (469) 896-4238

NPDES GENERAL NOTES

1. CONTRACTOR MUST ENSURE THAT THE CONSTRUCTION SITE IS PREPARED PRIOR TO THE ONSET OF ANY STORM.

CONTRACTOR SHALL HAVE ALL EROSION AND SEDIMENT CONTROL MEASURES IN PLACE.

2. ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE MAINTAINED UNTIL DISTURBED AREAS ARE STABILIZED.

3. ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE CHECKED BEFORE AND AFTER ALL STORMS TO ENSURE MEASURES ARE FUNCTIONING PROPERLY.

4. CONTRACTOR SHALL MAINTAIN A LOG AT THE SITE OF ALL INSPECTIONS OR MAINTENANCE OF BMPs AS WELL AS ANY CORRECTIVE CHANGES TO THE BMPs OR EROSION AND SEDIMENT CONTROL

5. IN AREAS WHERE SOIL IS EXPOSED, PROMPT REPLANTING WITH NATIVE COMPATIBLE DROUGH-RESISTANT VEGETAION SHALL BE PERFORMED.

6. ALL SEDIMENT DEPOSITED ON PAVED ROADWAYS SHALL BE SWEPT AT THE END OF EACH WORKING DAY OR AS NECESSARY.

7. CONTRACTOR SHALL PLACE BMPs AROUND ALL DRAINAGE STRUCTURE OPENINGS IMMEDIATELY AFTER THE STRUCTURE OPENING IS CONSTRUCTED. THESE SHALL BE MAINTAINED AND REMAIN IN PLACE UNTIL THE CONSTRUCTION IS COMPLETE.

8. CONTRACTOR SHALL IMPLEMENT HOUSEKEEPING PRACTICES AS FOLLOWS:

8.A. SOLID WATER MANAGEMENT:

PROVIDE A DESIGNATED WASTE COLLECTION AREA AND CONTAINERS. ARRANGE FOR REGULAR REMOVAL AND DISPOSAL.

CLEAR SITE OF TRASH INCLUDING ORGANIC DEBRIS, PACKAGING MATERIALS, SCRAP OR SURPLUS BUILDING MATERIALS AND DOMESTIC WASTE DAILY.

8.B. CONCRETE WASTE:

PROVIDE A DESIGNATED AREA FOR A TEMPORARY PIT TO BE USED FOR CONCRETE TRUCK WASH-OUT. DISPOSE OF HARDENED CONCRETE OFFSITE. AT NO TIME SHALL A CONCRETE TRUCK DUMP ITS WASTE AND CLEAN ITS TRUCK INTO THE CITY STORM DRAIN VIA CURB AND GUTTER. INSPECT DAILY TO CONTROL RUNOFF AND WEEKLY FOR REMOVAL OF HARDENED CONCRETE.

8.C. PAINT AND PRINTING SUPPLIES:

PROVIDE INSTRUCTION TO EMPLOYEES AND SUBCONTRACTORS REGARDING REDUCTION OF POLLUTANTS INCLUDING MATERIAL STORAGE, USE, AND CLEAN UP. INSPECT SITE WEEKLY FOR EVIDENCE OF IMPROPER DISPOSAL.

8.D. VEHICLE FUELING, MAINTENANCE AND CLEANING:

PROVIDE A DESIGNATED FUELING AREA WITH SECONDARY CONTAINMENT SUCH AS BERMING. DO NOT ALLOW MOBILE FUELING OF EQUIPMENT. PROVIDE EQUIPMENT WITH DROP PANS. RESTRICT ONSITE MAINTENANCE AND CLEANING OF EQUIPMENT TO A MINIMUM.

8.E. HAZARDOUS MATERIALS MANAGEMENT:

PREVENT THE DISCHARGE OF POLLUTANTS FROM HAZARDOUS MATERIALS TO THE DRAINAGE SYSTEM THROUGH PROPER MATERIAL USE, WASTE DISPOSAL AND TRAINING OF EMPLOYEES. HAZARDOUS WASTE PRODUCTS COMMONLY FOUND ON-SITE

INCLUDE BUT ARE NOT LIMITED TO PAINTS & SOLVENTS, PETROLEUM PRODUCTS, FERTILIZERS, HERBICIDES & PESTICIDES, SOIL STABILIZATION PRODUCTS, ASPHALT PRODUCTS AND CONCRETE CURING PRODUCTS.

N CITY OF LOMITA CITY OF LOS ANGELES
8 7
6 5
3 4
G
OIL
SD
S
W
R Know what'sbelow. Callbefore you dig.

Attachment No. 1
R Know what'sbelow. Callbefore you dig.

STANDARD NOTES FOR WATER CONSTRUCTION

1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION. LATEST EDITION AND SUPPLEMENTS THERETO, AS WRITTEN AND PROMULGATED BY PUBLIC WORKS STANDARDS, INC., HEREINAFTER REFERRED TO AS THE STANDARD

SPECIFICATIONS, THE CITY OF LOMITA STANDARD PLANS, ANY SPECIAL PROVISIONS, THE AMERICAN WATER WORKS ASSOCIATION STANDARDS LATEST EDITION, AND TO THE SATISFACTION OF THE PUBLIC WORKS DIRECTOR.

2. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO LOCATE, VERIFY DEPTH AND PROTECT ALL STRUCTURES, INCLUDING SUBSTRUCTURES, SHOWN ON THE PLANS. THE CONTRACTOR SHALL BEAR THE ENTIRE COST OF REPAIRING OR REPLACING ANY OF SAID STRUCTURES DAMAGED BY HIM/HER DURING PROSECUTION OF THE WORK. ALL REPAIRS AND REPLACEMENTS SHALL BE DONE IN THE PRESENCE OF THE INSPECTOR.

ALL LOCATIONS SHOWN ON THE PLANS FOR UTILITY LINES HAVE BEEN TAKEN FROM AVAILABLE RECORDS AND THEIR COMPLETENESS AND CORRECTNESS ARE IN NO WAY GUARANTEED.

3. THE CONTRACTOR SHALL NOTIFY UNDERGROUND SERVICE ALERT (USA) AT 1-800-227-2600, ALL PUBLIC UTILITY COMPANIES AND OWNERS OF PRIVATE FACILITIES WITHIN THE AREA OF CONSTRUCTION AT LEAST 2 WORKING DAYS IN ADVANCE OF PERFORMING ANY WORK WITHIN SAID AREA.

4. THE CONTRACTOR SHALL OBTAIN ALL NECESSARY PERMITS PRIOR TO STARTING WORK FROM THE CITY ENGINEER, AND OTHER LOCAL, STATE AND FEDERAL SO THAT INSPECTION MAY BE PROVIDED.

5. ALL CONTRACTORS AND SUBCONTRACTORS PERFORMING WORK SHOWN ON OR RELATED TO THESE PLANS SHALL CONDUCT THEIR OPERATIONS SO THAT ALL EMPLOYEES ARE PROVIDED A SAFE PLACE TO WORK AND THE PUBLIC PROTECTED. ALL CONTRACTORS AND SUBCONTRATORS SHALL COMPLY WITH THE "OCCUPATIONAL SAFETY AND HEALTH REGULATIONS" OF THE U.S. DEPARTMENT OF LABOR, AND WITH THE STATE OF CALIFORNIA DEPARTMENT OF INDUSTRIAL RELATIONS "CONSTRUCTION SAFETY ORDERS".

6. CONTRACTOR SHALL HIRE AND PROVIDE ALL PROFESSIONAL SURVEYING FOR THIS PROJECT AT HIS EXPENSE. PRIOR TO COMMENCEMENT OF WORK, ALL SURVEY MONUMENTS IN THE PROJECT AREA SHALL BE LOCATED AND TIED OUT. ALL CENTERLINE MONUMENTS OR TIES LOST OR DESTROYED BY THIS WORK SHALL BE REPLACED EITHER BY A LICENSED SURVEYOR OR A CIVIL ENGINEER REGISTERED PRIOR TO JANUARY 1, 1982 AND NEW TIE SHEETS PROVIDED TO LOS ANGELES COUNTY DEPARTMENT OF PUBLIC WORKS.

7. THE CONTRACTOR SHALL NOTIFY THE PUBLIC WORKS DEPARTMENT AT (310) 325-9830 PRIOR TO TRIMMING, REMOVING OR RELOCATING ANY EXISTING TREES.

8. ALL TRAFFIC SIGNS AND CONTROL DEVICES SHALL BE PROTECTED IN PLACE BY THE CONTRACTOR. ALL TRAFFIC CONTROL PAVEMENT MARKINGS SHALL BE REPLACED WITHIN 24 HOURS OF PLACEMENT OF TEMPORARY ASPHALT CONCRETE PAVING, WITHIN 7 DAYS OF PERMANENT ASPHALT CONCRETE PAVING, AND PRIOR TO OPENING TO TRAFFIC FOR P.C.C. PAVING.

9. THE CONTRACTOR SHALL DISINFECT WATER LINES UNDER THE DIRECTION OF THE CITY'S PUBLIC WORKS DIRECTOR. THE CITY OF LOMITA WATER DIVISION SHALL COLLECT WATER SAMPLES FOR ANALYSIS SUBSEQUENT TO DISINFECTING OF THE PIPELINE BY THE CONTRACTOR.

10. THE CONTRACTOR SHALL NOTIFY THE INSPECTOR AT LEAST TWO WORKING DAYS IN ADVANCE OF A PROPOSED WATER MAIN OR SERVICE LINE SHUT DOWN. THE CONTRACTOR SHALL NOTIFY THE CUSTOMERS AFFECTED BY THE PROPOSED SHUT DOWN AT LEAST 72 HOURS IN ADVANCE.

CUSTOMER NOTIFICATION SHALL CONSIST OF A DOOR HANGER SPECIFYING THE DATE(S) AND TIME(S) OF THE PROPOSED SHUT DOWN. NOTICES SHALL CONTAIN THE CONTRACTORS NAME, TELEPHONE NUMBER AND SHALL BE APPROVED BY THE INSPECTOR PRIOR TO DISTRIBUTION.

11. CONTRACTOR IS NOT PERMITTED TO TURN (OR EXERCISE) WATER VALVES. THE CONTRACTOR SHALL CONTACT THE CITY OF LOMITA WATER DIVISION AT (310) 325-9830 A MINIMUM OF FOUR (4) WORKING DAYS PRIOR TO REQUIRING VALVE SHUT DOWN AT EACH LOCATION.

12. CONTRATOR SHALL PRESSURE TEST AND CHLORINATE ALL NEW PIPELINES PRIOR TO CONNECTING TO EXISTING MAIN.

13. ALL VALVES WHERE TIE-INS ARE REQUIRED WILL BE BLIND FLANGED BY THE CONTRACTOR PRIOR TO PRESSURE TESTING.

14. CONTRACTOR TO FURNISH AND INSTALL INSTALL 2" TEMPORARY BLOW OFFS FOR DISINFECTION AND PRESSURE TESTING WHERE REQUIRED.

15. ALL WATER LINES SHALL HAVE 42" COVER FROM PROPOSED FINISHED GRADE UNLESS OTHERWISE SHOWN ON THE PLANS.

16. FOR PARALLEL CONSTRUCTION ALL WATER LINES SHALL BE INSTALLED WITH A TWO FOOT (MIN.) CLEARANCE FROM EXISTING UTILITY LINES (GAS, TELEPHONE, CABLE, POWER...). A MINIMUM OF 12" CLEARANCE SHALL BE PROVIDED WHEN CROSSING UTILITY LINES.

17. NO PVC PIPE SHALL BE INSTALLED UPSTREAM OF THE INLET SIDE OF METERS OR DETECTOR CHECK VALVES.

18. CONTRACTOR SHALL MAKE AVAILABLE FOR THE PUBLIC WORKS INSPECTOR'S REVIEW, ON A DAILY BASIS, AS-BUILT DRAWINGS FOR WORK PERFORMED UP TO AND INCLUDING THE PREVIOUS DAY'S ACTIVITIES. WORK SHALL NOT BE CONSIDERED AS COMPLETE UNTIL AS-BUILTS ARE SUBMITTED TO AND ACCEPTED BY THE PUBLIC WORKS DIRECTOR.

19. TRENCHES CUT INTO AN EXISTING ROADWAY WITHIN THE PUBLIC RIGHT OF WAY SHALL BE BACKFILLED AND PAVED AS PER THE TRENCH DETAIL FOR WATERLINE CONSTRUCTION.

20. TRENCH RESURFACING SHALL BE PER THE TRENCH DETAIL FOR WATERLINE CONSTRUCTION.

21. PIPE BEDDING SHALL CONFORM TO THE TRENCH DETAIL FOR WATERLINE CONSTRUCTION.

22. PIPE ZONE SHALL BE COMPACTED TO A MINIMUM 90% RELATIVE DENSITY. AGGREGATE BASE FOR PAVED AREAS SHALL BE COMPACTED TO A MINIMUM 95% RELATIVE DENSITY. BACKFILL SHALL BE TESTED AND APPROVED BY THE CONTRACTOR'S APPROVED SOILS ENGINEER.

23. ALL NECESSARY MATERIALS TESTING (INCLUDING SOILS, COMPACTION, ASPHALT, ETC.) SHALL BE DONE BY AN INDEPENDENT THIRD PARTY SOILS ENGINEERING FIRM AND/OR MATERIALS LABORATORY THAT HAS BEEN APPROVED BY THE PUBLIC WORKS DIRECTOR. THE COST FOR REPORTS AND TESTING SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.

24. IT IS THE CONTRACTOR'S RESPONSIBILITY TO SUBMIT SOILS REPORTS ON ALL TRENCHES TO THE ENGINEER OF WORK AND TO THE CITY

ENGINEER BY A QUALIFIED SOILS ENGINEER, WHICH CERTIFIES THAT THE TRENCH BACKFILL WAS COMPACTED AS DIRECTED BY THE SOILS ENGINEER IN ACCORDANCE WITH EARTHWORK SPECIFICATIONS. THE COST FOR THE TESTING AND REPORTS SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.

25. INSULATION FLANGE KITS SHALL BE INSTALLED AT ALL DISSIMILAR METAL INTERFACES, PSI OR APPROVED EQUAL.

26. ALL MECHANICAL JOINT GLAND KITS TO BE RESTRAINED WITH EBAA MEGALUG SERIES OR APPROVED EQUAL.

27. ALL FLANGE NUTS, BOLTS AND WASHERS SHALL BE 316 S.S. UNLESS OTHERWISE SHOWN.

28. ALL BURIED DUCTILE IRON PIPE, VALVES, FITTINGS, ETC. SHALL BE WRAPPED IN 8 MIL. POLYETHYLENE.

29. CONTRACTOR SHALL INSTALL BLUE WARNING TAPE IN TRENCH BACKFILL PER THE TRENCH DETAIL FOR WATERLINE CONSTRUCTION.

30. ALL MATERIAL PROPOSED FOR USE SHALL BE APPROVED BY THE CITY PRIOR TO CONSTRUCTION AND ALL ALTERNATE METHODS OR MATERIALS SHALL ALSO BE APPROVED BY THE CITY PRIOR TO USE.

31. FOR ALL TRENCH SHORING AND BRACING REQUIREMENTS, REFER TO CALIFORNIA DIVISION OF OCCUPATIONAL SAFETY & HEALTH AGENCY (CAL/OSHA) REQUIREMENTS

32. COMPLY WITH REQUIREMENTS OF AWWA C - 550, PROTECTIVE EPOXY COATINGS FOR VALVES.

SPECIAL NOTES TO CONTRACTOR

1. BEFORE STARTING ANY WORK ON THIS PROJECT, THE CONTRACTOR SHALL:

1.1. HAVE SUBMITTED A DESCRIPTION OF ALL MATERIALS, A WRITTEN LISTING OF ALL MATERIAL ITEMS TO BE FURNISHED TO AND/OR INSTALLED ON THE PROJECT, TO THE CITY AND POSSESS A RETURNED COPY OF SUCH MARKED "APPROVED" FOR THIS PROJECT

1.2. HAVE GIVEN THE CITY INSPECTORS THE TELEPHONE NUMBER, BUSINESS OR HOME ADDRESS AND MAILING ADDRESS AND NAMES OF PERSONS WHO CAN BE REACHED IN THE EVENT OF AN EMERGENCY OCCURRENCE ON THE PROJECT DURING THE TIME IS IN PROGRESS, 24 HOURS PER DAY, 7 DAYS PER WEEK.

2. FIRE HYDRANT RISERS SHALL BE INSTALLED AS SHOWN. ANY NECESSARY ADJUSTMENT OF FIRE HYDRANT BREAK OFF FLANGE ELEVATION SHALL BE PERFORMED AT CONTRACTOR'S EXPENSE TO MEET FINISH GRADE.

3. FIRE HYDRANTS TO BE FLOW TESTED PRIOR TO INSPECTION.

4. ALL NEW WORK SHALL BE TESTED VALVE TO VALVE AT 200 PSI FOR FOUR HOURS. CONTRACTORS SHALL DESIGN, FURNISH AND INSTALL ANY NECESSARY THRUST BLOCKS IN ACCORDANCE WITH W-140, OR AS SHOWN ON THE PLANS.

5. IN ADDITION TO ITEMS IN LIST OF MATERIALS, CONTRACTOR SHALL FURNISH ALL NECESSARY ADAPTERS, COUPLINGS, BOLTS, GASKETS, CAULKING MATERIALS, AND REPACING AS REQUIRED TO COMPLETE THE WORK.

6. THE CONTRACTOR SHALL VERIFY THE SIZE, TYPE, CLASS, PROTECTIVE LINNING AND COATING, AND DEPTH OF THE EXISTING WATER MAINS AND SHALL BE RESPONSIBLE FOR MAKING PROPER CONNECTIONS.

7. ALL EXCESS EXCAVATED TRENCH MATERIAL SHALL BE REMOVED FROM THE PROJECT SITE AND DISPOSED OF LEGALLY.

8. THE CITY OF LOMITA WATER DIVISION CANNOT GUARANTEE A COMPLETE SHUT DOWN OF EXISTING MAINS. THE CITY WILL ATTEMPT TO SHUT DOWN MAINS AS COMPLETELY AS POSSIBLE; HOWEVER, THE CONTRACTOR SHALL BE RESPONSIBLE FOR DEWATERING AND ISOLATION FOR TESTING PURPOSES.

9. DURING NON-CONSTRUCTION HOURS, ALL EXCAVATIONS MUST BE APPROPRIATELY SHORED AND PLATED OR BACKFILLED, EXCEPT BORE PITS WHICH SHALL BE SECURED WITH K-RAIL AND 6' HIGH CHAIN LINK FENCE PANELS SECURED IN PLACE TO THE SATISFACTION OF THE INSPECTOR. PLATES SHALL BE TACK WELDED, PINNED AND/OR SECURED IN PLACE BY ANOTHER METHOD APPROVED BY THE INSPECTOR.

10. STEEL PLATE BRIDGING IS REQUIRED, IN ALL PAVED AREAS, FOR ALL TRENCHING EXCAVATIONS NOT BACKFILLED BY THE END OF THE WORKDAY.

STEEL PLATE BRIDGING SHALL CONFORM TO THE FOLLOWING:

10.1. APPROACH PLATE (S) AND ENDING PLATES (IF LONGITUDINAL PLACEMENT) SHALL BE ATTACHED TO THE ROADWAY BY A MINIMUM OF 2 DOWELS PRE-DRILLED INTO THE CORNERS OF THEIR PLATE AND DRILLED 2 INCHES INTO THE PAVEMENT.

10.2. SUBSEQUENT PLATES ARE BUTTED TO EACH OTHER, FINE GRADE ASPHALT CONCRETE SHALL BE COMPACTED TO FORM RAMPS, MAXIMUM SLOPE OF 8.5% WITH A MINIMUM 1-FOOT TAPER TO COVER ALL EDGES OF THE STEEL PLATES. WHEN STEEL PLATES ARE REMOVED, THE DOWEL HOLES IN THE

PAVEMENT SHALL BE BACKFILLED WITH EITHER GRADED FINES OF ASPHALT CONCRETE MIX, CONCRETE SLURRY, OR AN EQUIVALENT SLURRY SATISFACTORY TO THE INSPECTOR. THE CONTRACTORS SHALL BE RESPONSIBLE FOR MAINTENANCE OF THE STEEL PLATES, AND ASPHALT CONCRETE RAMPS.

10.3. STEEL PLATE BRIDGING SHALL BE DESIGNED FOR HS20-44 TRUCK LOADING PER CALTRANS BRIDGET DESIGN SPECIFICATIONS MANUAL. THE CONTRACTOR SHALL MAINTAIN ON THE STEEL PLATE A NON-SKDI SURFACE HAVING A MINIMUM COEFFICIENT OF FRICTION TO 0.35 AS DETERMINED BY CALIFORNIA TEST METHOD 342. IF A DIFFERENT TEST METHOD IF USED, THE CONTRACTOR MAY UTILIZE STANDARD TEST PLATES WITH KNOWN COEFFICIENTS OF FRICTION TO CORRELATE SKID RESISTANCE RESULTS TO CALIFORNIA TEST METHOD 342.

