CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Stephenson Center Rennovation: This project consists of upgrades to the restroom facilities as well as restoration of the roof at Stephenson Center in Lomita Park. Design $ 858,200 $58,200 $45,800Tom Rico and Railroad Museum Rennovations: This project consists of replacing the roof at the Tom Rico Center building as well as the Railroad Museum Building. Design $ 656,040 $56,040 $42,300Appian Way Pump Station Roof Replacement: This project consists of removing the existing wooden roof of the Appian Way Pump Station and replacing it with a steel truss frame system.

Construction $904,355 $904,355 $537,797
City Hall HVAC Upgrades: This design-build project consists of upgrading the existing heating, ventilation and air conditioning (HVAC) system at City Hall into a more energy-efficient system.

Design 1,500,000 $ $0 $0
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Downtown Lomita Multi-Benefit Stormwater: This project includes stormwater features along Lomita Boulevard and Narbonne Avenue to mitigate flood risk, improve water quality, and reduce the heat island effect in the downtown Lomita area. Additional features include bioretention areas, pervious pavement, landscape, benches and a new bike lane along Lomita Boulevard.

Design $ 1,069,517 $1,069,517 $261,760
This project is under review by the City Attorney for further steps Status
Council approved contract amendment on 12/17/24. New geotechnical investigation is being scheduled to check infiltration rates at City Hall front lawn and rear parking lot. Project Modification Request (PMR) was submitted to Safe Clean Water on 10/31/24.

O V E R V I E W
Status Update
One more round of revisions to be made to the Design_Funding options are being considered from Prop 68, Prop A and Measure A.

Facilities O V E R V I E W
Stormwater
One more round of revisions to be made to the Design_Funding not Available yet for this fiscal year. Work is progressing, roof removed and is on track to continue through Xmas holidays and be completed by March 2025. We can have a ribbon cutting in time for February End 2025 and NOC in March 2025.

CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Narbonne South Water Main Replacement and Street Reconstruction: This project consists of constructing 1,600 feet of PVC water pipeline on Narbonne Avenue from PCH to the southern border of the City of Lomita. The entire width of the road will be rehabilitated as well.

Design $ 2,611,941 $232,941 $202,647
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Cypress Water Facility Upgrades: This project adds 4 Granular Activated Carbon (GAC) tanks to improve Lomita’s water quality by filtering out hazardous contaminants in the water after the facility shut down in 2019 due to the detection of benzene.

Construction $ 5,178,140 $5,281,227 $4,406,447
Zone G Water Main Replacement: This project consists of constructing 5,000 feet of water lines along Walnut Street, 247th Place and Ebony Lane within Zone G. Design $ 2,436,118 $202,118 $87,241Emergency Generator At Appian Way Station: This project consists of installation of an emergency generator that will be capable of servicing the Appian Way Pump Station as needed.

Construction $ 404,316 $404,316 $259,503
247th St Water Main Replacement: This project consists of installing 3,300 linear feet of new water main that will extend from 246th Street beyond the City boundaries, looping within the City of Los Angeles right of way and along Western Avenue.

Construction $ 2,382,955 $888,067 $483,714
Alta Vista Ave Water Main Replacement: Install a 8" water pipe to replace an aging 4" pipe from 263rd to the City Limits. Design $ 150,000 $0 $0 Water

O V E R V I E W
Water & Street

O V E R V I E W
Status
Preparation of application for EPA funding is in progress. Meanwhile, the 100% design package and Caltrans permitting is in progress. Design is anticipated to be completed this Spring 2025.

Status
SCADA Upgrades are in-process. Recent purchase order processed to replace deteriorating valves and pump motor. 60% Design Phase is progressing on-time. Final design projected for February 2025. Project is completed - Final inspection completed with final report awaiting issuance. Remaining construction items including traffic loops, street light conduit repair, and striping are expected to be completed before the end of February with closeout by early Spring. Final Design completed with on-going efforts with State Division of Drinking Water/DDW, Metropolitan Water District/MWD and Los Angeles Department of Water & Power/LADWP to obtain the necessary approvals.

CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Zone G Street Reconstruction - Phase 1: This project consists of overlaying and reconstructing certain streets in Zones G, which is the area north of Lomita Boulevard and east of Eshelman Avenue.

Construction $ 2,021,835 $1,644,428 $214,797
Sidewalk Repair Program: This project consist of repairing 27 sidewalks accorss the city. In some cases, work will include changes to driveway aprons to conform with Lomita Municipal Code 11-1.66.07 (C).

Construction $ 250,000 $148,201 $153,321
School Traffic Loading Study: This study aims to analyze the existing conditions and provide recommendations to improve safety for students and caregivers walking and bicycling to school is desired.

Study $ 289,000 $260,533 #REF!
Lomita Boulevard Repair: This task aims to investigate and repair the 300-ft long westbound segment of Lomita Boulevard past Lucille Ave, exhibiting excessive rutting resulting in a 2-inch-deep settlement.

Design $ 200,000 $24,977 $15,972
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Palos Verdes Drive Upgrades: This project aims to replace the irrigation and turf with drought-resistant landscape for water-conserving purposes as well as reconstructing the existing pedestrian path and erosion control along Palos Verdes Drive.

Design $ 50,000 $ 19,276 $ 19,276
Status
Excel Paving started construction on December 2. Project is expected to be complete by April 2025.Work is currently 100% complete. Project went over the budget plus contigency so we need to present to the committee on their next meeting for approximatly 5K increase and pay their last bill.Public workshops are planned for mid-January.Onward Engineering has received City's comments on the 60% design. Construction expected to be completed in Spring 2025.This project is two-parts: 1) Design upgrades for the Maintenance District has been completed. 2) Design for the erosion control to be arranged once funhding is secured.

Status
Parks O V E R V I E W
Streets

O V E R V I E W

CITY OF LOMITA CAPITAL IMPROVEMENT PROJECTS UPDATE
Project Description Phase Budget
Total Contracts
Approved to
Date (with
contingency)
Total Amount
Spent to Date
Sewer System Master Plan (SSMP): This study will identify any sewers that are undersized or need replacement/upsizing. Study $ 177,000 $137,544 $0 Wastewater

O V E R V I E W
Status
City met with Psomas to address the public sewer to private sewer issue. City will reach out to LAC Development Authority to discuss situation.