Studebaker Road Improvement Project
Data from December 6, 2022 Staff Report
Request for Cost/Schedule/Quality update
• Cost: $18.5 million total project cost
$12.25 million in grants/bonds
• Schedule: Spring/Summer 2023 bid issuance
Fall 2023 construction kickoff
• Quality: Complete Streets

Studebaker Road & Long Beach Transit
• Route 173 – PCH/Studebaker connects Norwalk
to Downtown Long Beach
• Weekday day travel: every 30 minutes
• Weekday evening travel: every 60 minutes
• Weekend day travel: every 45 minutes
• Weekend evening travel: every 60 minutes
• Total LBT bus stops along Studebaker: 51