CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
F-379 Stephenson Center Rennovation: This project consists of upgrades to the restroom facilities as well as restoration of the roof at Stephenson Center in Lomita Park.
Design $ 858,200 $58,200 $45,800
F-376 Tom Rico and Railroad Museum Rennovations: This project consists of replacing the roof at the Tom Rico Center building as well as the Railroad Museum Building.
Design $ 656,040 $56,040 $42,300
F-239
Appian Way Pump Station Roof Replacement: This project consists of removing the existing wooden roof of the Appian Way Pump Station and replacing it with a steel truss frame system.
Construction $904,355 $904,355 $116,394
F-368
City Hall HVAC Upgrades: This design-build project consists of upgrading the existing heating, ventilation and air conditioning (HVAC) system at City Hall into a more energy-efficient system.
Design $ 1,500,000 $0 $0
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
ST-369
Downtown Lomita Multi-Benefit Stormwater: This project includes stormwater features along Lomita Boulevard and Narbonne Avenue to mitigate flood risk, improve water quality, and reduce the heat island effect in the downtown Lomita area. Additional features include bioretention areas, pervious pavement, landscape, benches and a new bike lane along Lomita Boulevard.
Design $ 939,155 $939,155 $186,586
A public hearing is scheduled on October 15, 2024 to approve the final plans.
Status
Design is progressing. Currently at 10% stage_The location of the infiltration gallery is being finalized. A Project modification Request will be isued accordingly before the end of October.
O V E R V I E W
Status Update
One more round of revisions to be made to the Design_Funding options are being considered from Prop 68, Prop A and Measure A.
Facilities O V E R V I E W
Stormwater
One more round of revisions to be made to the Design_Funding not Available yet for this fiscal year.
Construction started in September. Work is progressing per schedule.
CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
WS-374
Narbonne South Water Main Replacement and Street Reconstruction: This project consists of constructing 1,600 feet of PVC water pipeline on Narbonne Avenue from PCH to the southern border of the City of Lomita. The entire width of the road will be rehabilitated as well.
Design $ 2,611,941 $199,940 $154,140
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
W-365
Cypress Water Facility Upgrades: This project adds 4 Granular Activated Carbon (GAC) tanks to improve Lomita’s water quality by filtering out hazardous contaminants in the water after the facility shut down in 2019 due to the detection of benzene.
Construction $ 5,178,140 $4,870,575 $4,316,785
W-375 Zone G Water Main Replacement: This project consists of constructing 5,000 feet of water lines along Walnut Street, 247th Place and Ebony Lane in Zone G of the City.
Design $ 2,436,118 $202,118 $87,241
W-134
Emergency Generator At Appian Way Station: This project consists of installation of an emergency generator that will be capable of servicing the Appian Way Pump Station as needed.
Construction $ 404,316 $404,316 $259,503
W-357
247th St Water Main Replacement: This project consists of installing 3,300 linear feet of new water main that will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right of way and along Western Avenue.
Construction $ 2,382,955 $888,067 $482,904
W-383 Alta Vista Ave Water Main Replacement: Install a 6" water pipe to replace an aging 4" pipe from 263rd to the City Limit
Design $ 150,000 $0 $0
Water
O V E R V I E W
Water & Street
O V E R V I E W
Status
Environmental review is expected to be submitted to the EPA for approval by the end of October. Meanwhile, the 100% design package is in propgress. Design is anticipated to be completed this winter.
Status
SCADA Upgrades are currently underway. Meanwhile, the City made the purchase order to replace deteriorating valves and the motor of the pump. 60% Design is progressing accordingly. Final design expected February 2025.
Delivery of last two items is pending due to supply chain issues overseas.
Construction work is expected to be completed by mid November.
Approval from State Drinking Water Division pending.
CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
S-368
Zone G Street Reconstruction - Phase 1: This project consists of overlaying and reconstructing certain streets in Zones G, which is the area north of Lomita Boulevard and east of Eshelman Avenue.
Construction $ 2,021,835 $1,644,428 $171,742
S-380
Sidewalk Repair Program: This project consist of repairing 27 sidewalks accorss the city. In some cases, work will include changes to driveway aprons to conform with Lomita Municipal Code 11-1.66.07 (C).
Construction $ 250,000 $148,201 $767
S-352
School Traffic Loading Study: This study aims to analyze the existing conditions and provide recommendations to improve safety for students and caregivers walking and bicycling to school is desired.
Study $ 289,000 $260,533 $10,677
S-382
Lomita Boulevard Repair: This task aims to investigate and repair the 300-ft long westbound segment of Lomita Boulevard past Lucille Ave, exhibiting excessive rutting resulting in a 2-inch-deep settlement.
Design $ 200,000 $24,977 $4,543
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
M-755
Palos Verdes Drive Upgrades: This project aims to replace the irrigation and turf with drought-resistant landscape for water-conserving purposes as well as reconstructing the existing pedestrian path and erosion control along Palos Verdes Drive.
Design $ 50,000 $ 19,276 $ 19,276
Project
ID # Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
SE-100 Sewer System Master Plan (SMP): This study will identify any sewers that are undersized or need replacement/upsizing. Study $ 177,000 $137,544 $123,946 Wastewater
O V E R V I E W
Status
Final report expected to be approved in November.
Status
Excel Paving to start construction in November/ December.
Rojas Construction has started work as of Sep 10. Work is progressing per schedule.
Existing conditions Technical Memo is under review by the City. Public workshops is expected to be held in October /November.
Onward Engineering is performing Design Analysis. Final deliverable expected in November/ December.
This project is two-parts: 1) Design upgrades for the Maintenance District has been completed. 2) Design for the erosion control to be arranged once funhding is secured.
Status
Parks O V E R V I E W
Streets
O V E R V I E W