11. THE CONTRACTOR SHALL PROVIDE TEMPORARY ACCESS TO ALL RESIDENTIAL AND NON-RESIDENTIAL DRIVEWAYS. ACCESS TO RESIDENTIAL DRIVEWAYS MUST BE OPEN AT THE CLOSE OF EACH DAY. ACCESS TO NONRESIDENTIAL DRIVEWAYS MUST BE MAINTAINED THROUGHOUT THE WORKING DAY. IF DRIVEWAYS ARE CLOSED, TEMPORARY ACCESS MUST BE PROVIDED BY THE CONTRACTOR AND APPROVED BY THE CITY

12. ALL EXISTING STREET INTERSECTIONS AND RESIDENTIAL DRIVEWAYS ARE TO BE COMPLETELY OPEN FOR TRAFFIC AT THE END OF EACH WORKING DAY. NO INTERSECTIONS OR STREETS SHALL BE COMPLETELY CLOSED AT ANY TIME. TRAFFIC PLATES AND/OR FLAGMEN SHALL BE PROVIDED BY THE CONTRACTOR AS NECESSARY. NO TRENCHES ARE TO BE LEFT OPEN OVERNIGHT AND SHALL BE PLATED. TRAFFIC LANES WILL BE BACKFILLED DAILY UNLESS OTHERWISE PERMITTED BY THE CITY ENGINEER.

13. THE CONTRACTOR SHALL SALVAGE ALL EXISTING WATERLINE VALVES (4" OR LARGER), WATER METERS, AND FIRE HYDRANTS REMOVED DURING CONSTRUCTION AND DELIVER SAID ITEMS TO THE CITY YARD.

14. PRIOR TO PERFORMING ANY INTERCONNECTION WORK, THE CONTRACTOR SHALL SUBMIT A WORKING SCHEDULE AND WORK PROCEDURE PLAN TO THE INSPECTOR. THE CONTRACTOR SHALL NOT PERFORM ANY INTERCONNECTION WORK UNTIL PERMISSION FOR THIS SCHEDULE AND PLAN HAS BEEN OBTAINED FROM THE PUBLIC WORKS DIRECTOR.

15. ALL UTILITIES AND OTHER STRUCTURES ALONG THE WATER LINES MUST BE POTHOLED AND FIELD VERIFIED BY THE CONTRACTOR PRIOR TO THE START OF CONSTRUCTION. ONCE THESE UTILITIES AND STRUCTURES HAVE BEEN EXPOSED BY THE CONTRACTOR, HE SHALL TAKE MEASUREMENTS AND VERIFY THEIR LOCATION WITH THE CITY'S REPRESENTATIVE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO PROTECT ALL EXISTING FACILITIES, WHETHER OR NOT THEIR EXISTENCE OR APPROXIMATE LOCATIONS ARE SHOWN ON THE PLANS, FROM DAMAGE DURING CONSTRUCTION. ALL UTILITY CROSSINGS AND TIE-IN CONNECTIONS SHALL BE POTHOLED AT LEAST 200 FEET IN ADVANCE OF INSTALLATION OF IMPROVEMENTS IN ORDER TO ADJUST ALIGNMENT IF NEEDED. COST FOR POTHOLING SHALL BE INCLUDED IN CONTRACTOR'S BID.

16. ALL MANHOLES, VALVE BOXES AND SIMILAR APPURTENANT STRUCTURES SHALL BE LEFT BELOW SUBGRADE DURING PAVING AND THE

CONTRACTOR SHALL RAISE SAID STRUCTURES TO FINISHED GRADE AFTER PAVING AND MAKING NECESSARY REPAIRS TO PAVEMENT AND INSURE VALVE BOXES ARE CLEAN FROM ANY SPOILS OF THE CONSTRUCTION PROCESS (TYPICAL FOR ALL, WHETHER SHOWN OR NOT). CONTRACTOR IS

RESPONSIBLE FOR MAPPING VALVES PRIOR TO CONSTRUCTION AND LOCATING AND ADJUSTING TO FINISHED GRADE DURING FINAL PAVEMENT REPLACEMENT.

17. PRIOR TO THE ORDERING OF MATERIALS AND THE CONSTRUCTION OF NEW WATER LINES, THE CONTRACTOR SHALL POTHOLE THE FOLLOWING AREAS OF THE CONSTRUCTION WORK: ALL AREAS OF POINTS OF CONNECTION TO EXISTING WATER MAINS FOR THE PURPOSE OF DETERMINING

EXISTING FITTING OR PIPE MATERIALS, ALL AREAS WHERE THERE IS A POTENTIAL FOR CONFLICTS BETWEEN THE NEW WATERLINE CONSTRUCTION AND EXISTING UTILITY LINE CROSSINGS, ADJACENT UNDERGROUND UTILITIES, AND/OR OTHER SUBSTRUCTURES. THIS EFFORT IS CONSIDERED A

NECESSARY PART OF THE CONSTRUCTION AND INSTALLATION OF THE NEW WATER LINES AND THE COST SHALL BE INCLUDED IN THE CONTRACTOR'S BID.

18. CONTRACTOR SHALL OBTAIN A TEMPORARY WATER METER FROM THE CITY WATER DEPARTMENT AND PAY FOR ALL WATER USED.

19. CONTRACTOR SHALL RESTORE SURFACE FEATURES AND REPAIR DAMAGE TO ADJACENT FACILITIES DAMAGED BY THE CONTRACTOR ACTIVITIES.

20. CONTRACTOR, AT HIS SOLE EXPENSE, SHALL WARRANT AND BE RESPONSIBLE FOR WATER MAIN AND ALL ASSOCIATED APPURTENANCES INCLUDING WATER SERVICES, VALVES, FITTINGS, BLOW-OFFS, AIR RELEASE VALVES, ETC. INSTALLED BY HIS FORCES, FOR A PERIOD OF ONE YEAR AFTER THE CITY ACCEPTS THE IMPROVEMENTS.

21. CONTRACTOR AT HIS SOLE EXPENSE, SHALL BE RESPONSIBLE FOR DEWATERING OF TRENCHES WHENEVER NECESSARY.

22. THE CONTRACTOR SHALL PREPARE AND SUBMIT A TRAFFIC CONTROL PLAN TO THE CITY ENGINEER PRIOR TO THE CONSTRUCTION OF THE PIPELINE. THE CONTRACTOR SHALL ADHERE TO ALL REQUIREMENTS IN PERMITS, TRAFFIC CONTROL PLANS AND CONTRACT DOCUMENTS WITH REGARD TO ACCESS, TRAFFIC ROUTING, HOURS OF CONSTRUCTION AND OTHER TRAFFIC CONTROL REQUIREMENTS. THE CONTRACTOR SHALL PROVIDE ALL AND NECESSARY TRAFFIC CONTROL MEASURES REQUIRED BY THE CITY OR AGENCY OF JURISDICTION. NO EXCAVATION WITHIN THE RIGHT-OF-WAY IS PERMITTED UNTIL THE CONTRACTOR HAS OBTAINED APPROVAL FROM THE CITY ENGINEER.

23. ASBESTOS CEMENT PIPE NOTE: SNAP CUT EXISTING AC PIPE AND REMOVE INTERFERING PORTIONS OF PIPE AS NECESSARY TO PROVIDE ROOM FOR NEW TEE/VALVE ASSEMBLY AND/OR CONNECTING PIPE AND FITTINGS. DO NOT UNDER ANY CIRCUMSTANCES ALLOW ASBESTOS PARTICLES TO BECOME AIRBORNE. DISPOSE OF AC PIPE IN ACCORDANCE WITH LOCAL, STATE AND FEDERAL REGULATION.

24. ALL STEEL PLATES MUST BE RECESSED AND SKID RESISTANT.

25. ALL DRAINAGE INLETS WITHIN THE PROJECT LIMITS MUST BE PROTECTED DURING CONSTRUCTION.

26. ALL DOWEL INSTALLATION SHALL UTILIZE CALTRANS STANDARDS.

27. BOND BREAKER SHALL BE USED BETWEEN JPCP AND LEAN CONCRETE BASE.

28. ALL MATERIALS WITHIN THE STATE OF CALIFORNIA RIGHT OF WAY SHALL FOLLOW CALTRANS STANDARDS.

INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR18 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO.

W-100.

INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO.

W-100.

CONSTRUCT NEW 1" SERVICE LINE PER CITY OF LOMITA STD. PLAN NO. W-101. ABANDON EXISTING SERVICE LINE IN PLACE. CONTRACTOR TO CONNECT TO EXISTING METER AND PROTECT EXISTING METER BOX.

INSTALL NEW 6" FIRE HYDRANT ASSEMBLY PER CITY OF LOMITA STD. PLAN NO. W-110 (INCLUSIVE OF GATE VALVE).

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 13 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 47 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 10 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 22.5 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 13 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 8" X 8" X 8" TEE, (MJ X MJ X MJ).

INSTALL 8" RESILIENT GATE VALVE, (MJ X MJ).

INSTALL 8" TO 6" REDUCER, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 31 FEET BEYOND THE 8 INCH END OF THE REDUCER OR TO THE NEXT FITTING IF THE DISTANCE IS LESS.

INSTALL MECHANICAL JOINT RESTRAINER GLAND (MEGALUGS).

INSTALL DUCTILE IRON (DI) SPOOL (LENGTH TO BE DETERMINED IN FIELD).

INSTALL DUCTILE IRON (DI) RESTRAINED LONG SOLID SLEEVE (MJ X MJ).

INSTALL DUCTILE IRON (DI) BLIND FLANGE.

CONSTRUCT THRUST BLOCK PER CITY OF LOMITA STD. PLAN NO. W-140.

EXISTING CAST IRON (CI) WATER MAIN TO BE ABANDONED IN PLACE. REMOVE INTERFERING PORTIONS, CUT AND PLUG WITH PCC (NO LESS THAN 6" THICK) AND ABANDON.

EXISTING DUCTILE IRON (DI) WATER MAIN. PROTECT IN PLACE.

RECONSTRUCT PCC BUS PAD PER DETAIL. SEE SHEET 10.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8.

PROVIDE TEMPORARY DRAINAGE INLET PROTECTION (CALTRANS STANDARD PLAN T-64 TYPE 6B). THE INSTALLATION SHALL PREVENT

SEDIMENT FROM ENTERING THE CURB INLET WITHOUT BLOCKING ANY PORTION OF THE VEHICLE TRAVEL LANE PER ULTRATECH ULTRA-GUTTER GUARD PLUS OR APPROVED EQUIVALENT.
1a
1b
2 3
4a
4b
4c
5 6
7 8
9 10
11 12
13 14
15 16
17 18

CITY OF LOS ANGELES CALTRANS R/W CITY OF LOMITA CITY OF LOS ANGELES 24911
1739
24911
1801-1811
1800
1728 25001 94.0' 39.8' 34.0' 10.0' 10.2' 29.0' 5.0' 11.9' 1b 1b

33.6'

8.6' 8.4'

10.2'
17 1b 17
DETAIL "A" CONNECTION

NOT TO SCALE
DETAIL "B" CONNECTION

NOT TO SCALE
DETAIL "C" CONNECTION

NOT TO SCALE
R Know what'sbelow. Callbefore you dig.

N
INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

INSTALL 8" X 8" X 8" TEE, (MJ X MJ X MJ).

INSTALL 8" RESILIENT GATE VALVE, (MJ X MJ).

INSTALL MECHANICAL JOINT RESTRAINER GLAND (MEGALUGS).

INSTALL DUCTILE IRON (DI) RESTRAINED LONG SOLID SLEEVE (MJ X MJ).

INSTALL DUCTILE IRON (DI) BLIND FLANGE.

CONSTRUCT THRUST BLOCK PER CITY OF LOMITA STD. PLAN NO. W-140.

EXISTING CAST IRON (CI) WATER MAIN TO BE ABANDONED IN PLACE. REMOVE INTERFERING PORTIONS, CUT AND PLUG WITH PCC (NO LESS THAN 6" THICK) AND ABANDON.

EXISTING DUCTILE IRON (DI) WATER MAIN. PROTECT IN PLACE.

RECONSTRUCT PCC BUS PAD PER DETAIL. SEE SHEET 10.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8. 1b
6 7
9 11
12 13
14 15
16 17

CALTRANS R/W

CITY OF LOS ANGELES
24811-24827
24911 8.0' 2.1' 30.9' 1b1a4a 8.4' 8.6' 33.6' 10.3' 4a 11.0' 5.9' 16 1717 1717 R Know what'sbelow. Callbefore you dig.

N
INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR18 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 13 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

RECONSTRUCT PCC BUS PAD PER DETAIL. SEE SHEET 10.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8. 1a
1b
4a
16 17

CITY OF LOMITA CITY OF LOS ANGELES CITY OF LOS ANGELES CALTRANS R/W 24743
1700
1803 1745 1741 1737 1731 1725 1719 1713 1707
1802 1746 1742 1736 1730 1724 1718 1712 1706 54.0' 14.7' 14.7' 12.3' 12.3' 10.3' 4.4'2.3'

45.0'

12.1' 32.9'

50.0'

50.0'

74.8'

5.9' - 18.9'

7.9'

2.9' 1b 2 2 2 2
2 2 2 2
1b
3 1a

5.8'
17 17
17 17
DETAIL "D" CONNECTION

NOT TO SCALE
DETAIL "E" CONNECTION

NOT TO SCALE
R Know what'sbelow. Callbefore you dig.

N
INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR18 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

CONSTRUCT NEW 1" SERVICE LINE PER CITY OF LOMITA STD. PLAN NO. W-101. ABANDON EXISTING SERVICE LINE IN PLACE. CONTRACTOR TO CONNECT TO EXISTING METER AND PROTECT EXISTING METER BOX.

INSTALL NEW 6" FIRE HYDRANT ASSEMBLY PER CITY OF LOMITA STD. PLAN NO. W-110 (INCLUSIVE OF GATE VALVE).

INSTALL 8" X 8" X 8" TEE, (MJ X MJ X MJ).

INSTALL 8" RESILIENT GATE VALVE, (MJ X MJ).

INSTALL MECHANICAL JOINT RESTRAINER GLAND (MEGALUGS).

INSTALL DUCTILE IRON (DI) RESTRAINED LONG SOLID SLEEVE (MJ X MJ).

CONSTRUCT THRUST BLOCK PER CITY OF LOMITA STD. PLAN NO. W-140.

EXISTING CAST IRON (CI) WATER MAIN TO BE ABANDONED IN PLACE. REMOVE INTERFERING PORTIONS, CUT AND PLUG WITH PCC (NO LESS THAN 6" THICK) AND ABANDON.

EXISTING DUCTILE IRON (DI) WATER MAIN. PROTECT IN PLACE.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8. 1a
1b
2 3
6 7
9 11
13 14
15 17

CITY OF LOS ANGELES CALTRANS R/W CITY OF LOMITA CITY OF LOS ANGELES 24713
1700
1801 1749 1743 1737 1731 1725 1719 1713 1707
1802 1746 1742 1736 1730 1724 1718 1712 1706 5.4' 9.7'2.6' 54.0' 15.0' 14.8' 12.2' 12.0' 5.4' 9.6'11.0' 3.9'

45.0'

12.2' 32.8'

50.0'

50.0'
1b 4a
1b

74.8'

5.9'

8.0'

2.9'
2 2 2 2
2 2 2 2
3 17
17 17
17 17
DETAIL "F" CONNECTION

NOT TO SCALE
DETAIL "G" CONNECTION

NOT TO SCALE
R Know what'sbelow. Callbefore you dig.

N
INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

CONSTRUCT NEW 1" SERVICE LINE PER CITY OF LOMITA STD. PLAN NO. W-101. ABANDON EXISTING SERVICE LINE IN PLACE. CONTRACTOR TO CONNECT TO EXISTING METER AND PROTECT EXISTING METER BOX.

INSTALL NEW 6" FIRE HYDRANT ASSEMBLY PER CITY OF LOMITA STD. PLAN NO. W-110 (INCLUSIVE OF GATE VALVE).

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 13 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 8" X 8" X 8" TEE, (MJ X MJ X MJ).

INSTALL 8" RESILIENT GATE VALVE, (MJ X MJ).

INSTALL 8" TO 6" REDUCER, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 31 FEET BEYOND THE 8 INCH END OF THE REDUCER OR TO THE NEXT FITTING IF THE DISTANCE IS LESS.

INSTALL MECHANICAL JOINT RESTRAINER GLAND (MEGALUGS).

INSTALL DUCTILE IRON (DI) SPOOL (LENGTH TO BE DETERMINED IN FIELD).

INSTALL DUCTILE IRON (DI) RESTRAINED LONG SOLID SLEEVE (MJ X MJ).

CONSTRUCT THRUST BLOCK PER CITY OF LOMITA STD. PLAN NO. W-140.

EXISTING CAST IRON (CI) WATER MAIN TO BE ABANDONED IN PLACE. REMOVE INTERFERING PORTIONS, CUT AND PLUG WITH PCC (NO LESS THAN 6" THICK) AND ABANDON.

EXISTING DUCTILE IRON (DI) WATER MAIN. PROTECT IN PLACE.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8. 1b
2 3
4a
6 7
8 9
10 11
13 14
15 17

CITY OF LOS ANGELES CALTRANS R/W CITY OF LOMITA CITY OF LOS ANGELES 24615
1700
1801 1749 1743 1739 1733 1725 1719 1713 1707
1802 1748 1742 1736 1732 1724 1718 1712 1706 13.6' 4.4'2.4' 60.0' 18.0' 17.8' 12.2' 12.0'

45.0'

12.3' 32.7'

50.0'

50.0'

74.8'

5.9'

7.9'

3.1' 11.8' 1.6' 6.2'
3 1b
1a
17 17
17 17
17 17
17 4a
4a
4a
4a
DETAIL "H" CONNECTION

NOT TO SCALE
DETAIL "I" CONNECTION

NOT TO SCALE
R Know what'sbelow. Callbefore you dig.

N
INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR18 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

INSTALL NEW 6" FIRE HYDRANT ASSEMBLY PER CITY OF LOMITA STD. PLAN NO. W-110 (INCLUSIVE OF GATE VALVE).

INSTALL 8" X 8" X 8" TEE, (MJ X MJ X MJ).

INSTALL 8" RESILIENT GATE VALVE, (MJ X MJ).

INSTALL MECHANICAL JOINT RESTRAINER GLAND (MEGALUGS).

INSTALL DUCTILE IRON (DI) RESTRAINED LONG SOLID SLEEVE (MJ X MJ).

CONSTRUCT THRUST BLOCK PER CITY OF LOMITA STD. PLAN NO. W-140.

EXISTING DUCTILE IRON (DI) WATER MAIN. PROTECT IN PLACE.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8. 1a
1b
3 6
7 9
11 13
15 17
1707 CITY OF LOS ANGELES CALTRANS R/W CITY OF LOMITA CITY OF LOS ANGELES 1801 1749 1745 1739 1733 1727 1721 1717 1711 24513
1802 1748 1744 1738 1732 1726 1720 1716 1710 1706 1700 10.6' 4.4'3.0' 54.0' 15.0' 14.8'

45.0' 12.2' 12.0'

12.1' 32.9'

74.8'

6.0'

8.0'

3.0'

50.0'

50.0'
1b 2 2
2 2
2 2
2 2
1b
3 17
17 DETAIL "J" CONNECTION

NOT TO SCALE
DETAIL "K" CONNECTION

NOT TO SCALE
DETAIL "L" CONNECTION

NOT TO SCALE
R Know what'sbelow. Callbefore you dig.

N
INSTALL NEW 8" POLYVINYL CHLORIDE (PVC) C900 DR14 WATER MAIN. CONSTRUCT TRENCH BACKFILL PER CITY OF LOMITA STD. PLAN NO. W-100.

CONSTRUCT NEW 1" SERVICE LINE PER CITY OF LOMITA STD. PLAN NO. W-101. ABANDON EXISTING SERVICE LINE IN PLACE. CONTRACTOR TO CONNECT TO EXISTING METER AND PROTECT EXISTING METER BOX.

INSTALL NEW 6" FIRE HYDRANT ASSEMBLY PER CITY OF LOMITA STD. PLAN NO. W-110 (INCLUSIVE OF GATE VALVE).

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 47 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 45 DEGREE BEND, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 10 FEET BEFORE AND AFTER BEND OR TO NEXT FITTING IF DISTANCE IS LESS.

INSTALL 8" X 8" X 8" TEE, (MJ X MJ X MJ).

INSTALL 8" RESILIENT GATE VALVE, (MJ X MJ).

INSTALL 8" TO 6" REDUCER, (MJ X MJ). INSTALL RESTRAINING JOINTS A MINIMUM OF 31 FEET BEYOND THE 8 INCH END OF THE REDUCER OR TO THE NEXT FITTING IF THE DISTANCE IS LESS.

INSTALL MECHANICAL JOINT RESTRAINER GLAND (MEGALUGS).

INSTALL DUCTILE IRON (DI) SPOOL (LENGTH TO BE DETERMINED IN FIELD).

INSTALL DUCTILE IRON (DI) RESTRAINED LONG SOLID SLEEVE (MJ X MJ).

