CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Stephenson Center Rennovation: This project consists of upgrades to the restroom facilities as well as restoration of the roof at Stephenson Center in Lomita Park. Design $ 858,200 $58,200 $45,800 Tom Rico and Railroad Museum Rennovations: This project consists of replacing the roof at the Tom Rico Center building as well as the Railroad Museum Building. Design $ 656,040 $56,040 $42,300 Appian Way Pump Station Roof Replacement: This project consists of removing the existing wooden roof of the Appian Way Pump Station and replacing it with a steel truss frame system.

Construction $904,355 $904,355 $238,300
City Hall HVAC Upgrades: This design‐build project consists of upgrading the existing heating, ventilation and air conditioning (HVAC) system at City Hall into a more energy‐efficient system.

Design 1,500,000 $ $0 $0
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Downtown Lomita Multi‐Benefit Stormwater: This project includes stormwater features along Lomita Boulevard and Narbonne Avenue to mitigate flood risk, improve water quality, and reduce the heat island effect in the downtown Lomita area. Additional features include bioretention areas, pervious pavement, landscape, benches and a new bike lane along Lomita Boulevard.

Design $ 939,155 $939,155 $201,251
Facilities O V E R V I E W
Stormwater
One more round of revisions to be made to the Design_Funding not Available yet for this fiscal year.

Work is progressing and is on track to be completed by March 2025.

This project is under review by the City Attorny for further steps Status
Project Modification Request (PMR) was submitted to Safe Clean Water on October 31st. The PMR amends the type of stormwater control measure proposed as well as its location due to design considerations.

O V E R V I E W
Status Update
One more round of revisions to be made to the Design_Funding options are being considered from Prop 68, Prop A and Measure A.

CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Narbonne South Water Main Replacement and Street Reconstruction: This project consists of constructing 1,600 feet of PVC water pipeline on Narbonne Avenue from PCH to the southern border of the City of Lomita. The entire width of the road will be rehabilitated as well.

Design $ 2,611,941 $199,940 $197,238
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Cypress Water Facility Upgrades: This project adds 4 Granular Activated Carbon (GAC) tanks to improve Lomita’s water quality by filtering out hazardous contaminants in the water after the facility shut down in 2019 due to the detection of benzene.

Construction $ 5,178,140 $4,870,575 #REF!
Zone G Water Main Replacement: This project consists of constructing 5,000 feet of water lines along Walnut Street, 247th Place and Ebony Lane in Zone G of the City.

Design $ 2,436,118 $202,118 $87,241
Emergency Generator At Appian Way Station: This project consists of installation of an emergency generator that will be capable of servicing the Appian Way Pump Station as needed.

Construction $ 404,316 $404,316 $259,503
247th St Water Main Replacement: This project consists of installing 3,300 linear feet of new water main that will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right of way and along Western Avenue.

Construction $ 2,382,955 $888,067 $483,714
Alta Vista Ave Water Main Replacement: Install a 6" water pipe to replace an aging 4" pipe from 263rd to the City Limit Design $ 150,000 $0 $0 Status
SCADA Upgrades are currently underway. Meanwhile, the City made the purchase order to replace deteriorating valves and the motor of the pump. 60% Design is progressing accordingly. Final design expected February 2025.

Delivery of last two items is pending due to supply chain issues overseas.

Construction work is expected to be completed by end of November and closeout by early next year.Design is completed and coordination is ongoing with MWD and LADWP Water

O V E R V I E W
Water & Street

O V E R V I E W
Status
Environmental review was submitted to the EPA for approval in October. Meanwhile, the 100% design package and Caltrans permitting is in progress. Design is anticipated to be completed this winter.

CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Zone G Street Reconstruction ‐  Phase 1: This project consists of overlaying and reconstructing certain streets in Zones G, which is the area north of Lomita Boulevard and east of Eshelman Avenue.

Construction $ 2,021,835 $1,644,428 $174,724
Sidewalk Repair Program: This project consist of repairing 27 sidewalks accorss the city. In some cases, work will include changes to driveway aprons to conform with Lomita Municipal Code 11‐1.66.07 (C).

Construction $ 250,000 $148,201 $83,367
School Traffic Loading Study: This study aims to analyze the existing conditions and provide recommendations to improve safety for students and caregivers walking and bicycling to school is desired.

Study $ 289,000 $260,533 $50,085
Lomita Boulevard Repair: This task aims to investigate and repair the 300‐ft long westbound segment of Lomita Boulevard past Lucille Ave, exhibiting excessive rutting resulting in a 2‐inch‐deep settlement.

Design $ 200,000 $24,977 #REF!
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Palos Verdes Drive Upgrades: This project aims to replace the irrigation and turf with drought‐resistant landscape for water‐conserving purposes as well as reconstructing the existing pedestrian path and erosion control along Palos Verdes Drive.

Design $ 50,000 $ 19,276 $ 19,276 This project is two‐parts: 1) Design upgrades for the Maintenance District has been completed. 2) Design for the erosion control to be arranged once funhding is secured.

Status
Parks O V E R V I E W
Streets

O V E R V I E W
Status
Excel Paving to start construction in November/ December.

Work is currently 60% complete. More locations may be added to the scope of work.

Public workshops are planned for mid‐January.

Onward Engineering is performing Design Analysis. Final deliverable expected in November/ December.

CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Sewer System Master Plan (SMP): This study will identify any sewers that are undersized or need replacement/upsizing. Study $ 177,000 $137,544 $132,801 Wastewater

O V E R V I E W
Status
Final report was approved by City Council on October 15th. Contract amendment was approved by City Council on November 5th. The amendment allows Psomas to assist the City with the Harbor Hills issue in which a public sewer is feeding into a private sewer.