SECTION E – Page 21

STANDARD SPECIFICATIONS
SECTION 7 – MEASUREMENT AND PAYMENT
7-3 PAYMENT
7-3.2 PARTIAL AND FINAL PAYMENT
Replace the last paragraph of this subsection with the following:

The closure date for period progress payments will be the twenty-fifth day of each month. Authorization to pay is commonly received on the second Wednesday of the following month. The Agency requires four to six weeks to review all progress payments, issue payment checks, present progress payment to Council for approval, and release payment to contractor. However, payments will be withheld pending receipt of any outstanding reports required by the Contract Documents. In addition, the final progress payment will not be released until the Contractor returns the control set of plans and specifications showing the as-built conditions.

The full five (5) percent retention will be deducted from all payments. The final retention will be authorized for payment thirty five (35) days after the date of recordation of the Notice of Completion.

The Contractor may substitute securities for any monies withheld by the Agency to ensure performance under the Contract as provided in Public Contract Code Sections 10263 and 22300. 7-3.3 DELIVERED MATERIALS
Replace Subsection 7-3.3 with the following:

Materials and equipment delivered but not incorporated into the Work will not be included in the estimate for progress payment.
7-3.4 Mobilization
Replace Subsection 7-3.4 with the following:

Mobilization and demobilization shall consist of preparatory work and operations including, but not limited to, those necessary for the movement of personnel, equipment, materials, and incidentals to the project site necessary for work on the project and for all other work and operations which must be performed or costs incurred including bonds, insurance, and financing prior to beginning work on the various contract items on the project site. Mobilization shall also include the time, materials, and labor to move the necessary construction equipment to and from the site, supervisory time on the job by the Contractor’s personnel to keep the construction site in a safe condition, and all other related work as required at all times and for all non-working days during the construction period. The Contractor is responsible for securing an adequate storage site for equipment and materials.

Contractor shall provide traffic control per California Temporary Traffic Control Handbook.

Contractor must maintain access for visitors to the properties. One driveway must always remain open and accessible. The cost for traffic control shall be paid per a separate lump sum bid item.

Payment for Mobilization shall be included in the other items of work and shall be considered full compensation and include but not be limited to, obtaining all business licenses and permits, as required for the entire project, from all related agencies, including, but not limited to, utility

Page 326 of 672 ends

SECTION E – Page 22

STANDARD SPECIFICATIONS
companies, private and public agencies and the City of Los Alamitos; and complying with the requirements specified in those licenses and permits; coordination, field office facility, implementation of Best Management Practices, and incidentals necessary to perform all related items of work.

SECTION 9 – CONSTRUCTION DETAILS
7-3.2 ORDER OF WORK
The Contractor shall phase the work on West Ward Ave. according to the following:
1) PCC improvements
2) Lowering of utilities (coordinate with utility agencies) 3) AC Pavement Reconstruction (Digouts)
4) Asphalt cold milling
5) Crack repair
6) Rout and seal cracks
7) HMA Overlay
8) Slurry Seal Joint Treatment
9) Utility cover adjustments (coordinate with utility agencies) 10) Pavement delineation
11) Restoration of Monuments
Any pavement repairs within designated cold milling areas shall be completed prior to cold mill operations. Cold milling operations shall not be performed more than 2-calendar days ahead of paving. Pavement repairs shall be constructed the same day they are removed. The Contractor must place concrete within 3 working days after the removal of existing concrete. Manhole frames and covers to be raised shall be raised and patched with ARHM within 3 calendar days of final day of ARHM overlay paving.

PAYMENT
Full compensation for conforming to those requirements will be considered as included in the prices paid for the various contract items of work and no separate payment will be made therefore.

