1 TO: City Council
FROM: Andrew Vialpando, City Manager
PREPARED BY: Lina Hernandez, Assistant City Manager
MEETING DATE: February 3, 2026
SUBJECT: Construction Services Agreement with Signergy for the Lomita Park Marquee Sign Replacement Project
RECOMMENDED ACTION
Award a Construction Services Agreement to Signergy for the manufacture and installation of the Lomita Park Marquee Sign in the amount of $69,595 plus $3,230 for removal of existing sign for a total of $72,825 with an additional contingency of $2,175 for a total construction budget not to exceed $75,000; appropriate $75,000 from the Park Equipment Replacement Fund and authorize the City Manager to execute the agreement.
BACKGROUND
The Lomita Park monument sign, located outside of the Tom Rico Center at 24424 Eshelman Avenue, has been in service for over 40 years. The existing sign has experienced significant deterioration due to the extended weather exposure. It is also utilizes outdated plastic block letters that require manual insertion into a changeable signboard. Recent advancements in signage technology offer superior image resolution, enhanced graphic capabilities, and features such as wireless connectivity. These improvements would provide for more efficient use of staff time and allow for dynamic messaging and better support the diverse range of activities and events hosted at Lomita Park.
DISCUSSION
Staff solicited bids from several qualified vendors to replace the monument sign. After thorough evaluation of pricing, design quality, and vendor experience, Signery, a locally based company in San Pedro with numerous successful installations in the region, was selected as the recommended vendor. The proposals offer the best combination of product quality, technological advancement, and competitive pricing.
CITY OF LOMITA
CITY COUNCIL REPORT
Item No. 8c
2 It will take three to five weeks to manufacture the new sign and two weeks for installation.
The proposed sign replacement project supports ongoing improvements at Lomita Park and highlights the park’s significance to the community. Given the sign’s high visibility location and maximizing operational efficiency, the new sign will be installed at the existing site. By incorporating state-of-the art technology, the replacement sign will enhance communication capabilities and further enhance the value and visibility of Lomita Park as a vital community resource.
Staff recommends that the City Council approve a Construction Services Agreement with Signery, identified as the most qualified contractor for the Lomita Park Marquee Sign Replacement Project. The agreement totals $69,595 plus $3,230 for existing sign removal with a contingency of $2,175 for a total contract amount not to exceed $75,000 and authorize the City Manager to execute the agreement.
FISCAL IMPACT
The total construction budget with Signergy is $75,000 which includes a base contract of $69,595 plus $3,230 for existing sign removal for a total of $72,825 and a contingency of $2,175. If approved, $75,000 will need to be appropriated from the Park Equipment Replacement Fund.
VISION, MISSION, VALUES, AND STRATEGIC OUTCOMES
The City’s Vision, Mission, and Values set the standard for the organization, establish priorities, uniformity and guidelines; and provide the framework for policy decision making. The Strategic Outcomes were implemented to provide a pathway to achieving the City’s Vision. This item aligns with Strategic Outcome No. 4: Quality of Life & Livability – Creating vibrant spaces and services for all ages.
OPTIONS
Approve recommended action.
ATTACHMENTS
1. Agreement with Signergy with proposal and rendering