INSTALL DUCTILE IRON (DI) BLIND FLANGE.

CONSTRUCT THRUST BLOCK PER CITY OF LOMITA STD. PLAN NO. W-140.

EXISTING CAST IRON (CI) WATER MAIN TO BE ABANDONED IN PLACE. REMOVE INTERFERING PORTIONS, CUT AND PLUG WITH PCC (NO LESS THAN 6" THICK) AND ABANDON.

EXISTING DUCTILE IRON (DI) WATER MAIN. PROTECT IN PLACE.

INSTALL 45 DEGREE BENDS AROUND EXISTING UTILITY PER DETAIL L ON SHEET 8. 1b
2 3
4b
4c
6 7
8 9
10 11
12 13
14 15
17 R Know what'sbelow. Callbefore you dig.

TYPICAL TRENCH DETAIL IN

CALTRANS RIGHT-OF-WAY

NOT TO SCALE

TYPICAL TRENCH DETAIL IN

CITY OF LOS ANGELES RIGHT-OF-WAY

NOT TO SCALE

TYPICAL TRENCH DETAIL IN

CITY OF LOMITA RIGHT-OF-WAY

NOT TO SCALE

NOTES TO CONTRACTOR

1. ALL WORK MUST BE AUTHORIZED BY THE ENCROACHMENT PERMIT, AND/OR AS DIRECTED BY THE STATE'S REPRESENTATIVE.

2. ALL TRACER WIRE MUST BE PLACED ON TOP OF THE CONDUIT UNLESS SPECIFIED NOT TO.

3. CLEARANCE BETWEEN THE TRENCH WALL AND ENCROACHMENT WORK LESS THAN 6 INCHES IN WIDTH SHALL BE A MINIMUM OF 2 INCHES.

CLEARANCE BETWEEN THE TRENCH WALL AND ENCROACHMENT WORK GREATER THAN 6 INCHES WIDTH SHALL BE A MINIMUM 6 INCHES.

4. WHEN THE TRENCH WIDTH IS LESS THAN 2' THE BACKFILL FOR SUBGRADE MUST CONSIST OF EITHER SLURRY CEMENT OR CONTROLLED LOW-STRENGTH MATERIAL (CLSM).

5. WHEN TRENCH WIDTH IS GREATER THAN 2' COMPACTED AGGREGATE BASE MAY BE USED FOR BACKFILL.

6. STRUCTURE BACKFILL MUST CONFORM TO SECTION 19-3.02C OF THE STANDARD SPECIFICATIONS.

7. FOR TRENCH LOCATED UNDER UNIMPROVED SURFACE, STRUCTURE BACKFILL CAN USE THE ORIGINAL SOIL. SOIL MUST BE COMPACTED BY MECHANICAL MEANS, PONDING, JETTING OR FLOODING ARE NOT ALLOWED. SLURRY CEMENT BACKFILL IS OPTIONAL AT THE DISCRETION OF THE CALTRANS DISTRICT.

8. SLURRY CEMENT BACKFILL MUST CONFORM TO SECTION 19-3.03E OF THE STANDARD SPECIFICATIONS.

9. AGGREGATE BASE SHALL CONFORM TO SECTION 26 OF THE STANDARD SPECIFICATIONS.

10. CLSM MUST CONFORM TO SECTION 19-3.02G OF THE STANDARD SPECIFICATIONS. WHEN CLSM IS UTILIZED THE MIX DESIGN AND TEST RESULTS MUST BE SUBMITTED TO THE STATE'S REPRESENTATIVE. SEE APPENDIX H OF THE ENCROACHMENT PERMITS MANUAL FOR ADDITIONAL INFORMATION.

11. COLD PLANED SURFACE AND OVERLAY SHALL BE TO THE NEAREST LANE LINE FOR THE ENTIRE LENGTH OF THE TRENCH/DISTURBED AREAS, AND/OR AS DIRECTED BY THE STAT'S REPRESENTATIVE.

12. A PAVING NOTCH ("T" CUT) SHALL BE COLD PLANED IN EXIST ASPHALT CONCRETE TO A MINIMUM WIDTH OF 1.0' BEYOND EACH SIDE OF THE TRENCH AND TO A DEPTH OF 3" FOR THE FINAL LAYER OF HMA.

13. HMA OR PCC TO REPLACE PAVEMENT SECTION SHAL MATCH EXISTING PAVEMENT DEPTH, UNLESS DIRECTED OTHERWISE BY THE STAT'S REPRESENTATIVE.

14. HOT MIX ASPHALT MUST CONFORM TO CALTRANS SPECIFICATION SECTION 39.

15. A TACK COAT OF ASPHALTIC EMULSION CONFORMING TO CALTRANS SPECIFICATION SECTION 39-2.01C (3) (f) SHALL BE APPLIED.

16. WHEN THE TRENCH IS WITHIN 4' OF CURB AND GUTTER, ADDITIONAL COLD PLANING MAY BE REQUIRED AT THE DISCRETION OF THE STATE'S REPRESENTATIVE.

17. PAVEMENT MARKINGS AND/OR STRIPING REMOVED OR DAMAGED DURING CONSTRUCTION MUST BE REPLACED AS DIRECTED BY THE STAT'S REPRESENTATIVE.

18. OTHER TRENCH RELATED DETAILS ARE SHOWN IN CHAPTER 6 OF THE ENCROACHMENT PERMITS MANUAL AS WELL AS THE TRENCHING AND SHORING MANUAL. BOTH PUBLICATIONS CAN BE FOUND ON THE STATE OF CALIFORNIA, DEPARTMENT OF TRANSPORTATION'S WEBSITE.

R Know what'sbelow. Callbefore you dig.

TYPICAL BUS PAD DETAILS

NOT TO SCALE
BUS
R Know what'sbelow. Callbefore you dig.

N

CALTRANS R/W

CITY OF LOS ANGELES

CALTRANS R/W

CITY OF LOS ANGELES
R Know what'sbelow. Callbefore you dig.

N
N
N

CALTRANS R/W

CITY OF LOS ANGELES

CITY OF LOS ANGELES

CALTRANS R/W CITY OF LOMITA CITY OF LOS ANGELES CITY OF LOS ANGELES CALTRANS R/W CALTRANS R/W CITY OF LOS ANGELES R Know what'sbelow. Callbefore you dig.

N
N
N
MAINTAIN 5' PEDESTRIAN WALKWAY WITHIN CROSSWALK AT ALL TIMES, OR PROVIDE FLAGGER TO ESCORT PEDESTRIANS THROUGH WORK AREA DURING WORK HOURS.

R Know what'sbelow. Callbefore you dig.

N
R Know what'sbelow. Callbefore you dig.

N
R Know what'sbelow. Callbefore you dig.

N
R Know what'sbelow. Callbefore you dig.

N
R Know what'sbelow. Callbefore you dig. N
R Know what'sbelow. Callbefore you dig. N
R Know what'sbelow. Callbefore you dig. N

CITY OF LOS ANGELES CALTRANS R/W CITY OF LOS ANGELES CALTRANS R/W R Know what'sbelow. Callbefore you dig.

NPDES NOTES:

N
LEGEND
PROVIDE TEMPORARY DRAINAGE INLET PROTECTION (CALTRANS STANDARD PLAN T-64 TYPE 6B). THE INSTALLATION SHALL PREVENT SEDIMENT FROM ENTERING THE CURB INLET WITHOUT BLOCKING ANY PORTION OF THE VEHICLE TRAVEL LANE PER ULTRATECH ULTRA-GUTTER GUARD PLUS OR APPROVED EQUIVALENT. 18 CITY OF LOMITA
24300 Narbonne Avenue
Lomita, CA 90717

CONTRACT DOCUMENTS AND SPECIFICATIONS
FOR
247
th STREET AREA WATER MAIN REPLACEMENT

BID OPENING
XXX XX, 2023
1:00 P.M.

Under the Supervision of:
__ ___ XX-XX-XXXX_____________
Name, Title Date
XXXXXX 2023
i

TABLE OF CONTENTS

SECTION A-NOTICE INVITING BIDS (A)
NOTICE INVITING BIDS..……………………………………………………... A-2

SECTION B-INSTRUCTIONS TO BIDDERS (B)
I. QUALIFICATION OF BIDDERS ……..………………………………..……..B-2
II. BIDDER’S RESPONSIBILITY ……………………………………………….B-3
III. ADDENDA TO CONTRACT DOCUMENT ………...……………………... B-3 IV. PREPARATION OF THE BID ………………..……………………………. B-4
V. BID BOND ……………………………………………………………………..B-5
VI. NON-RESPONSIVE BIDS AND REJECTION ………...………………….B-5 VII. AWARD OF CONTRACT …………………………………………………. B-5
VIII. EXECUTION OF CONTRACT …………………………………………….B-5
IX. APPRENTICESHIP EMPLOYMENT STANDARDS ……………………. B-6
X. PERMIT, LICENSE AND PUBLIC WORKS AGREEMENT …………..... B-6 XI. INSURANCE ………………………………………………………………… B-6
XII. PRE-BID INQUIRIES ……………………………………………………… B-6
XIII. LABOR CODE – SB 854 …………………………………………………. B-6
XIV. PREVAILING WAGE ……………………………………………………. B-6
XV. GUIDELINES DURING COVID-19 PANDEMIC………………………….B-6

SECTION C-BID DOCUMENTS
BIDDERS PROPOSAL …………………………………………………….…… C-2
CONTRACTOR’S AFFIDAVIT ……………………………………………….…C-7
BID BOND (10%) ………………………………….……………………………. C-9
LIST OF SUBCONTRACTORS ……………………………………………….. C-10
CONSTRUCTION PROJECT REFERENCES………………………….……. C-11
VIOLATIONS OF FEDERAL, STATE OR LOCAL LAWS ……..……….…... C-12 DISQUALIFICATION OR DEBARMENT …………………………..…….…... C-13
SECTION D – DOCUMENTS TO BE COMPLETED AND DELIVERED TO CITY

AFTER AWARD OF CONTRACT
PUBLIC WORKS AGREEMENT ................................................................. D-2 CONSTRUCTION OR SERVICE CONTRACT ENDORSEMENT .............. D-11 PERFORMANCE BOND ............................................................................. D-13 LABOR AND MATERIAL BOND ……………………………………............... D-15 WORKERS' COMPENSATION INSURANCE CERTIFICATION..................D-18

SECTION E - SPECIAL PROVISIONS

APPENDIX I - CONSTRUCTION AND DEMOLITION DEBRIS RECYCLING

SUMMARY

APPENDIX II - CITY BUSINESS LICENSE APPLICATION

APPENDIX III - CITY OF LOMITA WATER STANDARD PLANS
APPENDIX IV – CITY OF LOS ANGELES U PERMIT
APPENDIX V – CALTRANS ENCROACHMENT PERMIT
A-1

SECTION A

NOTICE INVITING BIDS
A-2

CITY OF LOMITA, CALIFORNIA

NOTICE INVITING BIDS
NOTICE IS HEREBY GIVEN that the City of Lomita, County of Los Angeles, California (hereinafter “City”) will receive sealed bids at the Office of the City Clerk, City Hall, 24300 Narbonne Avenue, Lomita CA 90717 until 1:00 PM on Day, Month XX, 2023 at which time all bids will be publicly opened and read in the City Council Chamber at the above address for:
247

TH STREET AREA WATER MAIN REPLACEMENT
This project consists of water main installations on 246th St, 247th St, 247th Pl, 248th St, Western Ave, and Lomita Blvd. The existing 4-inch/6-inch water main system was constructed between 1928 and 1930 and has exceeded its useful service life. To provide improved flow, pressure and fires protection, installing approximately 3,300 linear feet of new 8-inch PVC water mains is needed. The existing water main currently runs along the property line and the new 8-inch main will be installed in the street along 246th St, 247th St, 247th Pl, 248th St, Western Avenue and Lomita Blvd. Improvements will include trenching and installation of new 8-inch PVC water main, water main fittings, valves, water services, water meters and fire hydrants.

The Contractor shall perform all work required for such construction in accordance with the Contract Documents and subject to the terms and conditions of the Contract, complete and ready for use.

Each bid must be submitted in writing on a bid proposal furnished by the City. Bids must conform and be responsive to all contract documents. All bids must be sealed and must be plainly marked in the lower left-hand corner “247TH STREET AREA WATER MAIN REPLACEMENT”.

Plans and Specifications may be downloaded and printed from the City’s website at no charge at: https://lomitacity.com/current-bids-rfps/ Prospective bidders who only view and/or print the Plans and Specifications from the City’s website will not automatically be added to the City’s Plan Holder list for this project unless they send an email to the City at [email protected] and provide the firm’s name, address, telephone and contact person with a valid email address. This will ensure that the prospective bidder is listed as a “Plan Holder” and will be informed of any addenda and all information issued subsequent to obtaining the official form of proposal.

A-3
Addenda will be posted on the City website, but it shall be the bidder’s responsibility to inquire for any addenda/updates to this Notice Inviting Bid prior to submitting their bid.

Each proposal must be accompanied by a cash deposit, a certified or cashier's check, or a bidder's bond, made payable to the City of Lomita, in an amount not less than 10 percent of the total bid submitted.

The successful bidder will be required to furnish a faithful performance bond in the amount of 100 percent of the contract price, and a payment bond in the amount of 100 percent of the contract price, both in a form satisfactory to the City Attorney. The successful bidder will also be required to pay the State of California prevailing wage scale as determined by the Department of Industrial Relations, available at http://www.dir.ca.gov/Public-Works/PublicWorks.html.

The City reserves the right to reject any or all bids and to waive any informality or irregularity in any bid received and to be the sole judge of the merits of the respective bids received. The award, if made, will be made to the lowest responsible bidder. Plans and Specifications will be available for review at City Hall.

The contractor shall possess a valid State of California Contractors License, Class A.

All work shall be completed within 80 working days from the date of the Notice to Proceed (NTP).

All questions regarding this bid must be submitted in writing on or before 1:00 PM on Day, Month XX, 2023, to the Project Manager, via email at [email protected].

Kathleen Horn Gregory, CMC,
City Clerk
Publish in Daily Breeze on Date 1 and Date 2, 2023
B-1

SECTION B

INSTRUCTIONS TO BIDDERS
B-2

INSTRUCTIONS TO BIDDERS
I. QUALIFICATION OF BIDDERS

1. Competency of Bidders
The Bidder shall be thoroughly competent and capable of satisfactorily performing the Work covered by the Bid. As specified in the Bid Documents, the Bidder shall furnish statements of previous experience on similar work. When requested, the Bidder shall also furnish the plan of procedure proposed; the organization, machinery, plant and other equipment available for the Work; evidence of its financial condition and resources; and any other such documentation as may be required by the City to determine if the Bidder is responsible.

2. Contractor's License
At the time of submitting the Bid, the Bidder shall be licensed as a contractor in accordance with the provisions of Chapter 9, Division 3, of the California Business and Professions Code. The required prime contractor license for this project is a Class A Contractor’s license. However, the City reserves the right to award the Contract to a contractor with another class if the City determines that the license is proper for the work.

3. Contractor Registration Requirements
SB 854 amended the Labor Code to require all contractors bidding on public work to register with the Department of Industrial Relations (DIR) and to pay an annual fee. The registration requires contractors to provide the State with evidence of the contractors' compliance with a number of statutory requirements. The registration requirement took effect on July 1, 2014.

4. Bidder’s Submittal and Contract Award Prohibited
Under California Labor Code section 1771.1, as amended by SB 854, unless registered with the DIR, a contractor may not bid, nor be listed as a subcontractor, for any bid proposal submitted for public work on or after March 1, 2015. Similarly, a public entity cannot award a public work contract to a non-registered contractor, effective April 1, 2015. Also refer to Section 5-3.1 of the Special Provisions.

5. Bidder Qualifications
Bidder Qualifications called for to be submitted at the time of bid include, but are not necessarily limited to:

B-3
a. The Contractor shall have been in business under the same name and California Contractor’s License for a minimum of 10 continuous years prior to the bid opening date for this project. The license used to satisfy this requirement shall be of the same type as required by the contract. b. The Contractor shall provide a minimum of 3 references for the construction of street rehabilitation projects which have been successfully completed in the State of California with a construction cost of at least $2M. during the past 5 years
c. The Contractor or the Subcontractor performing the construction of street rehabilitation shall have a minimum of 10 years’ experience under the same name and California Contractor’s License
d. The Contractor shall perform above 50% of the contract with its own forces.

II. BIDDER RESPONSIBILITY
A responsible Bidder is a Bidder who has demonstrated the attribute of trustworthiness, as well as ability, fitness, capacity and experience to satisfactorily perform the work.

Bidders are notified that, in accordance with the Lomita Municipal Code, the City Council may determine whether the Bidder is responsible based on a review of the Bidder's performance on other contracts.

If, based on the provisions and criteria set forth in the Lomita Municipal Code, the Public Works Director proposes not to recommend the award of contract to the apparent low bidder, the Director shall notify the Bidder in writing of its intention to recommend to the City Council that the Council award the contract to the 2nd lowest responsible bidder. If the Bidder presents evidence in rebuttal to the recommendation, the Director shall evaluate the merits of such evidence, and based on that evaluation, make a recommendation to the City Council.

III. ADDENDA TO THE CONTRACT DOCUMENTS
The City may issue Addenda to the Contract Documents during the period of advertising for any reason. The Bidder shall acknowledge the receipt of the Addenda in their Bid. Failure of the Bidder to do so may result in the rejection of the Bid as non-responsive.

Addenda will be posted on the City website, but it shall be the bidder’s responsibility to inquire for any addenda/updates to this Notice Inviting Bid prior to submitting their bid.

IV. PREPARATION OF THE BID
B-4

1. Examination of Site, Plans and Specifications
Prior to submitting a Bid, the Bidder shall examine the Plans and the Work site, carefully read the Specifications, and satisfy itself that it has the abilities and resources to complete the Work. The Bidder agrees that if it is awarded the Contract, no claim will be made against the City based on ignorance or misunderstanding of the provisions of the Contract Documents, the nature and amount of the work, and the physical and climatic conditions of the work site.

The Contractor shall have included in the contract price a sufficient sum to cover all items, including labor, materials, tools, equipment and incidentals, that are implied or required for the complete improvements as contemplated by the drawings, specifications, and other contract documents.

2. Estimated Quantities
The quantities shown in the Bid are approximate only. The Contractor will be paid for the actual quantities of work based on field measurements as provided for in these Specifications. The City reserves the right to increase or decrease the amount of any item or portion of work to be performed or materials furnished, or to delete any item, in accordance with the Specifications.

3. Bid Instructions and Submissions
The Bid shall be submitted on the Bid Proposal forms included with the Specifications. All Bid Documents must be completed, executed and submitted with the Bid by the Bidder.

Required seven (7) Bid Proposal Documents:
1) Bidder's Proposal
2) Contractor's Affidavit
3) Bid Bond (10%)
4) List of Subcontractors
5) Construction Project References
6) Violations of Federal or State Law
7) Disqualification or Debarment
All prices submitted will be considered as including any and all sales or use taxes. The Bid Proposal must be completed in ink or in typewritten form.

The bid sum and all bid amounts on the form must be stated in words and numerals; in case of a conflict, words will take precedence.

B-5
In the case of discrepancy between unit bid price and total bid, the unit price shall prevail.

V. BID BOND
Each bid shall be accompanied by Bidder's Security in an amount equal to ten (10) percent of the bid amount, which security shall be lawful money of the United States of America and in one of the following forms: (i) cashier's check made payable to the City of Lomita, (ii) certified check made payable to the City of Lomita, or (iii bid bond executed by an admitted surety insurer and made payable to the City of Lomita. City Bid Bond form must be used.

VI. NON-RESPONSIVE BIDS AND BID REJECTION

1. A Bid in which any one (1) of the required eight (8) Bid proposal documents are not completed, executed and submitted may be considered nonresponsive and be rejected.

2. A Bid in which the Contract Unit Prices are unbalanced, which is incomplete or which shows alteration of form or irregularities of any kind, or which contains any additions or conditional or alternate Bids that are not called for, may be considered non-responsive and be rejected.

VII. AWARD OF CONTRACT
In accordance with the Lomita Municipal Code, the City Council reserves the right to reject any and all bids received, to take all bids under advisement for a period not-to-exceed ninety (90) days after date of opening thereof, to waive any informality or irregularity in the Bid, and to be the sole judge of the merits of material included in the respective bids received.

VIII. EXECUTION OF CONTRACT
After the Contract is awarded, the awardee shall execute the following eight (8) documents:
1) Contract - Public Works Agreement
2) Construction or Service Contract Endorsement
3) Performance Bond (100% of Bid price)
4) Labor and Material Bond (100% of Bid price)
5) Workers' Compensation Insurance Certificate
6) Verification of Insurance Coverage (Certificates and Endorsements) 7) Construction Permit Application Form
8) Business License Application Form
B-6
IX. APPRENTICESHIP EMPLOYMENT STANDARDS
The Contractor is directed to the provisions in Sections 1776, 1777.5 and 1777.6 of the California Labor Code concerning the employment of apprentices by the contractor or any subcontractor under them.