Page 327 of 672 ends

SECTION F – Page 23

SPECIAL PROVISIONS

SECTION F

BLOOMFIELD STREET IMPROVEMENT PROJECT
CIP NO. 22/23-06

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

SPECIAL PROVISIONS

SPECIAL PROVISIONS
Except as hereinafter amended, the provisions of the 2021 Edition of the “Green Book,” Standard Specifications for Public Works Construction (“SSPWC”), with the latest Supplements, prepared and promulgated by the Southern California Chapters of the American Public Works Association and the Associated General Contractors of America, and these modifications thereto are adopted as the “Standard Specifications” for the Agency. These Standard Specifications will be numbered as Sections 0 through 800 per the SSPWC.

Page 328 of 672 ends

SECTION F – Page 24

SPECIAL PROVISIONS

SPECIAL PROVISIONS

BLOOMFIELD STREET IMPROVEMENT PROJECT
CIP NO. 22/23-06

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
PART 2 - CONSTRUCTION MATERIALS
SECTION 201 - CONCRETE, MORTAR, AND RELATED MATERIALS
201-1 PORTLAND CEMENT CONCRETE
201-1.1 Requirements
201-1.1.1 General.

Add the following:

The same brand, type, and source of cement and aggregate shall be used for all portland cement concrete.

Fly ash shall not be used.
201-1.2 Materials.
201-1.2.4 Chemical Admixtures.

Add the following:

1. Retarding Densifier. The material shall be of the hydroxylated carboxylic acid type in liquid form and shall not entrain air or cause foaming. The retarding densifier shall be used in strict compliance with the printed recommendations of the manufacturer. There shall be no reduction in the cement content of the concrete mix because of the addition of the retarding densifier.

The admixture shall be such that its addition to the concrete mix will:
a. Decrease drying shrinkage;
b. Increase compressive strength for all concrete strength for all concrete ages from 3 days to 1 year;
c. Increase flexural strengths, modulus of elasticity and abrasion resistance;
d. Increase the slump and placement workability;
e. Retard the initial set and increase the density; and f. Shall contain no calcium or tri-ethanolamine.

At the discretion of the Engineer, the Contractor may be required to submit proof that the admixture he proposed to use meets the foregoing requirements. Such proof shall be in the form of comparative tests of plain and admixture containing mixes performed by an acceptable local laboratory with testing based on use of the project materials and in accordance with the requirements of ASTM C 157.

An approved admixture conforming to these requirements is plastiment retarding densifier in liquid form.
201-3 EXPANSION JOINT FILLER AND JOINT SEALANTS

Page 329 of 672 ends

SECTION F – Page 25

SPECIAL PROVISIONS
201-3.1 General.

Add the following:

Contractor shall submit materials to Engineer for approval. 201-3.4 Type “A” Sealant (Two-Part Polyurethane Sealant).

Replace the first paragraph with the following:

Type A Sealant shall be two component silicone sealant and shall be furnished and placed in accordance with Specifications for "Two Component, Machine Mixed, Type A Sealant" (State Specification 8030-61J-01). Submit two samples to the Engineer for approval.
201-4 CONCRETE CURING MATERIALS
201-4.1 Membrane Curing Compounds
201-4.1.1 General.

Add the following:

Concrete curing compound shall be Type 2.

SECTION 203 - BITUMINOUS MATERIALS
203-6 ASPHALT CONCRETE
203-6.1 General.

Add the following:

Asphalt concrete material used for remove and replace repairs within the roadway shall be Class and Grade B-PG 64-10. Asphalt concrete mix of C2 gradation may be used for leveling layer.
203-11 ASPHALT-RUBBER HOT MIX (ARHM)
Subsection 203-11 ASPHALT RUBBER HOT MIX is amended by adding thereto the following paragraphs:
203-11.2 Materials.

Add the following:

Contractor shall maintain a minimum quality control plans as follows:
a) Perform sieve analysis test Caltrans Test 202 on a sample taken immediately after 300 tons of production and every 500 tons thereafter.
b) Perform binder content test Caltrans Test 382 on a sample taken immediately after 300 tons production and every 1,000 tons thereafter.

Tests shall be performed and completed without interruption directly after samples are procured at the production plant laboratory.

