ATTACHMENT C
Red Car Trolley Construction
Alternative 2
Expenditure Estimated Cost
Barn Structure (w/fabrication) $53,000.00
Relocation of underground storm drains & inlets $45,000.00 Grading smaller portion of the field $50,000.00
Base (decomposed granite) $25,000.00
Path (decomposed granite) $15,000.00
Rail track relocation/installation $20,000.00
Lighting (inside atrium & panel upgrade) $15,000.00
Contingency (20%) $44,600.00
Estimated Total $267,600.00