X. PERMITS, LICENSES AND PUBLIC WORKS AGREEMENT
The Contractor shall procure and execute all permits, licenses, pay all charges and fees, and give all notices necessary and incidental to the completion of the Work. The Contractor shall execute a Public Works Agreement. A no fee Excavation Permit will be issued by the City of Lomita for this project. The Contractor shall obtain a City of Lomita Business License.

XI. INSURANCE
The Contractor shall maintain Automobile Liability, General Liability and Workers' Compensation Insurance as specified in the Public Works Agreement included in the Project Specifications.

XII. PRE-BID INQUIRIES
A Bidder with a Pre-Bid Inquiry must e-mail their question(s) on or before 1:00 PM on Tuesday, Nov XX, 2023, to the Project Manager, via email at [email protected]. Questions received after this date may not be considered.

XIII. LABOR CODE – SB 854
The bidder shall be registered with the Department of Industrial Relations (DIR) in accordance with the provisions of Section 1771.1 of the California Labor Code, as amended by SB 854. No public work contract may be awarded to a non-registered contractor or subcontractor after April 15, 2015.

XIV. PREVAILING WAGE
Pursuant to Section 1773 of the Labor Code, the general prevailing wage rates in the county, or counties, in which the work is to be done have been determined by the Director of the California Department of Industrial Relations. These wages are set forth in the General Prevailing Wage Rates for this project, available from the California Department of Industrial Relations’ Internet web site at http://www.dir.ca.gov/DLSR/PWD
XV. GUIDELINES DURING COVID-19 PANDEMIC
Contractors shall comply with all local, state and federal laws and regulations B-7
including, but not limited to, the Governor’s and Los Angeles County Health Officer’s orders and guidance related to COVID-19, social distancing, and best practices.

Contractors are required to check with the latest guidelines of the Los Angeles County Public Works and the Los Angeles County Public Health for construction sites during the Coronavirus/COVID-19 pandemic.

C-1

SECTION C

BID DOCUMENTS
(TO BE SUBMITTED WITH BID PACKAGE)
C-2
BIDDER’S PROPOSAL
247TH STREET AREA WATER MAIN REPLACEMENT
Company: _____________________________________________________ Honorable Mayor and Members
of the Lomita City Council
Lomita, California
In accordance with the Notice Inviting Bids pertaining to the receiving of sealed proposals by the City Clerk of the City of Lomita for the above titled improvement, the undersigned hereby proposes to furnish all Work to be performed in accordance with the Plans, Specifications, Standard Drawings, and the Contract Documents, for the unit price or lump sum set forth in the following schedule.

The undersigned hereby acknowledges that he/she has examined the copies of the plans, specifications and all Contract Documents for this project and is fully aware of scope of the work.

The undersigned also acknowledges that he/she has examined the project site and locality where the work is to be performed and the legal requirements and conditions affecting the cost, progress and performance of the work in strict accordance with the Contract Documents.

The undersigned also acknowledges that timely completion o f t h e p r o j e c t is important to the City. Therefore time being of the essence, he/she proposes that the work will be commenced and will be completed within the time specified in the Notice Inviting Bids.

Specification or Items not indicated on Bid Form: The Contractor is to accommodate those portions of the work required by the specifications or contract documents, whose method of payment is not included in other bid items elsewhere.

In addition, bid items costs associated with bonds, insurance, traffic control, labor, equipment, materials, overhead, profits, any and all other indirect costs shall be considered full compensation for each bid item.

All work shall be completed within 80 working days from the date the notice to proceed is issued by the Engineer.

C-3

PROJECT BID SCHEDULE
Item
No.

Item Description Qty. Unit Unit
Price Total Bid
1 Mobilization and demobilization. 1 LS $ $
2 Traffic control. 1 LS $ $
3 Excavation safety measures. 1 LS $ $
4 Construction surveying. 1 LS $ $
5 Water pollution control (includes BMP
installation and maintenance). 1 LS $ $
6 Re-establish survey monuments. 1 LS $
7 Sawcutting. 1 LS $ $
8 Construct new 8” PVC C900 DR 18
water main, including but not limited
to furnishing of fittings and end caps.

Construction shall be per City of
Lomita Standards and include
trenching, bedding, and backfill.
670 LF $ $
9 Construct new 8” PVC C900 DR 14
water main, including but not limited
to furnishing of fittings and end caps.

Construction shall be per City of
Lomita Standards and include
trenching, bedding, and backfill.
3,260 LF $ $
10 Provide and install 8” gate valve. 18 EA $ $
11 Furnish and install 1” water service,
connect to existing meter and box. 32 EA $ $
12 Cut existing water main and remove
interfering portions. Plug with
concrete and abandon.
1 LS $ $
13 Connect to existing water main
(includes installation of transition
coupling, if required per plans).
5 EA $ $
C-4
14 Construct AC pavement base course
including subgrade and base
preparation per City of Lomita trench
detail.
2,430 SF $ $
15 Cold plane asphalt concrete (2”)
depth per City of Lomita standards. 270 SY $ $
16 Construct AC pavement cap per City
of Lomita trench detail. 30 TON $ $
17 Construct AC pavement base course
including subgrade and base
preparation per City of Los Angeles
trench detail.
7,570 SF $ $
18 Cold plane asphalt concrete (2”)
depth per City of Los Angeles
standards.
841 SY $ $
19 Construct AC pavement cap per City
of Los Angeles trench detail. 95 TON $ $
20 Construct AC pavement base course
including subgrade and base
preparation per Caltrans trench
detail.
815 SF $ $
21 Cold plane asphalt concrete (2”)
depth per Caltrans standards.
91 SY $ $
22 Construct AC pavement cap per City
of Caltrans trench detail. 10 TON $ $
23 Construct PCC bus pad including
dowel installation, subgrade and base
preparation per Caltrans standards.
795 SF $ $
24 Replace damaged pavement striping,
markings, reflectors, legends. 1 LS $ $
25 Soil sampling if hazardous soil is
encountered (As Needed Only) 5 EA $ $
26 Excavation, haul away and disposal
of hazardous soil if encountered (As
Needed Only)
180 TN $ $
TOTAL BID (Items 1 through 26) $
TOTAL BID:

C-5
(Figures)
(Words)
*BID MAY BE REJECTED IF TOTAL IS NOT SHOWN IN FIGURES AND WORDS.

The undersigned furthermore agrees to enter into and execute a contract, with necessary bonds, at the unit prices set forth herein and in case of default in executing such contract, with necessary bonds, the check or bond accompanying this bid and the money payable thereon shall be forfeited thereby to and remain the property of the City of Lomita.

The above unit prices include all work appurtenant to the various items as outlined in the Specifications and all work or expense required for the satisfactory completion of said items. In case of discrepancies between unit prices and totals, the unit prices shall govern.

The undersigned declares that it has carefully examined the Plans, Specifications, and Contract Documents, and has investigated the site of the work and is familiar with the conditions thereon.

Contractor ______________________________
Date: _______________________ By:

Contractor’s State License No.: ___________Class______ Exp. Date:

Contractor’s Address: _________________________________________________ Phone: _______________________
C-6

CONTRACTOR'S AFFIDAVIT
STATE OF CALIFORNIA }
}
COUNTY OF _____________}
___________________________________________________, being first duly sworn, deposes and says:

1. That he is the ____________________________________________________ Title
of
(Name of Partnership, Corporation, or Sole Proprietorship) hereinafter called "Contractor," who has submitted to the City of Lomita a proposal for:
247TH STREET AREA WATER MAIN REPLACEMENT

2. That said proposal is genuine; that the same is not sham; that all statement of facts therein are true;

3. That such proposal was not made in the interest or behalf of any person, partnership, company, association, organization or corporation not named or disclosed;

4. That the Contractor did not, directly or indirectly, induce, solicit or agree with anyone else to submit a false or sham bid, to refrain from bidding, or to withdraw the bid, to raise or fix the bid price of the Contractor or anyone else, or to raise or fix any overhead, profit or cost element of the Contractor's price or the price of anyone else; and did not attempt to induce action prejudicial to the interest of the City of Lomita, or of any other bidder, or anyone else interested in the proposed contract;

5. That the Contractor has not in any manner sought by collusion to secure for itself an advantage over any other bidder or to induce action prejudicial to the interests of the City of Lomita, or of any other bidder or of anyone else interested in the proposed contract;

6. That the Contractor has not accepted any bid from any subcontractor or materialman through any bid depository, the bylaws, rules or regulations of which prohibit or prevent the Contractor from considering any bid from any subcontractor or materialman, which is not processed through said bid depository, or which prevent any subcontractor or materialman from bidding to any contractor who does not use the facilities of or accept bids from or through such bid depository;
C-7

7. That the Contractor did not, directly or indirectly, submit the Contractor's bid price or any breakdown thereof, or the contents thereof, or divulge information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, or to any individual or group of Individuals, except to the City of Lomita, or to any person or persons who have a partnership or other financial interest with said Contractor in its business.

Dated this _________ day of __________________________, 2023 Subscribed and Sworn to ________________________
Contractor
________________________
Title
before me this _________ day of _____________________, 2023. _________________________________
Notary Public in and for said
County and State.
(Seal)
C-8
BID BOND (10%)
KNOW ALL MEN BY THESE PRESENTS: That we,
_________________________________
as principal, and
as sureties, are held and firmly bound unto the City of Lomita, State of California, in the penal sum of ________________________ dollars ($______________), for the payment whereof we hereby bind ourselves, our successors, heirs, executors or administrators jointly and severally, firmly by these presents.

The condition of this obligation is such that, whereas the above bounded principal is about to file with and submit to the City of Lomita a bid or proposal for the performance of certain work as required in the City of Lomita, said work being: 247TH STREET AREA WATER MAIN REPLACEMENT in compliance with the Specifications therefor under an invitation of said City contained in a notice or advertisement for bids or proposals; now if the bid or proposal of the said principal shall be accepted and if the said work be thereupon awarded to the principal by said City and if the said principal shall enter into a contract with the said City in accordance with said bid or proposal, or if the bid or proposal of the said principal is rejected, then this bond shall be void and of no effect and otherwise in full force and effect.

WITNESS our hands this ______ day of _______________, 20___. ______________________________
Principal
______________________________
Surety/Attorney-in-Fact
______________________________
Signature
Name:

Local Address:

Phone No.:

Fax No.:

C-9

LIST OF SUBCONTRACTORS
247TH STREET AREA WATER MAIN REPLACEMENT
The Bidder is required to fill in the following blanks in accordance with the provisions of the Subletting and Subcontracting Fair Practices Act (Chapter 2 of Division 5, Title 1 of the Government Code of the State of California) and should familiarize itself with Section 2-3 of the Standard Specifications.

Name Under Which Subcontractor is Licensed:________________________________ License Number: ___________
Address of Office, Mill or Shop: ____________________________________________ Specific Description of Sub-Contract:________________________________________ Name Under Which Subcontractor is Licensed:________________________________ License Number: ___________
Address of Office, Mill or Shop: ____________________________________________ Specific Description of Sub-Contract:________________________________________ Name Under Which Subcontractor is Licensed:________________________________ License Number: ___________
Address of Office, Mill or Shop: ____________________________________________ Specific Description of Sub-Contract:________________________________________ Name Under Which Subcontractor is Licensed:________________________________ License Number: ___________
Address of Office, Mill or Shop: ____________________________________________ Specific Description of Sub-Contract:________________________________________ Subcontractors listed in accordance with the provisions of Section 2-3 must be properly licensed under the laws of the State of California for the type of work which they are to perform. Do not list alternate subcontractors for the same work.

C-10

CONSTRUCTION PROJECT REFERENCE
(Work similar in magnitude and degree of difficulty completed by Contractor within the past three [3] years.)

1. Name (Firm/Agency): _____________________________________________ Address: ________________________________________________________ Contact Person: Telephone No.: __________________
Title of Project: ___________________________________________________ Project Location: __________________________________________________ Date of Completion: Contract Amount: $ ____________

2. Name (Firm/Agency): _____________________________________________ Address: ________________________________________________________ Contact Person: Telephone No.: __________________
Title of Project: ___________________________________________________ Project Location: __________________________________________________ Date of Completion: Contract Amount: $ ____________

3. Name (Firm/Agency): _____________________________________________ Address: ________________________________________________________ Contact Person: Telephone No.: __________________
Title of Project: ___________________________________________________ Project Location: __________________________________________________ Date of Completion: Contract Amount: $ ____________
C-11

VIOLATIONS OF FEDERAL, STATE OR LOCAL LAWS

1. Has your firm or its officers been assessed any penalties by an agency for noncompliance or violations of Federal, State or Local labor laws and/or business or licensing regulations within the past five (5) years relating to your construction projects?
Yes/No: ____________________Federal/State:____________________ If “yes,” identify and describe, (including agency and status):

Have the penalties been paid? Yes/No:

2. Does your firm or its officers have any ongoing investigations by any public agency regarding violations of the State Labor Code, California Business and Professions Code or State Licensing Laws?
Yes/No: ______ Code/Laws: ____________ Section/Article: _______________ If “yes,” identify and describe, (including agency and status):

C-12

DISQUALIFICATION OR DEBARMENT
Has your firm, any officer of your firm, or any employee who has a proprietary interest in your firm ever been disqualified, removed, or otherwise prevented from bidding on, performing work on, or completing a federal, state or local project because of a violation of law or a safety regulation? Yes/No: _______________. If yes, provide the following information (if more than once, use separate sheets):

Date: _______________ Entity:

Location:

Reason:

Provide Status and any Supplemental Statement:

Has your firm been reinstated by this entity? Yes/No:

D-1

SECTION D

CONTRACT DOCUMENTS

TO BE SUBMITTED
WITHIN TWENTY ONE (21) CALENDAR DAYS

AFTER AWARD OF CONTRACT
D-2

CITY OF LOMITA

PUBLIC WORKS AGREEMENT

CITY OF LOMITA

PUBLIC WORKS AGREEMENT
This Public Works Agreement (“Agreement”) is made and entered into as of the date executed by the City Manager and attested to by the City Clerk, by and between (hereinafter referred to as "CONTRACTOR") and the City of Lomita, California, a municipal corporation (hereinafter referred to as "CITY").

R E C I T A L S
A. Pursuant to the Notice Inviting Sealed Bids for 247TH STREET AREA WATER MAIN REPLACEMENT, bids were received, publicly opened, and declared on the date specified in the notice.

B. On XXXX XX, 2023, Lomita’s City Council declared CONTRACTOR to be the lowest responsible bidder and accepted the bid of CONTRACTOR.

C. The City Council has authorized the City Manager to execute a written contract with CONTRACTOR for furnishing labor, equipment and material for the 247TH STREET AREA WATER MAIN REPLACEMENT Project in the City of Lomita.

NOW, THEREFORE, in consideration of the foregoing and the mutual covenants herein contained, it is agreed:

1. GENERAL SCOPE OF WORK: CITY agrees to engage CONTRACTOR and CONTRACTOR agrees to furnish all necessary labor, tools, materials, appliances, and equipment for and do the work for the 247th Street Area Water Main Replacement Project in the City of Lomita. The work shall be performed in accordance with the Plans and Specifications dated XXXX 2023 (the “Specifications” attached as Exhibit A) and in accordance with bid prices set forth in CONTRACTOR’S Bid Proposal (attached as Exhibit B) and in accordance with the instructions of the City Engineer.

2. INCORPORATED DOCUMENTS TO BE CONSIDERED COMPLEMENTARY:

The contract documents for the aforesaid project, a complete set of which is on file with the Lomita City Clerk’s Office, shall consist of the Notice Inviting Bids, Instructions to Bidders, Bid Proposal, Builders General Provisions, Standard Specifications, Special Provisions, and all referenced specifications, details, standard drawings, and appendices; together with this Agreement and all required bonds, insurance certificates, permits, notices and affidavits; and also, including any and all addenda or supplemental agreements clarifying, amending, D-3
or extending the work contemplated as may be required to insure its completion in an acceptable manner. All of the provisions of said contract documents are made a part hereof as though fully set forth herein. This contract is intended to require a complete and finished piece of work and anything necessary to complete the work properly and in accordance with the law and lawful governmental regulations shall be performed by CONTRACTOR whether set out specifically in the contract or not. Should it be ascertained that any inconsistency exists between the aforesaid documents and this written agreement, the provisions of this Agreement, the Builders General Provisions and the Standard Specifications, in that order, shall control. Collectively, these contract documents constitute the complete agreement between CITY and CONTRACTOR and supersede any previous agreements or understandings.

3. COMPENSATION: CONTRACTOR agrees to receive and accept the prices set forth in its Bid Proposal as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder. Said compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the aforesaid contract documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work.

4. TIME OF PERFORMANCE: CONTRACTOR agrees to complete the work within 80 working days from the date of the notice to proceed. By signing this Agreement, CONTRACTOR represents to CITY that the contract time is reasonable for completion of the work and that CONTRACTOR will complete such work within the contract time. In accordance with Government Code Section 53069.85, CONTRACTOR agrees to forfeit and pay CITY as liquidated damages, not as a penalty, the sum of $1000.00 per day for each and every day of unauthorized delay beyond the completion date, which amount shall be deducted from any payments due or to become due the CONTRACTOR.

5. PREVAILING WAGES:

Pursuant to Labor Code § 1720, and as specified in 8 California Code of Regulations § 16000, CONTRACTOR must pay its workers prevailing wages. It is CONTRACTOR’s responsibility to interpret and implement any prevailing wage requirements and CONTRACTOR agrees to pay any penalty or civil damages resulting from a violation of the prevailing wage laws.

In accordance with Labor Code § 1773.2, copies of the prevailing rate of per diem wages are available upon request from CITY’s Engineering Division or the website for State of California Prevailing wage determination at http://www.dir.ca.gov/DLSR/PWD. CONTRACTOR must post a copy of the prevailing rate of per diem wages at the job site.

CITY directs CONTRACTOR’s attention to Labor Code §§ 1777.5, 1777.6 and 3098 concerning the employment of apprentices by CONTRACTOR or any subcontractor.

D-4
Labor Code § 1777.5 requires CONTRACTOR or subcontractor employing tradesmen in any apprenticeship occupation to apply to the joint apprenticeship committee nearest the site of the public works project and which administers the apprenticeship program in that trade for a certificate of approval. The certificate must also fix the ratio of apprentices to journeymen that will be used in the performance of the contract. The ratio of apprentices to journeymen in such cases will not be less than one to five except:

When employment in the area of coverage by the joint apprenticeship committee has exceeded an average of 15 percent in the 90 days before the request for certificate, or
When the number of apprentices in training in the area exceeds a ratio of one to five, or
When the trade can show that it is replacing at least 1/30 of its membership through apprenticeship training on an annual basis state-wide or locally, or When CONTRACTOR provides evidence that CONTRACTOR employs registered apprentices on all of his contracts on an annual average of not less than one apprentice to eight journeymen.

CONTRACTOR is required to make contributions to funds established for the administration of apprenticeship programs if CONTRACTOR employs registered apprentices or journeymen in any apprenticeable trade on such contracts and if other contractors on the public works site are making such contributions.

CONTRACTOR and any subcontractor must comply with Labor Code §§ 1777.5 and 1777.6 in the employment of apprentices.

Information relative to apprenticeship standards, wage schedules and other requirements may be obtained from the Director of Industrial Relations, ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.

CONTRACTOR and its subcontractors must keep an accurate certified payroll records showing the name, occupation, and the actual per diem wages paid to each worker employed in connection with this Agreement. The record will be kept open at all reasonable hours to the inspection of the body awarding the contract and to the Division of Labor Law Enforcement. If requested by CITY, CONTRACTOR must provide copies of the records at its cost.

6. LEGAL HOURS OF WORK: Eight (8) hours of labor shall constitute a legal day's work for all workmen employed in the execution of this contract, and CONTRACTOR and any subcontractor under it shall comply with and be governed by the laws of the State of California having to do with working hours D-5
set forth in Division 2, Part 7, Chapter 1, Article 3 of the Labor Code of the State of California as amended.

CONTRACTOR shall forfeit, as a penalty to CITY, twenty-five dollars ($25.00) for each laborer, workman or mechanic employed in the execution of the contract, by him or any subcontractor under it, upon any of the work hereinbefore mentioned, for each calendar day during which the laborer, worker or mechanic is required or permitted to labor more than eight (8) hours in violation of the Labor Code.

7. TRAVEL AND SUBSISTENCE PAY: CONTRACTOR agrees to pay travel and subsistence pay to each worker needed to execute the work required by this Agreement as such travel and subsistence payments are defined in the applicable collective bargaining agreements filed in accordance with Labor Code Section 1773.8.

8. CONTRACTOR'S LIABILITY: The City of Lomita and its officers, agents and employees ("Indemnitees") shall not be answerable or accountable in any manner for any loss or damage that may happen to the work or any part thereof, or for any of the materials or other things used or employed in performing the work; or for injury or damage to any person or persons, either workers or employees of CONTRACTOR, of its subcontractors or the public, or for damage to adjoining or other property from any cause whatsoever arising out of or in connection with the performance of the work. CONTRACTOR shall be responsible for any damage or injury to any person or property resulting from defects or obstructions or from any cause whatsoever.