A copy of test results shall be provided to the Engineer immediately upon completion of

Page 330 of 672 ends

SECTION F – Page 26

SPECIAL PROVISIONS
each test or upon request thereafter if Engineer is not present at time of the test.

Adjustments shall be made immediately if test results indicate a need for adjustment. 203-11.2.3 Crumb Rubber Modifier (CRM).

Replace the first paragraph with the following:

The material shall consist of a combination of scrap tire CRM and high natural CRM meeting the requirements of this subsection. Scrap tire CRM shall consist of ground or granulated rubber derived from any combination of automobile tires, truck tires or tire buffing. Whole scrap tire rubber shall be derived from scrap tires generated entirely within the State of California, and the certification of compliance shall so certify.

The high natural rubber shall be a single source material and not a blend of more than one source.

The high natural CRM and CRM rubber components shall not be pre-mixed prior to mixing with paving asphalt.

The percentage of high natural CRM shall be equal to 1000 divided by the percentage of natural rubber in the high natural CRM (using whole number percentages), e.g., 1000/40% equals 25 percent. The remainder of CRM shall be scrap tires.

The maximum value for Natural Rubber Content in Table 203-11.2.3.1(B) is hereby deleted.

Delete the sixth (last) paragraph of Subsection 203-11.2.3.1. 203-11.2.4 Aggregate.

Replace this section with the following:

The aggregate for ARHM shall conform to the “quality requirements” for asphalt concrete Type A as specified in Caltrans Standard Specifications.

All aggregate used for ARHM shall be crushed aggregate.

Any change in source of aggregate supply requires 2 weeks advance notice in writing to the Engineer, and submittals and testing in conformance with specifications for a new mix design. No single bin shall receive aggregate from more than one source. Contractor shall provide a copy of aggregate delivery tickets for aggregate delivered for use on the project. 203-11.3 Composition and Grading.

Add the following:

Asphalt-rubber hot-mix shall be type and class ARHM-GG-C.

Optimum binder content shall be based on Caltrans 367 procedure without modification using air voids of 4%. Once full compliance with specifications is established at 4% air

Page 331 of 672 ends

SECTION F – Page 27

SPECIAL PROVISIONS
voids, the binder content shall thereafter be increased to provide 3.5% voids to conform to the residential traffic in the project, all other factors being within specification.

Variations of percent air voids below the minimum specified will be cause to terminate paving operations until changes to conform to the specified percent air voids are demonstrated and approved by the Engineer.

The gradation ranges shown in Table 203-11.3, including the ¾” sieve range added herein, shall be considered the Contract Compliance Range. The Operating Range for the ½” sieve shall be 94% to 99%. The Operating Range for all other sieves, except the 200 sieve, shall be 2 percentage points inside the Contract Compliance Range. If gradation test results do not meet the Operating Range requirements but meet the Contract Compliance Range, placement of ARHM may be continued for the remainder of the day.

However, another day’s work shall not be started until tests, or other information, indicate to the satisfaction of the Engineer that the next material to be used in the work will comply with the requirements specified for Operating Range. 203-11.4 Mixing Asphalt and CRM.

Add the following:

The required mixing/reaction time is hereby modified to 75 minutes minimum. The minimum reaction period shall be the time from complete incorporation of materials into the mix to the time that the asphalt-rubber meets all specifications for reacted material.

Reaction shall be considered complete only after the second of two viscosity readings taken 15 minutes apart is less than the first. The Engineer’s decision shall be final for determination of the minimum reaction period.

All material shall be tested for viscosity and verified as to completer reaction prior to transfer to any storage tank or use of the reaction tank for feet to the hot mix plant.

Material reacted lower than specified temperature, but above 185 degrees C (365 F), or transferred to a storage tank prior to completion of reaction as specified, shall be reacted for a total period of 3 hours prior to use. Any such transfer shall be described in the comments column of the Asphalt Rubber Batch Log.

