CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
F-379
Stephenson Center Rennovation: This project consists of upgrades to the restroom facilities as well as restoration of the roof at Stephenson Center in Lomita Park.
Design $ 858,200 $58,200 $45,800
F-376
Tom Rico and Railroad Museum Rennovations: This project consists of replacing the roof at the Tom Rico Center building as well as the Railroad Museum Building.
Design $ 656,040 $56,040 $42,300
F-239
Appian Way Pump Station Roof Replacement: This project consists of removing the existing wooden roof of the Appian Way Pump Station and replacing it with a steel truss frame system.
Construction $904,355 $904,355 $81,284
F-368
City Hall HVAC Upgrades: This design-build project consists of upgrading the existing double deck heating, ventilation and air conditioning (HVAC) system at City Hall into a more energy-efficient system.
Design 1,740,799 $ $0 $0
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
ST-369
Downtown Lomita Multi-Benefit Stormwater: This project includes stormwater features along Lomita Boulevard and Narbonne Avenue to mitigate flood risk, improve water quality, and reduce the heat island effect in the downtown Lomita area. Additional features include bioretention areas, pervious pavement, landscape, benches and a new bike lane along Lomita Boulevard.
Design $ 939,155 $939,155 $186,586
Facilities O V E R V I E W
Stormwater
100% plans are in progress_Funding not Available yet for this fiscal year.
Pre-construction meeting scheduled for Sep 9.
Preliminary Design to Council anticipated on Oct. 15
Status
Design is progressing. Currently at 10% stage_Multiple sites are under consideration for the location of the infiltration gallery.
O V E R V I E W
Status Update
100% plans are in progress_Funding options are being considered from Prop 68, Prop A and Measure A.
Attachment No. 1
CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
WS-374
Narbonne South Water Main Replacement and Street Reconstruction: This project consists of constructing 1,600 feet of PVC water pipeline on Narbonne Avenue from PCH to the southern border of the City of Lomita. The entire width of the road will be rehabilitated as well.
Design $ 2,611,941 $199,940 $151,552
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
W-365
Cypress Water Facility Upgrades: This project adds 4 Granular Activated Carbon (GAC) tanks to improve Lomita’s water quality by filtering out hazardous contaminants in the water after the facility shut down in 2019 due to the detection of benzene.
Construction $ 5,178,140 $4,870,575 $4,316,785
W-375
Zone G Water Main Replacement: This project consists of constructing 5,000 feet of water lines along Walnut Street, 247th Place and Ebony Lane in Zone G of the City.
Design $ 2,436,118 $202,118 $86,335
W-134
Emergency Generator At Appian Way Station: This project consists of installation of an emergency generator that will be capable of servicing the Appian Way Pump Station as needed.
Construction $ 404,316 $404,316 $259,503
W-357
247th St Water Main Replacement: This project consists of installing 3,300 linear feet of new water main that will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right of way and along Western Avenue.
Construction $ 2,382,955 $888,067 $480,423
W-383
Alta Vista Ave Water Main Replacement: Install a 6" water pipe to replace an aging 4" pipe from 263rd to the City Limit Design $ 150,000 $0 $0 Status
SCADA Upgrades are currently underway. An inventory of items to be repaired is in progress by Hazen & Sawyer.
Potholing report to be submitted in September/October.
Delivery of last two items is pending due to supply chain issues.
Construction work in ongoing. 1300 ft out of 4800 ft of pipe have been installed to date.
Approval from State Drinking Water Division pending.
Water
O V E R V I E W
Water & Street
O V E R V I E W
Status
Environmental reviews ongoing as the design consultant is working on final 100% design.
Design is anticipated to be completed this winter.
CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
S-368
Zone G Street Reconstruction - Phase 1: This project consists of overlaying and reconstructing certain streets in Zones G, which is the area north of Lomita Boulevard and east of Eshelman Avenue.
Construction $ 2,021,835 $1,644,428 $171,742
S-380
Sidewalk Repair Program: This project consist of repairing 27 sidewalks accorss the city. In some cases, work will include changes to driveway aprons to conform with Lomita Municipal Code 11-1.66.07 (C).
Construction $ 250,000 $148,201 $0
S-352
School Traffic Loading Study: This study aims to analyze the existing conditions and provide recommendations to improve safety for students and caregivers walking and bicycling to school is desired.
Study $ 289,000 $260,533 $10,677
S-382
Lomita Boulevard Repair: This task aims to investigate and repair the 300-ft long westbound segment of Lomita Boulevard past Lucille Ave, exhibiting excessive rutting resulting in a 2-inch-deep settlement.
Design $ 200,000 $24,977 $0
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
M-755
Landscape Maintenance District Upgrades & Erosion Control : This project aims to replace the irrigation and turf with drought-resistant landscape for water-conserving purposes as well as reconstructing the existing pedestrian path and erosion control along Palos Verdes Drive.
Study n/a $ 19,276 $ 19,276 Design completed for Maintenance District. Design to be completed for erosion control along PV Drive. Construction to be planned once funding is secured.
Status
Parks O V E R V I E W
Streets
O V E R V I E W
Status
Construction Award to be considered during Sep 3rd Council Meeting to Excel Paving.
Pre-construction meeting held on 8/27. NTP to be sent out second week of September City's consultant, Toole Design, is progressing with review of existing conditions and data analysis. Site walks to each of the 4 schools will be completed early to mid September.
Onward Engineering is performing Design Analysis. Final deliverable expected in November.
CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
SE-100
Sewer System Master Plan (SMP): This study will identify any sewers that are undersized or need replacement/upsizing. Study $ 137,000 $137,544 $117,963 Wastewater
O V E R V I E W
Status
Additional study underway for Harbor Hills. City provided final comments on Sewer System Master Plan to Psomas. Anticipated presentation to council late September