CONTRACTOR will indemnify Indemnitees against and will hold and save Indemnitees harmless from any and all actions, claims, damages to persons or property, penalties, obligations or liabilities that may be asserted or claimed by any person, firm, entity, corporation, political subdivision, or other organization arising out of or in connection with the work, operation, or activities of CONTRACTOR, its agents, employees, subcontractors or invitees provided for herein, whether or not there is concurrent passive negligence on the part of any Indemnitee. In connection therewith:
a. CONTRACTOR will defend any action or actions filed in connection with any such claims, damages, penalties, obligations or liabilities and will pay all costs and expenses, including attorneys' fees, expert fees and costs incurred in connection therewith.
b. CONTRACTOR will promptly pay any judgment rendered against CONTRACTOR or Indemnitees covering such claims, damages, penalties, obligations and liabilities arising out of or in connection with such work, operations or activities of CONTRACTOR hereunder, and CONTRACTOR agrees to save and hold the Indemnitees harmless therefrom.
c. In the event Indemnitees are made a party to any action or proceeding filed or prosecuted against CONTRACTOR for damages or other claims arising out of or in connection with the work, operation or activities hereunder, CONTRACTOR agrees to pay to Indemnitees and any all costs and expenses incurred by Indemnitees in such action or proceeding together with reasonable attorneys' fees.

D-6
CONTRACTOR'S obligations under this section apply regardless of whether or not such claim, charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine or penalty, or liability was caused in part or contributed to by an Indemnitee. However, without affecting the rights of CITY under any provision of this agreement, Contractor shall not be required to indemnify and hold harmless CITY for liability attributable to the active negligence of CITY, provided such active negligence is determined by agreement between the parties or by the findings of a court of competent jurisdiction. In instances where CITY is shown to have been actively negligent and where CITY active negligence accounts for only a percentage of the liability involved, the obligation of Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of City.

So much of the money due to CONTRACTOR under and by virtue of the contract as shall be considered necessary by CITY may be retained by CITY until disposition has been made of such actions or claims for damages as aforesaid.

It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California.

This indemnity provision shall survive the termination of the Agreement and is in addition to any other rights or remedies which Indemnitees may have under the law.

This indemnity is effective without reference to the existence or applicability of any insurance coverage which may have been required under this Agreement or any additional insured endorsements which may extend to Indemnitees.

CONTRACTOR, on behalf of itself and all parties claiming under or through it, hereby waives all rights of subrogation and contribution against the Indemnitees, while acting within the scope of their duties, from all claims, losses and liabilities arising out of or incident to activities or operations performed by or on behalf of the CONTRACTOR regardless of any prior, concurrent, or subsequent passive negligence by the Indemnitees.

9. THIRD PARTY CLAIMS. In accordance with Public Contracts Code § 9201, CITY will promptly inform CONTRACTOR regarding third-party claims against CONTRACTOR, but in no event later than ten (10) business days after CITY receives such claims. Such notification will be in writing and forwarded in accordance with the “Notice” section of this Agreement. As more specifically detailed in the contract documents, CONTRACTOR agrees to indemnify and defend the City against any third-party claim.

10. WORKERS COMPENSATION: In accordance with California Labor Code Sections 1860 and 3700, CONTRACTOR and each of its subcontractors will be required to secure the payment of compensation to its employees. In accordance with the provisions of California Labor Code Section 1861, CONTRACTOR, by signing this contract, certifies as follows: "I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

D-7

11. INSURANCE: With respect to performance of work under this contract, CONTRACTOR shall maintain and shall require all of its subcontractors to maintain insurance as required in the Builders General Provisions.

12. ASSIGNMENT: This Agreement is not assignable nor the performance of neither party's duties delegable without the prior written consent of the other party. Any attempted or purported assignment or delegation of any of the rights of obligations of either party without the prior written consent of the other shall be void and of no force and effect.

13. INDEPENDENT CONTRACTOR: CONTRACTOR is and shall at all times remain as to the CITY, a wholly independent contractor. Neither the CITY nor any of its agents shall have control of the conduct of CONTRACTOR or any of CONTRACTOR'S employees, except as herein set forth. CONTRACTOR shall not at any time or in any manner represent that it or any of its agents or employees are in any manner agents or employees of CITY.

14. TAXES: CONTRACTOR is responsible for paying all retail sales and use, transportation, export, import, special or other taxes and duties applicable to, and assessable against any work, materials, equipment, services, processes and operations incidental to or involved in this contract. CONTRACTOR is responsible for ascertaining and arranging to pay them. The prices established in the contract shall include compensation for any taxes CONTRACTOR is required to pay by laws and regulations in effect at the bid opening date.

15. LICENSES: CONTRACTOR represents and warrants to CITY that it has all licenses, permits, qualifications, insurance, and approvals of whatsoever nature which are legally required of CONTRACTOR to practice its profession.

CONTRACTOR represents and warrants to CITY that CONTRACTOR shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this Agreement any licenses, permits, insurance, and approvals which are legally required of CONTRACTOR to practice its profession. CONTRACTOR shall maintain a City of Lomita business license, if required under CITY ordinance.

16. RECORDS: CONTRACTOR shall maintain accounts and records, including personnel, property, and financial records, adequate to identify and account for all costs pertaining to this Agreement and such other records as may be deemed necessary by CITY or any authorized representative, and will be retained for three years after the expiration of this Agreement. All such records shall be made available for inspection or audit by CITY at any time during regular business hours.

17. SEVERABILITY. If any portion of these contract documents are declared by a court of competent jurisdiction to be invalid or unenforceable, then such portion will be deemed modified to the extent necessary in the opinion of the court to render such portion enforceable and, as so modified, such portion and the balance of this Agreement will continue in full force and effect provided that it does not frustrate the mutual intent of the parties herein.

18. WHOLE AGREEMENT: This Agreement supersedes any and all other agreements either oral or written, between the parties and contains all of the D-8
covenants and agreements between the parties pertaining to the work of improvements described herein. Each party to this Agreement acknowledges that no representations, inducements, promises, or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which are not embodied herein, and that any other agreement, statements, or promise not contained in this Agreement shall not be valid or binding. Any modification of this Agreement will be effective only if signed by the party to be charged.

19. AUTHORITY: CONTRACTOR affirms that the signatures, titles, and seals set forth hereinafter in execution of this Agreement represent all individuals, firm members, partners, joint ventures, and/or corporate officers having a principal interest herein. Each party warrants that the individuals who have signed this Agreement have the legal power, right, and authority to make this Agreement and to bind each respective party. This Agreement may be modified by written amendment. CITY’s City Manager may execute any such amendment on CITY’s behalf.

20. NOTICES: All notices permitted or required under this Agreement shall be in writing and shall be deemed made when delivered to the applicable party’s representative as provided in this Agreement. Additionally, such notices may be given to the respective parties at the following addresses, or at such other addresses as the parties may provide in writing for this purpose.

Such notices shall be deemed made when personally delivered or when mailed forty-eight (48) hours after deposit in the U.S. mail, first-class postage prepaid, and addressed to the party at its applicable address. Courtesy copies of notices may be sent via electronic mail, provided that the original notice is deposited in the U.S. mail or personally delivered as specified in this Section.

21. DISPUTES. Disputes arising from this Agreement will be determined in accordance with the contract documents and Public Contracts Code §§ 10240- 10240.13.

22. NON-DISCRIMINATION: No discrimination shall be made in the employment of persons in the work contemplated by this Agreement because of race, religion, color, medical condition, sex, sexual orientation, national origin, political affiliation or opinion, or pregnancy or pregnancy-related condition. A violation of this

CITY OF LOMITA, CA
24300 Narbonne Avenue, Lomita, CA 90717
Attention:

CONTRACTOR:
______________________
________________________________
Attention:

D-9
section exposes CONTRACTOR to the penalties provided for in Labor Code Section 1735.

23. NO THIRD PARTY BENEFICIARY. This Agreement and every provision herein is for the exclusive benefit of the Contractor and the City and not for the benefit of any other party. There will be no incidental or other beneficiaries of any of the Contractor’s or the City’s obligations under this Contract.

24. TIME IS OF ESSENCE. Time is of the essence for each and every provision of the Contract Documents.

25. ACCEPTANCE OF FACSIMILE OR ELECTRONIC SIGNATURES. The Parties agree that this Agreement will be considered signed when the signature of a party is delivered by facsimile transmission, scanned and delivered via electronic mail, or delivered using digital signature technology approved by CITY. Such facsimile or electronic signatures will be treated in all respects as having the same effect as an original signature.

26. GOVERNING LAW: This Agreement shall be governed by the laws of the State of California, and exclusive venue for any action involving this Agreement will be in Los Angeles County.

D-10
IN WITNESS WHEREOF, the parties hereto have executed this Agreement with all the formalities required by law on the respective dates set forth opposite their signatures.

State of California
CONTRACTOR’S License No.

CONTRACTOR
By:

DATE
CONTRACTOR’S Business Phone
Emergency Phone at which CONTRACTOR can be reached at any time:

CITY OF LOMITA, CALIFORNIA
By:

DATE Ryan Smoot, CITY MANAGER
ATTEST:

By:

DATE Kathleen Horn Gregory, CITY CLERK
APPROVED AS TO FORM:

By:

DATE Trevor Rusin, CITY ATTORNEY
Attachments: Exhibit A: Contractor’s Bid Proposal
D-11

CITY OF LOMITA

CONSTRUCTION OR SERVICE CONTRACT ENDORSEMENT
To be attached to and made a part of all policies insuring the liability of any person, form or corporation performing services under contract for the City of Lomita.

Not withstanding any inconsistent expression in the policy to which this endorsement is attached, or in any other endorsement now or hereafter attached thereto, or made a part thereof, the protection afforded by said policy shall:

1. Include the City of Lomita as an additional insured. (To include the elected officials, appointed officials, and employees.)

2. Indemnify and save harmless the City of Lomita against any and all claims resulting from the undertaking specified in the contract known as:

PROPOSAL, SPECIFICATIONS, BOND AND AFFIDAVIT
FOR
247TH STREET AREA WATER MAIN REPLACEMENT
This hold harmless assumption on the part of the underwriters shall include all costs of investigation and defense, including claims based on damage to substructures not shown, not located on the plans, or shown incorrectly.

3. Not be cancelled except by notice to the City Attorney of the City of Lomita at least thirty (30) days prior to the date of cancellation.

4. Provide single limit for Bodily Injury Liability and Property Damage Liability combined, $3,000,000 each Occurrence, and $5,000,000 Aggregate.

5. Limited classifications, restricting endorsements, exclusions or other special provisions contained in the policy shall not act to limit the benefits of coverage as they shall apply to the City of Lomita as enumerated in this endorsement.

However, nothing herein contained shall affect any rights of the insurer against the insured.

6. It is further expressly agreed by and between the parties hereto that the following two provisions, (a) and (b), are a part of this contract:
(a) That the CONTRACTOR specifically agrees to comply with applicable provisions of Section 1777.5 of the Labor Code relating to the employment by contractor or subcontractor under it, of journeyman or apprentices, or workmen, in any apprenticeable craft or trade.
(b) By my signature hereunder, as CONTRACTOR, I certify that I am aware of the provisions of Section 3700 of the Labor Code which requires every employer to be insured against liability for Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that code, D-12
and I will comply with such provisions before commencing the performance of the work of this contract.

The limits of liability as stated in this endorsement apply to the insurance afforded by this endorsement notwithstanding that the policy may have lower limits of liability applying elsewhere in the policy.
______________________________
Duly Authorized Agent
Attached to and forming part of
Policy No.: _______________
of the: ___________________
Date: ____________________
Expiration Date: ___________
D-13

PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS:

That we, as Principal(s) and
a corporation, incorporated, organized, and existing under the laws of the State of _____________, and authorized to execute bonds and undertakings and to do a general surety business in the State of California, as Surety, are jointly and severally held and firmly bound unto the City of Lomita, a municipal corporation, located in the County of Los Angeles, State of California, in the full and just sum of:
______________________________________________________________ Dollars ($__________________), lawful money of the United States of America, for the payment of which sum, well and truly to be made, we bind ourselves and our respective heirs, executors, administrators, representative, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that: WHEREAS, said Principal(s) have/has entered into, or are/is about to enter into, a certain written contract or agreement, dated as of the ______ day of ____________, 20____, with the said City of Lomita for the 247TH STREET AREA WATER MAIN REPLACEMENT, all as is more specifically set forth in said contract or agreement, a full, true and correct copy of which is hereunto attached, and hereby referred to and by this reference incorporated herein and made a part hereof;
NOW, THEREFORE, if the said Principal(s) shall faithfully and well and truly do, perform and complete, or cause to be done, performed and complete, each and all of the covenants, terms, conditions, requirements, obligations, acts and things, to be met, done or performed by said Principal(s), including any guarantee period as set forth in, or required by, said contract or agreement, all at and within the time or times, and in the manner as therein specified and contemplated, then this bond and obligation shall be null and void; otherwise it shall be and remain in full force, virtue and effect.

The said Surety, for value received, hereby stipulates and agrees that no amendment, change, extension of time, alteration or addition to said contract or agreement, or of any feature or item or items of performance required therein or thereunder, shall in any manner affect its obligations on or under this bond; and said Surety does hereby waive notice of any such amendment, change, extension of time, alteration, or addition to said contract or agreement, and of any feature or item or items of performance required therein or thereunder.

D-14

PERFORMANCE BOND (CONTINUED)
In the event any suit, action or proceedings is instituted to recover on this bond or obligation, said Surety will pay, and does hereby agree to pay, as attorney's fees for said City, such sum as the Court in any such suit, action or proceeding may adjudge reasonable.

EXECUTED, SEALED AND DATED this _________ day of _____________, 20____.

CORPORATE SEAL PRINCIPAL(S):

BY _____________________________
BY _____________________________
CORPORATE SEAL SURETY:

BY _____________________________
D-15

LABOR AND MATERIAL BOND
KNOW ALL MEN BY THESE PRESENTS:

That we, ________________________________________________ as Principal(s) and ____________________________________________ a corporation, incorporated, organized, and existing under the laws of the State of ______________, and authorized to execute bonds and undertakings and to do a general surety business in the State of California, as Surety, are jointly and severally held and firmly bound unto:
(a) The State of California for the use and benefit of the State Treasurer, as exofficio Treasurer and custodian of the Unemployment Fund of said State; and (b) The City of Lomita, California; and
(c) Any and all persons who do or perform or who did or performed work or labor upon or in connection with the work or improvement referred to in the contract or agreement hereinafter mentioned; and
(d) Any and all materialmen, persons, companies, firms, association, or corporations, supplying or furnishing any materials, provisions, provender, transportation, appliances or power, or other supplies used in, upon, for or about or in connection with the performance of the work or improvement contracted to be executed, done, made or performed under said contract or agreement; and (e) Any and all persons, companies, firms, associations, or corporations furnishing, renting, or hiring teams, equipment, implements or machinery for, in connection with, or contributing to, said work to be done or improvement to be made under said contract or agreement; and
(f) Any and all persons, companies, firms, associations, or corporations who supply both work and materials;
and whose claim has not been paid by said Principal(s), in full and just sum of ______________________________________________________________ Dollars ($___________________), lawful money of the United States of America, for the payment of which will and truly to be made, said Principal(s) and said Surety do hereby bind themselves and their respective heirs, executors, administrators, representatives, successors and assigns, jointly and severally, firmly by these presents.

D-16

LABOR AND MATERIAL BOND (CONTINUED)
THE CONDITION OF THE FOREGOING OBLIGATION IS SUCH, THAT: WHEREAS, said Principal(s) have/has entered into or are/is about to enter into a certain written contract or agreement, dated as of the _______ day of __________________20 ___, with the City of Lomita for the 247TH STREET AREA WATER MAIN REPLACEMENT, all as is more specifically set forth in said contract or agreement, a full, true and correct copy of which is hereunto attached, and hereby referred to and by this reference incorporated herein and made a part hereof;
NOW, THEREFORE, if the said Principal(s) (or any of his/her, its, or their subcontractors) under said contract or agreement fails or fail to pay:
(1) For any materials, provisions, provender, transportation, appliances, or power, or other supplies; or
(2) For the hire of any teams, equipment, implements, or machinery; or (3) For any work or labor; supplies, furnished, provided, used, done or performed in, upon, for or about or in connection with the said work or improvement; or (4) For amounts due under the Unemployment Insurance Act of the State of California with respect to such work or improvement;
the Surety on this bond will pay the same in an amount not exceeding the sum hereinabove specified in this bond; and, also, in case suit is brought upon this bond, said Surety will (and does hereby agree to) pay a reasonable attorney's fee, to be fixed and taxed as costs, and included in the judgment therein rendered.

This bond shall (and it is hereby made to) insure to the benefit of any and all persons entitled to file claims under Section 1192.1 of the Code of Civil Procedure of the State of California, so as to give a right of action to them or their assigns in any suit brought upon this bond, all as contemplated under the provisions of Section 4205 of the Government Code, and of Chapter 1 of Title 4 of Part 3 of the Code of Civil Procedure, of the State of California.

This bond is executed and filed in connection with said contract or agreement hereunto attached to comply with each and all of the provisions of the laws of the State of California above mentioned or referred to, and of all amendments thereto, and the obligors so intend and do hereby bind themselves accordingly.

D-17

LABOR AND MATERIAL BOND (CONTINUED)
The said Surety, for value received, hereby stipulates and agrees that no amendment, change, extension of time, alteration, or addition to said contract or agreement, or of any feature or item or items of performance required therein or thereunder, shall in any manner affect its obligations on or under this bond; and said Surety does hereby waive notice of any such amendment, change, extension of time, alteration, or addition to said contract or agreement, and of any feature or item or items of performance required therein or thereunder.

EXECUTED, SEALED AND DATED this ______ day of __________________, 20 ___ CORPORATE SEAL PRINCIPAL:

BY ______________________________
CORPORATE SEAL SURETY:

BY ______________________________
D-18

WORKERS' COMPENSATION INSURANCE CERTIFICATION
247

TH STREET AREA WATER MAIN REPLACEMENT
In compliance with Section 7-4 of the Standard Specifications, the CONTRACTOR shall complete and submit the following certification with a Certificate of Insurance before execution of the contract.

I am aware of, and will comply with, Section 3700 of the Labor Code, requiring every employer to be insured against liability for Workers' Compensation or to undertake selfinsurance before commencing any of the work.

DATED: _______________________
_____________________________

CONTRACTOR
By: _________________________
Signature
Title:_________________________
E-1

SECTION E

SPECIAL PROVISIONS
The following Special Provisions supplement and amend the latest editions of the Standard Specifications for Public Works Construction (SSPWC “Greenbook”), and the Standard Specification of the State of California Department of Transportation (Caltrans), as noted herein. These Special Provisions have been arranged in a format that parallels the SSPWC “Greenbook” Standard Specifications.

E-2
PART 1 - GENERAL PROVISIONS
SECTION 1 - GENERAL, TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE,

AND SYMBOLS
1-2 TERMS AND DEFINITIONS. Add or redefine the following:

AGENCY – The City of Lomita, herein referred to as City.

BOARD – The City Council of the City of Lomita, herein referred to as City Council.

ENGINEER –The Public Works Director/City Engineer of the City of Lomita, acting either directly or through properly authorized agents, such agents acting within the scope of the particular duties entrusted to them.

CLAIM -- A separate demand by the Contractor for (A) a time extension, (B) payment of money or damages arising from work done by or on behalf of the Contractor pursuant to the Contract and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (C) an amount the payment of which is disputed by the Agency. 1-7 AWARD AND EXECUTION OF THE CONTRACT.
1-7.1 General. Replace the entire sub-section with the following:

Within twenty one (21) calendar days after the date of the City’s award of contract, the Contractor shall execute and return all Contract Documents required by the City. The City reserves the right to terminate the award if the above requirement is not met. Such termination will result in the forfeiture of the Proposal Guaranty.

Per Lomita Municipal Code the City of Lomita reserves the right to reject any and all proposals, to waive any informality or irregularity in such bids, and determine the lowest responsible bidder.

The Contract Agreement shall not be considered binding upon the City until executed by the authorized City officials.
1-7.2 Contract Bonds. Add the following
The "Performance Bond" shall remain in effect for one year following the date specified in the Notice of Completion or, if no Notice of Completion is recorded, for one year following the date of final acceptance of the project by the City Council.

SECTION 2 - SCOPE OF THE WORK
2-1 WORK TO BE DONE. Add the following:

Scope of Work. The Work generally consists of furnishing all labor, materials, tools, equipment, and incidentals necessary to construct new water mains on 246th Street, 247th Street, 247th Place, 248th Street, Lomita Boulevard, and Western Avenue as specified in the Specifications and these Special Provisions, and as directed by the Engineer.

E-3
The Work also includes all necessary traffic control; preparing and updating construction schedules; posting signs for “NO PARKING” and arranging for towing of cars, if necessary; protecting all utility covers in place; and installing temporary pavement markers. 2-2 PERMITS. Replace the subsection with the following:

The Contractor shall obtain a Business License and Encroachment Permit before commencing construction.
2-5.4 HAUL ROUTES.