Each batch of binder shall be tested for viscosity after the minimum reaction time has passed and the following information shall be recorded:
-Temperature of stored asphalt cement material at time of loading -Time at which the reaction tank is fully loaded
-Tons of asphalt rubber added to the tank for the batch -Total asphalt rubber in the tank after loading
-The beginning time of reaction (Fully loaded and above 375° F) -Binder temperature at time of sampling
-Temperature of tested material
-Viscosity reading
-Time of viscosity test (All test results must be completed prior to use.) A copy of the Asphalt Rubber Batch Log shall be provided to the Engineer upon request.

A copy of the batch log sheet and all circle charts for the day shall be faxed to the Engineer within 12 hours of ending production of ARHM for the day.

Page 332 of 672 ends

SECTION F – Page 28

SPECIAL PROVISIONS
(A log sheet form will be provided at the preconstruction meeting.) Construction shall be considered unauthorized until Contractor has faxed the log to the Engineer as arranged at the preconstruction meeting and has in his possession a fax confirmation sheet with a time and date conforming to specification. Under any circumstances, Engineer must be contacted for clearance to pave. 203-11.5 Equipment for production of Asphalt-Rubber.

Add the following to Item C) of 203-11.5:

Reaction Tank. The asphalt-rubber material shall be held in a reaction tank separate from the storage tank feeding the ARHM plant, until the reaction is complete. The reaction tank shall have agitation sufficient to increase the viscosity of the mixture to a peak viscosity reading at least 20 percent higher than the viscosity reading of the material measured at a time that the material otherwise meets specifications for reacted material.

The time of reaction may be extended as needed to produce this result. It shall be the responsibility of the Contractor to demonstrate to the Engineer through viscosity readings at appropriate times that the equipment conforms to these requirements. If this cannot be demonstrated, the reaction time shall be 3 hours. Once established, the reaction time shall be the minimum time for reaction unless there are changes in materials or equipment, in which case a new reaction time shall be established per specifications. The Engineer's decision shall be final.

The reaction tank shall have a functioning paper circle chart thermometer device, which shall record tank temperatures whenever asphalt rubber is in any stage of production.

Seven days before production of asphalt rubber starts, the Contractor shall provide the Engineer approximately double the number of charts estimated to be needed to produce the necessary binder quantity. These charts will be numbered and signed by the Engineer and returned to the Contractor prior to start of production. These signed and numbered charts shall be used throughout production of the asphalt rubber binder. Charts shall be used in the consecutive order as numbered by the Engineer beginning with number one, and shall be returned weekly after use to the Engineer. Charts will be identified with the date they were used by the Contractor at time of installing on the equipment, and shall be identified as to the tank to which they were attached. Production of asphalt rubber shall be terminated if this procedure is not followed and will not be restarted until Contractor demonstrates to the Engineer that it is capable of complying with this requirement.

At the start of each production day, the paper chart shall be replaced with a new signed, dated and numbered sheet, the lead scribe shall be sharpened or ink well filled, and the circle chart shall be calibrated against a sample of material drawn early from the first batch of the day. Any calibration adjustments shall be recorded in the appropriate space provided on the batch log sheet. A spare functional circle chart device shall be at the plant at all times for immediate installation should failure occur on a circle chart device being used. Calibration shall be performed as part of such installation. The lack of a functional circle chart device on the reaction tank shall be cause to terminate production of asphalt rubber binder. A blunt lead scribe or low ink, or a paper chart used on a prior day will be considered to render the device non-functional.

Storage Tank. After a complete reaction is verified by viscosity readings acceptable to

Page 333 of 672 ends

SECTION F – Page 29

SPECIAL PROVISIONS
the Engineer, the material shall be held in a storage tank that is fully isolated from material that is not fully reacted. This tank shall be the only tank feeding the ARHM plant. No material shall be transferred to the storage tank feeding the plant until reaction is complete in the reaction tank.

