STUDEBAKER CORRIDOR
COMPLETE STREET PROJECT
2nd Street to Los Coyotes Diagonal /
Carson Street
Previous Council Update December 6, 2022
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
“The target is to finish the design this fiscal year, get the project out to bid in Spring or Summer, and
[we’re] looking at Fall as a target to kick off
construction.”
“[We] anticipate to continue securing funds for the
project; that will be part of the next fiscal year
budget development process.”
- Eric Lopez, Director of Public Works
2 Project Overview
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
3 Safe Streets Long Beach Plan:
Primary Goal: Eliminate Fatal and Severe Crashes on City Streets
Keystone Action 2.1: Reduce illegal speeding by narrowing roads
Bicycle Master Plan:
Primary Goal: Design bikeways comfortable for people of all ages and abilities
Strategies 1.1, 1.2: Expand protected bikeway network,
focus on intersections and bridges (pg. 74)
Studebaker Project Goals:
✓ Calm traffic near schools and parks
✓ Close gaps in Long Beach’s protected bikeway network
✓ Add sustainable urban greening
✓ Expand transit and pedestrian amenities
✓ Reduce greenhouse gases
✓ Connect libraries and parks to the City’s fiber-optic network Safe Streets Long Beach Plan, Figure 8:
Common Collision Types Involving Bicyclists and Motorists Separated Bikeways Reduce Risk
of Most Common Bicycle Collisions
Project Location and Project Limits
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
N
Carson Street(City Limit)
4 Project Features
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Roadway Improvements
Class IV Bikeway
Bus Stop Improvements
Curb Enhancements &
Protected Intersections
Landscape/Irrigation
Improvements
Traffic Signal Improvements
ADA Improvements
Fiber Optic
Communication
5 Typical Section – 2nd Street to north of Loynes Drive
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Raised
Buffer
Median
6 Typical Section – Stearns Street to Spring Street
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
7 Typical Section – Spring Street to Wardlow Road
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
8 Intersection Rendering – SW Corner of Studebaker Rd & 2nd St (looking north)
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
9 Rendering – Studebaker Rd (looking north) overcrossing at SR-22/7th St
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
10 Mixed-Use Path Two Southbound Lanes One Northbound Lane Landscape Rendering – NB Studebaker between 2nd Street & Loynes
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
• Meandering
jagged rock
hardscape in a
wave back and
forth in median
• Tree & shrub
placement in
“wave pockets” on
outside of median
• Green street rock
swale between
bike lane
• Concept
Rendering – Final
Design Pending
11 Intersection Rendering – SB Studebaker at Anaheim Rd (looking north)
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
12 Re-Configured T-Intersection Concept at Los Coyotes Diagonal – Existing vs. Proposed
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
• Vertical Gateway Sign
proposed at this
intersection
13 Re-Configured T-Intersection Concept at Los Coyotes Diagonal – Landscape Rendering
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
14 90% Engineer’s Cost Estimate
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Construction Tasks Estimate
General Items (Mobilization, Survey, Traffic Control, etc.) $3,563,500 Removals and Demo $3,134,400
Pavement Improvements $8,250,600
PCC Improvements $6,848,000
Drainage and Water Quality $2,069,000
Utilities $125,500
Striping and Signage $894,500
Traffic Signals, Lighting and Fiber $6,307,300
Landscape and Irrigation $2,299,200
Cost Escalation (mid-point construction) $1,008,000
Estimated Base Construction Cost $34,500,000
With Contingency
10% Contingency &
Design Development
$3,450,000
Total Estimated
Construction Cost
$37,950,000
15 Corridor Project Comparisons
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Studebaker Road Artesia Great Boulevard Market Street
Total Estimated Construction
Cost & Contingency
$37,950,000
($45m – 49m fully loaded)
$36,217,830
($43.9m fully loaded)
$12,721,925
($15.7m fully loaded)
Project Length 5 Miles 3.25 Miles 2 Miles
Const. Cost per Mile $7.6 Million/Mile $11.1 Million/Mile $6.4 Million/Mile Number of Lanes 4 Total (2 North / 2 South) 4 Total (2 East / 2 West) 2 Total (1 East / 1 West) Project Scope Highlights • Full Depth Remove existing pavement & Place new asphalt section (south of Loynes)
• Cold Mill Remove existing pavement & Place
new asphalt section
• Construct new medians
• New irrigation and landscaping at new medians
• New traffic signal poles
• Fiber optic installation
• Class 1 multi-use bicycle & pedestrian lane with
median buffer (south of Anaheim)
• Class 4 bicycle lane (north of Anaheim) & Bus
transit platforms
• Re-align / Construct new LCD / Studebaker
intersection
• Cold Mill Remove existing
pavement & Place new asphalt
section or overlay
• Remove existing medians &
Construct new medians
• New irrigation and landscaping
at new medians
• New street lighting poles and
traffic signal poles
• Fiber optic installation
• Class 4 bicycle lane & Bus
transit platforms
• Cold Mill Remove existing
pavement & overlay
• New irrigation mainline and
landscaping at parkway
• No median
irrigation/landscaping
• New street lighting poles
and traffic signal poles
• Fiber optic installation
(conduit only)
• Class 2 bicycle lane, with
areas of Class 4 bicycle lane
16 Market Street Project - Progress Photos
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Phase 1 – LA River to
Long Beach Blvd
17 Market Street Project - Progress Photos
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Phase 2 – Long Beach Blvd
to Atlantic Ave
18 Artesia Great Blvd Project - Progress Photos
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
19 Project Funding Snapshot
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Funding Source Currently in Budget Pursuing / In Process Prospective MTA MM5509.05 $8,750,000 - -
Measure A $8,500,000 - -
Measure R $4,100,000 - -
Measure M $2,348,279 - -
Prop C $1,023,000 - -
STPL-5108(206) - $6,665,000 -
OCTA Settlement - $6,500,000 -
Clean California Grant (GWMA) - $2,000,000 -
Congressman Garcia Earmark Recommendation - $5,000,000 - Measure W (Potential match for Clean California) - $2,000,000 - FY24 CIP Corridor Funding - - TBD
Traffic Impact / Development Fees - - TBD
Previous FY CIP Funding (unencumbered) - - TBD
Total $24,721,279 Up to $22,165,000
20 Project Summary
STUDEBAKER CORRIDOR COMPLETE STREET PROJECT
Update and provide enhancements to the major corridor, Studebaker Road, which almost entirely encompasses the City’s limits in the north to south direction and as the major roadway alternative to the heavily congested I-605 Freeway that runs parallel and adjacent Increasing traffic efficiency and reliability for north-south general purpose traffic flow along Studebaker Road and enhance connectivity between major trip generatorsand transportation facilities on this key major corridor including Marina Pacifica to the south, CSULB to the west, El Dorado Regional Park to the east, and the City of Lakewood to the north Upgrade traffic signals and provide intersection capacity enhancements along Studebaker Road Improve speed and reliability for buses, including upgraded transit bus stops integrated with pedestrian and bicycle lane
Improve safety for pedestrians and bicyclists by reducing pedestrian crossing distance by installing protected intersections and by installing protected bike lanes along the corridor 21 Thank you
22 Eric Lopez, Director
Department of Public Works