Only the designated truck routes shall be used for hauling materials away from the job site or delivering materials to the job site
2-5.4.1 VEHICULAR ACCESS -
When the Contractor begins excavation of a residential driveway, safe access shall be provided within 4 hours and not later than the end of the same workday in which excavation began.

The Contractor shall be responsible to provide at least 48 hour written notice to each affected property before closing or partially closing any driveway or pedestrian access.

At least three (3) days prior to starting work in any location or any street closure, the Contractor shall distribute written notices to all homeowners and residents within 100 feet of the project that will be impacted by the work. The written notices shall be reviewed and approved by City before the Contractor sending them out.
1) The Contractor shall provide a minimum 1-inch thick temporary asphalt surface for an access ramp or sidewalk if it is not able to install the permanent improvement within 5 working days following the removal of the existing material at any location.

The offset at any transverse or longitudinal joint shall not be more than one-half (1/2) inch. On the temporary asphalt surface: the running slope shall not exceed 1:20; the cross slope shall not exceed 1:50. The Contractor shall not be allowed any additional compensation for the installation and removal of temporary asphalt.

Should any change in these requirements be necessitated by extraordinary occurrences or requirements during the execution of the Work, the Contractor shall obtain prior written approval of the Engineer.

Add the following subsections:
2-5.4.2 TRAFFIC CONTROL PLAN - Traffic control plans have been included in the construction plan set and have been approved by Caltrans and the City of Los Angeles Department of Transportation for traffic control set-ups within their jurisdictions. The Contractor hereby understands and agrees that failure to adhere to, or deviation from, the approved traffic control plans, without prior approval of the Engineer, shall constitute a breach of Contract.

Full compensation for complying with the submittal requirements, furnishing, placing and removing traffic control shall be on a lump sum basis per the Contract Unit Price. 2-5.4.3 TEMPORARY PAVEMENT MARKINGS - Temporary pavement markers/striping shall be provided by the Contractor prior to leaving the Work site. These temporary markings shall be as follows:

E-4
All temporary striping and signs shall be maintained, or replaced as necessary by the Contractor, until permanent striping are restored.

All costs associated with the above requirements shall be included in the Contract Unit Price for Traffic Control.
2-5.4.4 TEMPORARY “NO PARKING" SIGNS - The Contractor is responsible to post "Temporary No Parking" signs at least seventy two (72) hours in advance of the first date of work and the required enforcement. If work is to begin on either a Monday or Tuesday, the Contractor shall post the signs on a Friday. Each sign must include text indicating the beginning and end dates and the hours in effect. "Tow-Away" and "No Parking" must be shown on each sign face. If it is required to temporarily restrict parking 24 hours/day then "Tow-Away" and "No Parking Anytime" must be shown on each sign face. The signs shall be mounted on either 1” x 2” X 3’ high wood stakes, Type II barricades, or 39-inch high delineators. Signs shall be spaced at approximately 100’ intervals on the effected side(s) of the street. Signs shall not be posted on trees, traffic signal poles, utility poles, street lights, or any other street furniture.

Signs shall be professionally made of moisture-resistant, heavy duty cardboard or other approved material. All signs shall be maintained by the Contractor and kept free of graffiti. Any sign that becomes illegible or is removed shall be replaced within twenty-four (24) hours. The Contractor shall only be permitted to restrict parking for the minimum time necessary to complete on-going work. The Contractor shall be responsible to remove and repost "Temporary No Parking" signs when work will be delayed for more than five (5) consecutive days, or if the work must go beyond the end date shown on the signs, or otherwise directed by the Engineer.

The Contractor shall obtain approval for the signs and the placement thereof from the Engineer.

Immediately after this approval and posting, the Contractor shall notify Los Angeles County Sheriff Department – Lomita Station, (310) 539-1661 for review and enforcement. The parking restriction cannot be enforced until the signs have been in place 48 hours and the Police notified.

The Contractor shall maintain said signs through the day of work, and shall remove all of said signs on or within one (1) calendar day of the completion of work within the restricted parking area.

Full compensation for furnishing, placing, maintaining and removing temporary signs shall be considered as included in the Contract Unit Price for Traffic Control Add the following subsection:
2-5.4.5 TRASH PICK-UP - Trash pick-up days are as follow:
- Wednesdays
The Contractor shall ensure streets affected by the work are accessible to the City’s trash trucks.
2-5.4.6 STREET CLOSURES, DETOURS, BARRICADES
In addition to the requirements of this subsection, the Contractor shall conform to the requirements for street closures, detours, and barricades as stipulated in the Special Provisions.

However, deviations from the requirements stipulated in the Special Provisions may be E-5
permitted upon written approval of the Public Works Director when such deviations are in the best interest of the City.

Replace the second paragraph with the following:

The Contractor shall notify the Public Works Department at (310) 325-7110, at least ten (10) working days in advance of closing or partially closing any street and comply with their requirements. In addition, the Contractor shall notify the Los Angeles County Sheriffs Department, (310) 539 -1661 and Los Angeles County Fire Department at (310) 326-2461 at least two (2) working days in advance of such closing.

Add the following:

The Contractor shall install, maintain, and remove all temporary delineators, barricades, lights, warning signs and other devices necessary to control traffic as specified in the project plans, traffic control plans and these specifications. Materials for a temporary facility may be provided from new or used materials. If used materials are provided, they shall be sound, in good condition and otherwise meet the requirements of new materials. All traffic control devices shall be free of graffiti, and the Contractor shall be responsible to immediately clean and/or replace any device to the satisfaction of the Engineer.

Full compensation for furnishing, installing, maintaining and removing the above traffic control devices shall be considered as included in the Contract Unit Price for Traffic Control.

Where streets in which improvements are being constructed are specified hereinafter to be closed to through traffic, it shall be understood that such closures shall apply only to the portions of such streets where construction is actually in progress.

After award of the contract, the Contractor shall submit to the City its proposed schedule for closure based on the Traffic Control Plan and comply with the requirements specified herein.

This submittal shall be made sufficiently in advance (street closure schedules MUST be submitted ten (10) days prior to closing the affected street) of any rerouting or diversion of traffic by the Contractor to allow for a review of the Contractor's proposed traffic control by the Public Works Director.
2-5.4.7 PROJECT CONSTRUCTION SIGNS AND PORTABLE CHANGEABLE MESSAGE SIGNS - The Contractor shall furnish and install signs at locations to be determined by the Engineer. The signs shall be in accordance with City of Lomita Standard Plan No. T503.

The Contractor shall furnish and install two (2) Portable Changeable Message signs (PCMS) on the construction site for use during construction of the project and including two weeks prior to the start of construction. Each PCMS shall be manufactured by Solar Tech and be model MB2 (contact BC Rentals at (714) 279-6868 for information). The Contractor shall install a locking device on each PCMS to prohibit access to the computer keyboard. The Contractor shall provide to the Engineer the key or combination to each locking device and the computer password to each PCMS OR possess any equipment, on any working day, to enter or modify a message for each PCMS as directed by the Engineer. Contractor shall relocate each PCMS as directed by Engineer at no additional cost to the City.

Full compensation for furnishing, installing, maintaining and removing signs shall be on a lump sum basis as part of the Traffic Control Bid Item.

E-6
2-8 EXTRA WORK
Add the following:

Payment for additional work and all expenditures in excess of the Contract Price must be authorized in writing by the Engineer. Such authorization shall be obtained by the Contractor prior to engaging in additional work. It shall be the Contractor's sole responsibility to obtain written approval from the Engineer for any change(s) in material or in the work proposed by suppliers or subcontractors. No payment shall be made to the Contractor for additional work which has not been approved in writing, and the Contractor hereby agrees that it shall have no right to additional compensation for any work not so authorized.

The Contractor shall be responsible to provide all data and to obtain all approvals required by the Specifications, including submittal of Daily Extra Work Reports. Disputed work claims shall comply with 2-8 as modified herein.

SECTION 3 – CONTROL OF THE WORK
3-7 CONTRACT DOCUMENTS.
3-7.1 General. Add the following sentence to the first paragraph to read as follows:

The Contractor shall maintain a control set of Plans and Specifications on the Work site at all times. All final locations determined in the field, and any deviations from the Plans and Specifications, shall be marked in red on this control set to show as-built conditions. Upon completion of the Work, the Contractor shall submit the control set to the Engineer for approval.

Final payment will not be made until this requirement is met.

Add the following subsections:
3-7.1.1 Plans. Included as part of the Contract Documents are the following, which show the location, character, dimensions or details of the Work:
1) Project Plans
The plans and data provided with the Contract Documents are based on existing plans and documents. The plans and data are provided for information only. The Owner does not guarantee their accuracy and correctness. If the Bidder in preparing the Bid Proposal uses this information, the Bidder assumes all risks resulting from conditions differing from the information shown. The Bidder, in consideration for the information being provided, hereby releases the City, from any responsibility of obligation as to the accuracy of such information or for any additional compensation for work performed due to assumptions based on the use of such information.
2) Standard Plans
a. City of Lomita Standard Plans, latest edition
b. Standard Plans for Public Works Construction, latest edition, promulgated by Public Works Standards, Inc.
c. Standard Plans of the State of California Department of Transportation (Caltrans), latest edition
d. City of Los Angeles Standard Plans, latest edition
E-7
3-7.1.2 SPECIFICATIONS. The Work shall be performed or executed in accordance with these Provisions and the following:
1) Standard Specifications for Public Works Construction, latest edition and supplements thereto, hereinafter referred to as the Greenbook, as written and promulgated by Public Works Standards, Inc. The Greenbook is published by BNi Building News, Inc., 1612 South Clementine Street, Anaheim, CA 92802, Phone:
(800) 873-6397.
2) Sections 56-2, 84, 85, 86 and 90-10 of the State of California Department of Transportation (Caltrans) Standard Specifications, latest edition. 3-7.2 Precedence of the Contract Documents. Replace the entire subsection with the following:

If there is a conflict between any of the Contract Documents, the document highest in precedence shall control. The order of precedence shall be as follows:
1) Permits issued by other agencies.
2) Change Orders (including Plans and Specifications attached thereto). 3) Public Works Agreement
4) Addenda
5) Special and General Provisions
6) Plans
7) City Standard Plans
8) Other Standard Plans
9) Greenbook
10)Reference Specifications
With reference to the Plans/Drawings, the order of precedence is as follows:
1) Change Order plans govern over Addenda and Contract plans 2) Addenda plans govern over Contract plans
3) Contract plans govern over standard plans
4) Detail plans govern over general plans
5) Figures govern over scaled dimensions
Within the Specifications, the order of precedence is as follows:
1) Change Orders
2) Permits from other agencies/Supplemental Agreements
3) Special Provisions
4) Instruction to Bidders
5) Referenced Standard Plans
6) Referenced Standard Specifications
If the Contractor, in the course of the Work, becomes aware of any claimed errors or omissions in the Contract Documents or in the City's fieldwork, the Contractor shall immediately inform the Engineer. The Engineer shall promptly review the matter, and if the Engineer finds an error or omission has been made the Engineer shall determine the corrective actions and advise the Contractor accordingly. If the corrective work associated with an error or omission increases or decreases the amount of work called for in the Contract, the City shall issue an appropriate Change Order in accordance with subsection 2-8. After discovery of an error or omission by the Contractor, any related work performed by the Contractor shall be done at the Contractor's risk E-8
unless authorized by the Engineer.
3-8 SUBMITTALS.

Submittals are required for the following:
• Construction Schedule
• Traffic Control Plan (TCP) prepared by a registered Civil or Traffic Engineer • Water Pollution Control Plan
• Asphalt Concrete Mix Designs (Level Course and AC overlay) • Concrete Mix Designs
• Base Material Mix Design
• Striping and Marking Materials
All Contractor submittals shall be carefully reviewed against the contract documents by an authorized representative of the Contractor, prior to submittal to the Engineer. A letter shall be included with each submittal stating the contract documents have been reviewed and the submitted product is correct for the project application and in strict conformance with the contract documents. The letter affidavit must be dated and signed by both the Contractor and the product manufacturer or service provider. In the case of shop drawings, each sheet shall be so dated and signed for approval. No consideration for review by the Engineer of any Contractor submittals will be made for any items which are not accompanied by affidavit by the Contractor.

All submittals without an affidavit will be returned to the Contractor without action taken by the Engineer, and any delays caused thereby shall be the total responsibility of the Contractor.

The Engineer's review of Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions. The Contractor shall assume all responsibility and risk for any misfits due to any errors in Contractor submittals. The Contractor shall be responsible for the dimensions and the design of adequate connections and details. 3-12 WORK SITE MAINTENANCE.
3-12.1 GENERAL. Add the following:
3-12.1 Temporary Light, Power, and Water. The Contractor shall obtain a construction water meter from the City. An $800 deposit is required and refundable upon return of the meter in good working condition. The Contractor shall pay for the water used, at the City’s current water rates.
3-12.1.2 Graffiti Removal. The Contractor shall maintain the Work, all of its equipment, and all traffic control devices, including signage, free of graffiti throughout the duration of the Contract.

The Contractor shall respond to any request from the Engineer to remove graffiti within 4 hours of notification. Should the Contractor fail to respond to such request, the City reserves the right to make other arrangements for the requested graffiti removal and deduct the cost from any monies due the Contractor.
3-12.4 STORAGE OF EQUIPMENT AND MATERIALS.
3-12.4.2 STORAGE IN PUBLIC STREETS. Add the following:

E-9
Contractor’s Storage Yard. The Contractor shall be responsible for obtaining a storage yard for the duration of the Work. If the proposed location of the yard is located within the boundaries of the City, the Contractor shall obtain prior approval from the Engineer. Contractor’s equipment will not be allowed to park overnight on any City street. 3-13 COMPLETION, ACCEPTANCE AND WARRANTY. Add the following:

It is the intent of the Specifications that only first-class materials and workmanship will be acceptable. The Contractor shall take all necessary measures to protect Work from damage and prevent accidents and vandalism during any and all phases of the work.

Until the final acceptance of the Work by the City, by written action of the Engineer, the Contractor shall have the charge and care thereof and will bear the risk of injury or damage to any part of the Work by the action of the elements, vandalism, or any other cause. The Contractor shall rebuild, repair, restore and make good all injuries or damages to any portion of the Work occasioned by any cause before its completion and acceptance and will bear the expense thereof.

If, in the Engineer’s judgment, the Work has been completed and is ready for acceptance, the Engineer will so certify and will determine the date when the Work was completed. This will be the date when the Contractor is relieved from responsibility to protect the Work. The Engineer may cause a Notice of Completion to be filed and recorded with the Los Angeles County Recorder’s Office. At the Engineer’s option, the Engineer may certify acceptance to the City Council who may then cause a Notice of Completion to be filed and recorded with the Los Angeles County Recorder’s Office.

Add the following subsection:
3-13.4 Manufacturer’s Warranties. Manufacturer's warranties shall not relieve the Contractor of liability under these Specifications. Such warranties only shall supplement the Contractor's responsibility.

SECTION 4 - CONTROL OF MATERIALS
4-1 GENERAL- Add the following paragraph after the second paragraph:

The Contractor and all subcontractors, suppliers, and vendors, shall guarantee that the entire Work will meet all requirements of this contract as to the quality of materials, equipment, and workmanship.

The Contractor, at no cost to the City, shall make any repairs or replacements made necessary by defects in materials, equipment, or workmanship that become evident within one year after the date of recordation of the Notice of Completion.

Within this one year period, the Contractor shall also restore to full compliance with requirements of this contract any portion of the Work which is found to not meet those requirements. The Contractor shall hold the City harmless from claims of any kind arising from damages due to said defects or noncompliance.

Security of this guarantee shall be in the form of a Maintenance Bond furnished to the City by the Contractor. There shall be specific wording in the Maintenance Bond, that includes the E-10
guarantee or warranty of the labor and materials for a one year period, commencing from the recording date of the Notice of Completion by the County Recorder. The guaranteed amount shall be for 100 percent of the total amount earned to date as indicated on the final progress payment. The City reserves the right to withhold the retention until the Maintenance Bond has been accepted by the City.

The Contractor shall make all repairs, replacements, and restorations covered by the Maintenance Bond within 10 working days after the date of the Engineer's written notice. Failure to comply with such notice, will cause the City to file claim against the bond.

Excepted from the Maintenance Bond will be defects caused by acts of God, acts of the City, acts of vandals, or by acts of others outside or beyond the control of the Contractor.

If the work, or any portion thereof, shall be damaged in any way, or if any defective materials or faulty workmanship shall be discovered at any time prior to the final payment, the Contractor shall forthwith, at its own cost and expense, repair said damage, or replace such defective materials, or remedy such faulty workmanship in a manner satisfactory to the Engineer. 4-2 PROTECTION. Add the following:

The Contractor shall assume all risks and expense of interference and delay in his operations, and the protection from or the repair of damage to improvements being built under the contract, as may be caused by water of whatever quantity from floods, storms, industrial waste, irrigation, underground or other sources. However, the Contractor shall be entitled to an extension of time in accordance with the provisions of Subsection 6-4. The Contractor shall also assume full responsibility and expense of protecting, or removing and returning to the site of Work, all equipment or materials under his care endangered by any action of the elements.

Furthermore, the Contractor shall indemnify and hold the City harmless from all claims or suits for damages arising from his operations in dewatering the Work and control of water.

SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITIES
5-7 SAFETY. Add the following:
5-7.2.4 PUBLIC SAFETY DURING NON-WORKING HOURS
Notwithstanding the Contractor's primary responsibility for safety on the job site when the Contractor is not present, the Engineer at Engineer's option after attempting to contact the Contractor may direct City Forces to perform any functions Engineer may deem necessary to ensure public safety at or in the vicinity of the job site. If such procedure is implemented, the Contractor will bear all expenses incurred by the City.

In all cases the judgment of the Engineer shall be final in determining whether or not an unsafe situation exists.
5-7.2.5 WRITTEN COMMUNICATIONS
Contractor’s written communications, including letters, field memoranda, requests for substitution (RFS) and requests for information (RFI) shall be written in a clear and concise manner. In particular, RFSs and RFIs shall clearly describe the condition or issue of concern, the cause of the condition or issue and the proposed solution or specific question being posed E-11
to the Engineer. Contractor shall not be entitled to any delays or additional compensation as a result of issues that in the Engineer’s opinion originated with, or were exacerbated by, poor written communications by the Contractor.

SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK
6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK. Replace the entire subsection with the following:
6-1.1 General. Within ten (10) working days after the date of the City’s execution of the Contract, the Contractor shall submit a proposed construction schedule to the Engineer for approval. The schedule shall be in accordance with the Specification and these Special Provisions.

Prior to issuing the Notice to Proceed, the Engineer will schedule a Pre-Construction Meeting with the Contractor to review the proposed construction schedule and delivery dates, arrange utility coordination and clarify inspection procedures.

Notwithstanding any other provisions of the Contract, the Contractor shall not be obligated to perform any work and the City will not be obligated to accept or pay for any work performed by the Contractor prior to delivery of a Notice to Proceed. The City's knowledge of work being performed prior to delivery of the Notice to Proceed shall not obligate the City to accept or pay for such work. The Contractor shall provide all required Contract bonds and evidences of insurance prior to commencing work.
6-1.2 Criteria. Construction schedules shall consider the following:
1- TRASH COLLECTION. Trash pick-up days are as follow:
- Wednesdays
2- TEMPORARY PAVEMENT MARKINGS; CAT-TRACKING AND STRIPING:

Reflective yellow and white “Tabs” MUST be installed following the installation of asphalt to indicate locations of lane lines, STOP limit lines, and all yellow crosswalks and shall be maintained until new striping is installed. Cat-tracking layout for final pavement markings shall be completed at least 48 hours prior to scheduled placement and the Engineer shall approve cat-tracking prior to final placement. Striping shall take place a minimum of seven (7) days after paving.
3- WORK HOURS. Work shall be performed between the hours of 7:00 A.M. and 4:00 P.M. unless otherwise approved by the Engineer. The Contractor will be allowed to work on Fridays when City Hall is scheduled to be closed. No work shall occur on Sundays or holidays. The following days are holidays: Memorial Day May 29, 2023, Independence Day, July 4, 2023; Labor Day, September 4, 2023; Veteran’s Day, November 10, 2023; Thanksgiving, November 23 and 24, 2023.
6-1.3 Compensation. Compensation for all scheduling activities will be made on the lump sum basis per the Contract Unit Price for “MOBILIZATON AND DEMOBILIZATION,” in the Bidder’s Proposal.

E-12
6-10 SEQUENCE OF CONSTRUCTION
6-10.1 Multiple Headings. In order to meet the contract schedule, the Contractor will be allowed to initiate and maintain two or more construction headings. However, the Contractor will not be allowed to have multiple phases of work occurring that have the corresponding traffic control devices in conflict with each other.