SECTION 206 - MISCELLANEOUS METAL ITEMS
Add new Section 206-7 ORNAMENTAL VINE ARBOR & DECORATIVE RAILING ON TOP

OF WALL
206-7 ORNAMENTAL VINE ARBOR & DECORTAIVE RAILING ON TOP OF WALL 206-7.1 Materials. The fabrication of ornamental vine arbor and decorative railing shall be in accordance with Section 304-2.

Steel vine arbor materials shall be tubular sections of hot rolled mild steel conforming to ASTM A-501, size and wall thickness as noted on drawings, minimum 11 gauge wall thickness.

All materials shall be hot-dipped galvanized in accordance with Subsection 210-3.

Decorative railing materials shall be as specified on the drawings. 206-7.2 Submittals.
206-7.2.1 General. Contractor shall submit [three (3)] copies of shop drawings, material lists, paints, and manufactured item submittals to the Engineer for review within [15-] calendar days of award of contract.
206-7.2.2 Shop Drawings. Shop drawings shall be submitted in accordance with Section 2-5.3 of the Standard Specifications.

Shop drawings for vine arbor and railing shall indicate complete layout of the work based on field measurements, and shall clearly indicate all deviations from the Plans.

Shop drawings for vine arbor and railing shall not be copies of details on the Plans, but shall be supplemental drawings indicating methods of fabrication and installation; and material list. Certificates of compliance of material to the specification shall be furnished.
206-7.2.3 Manufactured Items. Catalog cuts and manufacturer's specifications shall be submitted for all items to be incorporated in the work. 206-7.3 Payment.

Page 334 of 672 ends

SECTION F – Page 30

SPECIAL PROVISIONS
This Bid Item shall include all labor, material and equipment required to construct the handrail complete in place per the plans. Handrails shall conform to the provisions of Section 206-5 of the Standard Specifications and shall be placed in accordance with Section 304-2 of the Standard Specifications.

Payment for Construct Handrail per SPPWC Std 606-4 shall be paid for at the contract unit price per Linear Foot (LF) and shall include full compensation and include but not limited to, furnishing all labor, materials, tools, equipment, fabricating, installing, and incidentals and for doing all the work involved complete in place and no additional compensation will be allowed therefore.

SECTION 211 - MATERIAL TESTS
211-1 COMPACTION TESTS.
211-1.1 Laboratory Maximum Density.

Add the following:

Laboratory maximum density tests shall be performed in accordance with Test Method No. Calif. 216G, Part II. The correction for oversized material as stated in Test Method No. Calif. 216 shall be replaced with Note 2 of ASTM D1557. 211-1.2 Field Density.

Add the following:

Field density tests will be made by the Engineer during the course of construction at the expense of the CITY. If field density tests indicate that any portion of the compacted subgrade has density lower than that specified, the Contractor shall rework that portion until the specified density is obtained. Retest of areas which have failed compaction will be performed by the Engineer at the Contractor's expense.

Page 335 of 672 ends

SECTION F – Page 31

SPECIAL PROVISIONS
PART 3 - CONSTRUCTION METHODS
SECTION 300 - EARTHWORK
300-1 CLEARING AND GRUBBING
300-1.1 General.

Add the following:

In addition to the work outlined in Subsection 300-1 of the Standard Specifications, the following items of work are included in other bid items and no additional payment will be made therefore.
(1) Maintain dust control at all times by watering; including developing a water supply and furnishing and placing all water required for work done in the contract, including water used for extra work and water used for irrigation purposes.
(2) Protection of utilities, trees, fences, walls and other facilities within the construction zone, except those specifically directed by the Engineer to be removed or relocated.
(3) Clearing and removal of debris from site of work.
(4) Removal of structures, as directed by Engineer to be removed or abandoned. (5) Delay in work necessary to accommodate utility relocations by others. (6) Other items of work as directed in Appendix Part II, Mitigation Monitoring and Reporting Program.
(7) Other items of work as directed in these specifications. 300-1.3 Removal and Disposal of Material.
300-1.2 Root Pruning and Tree Trimming.

