Market Street Pedestrian & Streetscape Enhancements
City Council Meeting – April 5, 2022
The Los Angeles River to 800 Feet East of Cherry Avenue – 2.2 Miles Project Limits – Market Street
2 • Two travel lanes each direction
• Parking lane each direction
• 5-Foot-wide sidewalks
• Path of travel obstructions
• Outdated curb ramps
• Poor pavement conditions
Existing Conditions
3 • Roadway Pavement Rehabilitation
• Sidewalk Extension
• Bulb-outs
• Decorative & Pedestrian Lighting
• Path of Travel Improvements
• Safety Improvements
• Lane Narrowing
• Class II/III/IV Bike Lanes
Project Scope
4 • New Fiber Optic Facilities
• Traffic Signal Upgrades
• ADA-Compliant Curb Ramps
• Sidewalk Repairs
• Driveway Repairs
• Landscaping
Class II/III/IV Bike Lanes
Pedestrian Improvements
5 Bulb-outs at Select Locations
Rectangular Rapid Flashing Beacons
Safety Improvements
6 High Visibility Crosswalks
• New Curb Ramps
• Replace Sidewalk
• Relocate Fire Hydrants
• Additional Sidewalk around
obstructions
Path of Travel Improvements
7 Street Light Improvements
8 Installation of decorative lighting and
pedestrian lighting at bulb out locations
Decreased travel lane width in each direction
LA River to Long Beach Boulevard
Complete Streets Redesign
9 Removal of center turn lane -
Long Beach Boulevard to Orange Avenue
Project Funding
10 Source Amount
State Local Partnership Program (LPP) $2,838,000
Federal Surface Transportation
Program (STPL)
$2,653,163
Federal Congestion Mitigation & Air
Quality Improvement Program (CMAQ)
$3,233,837
AB2766 $107,451
Prop A $21,000
Prop C $799,930
Measure R $500,000
Measure M $200,000
Gas Tax $500,000
Transportation Development Act (TDA) $300,000
Total $11,153,381
All American Asphalt - $8,318,600
Construction Award
Contract Award & Schedule
11 Target Schedule
• Estimated Groundbreaking – May 2022
• Estimated Completion – September 2023
Thank you Department of Public Works
12 Thank you! Questions?