LONG BEACH MUNICIPAL URBAN STORMWATER

TREATMENT PROJECT (LB-MUST)
City Council Meeting - July 5, 2022
2 3
Treatment
Facility
Wetlands
Water Reuse
Outflow to
LA River Via
SD-01
Phase 1 Conceptual Depiction – Not to Scale
SD-02
Conveyance
3 3
Phase 1: Initial Operations – Construction In Progress
• Construct 2 MGD Treatment
Facility
Program Phases
0 4
Phase 1: Initial Operations – Construction In Progress
• Construct 2 MGD Treatment Facility
• SD-02 Pump Station Connection
• Brackish Wetlands
Phase 2: 2 MGD Operations – Design
• Expand Pump Station Connections
• Pilot irrigation & Reuse at Facility/Wetlands
Phase 3+: 4 MGD Expansion – Concept Design
• Drake/Chavez – Irrigation & Reuse, additional Wetlands • Expand Facility
• Expand Conveyance network
Treatment
Facility
Wetlands
Water Reuse
LA-02, LA-03, LA-F14,
SD-06 Conveyance
Outflow to
LA River Via
SD-01
Phase 2 Conceptual Depiction – Not to Scale
SD-02
Conveyance
LA-01, SD-01
Conveyance
Irrigation
Reuse
5 5
Minimum Scope Estimated $8M
• $4M in Grant Funding
Secured
• $4M in Matching Funds
Identified
Phase 2 Project Costs
6 • Minimum Scope Estimate $8M
o $4M in Grant Funding Secured
o $4M in Matching Funds Identified
o Additional Grant Opportunities
• Minimum scope
o Complete design for all Phase 2 pump station connections o Connect to select pump stations
o Pilot reuse
• Goal: Secure additional funding and connect to all Phase 2 pump stations
Project Timeline Updates
7 2020
• Completed: Street, Utility, & Ground Improvements
2021-2023
• In Construction: Facility & Wetlands
2022-2024
• Phase 2 Design
2024-2026
• Phase 2 Construction

Facility Construction Progress Photos
8 Sitework, Utilities, Slab Rebar & Forming

Wetlands Construction Progress Photos
9 Warehouse cleanup, abatement, and demolition

10 10
11 Drake Park
Willmore Neighborhood
LA River
Path
Future Connections
to Chavez Park

12 13

Thank you
Eric Lopez
Director of Public Works
[email protected]
14 Melissa You
Project Management Officer
Stormwater Management
[email protected]
Colin Averill, PE
Civil Engineer
LB-MUST Project Manager
[email protected]