Add the following:

Tree branches which hang within 13.5 feet above finished roadway grade or within 9 feet above finished sidewalk or parkway grade shall be removed to the branch collar in accordance with the current pruning standards of the International Society of Arboriculture (ISA). The Contractor shall remove additional tree branches, under the direction of the Engineer, in such a manner that the tree will present a balanced appearance. No paint or tree sealant shall be applied to the resulting scars. All pruning shall be done under the supervision of an ISA Certified Arborist in the Contractor’s employ.

All the root pruning required to place or replace walks, or other permanent

Page 336 of 672 ends

SECTION F – Page 32

SPECIAL PROVISIONS
facilities shall be limited to the minimum amount necessary to set forms.

All roots 2 inches and larger shall be cut with sharp tool such as axe or chainsaw.

No roots shall be broken off by trenching or other heavy equipment.

No root shall be removed within five (5) diameters of the tree trunk measured at 4 feet, 9 inches above grade without the express written permission of the City.

Any such root removed without the City’s written permission may create a hazardous condition for which the Contractor shall be liable.

Should the Contractor create a hazardous condition in the sole judgment of the Engineer the Contractor shall remove the tree and replace it with a specimen of the same species and value at the Contractor’s expense.

All significant root pruning (3-inch diameter and larger) shall be performed under the direct supervision of an ISA Certified Arborist in the Contractor’s employ.

All trees noted on the drawings for tree pruning shall have crown reduction and crown thinning performed in accordance with standards published by the Western Chapter of the International Society of Arboriculture (ISA). All pruning shall be performed by ISA certified tree workers under direct supervision of an ISA certified arborist. The Contractor shall furnish such credentials to the Engineer prior to commencement of any tree work.

Add the following Subsection 300-1.2.1:
300-1.2.1 Protection of Existing Trees to Remain.

All trees to remain in place within the limits of work shall be protected from damage by workmen, equipment, and operations. Insofar as prosecution of the work allows, following removal of surrounding pavements, etc., the root area beneath the tree drip line shall be protected from damage, including compaction. Protection shall include temporary fencing, barricades, etc. Warning tape will not be considered sufficient. 300-2 UNCLASSIFIED EXCAVATION
300-2.1 General.

Replace the first paragraph with the following:

Unclassified excavation shall consist of all excavation, including roadways, all types of bituminous pavement, and concrete pavement, curb, walk, gutters, cross gutters, driveways, and access ramps. Removals shall be in accordance with Section 401 Removals.
300-2.9 Payment.

Page 337 of 672 ends

SECTION F – Page 33

SPECIAL PROVISIONS
Replace the first sentence with the following:

Payment for unclassified excavation performed as part of the work for “remove and construct” bid items, shall be paid for as part of the work for that item, and no additional compensation will be allowed.
300-4 UNCLASSIFIED FILL
300-4.1 General.

Add the following:

The site shall be graded to the limit lines and elevations shown on the drawings with such allowances as may be required for the construction of walks, and other site improvements. Tolerance for rough grading is 1/10th of a foot (30mm), plus or minus, at drainage swales, building pads, and paved areas. At other areas, appearance shall be the governing factor.

Finish grades shall slope to drain without water pockets or irregularities and shall conform to the intent of all plans and sections, after thorough settlement, and compaction of the soil. Finished grades shall meet all existing or established controls of sidewalks, curbs, and walls and shall be of uniform slope and grade between points of fixed elevations or elevation controls from such point to established grades. Tolerance for finish grading is ¼ inch (6mm), plus or minus.

Make-up fill material in landscaped areas shall be Class A topsoil for the upper 12 inches of fill.
300-4.10 Payment.