SECTION 7 - MEASUREMENT AND PAYMENT
7-2 LUMP SUM WORK
Add the following:

Contractor shall submit a detailed schedule of value for all lump sum bid items to the Engineer within 15 days after award of contract.
7-3 PAYMENT
7-3.1 General
Revise paragraph one to read: The unit and lump sum bid prices for each item of work shown on the proposal shall include full compensation for furnishing the labor, materials, tools, and equipment and doing all the work, including restoring all existing improvements, to complete the item of work in place and no other compensation will be allowed thereafter. Payment for incidental items of work not separately listed shall be included in the prices shown for the other related items of work. The following items of work pertain to the bid items included within the Proposal:

Item No.1 Mobilization and Demobilization: Work under this item shall include the cost to secure bonds and insurance, movement of personnel, equipment, materials and incidentals to and from the project sites, securing a temporary construction yard, maintaining the project in a safe, clean and orderly manner during construction and final cleanup of the work and staging sites.

Included in this item are any costs associated with construction activities including construction survey required to conform to the notes on the construction plans.

Payment for “ Mobilization and Demobilization” shall be made at the lump sum price indicated in the Bid Sheets and progress payments shall be made upon the judgment of the Engineer as percent complete.

Item No.2 Traffic Control: It shall be the Contractor’s responsibility to prepare and provide final Traffic Control throughout the construction period. Final traffic control implementation shall be provided under the supervision of the Contractor with the concurrence of the Engineer.

The final TCP implementation by the Contractor shall conform to the requirements of the latest editions of California MUTCD, the WATCH Manual, and these Special Provisions and as approved by the Engineer. The full and normal responsibility for TCP implementation is the Contractor’s responsibility as if no plans are or were provided by the City.

E-13
An adequate number of flag persons shall be stationed at construction locations where traffic control is required including intersections of streets, wherever it is necessary to temporarily stop or detour traffic for the construction or the movement of materials and equipment. During the construction activity hours flaggers and workers shall wear bright orange vests and hardhats while working in or around the construction area. Traffic stoppages shall be limited to time periods approved by the Engineer. No intersection shall be closed longer than 30 minutes without the approval of the Engineer. The TCP is considered to include trained flaggers used at both major and minor street intersections and or as recommended or required by the project inspector or Engineer without any additional compensation to the Contract.

It is anticipated that, from time to time, changes to the approved TCP may be needed due to unanticipated field conditions. The Contractor, if so directed by the Inspector or Engineer, shall make adjustments to address any deficiency identified by City forces at no additional cost to the City.

Pedestrian and bicycle traffic must be provided for and maintained in a safe manner throughout the construction period. Pedestrian and emergency vehicular access shall be maintained to all residences, businesses and manufacturing establishments within the construction area.

Signs, lights, flags, flag persons, and other warning and safety devices shall conform to the requirements set forth in the current editions of the WATCH Manual and California MUTCD. If attention is directed to the existence of a hazard and Contractor fails to provide remediation, or, such devices as may be needed, said devices may be placed by the City. The cost of said placement by the City, as for all TRAFFIC CONTROL, shall be the sole responsibility of the Contractor; said costs, if any, shall be deducted from the progress payment and from the total contract price for the work.

The contractor shall notify the occupants of all affected properties at least forty-eight (48) hours prior to any temporary obstruction of access. Vehicular access to property line shall be maintained, except as required for construction for a reasonable period of time. No overnight closure of any driveway will be allowed, except as permitted by the Engineer.

At least one twelve foot (12') wide traffic lane shall be provided for each direction of travel on all streets at all times. The traffic lanes shall be maintained on pavement, and shall remain unobstructed.

Clearances from traffic lanes shall be five (5) feet to the edge of any excavation and two (2) feet to the face of any curb, pole, barricade, delineator, or other vertical obstruction, unless approved by the Engineer in writing in advance of such work.

Detouring is discouraged but will be considered for usage by the City. If approved, any detouring shall be accomplished by use of traffic signs, barricades, flag persons, etc. conforming to the requirements of the WATCH or California MUTCD, and the Engineer.

Payment for “Traffic Control” shall be made at the lump sum price indicated in the Bid Sheet.

The contract lump sum price for “Traffic Control” shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all the traffic control related work involving placing, removing, storing, maintaining, moving to new locations, replacing and disposing of the components of traffic control system as specified in the State Standard Specifications, SSPWC, and these Special Provisions, and as directed by the Engineer. The E-14
lump sum price shall also include steel plates and temporary AC including installation and removal, all associated temporary signing and striping, flashing arrow signs, PCMS signs, and flagging and/or flagger costs and no additional compensation will be made therefor.

Item No.3 Excavation Safety Measures: Excavation Safety Measure shall conform to Section 5-7 Safety of SSPWC.

Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs of providing a safe work site for public and workers as required to complete the work in place including shoring and all necessary trench safety measures required by OSHA.

Payment for “Excavation Safety Measures” shall be made at the lump sum price as indicated in the Bid Sheets.

Item No.4 Construction Surveying: Construction staking and monumentation shall conform to Section 3-10 Surveying of SSPWC.

Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs of surveying, establishing horizontal and vertical controls, providing construction staking, establishing centerline ties, adjusting survey monuments, filing pre- and post-construction corner records with the County, and other survey items as required to complete the work in place.

Payment for “Construction Surveying” shall be made at the lump sum price indicated in the Bid Sheets.

Item No.5 Water Pollution Control (Includes BMP Installation and Maintenance): The contract unit price shall include, but not be limited to, all labor, tools, equipment and material costs for installing and maintaining BMPs for water pollution control.

Payment for “Water Pollution Control (Includes BMP installation and Maintenance)” shall be made at the lump sum price as indicated in the Bid Sheets.

Item No.6 Re-establish Survey Monuments: Re-establish Survey Monuments shall conform to Section 3-10 Surveying and Section 400-2 Permanent Survey Markers of SSPWC.

Section 400-3 Payment shall be replaced with the following:

No separate or additional payment will be made for 1) protection of existing improvements, and 2) restoration of existing improvements. Permanent survey marker will be restored by the contractor as its own expense and have no cost to the City.

Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs of surveying, adjusting survey monuments, filing pre- and post-construction corner records with the County, re-establishing property corners disturbed by the work, preparing record of survey, protecting and restoring existing monuments and other survey items as required to complete the work in place.

Payment for “Re-establish Survey Monuments” shall be made at the lump sum price as indicated in the Bid Sheets.

E-15
Item No.7 Sawcutting: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for sawcutting AC pavement, and all other work items as required to complete the work in place.

Payment for “Sawcutting” shall be made at the lump sum price as indicated in the Bid Sheets.

Item No. 8 Construct New 8” PVC C900 DR 18 Water Main, Including But Not Limited To Furnishing Of Fittings And End Caps. Construction Shall Be Per City OF Lomita Standards And Include Trenching, Bedding and Backfill: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for trenching, installing new water main and fittings, placing bedding, and backfilling trenches, and all other work items as required to complete the work in place.

Payment for “Construct New 8” PVC C900 DR 18 Water Main, Including But Not Limited To Furnishing Of Fittings And End Caps. Construction Shall Be Per City OF Lomita Standards And Include Trenching, Bedding and Backfill” shall be made on a per linear foot unit price basis as indicated in the Bid Sheets.

Item No. 9 Construct New 8” PVC C900 DR 14 Water Main, Including But Not Limited To Furnishing Of Fittings And End Caps. Construction Shall Be Per City OF Lomita Standards And Include Trenching, Bedding and Backfill: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for trenching, installing new water main and fittings, placing bedding, and backfilling trenches, and all other work items as required to complete the work in place.

Payment for “Construct New 8” PVC C900 DR 14 Water Main, Including But Not Limited To Furnishing Of Fittings And End Caps. Construction Shall Be Per City OF Lomita Standards And Include Trenching, Bedding and Backfill” shall be made on a per linear foot unit price basis as indicated in the Bid Sheets.

Item No. 10 Provide and Install 8” Gate Valve: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing the existing monitoring well box and cover, temporarily lowering and/or covering the well to facilitate paving operation, reinstalling existing monitoring well box and cover to grade, restoring all existing improvements damaged by the work, and all other work items as required to complete the work in place.

Payment for “Provide and Install 8” Gate Valve” shall be made on a per each unit price basis as indicated in the Bid Sheets.

Item No. 11 Furnish and Install 1” Water Service, Connect to Existing Meter and Box:

Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing the existing monitoring well box and cover, temporarily lowering and/or covering the well to facilitate paving operation, reinstalling existing monitoring well box and cover to grade, restoring all existing improvements damaged by the work, and all other work items as required to complete the work in place.

Payment for “Furnish and Install 1” Water Service, Connect to Existing Meter and Box” shall be made on a per each unit price basis as indicated in the Bid Sheets.

E-16
Item No. 12 Cut Existing Water Line and Remove Interfering Portions. Plug with Concrete and Abandon: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing the existing monitoring well box and cover, temporarily lowering and/or covering the well to facilitate paving operation, reinstalling existing monitoring well box and cover to grade, restoring all existing improvements damaged by the work, and all other work items as required to complete the work in place.

Payment for “Cut Existing Water Line and Remove Interfering Portions. Plug with Concrete and Abandon” shall be made on a per each unit price basis as indicated in the Bid Sheets.

Item No. 13 Connect to Existing Water Main (Includes Installation of Transition Coupling, if Required Per Plans): Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing the existing monitoring well box and cover, temporarily lowering and/or covering the well to facilitate paving operation, reinstalling existing monitoring well box and cover to grade, restoring all existing improvements damaged by the work, and all other work items as required to complete the work in place.

Payment for “Connect to Existing Water Main (Includes Installation of Transition Coupling, if Required Per Plans)” shall be made on a per each unit price basis as indicated in the Bid Sheets.

Item No.14 Construct AC Pavement Base Course Including Subgrade and Base Preparation Per City of Lomita Trench Detail: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for applying a tack coat, placing, spreading and compacting the variable depth asphalt concrete leveling course and all other work items as required to complete the work in place.

Payment for “Construct AC Pavement Base Course Including Subgrade and Base Preparation Per City of Lomita Trench Detail” shall be made on a per ton unit price basis as indicated in the Bid Sheets.

Item No.15 Cold Plane Asphalt Concrete (2”) Depth Per City of Lomita Trench Detail”:

Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for cold milling the asphalt concrete pavement, providing additional motorized street sweepers per Section 3-12.1, removal and disposal of pavement fabric if encountered, constructing temporary asphalt concrete ramps along milled edges, hauling and disposing the milled material offsite, and all other work items as required to complete the work in place.

Cold mill operation shall conform to Section 404 and all applicable sections of the SSPWC and shall consist of all excavation required and directed by the Engineer.

Payment for “Cold Plane Asphalt Concrete (2”) Depth Per City of Lomita Trench Detail” shall be at the unit price bid per square foot. The contract unit price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in “Cold Mill Existing Pavement 2” including disposing of material removed and no additional compensation will be allowed therefor.

Item No.16 Construct AC Pavement Cap Per City of Lomita Standards: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for E-17
applying a tack coat, spreading and compacting the asphalt concrete finish course and all other work items as required to complete the work in place.

Payment for “Construct AC Pavement Cap Per City of Lomita Standards” shall be made on a per ton unit price basis as indicated in the Bid Sheets.

Item No.17 Construct AC Pavement Base Course Including Subgrade and Base Preparation Per City of Los Angeles Trench Detail: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for applying a tack coat, placing, spreading and compacting the variable depth asphalt concrete leveling course and all other work items as required to complete the work in place.

Payment for “Construct AC Pavement Base Course Including Subgrade and Base Preparation Per City of Los Angeles Trench Detail” shall be made on a per ton unit price basis as indicated in the Bid Sheets.

Item No.18 Cold Plane Asphalt Concrete (2”) Depth Per City of Los Angeles Trench Detail”: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for cold milling the asphalt concrete pavement, providing additional motorized street sweepers per Section 3-12.1, removal and disposal of pavement fabric if encountered, constructing temporary asphalt concrete ramps along milled edges, hauling and disposing the milled material offsite, and all other work items as required to complete the work in place.

Cold mill operation shall conform to Section 404 and all applicable sections of the SSPWC and shall consist of all excavation required and directed by the Engineer.

Payment for “Cold Plane Asphalt Concrete (2”) Depth Per City of Los Angeles Trench Detail” shall be at the unit price bid per square foot. The contract unit price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in “Cold Mill Existing Pavement 2” including disposing of material removed and no additional compensation will be allowed therefor.

Item No.19 Construct AC Pavement Cap Per City of Los Angeles Standards: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for applying a tack coat, spreading and compacting the asphalt concrete finish course and all other work items as required to complete the work in place.

Payment for “Construct AC Pavement Cap Per City of Lomita Standards” shall be made on a per ton unit price basis as indicated in the Bid Sheets.

Item No.20 Construct AC Pavement Base Course Including Subgrade and Base Preparation Per Caltrans Trench Detail: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for applying a tack coat, placing, spreading and compacting the variable depth asphalt concrete leveling course and all other work items as required to complete the work in place.

Payment for “Construct AC Pavement Base Course Including Subgrade and Base Preparation Per Caltrans Trench Detail” shall be made on a per ton unit price basis as indicated in the Bid Sheets.

E-18
Item No.21 Cold Plane Asphalt Concrete (2”) Depth Per Caltrans Trench Detail”: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for cold milling the asphalt concrete pavement, providing additional motorized street sweepers per Section 3-12.1, removal and disposal of pavement fabric if encountered, constructing temporary asphalt concrete ramps along milled edges, hauling and disposing the milled material offsite, and all other work items as required to complete the work in place.

Cold mill operation shall conform to Section 404 and all applicable sections of the SSPWC and shall consist of all excavation required and directed by the Engineer.

Payment for “Cold Plane Asphalt Concrete (2”) Depth Per Caltrans Trench Detail” shall be at the unit price bid per square foot. The contract unit price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in “Cold Mill Existing Pavement 2” including disposing of material removed and no additional compensation will be allowed therefor.

Item No.22 Construct AC Pavement Cap Per Caltrans Standards: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for applying a tack coat, spreading and compacting the asphalt concrete finish course and all other work items as required to complete the work in place.

Payment for “Construct AC Pavement Cap Per Caltrans Standards” shall be made on a per ton unit price basis as indicated in the Bid Sheets.

Item No.23 Construct PCC Bus Pad Including Dowel Installation, Subgrade and Base Preparation Per Caltrans Standards: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for grading and compacting subgrade, constructing concrete bus pad per Section 201 and 302-6 of the SSPWC, installing expansion joint material, constructing weakened plane joints, restoring all existing improvements damaged by the work, and all other work items as required to complete the work in place.

Payment for “Construct PCC Bus Pad Including Dowel Installation, Subgrade and Base Preparation Per Caltrans Standards” shall be made on a square foot unit price basis as indicated in the Bid Sheets.

Item No.24 Replace Damaged Pavement Striping, Markings, Reflectors, and Legends:

Traffic striping, legend, and pavement markers within the area of work shall be installed in accordance with the improvement plan, the State Standard Specifications, Sections 84 and 85, Revised Standard Plans A20A to A20E, and Standard Plans A24A to A24F and Sections 214 and 314 of SSPWC.

Traffic striping, stop limit/crosswalk lines, and legend shall be thermoplastic unless otherwise called for on the plans. All pavement markers shall be adhered with “epoxy”; Bituminous adhesive will not be accepted.

Blue raised retro-reflective bidirectional pavement marker shall be installed 6 inches off the street centerline at each fire hydrant, on the fire hydrant side of the roadway per California MUTCD section 3B.11 and figure 3B-102 (CA). Installation of Blue Reflectorized Pavement Markers including Pavement Markers across fire hydrants shall be considered as included in the lump sum for this item of work.

E-19
Payment for “Furnish and Install Striping, Markings, Reflectors, Raised Pavement Markers” detailed on the plans shall be on a lump sum price basis and shall be considered full compensation for furnishing labor, materials, equipment, and disposal to complete the construction, including installing traffic striping, pavement legends, markings, markers and blue raised markers for fire hydrant all in place as shown on plans and no additional compensation will be allowed therefor.

Item No.25 Soil Sampling if hazardous Soil is Encountured (As Needed Only): Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for coring into the existing asphalt, taking soil samples, sample analysis, preparation of an analysis report, and all other work items as required to complete the work in place.

Soil sampling and testing shall be done by a qualified environmental consultant. Contractor shall prepare a soil sampling plan only after possible hazardous soil is found. Soil samples will only need to be collected if the soil excavated has apparent soil contamination or odor. If possible soil contamination is encountoured then the Contractor shall analyze for the following constituents:
• Total Petroleum Hydrocarbons GRO/DRO/ORO (EPA Method 8015B) • Volatile Organic Compounds (EPA Method 5035/8260B)
• Cam 17 Metals (6010B/7196A/7471A)
• WET STLC (EPA Method 6010B)
Payment for “Soil Sampling if Hazardous Soil is Encountered (As Needed Only)” shall be at the unit price bid per each. The contract unit price shall include full compensation for furnishing all labor, materials, tools, equipment, lab testing, and incidentals, and for doing all work involved in “Soil Sampling if Hazardous Soil is Encountered (As Needed)” including disposing of material removed and no additional compensation will be allowed therefor.

Item No.26 Excavation, Haul Away and Disposal of Hazardous Soil if Encountered (As Needed): Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for sawcutting, excavation, haul away, disposal, special handling requirements, hazardous dump fees, and all other work items as required to complete the work in place.

Payment for “Excavation, Haul Away and Disposal of Hazardous Soil if Encountered (As Needed)” shall be at the unit price bid per ton. The contract unit price shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in “Excavation, Haul Away and Disposal of Hazardous Soil if Encountered (As Needed)” including disposing of material removed and no additional compensation will be allowed therefor.
7-4.3 MARKUP. Replace the entire subsection with the following:

The markups mentioned hereinafter shall include, but are not limited to, all costs for the services of superintendents, project managers, timekeepers and other personnel not working directly on the change order, and pickup or yard trucks used by the above personnel. These costs shall not E-20
be reported as labor or equipment elsewhere except when actually performing work directly on the change order and then shall only be reported at the labor classification of the work performed.
(a) Work by Contractor. The following percentages shall be added to the Contractor’s costs and shall constitute the mark-up for all overhead and profit, which shall be deemed to include all items of expense not specifically designated as cost or equipment rental in Subsections 3-7-

4.2.1, 7-4.2.2, and 7-4.2.3.

Labor 20
Materials 15
Equipment Rental 15
Other Expenditures 15
To the sum of the costs and markups provided for in this subsection, one (1) percent shall be added as compensation for bonding.
(b) Work by Subcontractor. When any part of the extra work is performed by a subcontractor, the markup established in 7-4.2.1 shall be applied to the subcontractor’s actual cost of such work. A markup of ten (10) percent on the first $5,000 of the subcontracted portion of the extra work and a mark-up of 5 percent on work added in excess of $5,000 of the subcontracted portion of the extra work may be added by the Contractor.

The markups specified in parts (a) and (b) above shall be considered as including, but not limited to, the Contractor’s labor costs for personnel not working directly on the extra work, including the cost of any tools and equipment that they may use. Such costs shall not be reported as labor or equipment costs elsewhere except when they are actually used in the performance of the extra work. Labor costs shall in that case be reported for the labor classification corresponding to the type and nature of extra work performed.

E-21
PART 2 - CONSTRUCTION MATERIALS
SECTION 200 - ROCK MATERIALS
200-2 UNTREATED BASE MATERIALS
200-2.1 General. Replace the entire subsection with the following:

Untreated base for pavement, curb, gutter, cross gutters, bus pads, hardscape and other improvements shall be Crushed Aggregate Base conforming to 200-2.2. 201-1 PORTLAND CEMENT CONCRETE
The Portland cement concrete pavement class shall be: 520-A-2500.

SECTION 203 - BITUMINOUS MATERIALS
203-5.4 EMULSION - AGGREGATE SLURRY (EAS)
203-5.4.1 General. Replace the first sentence with the following:

Emulsion-aggregate slurry shall be a stable mixture of emulsified asphalt, mineral aggregate, water and retardant and is herein referred to as slurry. 203-5.4.2 Materials. Replace the entire subsection with the following:

The ingredients of the slurry shall conform to the following:
1) Emulsified asphalt shall be Polymer Modified cationic quick-set type, CQS-1h containing

2.5% minimum Ultrapave 65K styrene/butadiene/rubber latex as manufactured by Textile Rubber and Chemical Company or approved equal. CQS-1h shall conform to the requirement of 203-1.3 and the following specifications when tested according to appropriate ASTM methods:

TABLE 203-5.2(A)
CQS-1h QUICK SET EMULSION
Tests ASTM
Test
Requirements
Min.

Furol Viscosity @ 77F, sec. D244 15 100
Residue from distillation, % by weight D244 60 Min.

Sieve Test, % retained on No. 20 D244 10 Max.

Particle Charge Test (Cationic) Positive
Storage Stability; One-Day Settlement D244 1% Max.

Residue
Penetration 0.1 mm D5 45 80
Solubility in TCE,
% Ductility, 77F,
D2042
D113

97.5 Min.
40 Min.

E-22
Test for Polymer Content
Torsional Recovery, % Caltrans 322 18.0 Min.