Replace this subsection with the following:

Full compensation for furnishing all labor, materials, tools and equipment, and doing all the work involved in unclassified fill construction shall be considered as included in the price paid for “construct” bid item and shall include full compensation for the cost of all grading, shaping, compacting or consolidating and extra fill, if required, or other work that is required under this subsection. No additional payment will be made for unclassified fill.

SECTION 302 -ROADWAY SURFACING
302-5 ASPHALT CONCRETE PAVEMENT
302-5.1 General.

Add the following:

Cracks, joints, and holes to be filled shall be cleaned after cold milling.

Page 338 of 672 ends

SECTION F – Page 34

SPECIAL PROVISIONS
AC for AC pavement repairs and for PCC pavement repairs shall be placed the same day as removals are performed.

Add the following Subsection:
302-5.1.1 Preparation Crack Treatment.

A singular crack shall be considered to be a crack on the perimeter of an otherwise uncracked asphalt pavement area, a pavement block, exceeding 4 feet in minimum dimension. Such pavement area is defined by the cracks forming its perimeter. If asphalt concrete pavement is being constructed directly upon an existing asphalt concrete pavement: 1) Contractor shall spray all weeds in cracks with an approved herbicide, such as brand Roundup, a minimum of 1 week prior to paving. All weeds shall be resprayed if rain occurs within 48 hours after application; 2) all holes and cracks exceeding 1.5 inches deep by 5 inches wide by 7 inches long in all 3 dimensions shall be cleaned, tacked and filled with temporary 3/8” (cutback) asphalt concrete compacted level with the top of the existing pavement; 3) all cracks and holes with weeds shall be routed clear to a depth of one-inch; 4) All cracks and joints 1/4 inch or greater in width shall be blown clear with high pressure air; and 5) all singular cracks and joints shall be filled SS1-h or equal. Crack and joint filling shall utilize a banding type applicator (Crack banding machine or equivalent) or a “shoe” attachment on a wand, capable of spreading a band 2 to 3 inches wide over the crack, while at the same time striking off the crackfiller at a uniform thickness between 3/32 and 5/32-inch. Thickness shall not exceed 5/32-inch, but if so, crackfiller shall be reheated and replaned to the specified thickness by a method approved by the Engineer.

All crack preparation shall be performed after cold milling, and cracks in cold milled areas.

Engineer shall be notified in writing 24 to 48 hours prior to performing crack filling.

302-5.4 Tack Coat.

Add the following:

This item shall consist of a Bituminous Surface Pavement Tack Coat composed of a blend of elastic Polymer modified asphalts, thermoplastic resins and digested whole tire rubber. The Material is applied at 325 to 425 degrees F with a distributor truck at typical application rates of 0.08 to 0.15 gal/square yard. The exact application rate will be determined by surface conditions at time of application.

Paving asphalt (also referred to as tack coat) shall be Thermoplastic Polymer Modified No Track Tack, for ARHM and AC overlay and where specified for slurry seals, and SS 1h otherwise. The Thermoplastic Polymer Modified No Track Tack shall meet the following criteria:

Page 339 of 672 ends

SECTION F – Page 35

SPECIAL PROVISIONS
Test Method Typical Properties Specification
Digested whole tire rubber 2 1-3
Softening Point Degree F D36 165 160 Min
Penetration @ 77 Deg. F 100g, 5 sec, Dmm D-5 16 10 Min
Brookfield Viscosity @ 275 Deg. F cPs* D4402 975 3000 Max Brookfield Viscosity @ 350 Deg. F cPs* D4402 185 300 Max *BKF LV II, spdl #21 @ 20 RPM
The tack coat shall be applied to the existing pavement on the areas to receive the AC where specified. The Engineer shall approve the exact rate and number of applications.

Two heavy coats of SS 1h shall be applied to vertical joints for patching. All contact surfaces with new asphalt shall be painted tack coat immediately before the asphalt concrete is placed.

The tack coat shall be applied as specified in Subsection 302-5.4 of the Standard specifications and these special Provisions. Thermoplastic Polymer Modified No Track Tack shall be applied only when the existing surface is dry and the atmospheric temperature is 50 deg. F and rising. NO material shall be applied when rain is imminent.