Polymer Solids Content, % by weight of Asphalt Solids Caltrans 401 2.5 3.0 2) The Retarder for quick-setting emulsion and the asphalt modifier shall be a type approved by the Engineer. The amount of retarder and asphalt modifier to be included in the quick-set slurry shall be that amount necessary to ensure that the applied slurry can support vehicular traffic within 60 minutes after the last application. 3) Water shall be potable and compatible with the other ingredients of theslurry. 4) Aggregate shall be rock dust produced by the crushing of rock and gravel. The aggregate without any additive shall conform to the following requirements:

TABLE 203-5.2(B)

TESTS ASTM

METHOD REQUIREMENTS
Percentage Wear 500 Revolutions' C131 35% Maximum
Sand Equivalent D2419 55 Minimum
Soundness (5 Cycles) C 88 15% Maximum
1ASTM C131 to be run on plus four graded material before final crushing. a) The Contractor shall provide an aggregate stockpile 24-hours prior to starting the work. Location to be approved by the Engineer if within City right-of-way. b) Contractor shall schedule and coordinate the delivery of aggregate to the stockpile(s) such that: (1) deliveries originate at the plant and arrive at the stockpile site within normal work hours on the same calendar day; (2) delivery site and project name are explicitly stated on each delivery ticket; (3) successive deliveries on the same calendar day show the cumulative total for that day; (4) copies of all delivery tickets shall be delivered to the Engineer before the end of the working day. Any delivery tickets not so delivered may be rejected by the CITY. Any deviation from this process must have the prior approval of the Engineer.
c) The Contractor shall furnish calibrated vehicle weigh scales at the stockpile site for use by the CITY. The portable scales will be utilized for inspection and all mixers shall be weighed prior to transit. All equipment and tools necessary for field measurement of the emulsion and aggregate by the CITY shall be furnished and maintained by the Contractor.

The Contractor shall be responsible for the initial setup of the weigh scales at the stock-pile site and all necessary relocations during the slurry seal operations.

E-23
The cost to furnish the vehicle scales, all equipment, and tools necessary for field testing shall be included in the Contract Unit Price for the Emulsion Aggregate slurry and no additional compensation shall be allowed. 203-6 ASPHALT CONCRETE
The asphalt pavement class and grade shall be:

Base Course: B-PG 64-10
Asphalt Concrete Cap: C2-PG 64-10
SECTION 209 – PRESSURE PIPE
209-4 PVC PRESSURE PIPE.
209-4.1 General. Add the following:

PVC pipe shall comply with AWWA C900. Unless otherwise specified on the Plans or Specifications, the minimum pipe wall thickness shall be equal to Pressure Class 235.

SECTION 214 - TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS AND

PAVEMENT MARKERS
All striping and markings on this project shall be thermoplastic per Section 214-5. Striping layout shall be restored to existing conditions.

SECTION 215 – MISCELLANEOUS POTABLE WATER DISTRIBUTION SYSTEM

MATERIALS
215-1 VALVES.
215-1.1 General. All valves and gates shall be new and of recent manufacture. The flanges shall be plain faced and shall conform in dimensions and drilling to ANSI B16.1 Class 125 or ANSI/AWWA C153. Each valve body shall be tested to a pressure equal to twice its design water working pressure, except that gate valves shall be tested in accordance with the requirements of AWWA C500.

All interior parts of valves manufactured of bronze or brass except valve stems, shall conform to the requirements of ASTM B62. Gate valve stems shall be of bronze, containing not more than 5 percent of zinc, not more than 2 percent of aluminum, and having a minimum tensile strength of 60,000 psi, a yield strength of 40,000 psi, and elongation of at least 10 percent in two inches, as determined from a test coupon poured from the same ladle from which the valve stems to be furnished are poured.

Except as otherwise provided, all ferrous surfaces (excluding non-corrosive surfaces) in the water passages of all valves, 4 inch and larger, shall be fuse coated with an epoxy coating in accordance with AWWA C550. All buried valves shall be provided with an exterior protective coating.

E-24
Unless otherwise shown on the Plans, all in-line valves shall be furnished with mechanical ends.
215-1.2 Resilient-Seated Gate Valves. Gate valves, size 3 inches through 12 inches, shall be resilient seat, solid wedge, non-rising stem type equipped with “O” ring seals and conforming to AWWA C509. Gate valves shall be rated for 250 psi working pressure.

Valves shall have a 2-inch square operating nut or hand wheel, as shown on the Plans, and shall open with a counter-clockwise rotation of the operator.

Gate valves shall be Mueller A-2360 to match pipe size with flanged or mechanical ends. 215-1.8 Miscellaneous Small Valves. Miscellaneous small valves shall be as specified in the Plans or Specifications. Where not specifically labeled, valves smaller than 3-inch shall be lever-operated ball valves, as manufactured by The James Jones Company or approved equal. 215-1.9 Air and Vacuum Release Valves. Air and vacuum release valves shall be cast-iron body valves with bronze trim and stainless steel float. They shall be APCO No. 144 Air and Vacuum Release Valves as manufactured by Valve and Primer Corporation, Chicago, Illinois, or approved equal.
215-1.10 Abandoning existing valves. All existing valves shall be abandoned by Contractor unless otherwise noted on the plans. After pipelines have been tested and disinfected by Contractor, and accepted by City, and after City has completed all service connections and waterline connections, Contractor shall remove valve cans a minimum of 12" below finish grade, remove operating nut extensions, and fill valve cans with concrete. Thereafter, Contractor shall sawcut existing asphalt concrete pavement (2' square section) around existing valve boxes, remove said asphalt concrete pavement or concrete and dispose of same at a legal disposal site, and place concrete or asphalt concrete pavement over abandoned valve boxes. Valve box caps and extensions shall be returned to the City. 215-2 Fire Hydrants. Fire hydrants shall be as manufactured by The James Jones Company, Model J-3700 or J-3765 as shown on the Plans and shall conform to the requirements of AWWA C503. Each fire hydrant shall be assembled with a gray- iron 6-inch nominal diameter hydrant extension with break-away grooves and flanged ends, and a gray-iron 6- inch nominal diameter hydrant bury with top end flanged and bottom end having a mechanical joint connection.

Flanges shall be 6-hole pattern. The hydrant flange shall be connected to the extension by means of breakaway bolts in accordance with AWWA C110.
215-2.1 Abandoning Existing Fire Hydrants.
a. Existing fire hydrants shall be abandoned by Contractor unless otherwise noted on the plans. After pipelines have been tested and disinfected by Contractor, and accepted by City, Contractor shall remove fire hydrants and fire hydrant burys a minimum of 12" below finish grade and fill fire hydrant burys with concrete. Thereafter, Contractor shall sawcut existing concrete at construction joints around abandoned fire hydrant burys, remove said concrete and dispose of same at a legal disposal site, and place concrete over abandoned fire hydrant burys.

E-25
b. If existing fire hydrants are located in an area without concrete, Contractor shall remove and replace in kind area around abandoned fire hydrant burys. c. Contractor shall restore landscaping and existing improvements around abandoned fire hydrants.
d. Contractor shall notify City Fire Department of the location of the fire hydrants that are out of service.
e. Hydrants to be delivered to the City of Lomita, Public Works Yard. 215-3 BLOW-OFF HYDRANTS. Blow-off hydrants shall be as manufactured by The John C. Kupferle Foundry Company, St. Louis, Missouri, Model Eclipse No. TF550 with 2-inch female iron pipe inlet. The Blow-off assembly shall include the 2” service line, 2” ball valve, and other appurtenances as indicated in City of Lomita Standard Plan W-124. 215-4 INSULATING COUPLINGS, BUSHINGS AND UNIONS. Insulating couplings, bushings and unions shall be furnished to provide dielectric protection from electrolytic corrosion at all points where piping and fittings of dissimilar metals are joined, as manufactured by Smith Blair; Corrosion Control Products, Co.; or approved equal. Couplings, bushings, and unions shall be lined with an inert, non-conductive, linen impregnated material and threaded to NPS standards, with sufficient separation between pipe ends to prevent bridging.
215-4.1 Insulating Flange Kits. Kits shall be furnished as shown on the Plans and shall consist of a dielectric gasket, insulating sleeves and washers. a) Gaskets. Gaskets shall be Type "E" neoprene faced phenolic material for operation between 20 and 150 degrees Fahrenheit per ANSI B16.21. b) Insulating Sleeves. Insulating sleeves shall be 1/32-inch thick, full length, CE phenolic tubing for operation between 20 and 150 degrees Fahrenheit. For installation at threaded valve flanges, the sleeves shall be half-length. c) Insulating Washers. Insulating washers shall be laminated CE phenolic for operation at ambient temperatures to be placed directly adjacent to the flange face.

Moisture, soil, or other foreign matter must be carefully prevented from contacting any portion of the mating surfaces prior to installing insulator gasket. If moisture, soil, or other foreign matter contacts any portion of the surfaces, the entire joint shall be disassembled, cleaned with a suitable solvent, and dried prior to re-assembly.
215-5 SERVICE LATERALS. New service laterals shall be Type K soft copper and shall conform to City of Lomita Standard Plan Nos. W-101, W-102, and W-103. Sizes of service laterals to be installed are as shown on the Plans.

No joints shall be made in service lateral runs without the Engineer’s approval. All joints so allowed shall be silver-solder joints.

E-26
215-6 FLEXIBLE COUPLINGS. Unless otherwise specified, flexible couplings shall conform to the following:
1) Each coupling shall consist of one steel middle ring, two steel followers, gaskets, and sufficient numbers of Type 316 stainless steel bolts to compress the gasket without distorting the followers.
2) The thickness of the middle ring shall be such that the stress in the steel shall not exceed 50 percent of the yield point when subjected to the hydrostatic test pressure of the pipeline. The pressure rating shall be no less than the indicated design pressure. The middle ring thickness shall not be less than the thickness of the pipe jointed.
3) Middle rings shall be cold expanded a minimum of one-percent increase in diameter to test the weld and the size of the proper dimension. 4) The middle rings shall be coated with Keysite 740 or approved coating to a minimum dry film thickness of 10 mils. Follower rings shall be coated with a compatible shop coat for field coating.
5) Bolts shall be 5/8-inch diameter carriage bolts with hexagon nuts. The steel shall have minimum yield strength of 40,000 psi.
6) Buried coupling shall be coated with fusion bonded epoxy and provided with Type 316 stainless steel bolts and nuts.
7) Provide thrust ties where shown and where required to restrain the force developed by 1-1/2 times the operating pressures specified. Attach thrust ties to ductile iron pipe with socket clamps against a grooved joint coupling or flange. 8) Flexible couplings shall be by one of the following manufacturers: Baker, Dresser, Rockwell or Ford.

E-27
PART 3 - CONSTRUCTION METHODS
SECTION 300 – EARTHWORK
300-1 CLEARING AND GRUBBING.
300-1.1 General. Replace the entire subsection with the following:

Unless otherwise stated on the Plans or Specifications, all material removed from the Work shall become the property of the Contractor and shall be disposed of in a lawful manner.

Removals shall include, but not limited to, all excess excavation material, trees and plants, debris, interfering portions of curb, gutters, asphalt and PCC concrete pavements and sidewalks (including base, where applicable), and miscellaneous items as shown on the Plans. The Contractor shall conform to the following requirements:
1) The Contractor shall not start any removal work unless it is prepared to perform reconstruction work within 24 hours of the time removals were begun, unless otherwise approved by the Engineer.
2) The Contractor shall complete forming and pouring of PCC construction within five (5) working days following the removal of existing material at any location. 3) The Contractor shall not remove on-site improvements until it is prepared to construct the adjacent street section and shall promptly restore all such improvements as applicable, upon completion of the adjacent street work.

All concrete removed shall be hauled off the Work site no later than the calendar day following the day that the removal is performed.

The limits for sidewalk, curb and gutter and driveway shown on the plans are approximate.

The actual removal and/or construction limits shall be as marked and/or directed by the Engineer in the field.

In order to protect the public streets from deterioration due to hauling of materials, the Contractor shall submit, prior to the Pre-Construction Meeting, for approval a proposed route for hauling of materials for disposal. Upon approval, the Contractor shall strictly adhere to that route, unless written permission from the Engineer is obtained to change the route.

Add the following subsection:
300-1.5 CONSTRUCTION AND DEMOLITION DEBRIS RECYCLING.

GENERAL. Consistent with the City’s efforts to comply with the California Integrated Waste Management Act of 1989 (AB 939), the Contractor shall reduce, reuse, and/or recycle to the maximum extent feasible, the construction and demolition debris (debris) generated by this E-28
Contract hereby diverting the debris from disposal facilities, saving landfill space, and conserving virgin materials and natural resources.

RECYCLING SUMMARY. The Contractor shall file with the City Engineer, prior to the acceptance of the work, a Recycled Materials Certificate using the Recycling Summary form on Appendix III. The Recycled Materials Certificate shall list all recycled materials used in connection with work or delivered off-site for recycling. Certificate shall include for each recycled material type: a) Material description, b) Material quantity, c) Method of measurement, d) Material origination location, e) Material deposition location.

UNCLASSIFIED EXCAVATION.
300-2.2 Unsuitable Material.
300-2.2.1 GENERAL. Add the following:

Unclassified excavation shall include excavating, removing, hauling, and disposal of all material including asphalt concrete pavement to the subgrade elevations indicated on the plans as required to construct the new improvements. Removal of asphalt concrete, aggregate base, and native soil shall be made at the locations shown on the plans, or as specified in the field by the Engineer.

If unsuitable material is found, the Contractor shall remove said material to the limits to be determined by the Engineer and shall replace said material with select fill or base material, as to be determined by the Engineer.

Payment for unsuitable material excavation and backfill shall be measured and paid for as Unclassified Excavation and Crushed Aggregate Base, respectively.

SECTION 301 – SUBGRADE PREPARATION, TREATED MATERIALS, AND

PLACEMENT OF BASE MATERIALS
301-1 SUBGRADE PREPARATION
301-1.6 Adjustment of Manhole Frame and Cover Sets to Grade - Add the following:

All surface utility covers (even those to be adjusted to grade by others) shall be located in the field prior to beginning any work on this project. The Contractor shall remove existing concrete pads or collars that might interfere with the adjustment of the valve cover to the grade of the asphalt concrete surface. Any damage to existing utility systems or appurtenances by the Contractor shall be replaced at the Contractor's expense.

The Contractor shall also be responsible for coordinating his work with the various utility agencies that will be required to adjust their own surface utility covers to grade as noted on the plans. This includes tying out their covers and notifying all surface utility agencies prior to performing any work that will affect their facilities. If the required adjustment of the agency E-29
adjusted utility covers will impact the Contractor’s subsequent work then the Contractor shall coordinate his work schedule and/or perform follow up work to ensure that the quality of the final product is not compromised.

Refer to subsection 301-1.6.1 of these Special Provisions for adjustment of Los Angeles County Sanitation District manhole covers. Other surface utility covers within the area to be paved or graded shall be set to finish grade by the Contractor in accordance with 302-5.8 unless otherwise specified.
301-1.6.1 ADJUSTMENT OF LOS ANGELES COUNTY SANITATION DISTRICT (CSD) MANHOLES TO GRADE.

When County Sanitation Districts (CSD) manholes must be adjusted to new grade, the work will be done by CSD in conjunction with the Contractor pursuant to the following procedures:

1. The Contractor shall notify CSD’s Superintendent of Maintenance at (310)638-1161 a minimum of three (3) working days prior to the start of any work involving CSD manholes.

2. If grade over manhole is to be lowered:
a. The Contractor shall furnish and deliver a temporary steel cover plate of adequate thickness and size approved by CSD for the manhole. b. The Contractor shall excavate around the manhole to a depth and distance outside of the manhole as required for CSD to remove the manhole frame and cover.
c. CSD will remove the manhole frame and cover and the interfering portion of the manhole shaft and place the cover plate over the manhole. d. The Contractor shall store and protect the frame and cover and fill and/or pave over the cover plate to final grade.
e. The Contractor shall remove the pavement and/or fill as required for CSD to raise the manhole to final grade. Pavement and/or fill shall be removed to a minimum depth of not less than 6 inches below final grade and 12 inches around the manhole if the cover plate is more than 6 inches below final grade.
f. CSD will raise the manhole and set the frame and cover to final grade. g. The Contractor shall backfill and compact and complete the pavement around the manhole.

3. If grade over manhole is to be raised:
a. The Contractor shall fill and/or pave directly over the manhole frame and cover to final grade.
b. Repeat steps e. through g. of Item 2 above.

The Contractor shall be responsible for furnishing, placing, and maintaining barricades and lights as necessary to protect the public from danger due to the work being performed.
301-1.7 Payment. Replace the first last three paragraphs with the following:

E-30
Payment for adjusting sewer or storm drain manhole frames and covers to grade shall be made at the Contract Unit Price per Each for Adjust Existing Utility Manholes to New Grade and shall include all labor, tools, equipment, and materials necessary for doing the work.

No other compensation will be allowed.

SECTION 306 – OPEN TRENCH CONDUIT CONSTRUCTION
306-1 GENERAL. Add the following:

All trenches shall be sawcut to the bottom of the existing concrete or asphalt section to minimize damage to adjacent pavement. The bottom of the trench shall be excavated uniformly to the grade of the bottom of the pipe and shall be given a final trim using a string line for establishing grade, such that each pipe section when first laid will be continually in contact with the ground along the extreme bottom of the pipe.

Tunneling shall be performed under existing curb, gutter and cross-gutter as shown on the Plans. The Contractor shall exercise caution and care to prevent any damage in tunneling under these structures. There shall be no additional payment for this tunneling work.

Payment for this work shall be included in the Contract Unit Price for the installation of the main pipeline, Meter Installation, Air/Vacuum Valve Assembly, or Blow-off Valve Assembly as appropriate.
306-3.3 REMOVAL AND ABANDONMENT OF EXISTING CONDUITS AND STRUCTURES.

Add the following:
306-3.3.1 ABANDONING EXISTING WATER MAINS. The Contractor shall remove existing water mains and appurtenances from service at the locations shown on the Plans or as directed by the Engineer. Water mains specified to be abandoned in place, 12 inches in diameter and larger shall be filled with cement grout and have their ends cut, plugged and capped. Water mains specified to be abandoned in place, 10 inches in diameter and smaller shall have their ends cut, plugged with concrete, capped and left intact. 306-3.3.2 ABANDONING WATER SERVICES. The Contractor shall abandon water services at the locations as shown on the Plans and in accordance with the following requirements:
1) The Contractor shall cut and disconnect, at the meter boxes and at the mains, all existing service lines, which are connected to the existing water mains to be abandoned in place.
2) The Contractor shall remove the meter and deliver to the City yard. 3) The Contractor shall remove and dispose of the existing meter box. 4) All existing corporation stops shall be turned off, service lines disconnected and corporation stops capped.

E-31
5) The Contractor shall backfill the cavity and restore the surface to match the surroundings.
306-3.4 MAXIMUM LENGTH OF OPEN TRENCH
Contractor shall excavate open trench 100 feet ahead of pipe laying operations to allow any adjustment in grade necessary to resolve unforeseen utility conflicts.

All trenches shall be backfilled and have 3” temporary pavement installed or covered with steel traffic rated plated each working day, The last twenty (20) feet of each trench may be open provided that this length is covered with traffic rated plating. Steel plates shall be nonskid and shall be tacked down or spiked and placed flush with the surrounding pavement.

The Contractor shall be required to place temporary AC at the edges of the steel plates.

APPENDIX I

CONSTRUCTION AND DEMOLITION

DEBRIS RECYCLING SUMMARY

APPENDIX II

CITY BUSINESS LICENSE APPLICATION

APPENDIX III

CITY OF LOMITA

WATER STANDARD PLANS

APPENDIX IV

CITY OF LOS ANGELES

U PERMIT

APPENDIX V

CALTRANS

ENCROACHMENT PERMIT

NOTICE OF EXEMPTION
Project Description:
247th Street Area Water Main Replacement – This project consists of abandoning a watermain that runs north and south within private properties crossing 246th Street, 247th Street, 247th Place, and 248th Street. The proposed new water main will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right of way and along Western Avenue (which is Caltrans right of way), and connecting back to the City of Lomita along 247th Street, 247th Place, 248th Street and Lomita Blvd. This project consists of constructing approximately 3,300 linear feet of PVC water pipeline and appurtenances (fire hydrants, valves, services, and fittings). The existing pipeline located in private property will be abandoned. The new main will provide the same capacity.

Finding:

The City Council of the City of Lomita has reviewed the above proposed project and finds it to be exempt from the provisions of the California Environmental Quality Act (CEQA).

Ministerial Project
Replacement or Reconstruction of existing structures and facilities, Exemption (CEQA Guidelines, Section 15302 Class 2)
Statutory Exemption
Emergency Project
Quick Disapproval [CEQA Guidelines, Section 15270]
No Possibility of Significant Effect [CEQA Guidelines, Section 15061(b)(3)] Supporting Reasons In accordance with Section 15302 Replacement or Reconstruction, Class 2 consist of replacement of existing structure or facilities where the new facilities will be located on the same site as the old structure replaced and will have substantially the same purpose and capacity as the structure replaced. Per this California Environmental Quality Act (CEQA) Guidelines, the installation and use of the new underground pipe will be to supply water to the same customers, replacing old 1928 pipes and providing the same water capacity. 9/19/23
(Date) Carla Dillon, Director of Public Works
Public Works Department