Paving of overlay shall not proceed until the tack coat has stiffened sufficiently to not stick to truck tires. Upon occurrence of tracking of tack coat, paving shall cease, except remaining material in the hopper shall be used, and the tack shall be allowed time to setup.

The Thermoplastic Polymer Modified No Track Tack shall be heated slowly to 325-425 degrees F. At no time shall the product be heated above 450 degrees F. The product shall be applied through a distributor truck equipped with a heating unit and shall maintain tack coat at or above 325 degrees F. It shall be equipped with a full circulating spreader bar and pumping system capable of applying the Thermoplastic Polymer Modified No Track Tack material within + 0.01 gallons per square yard tolerance of specified application rate and give uniform covering of the surface to be treated. The distributor shall also include a tachometer, pressure gauge, and volume measuring device and thermometer. The application rates shall be 0.15 gallons per square yard for all ARHM or AC overlay and slurry seal (where specified) or as otherwise directed by the Engineer. If the pavement temperature reaches over 130 degrees F, the application rate will be reduced to minimum 0.08 gallons per square yard on overlay applications.

Paving asphalt shall not be applied until the preparation of the existing surface has been completed and thoroughly cleaned, and then only so far in advance of placing the asphalt concrete overlay as permitted by the Engineer. Slurry seal shall be applied on the same day as receiving tack coat. The Thermoplastic Polymer Modified No Track Tack shall not be left exposed overnight. Immediately in advance of placing the overlay, additional tack coat shall be applied as directed by the Engineer, to areas where the tack coat has been destroyed or otherwise rendered ineffective, and no additional compensation will be allowed for such work.

Page 340 of 672 ends

SECTION F – Page 36

SPECIAL PROVISIONS
Existing concrete curb faces and all concrete not to be overlaid shall be protected against disfigurement from the asphalt tack coat. Residue of the material shall be removed from concrete surfaces to return the concrete to its original condition unless otherwise directed by the Engineer.

Excessive tracking of tack coat onto adjacent pavements will require immediate clean-up.

If significant amounts of asphalt tack coat are tracked onto existing adjacent pavements, the contractor shall be required to clean it off to the satisfaction of the Engineer or provide a slurry seal to restore the pavement at their own expense. This shall apply to the entirety of asphalt haul routes to and from the project sites.

On all vertical joins of AC patching, apply SS-1H tack coat uniformly in two coats of .20 gallons per square yard each with full "break" in between, or .20 gallons per square yard PG 64-10 uniformly in one coat. Tack coat shall not be applied when the temperature of the surface to be tacked is below 40o F in the shade. A tack coat shall be applied at the following:

1. Pavement joins;

2. Areas where new pavement meets existing pavements;

3. Areas where lift sections from pavement placed on different days meet;

4. Trenches;

5. Areas where existing striping has been sandblasted; and

6. Raised valves and manhole covers.

Full compensation for furnishing and applying tack coat shall be considered as included in the contract price paid per ton of Asphalt Concrete Paving and no separate payment will be made therefor.
302-5.5 Distribution and Spreading.

Add the following:

Each paving machine used will require a paving foreman for each machine along with a full set of rollers as specified and two rakers and one shoveler laborer at a minimum. 302-5.6 Rolling.
302-5.6.1 General.

Add the following:

Rolling along a joint shall be such that the widest part of the roller is on the hot side of the joint.

Rubber tire rollers shall be used on any leveling course.

Three rollers shall be provided for installation of AC greater than 200 tons per hour, regardless of thickness.
302-5.7 Joints.

Page 341 of 672 ends

SECTION F – Page 37

SPECIAL PROVISIONS
Replace the first sentence of the first paragraph with the following:

Join lines between successive runs shall be within 6 inches of lane lines or center of street or a minimum of 14 feet outside of the outer most lane line or center of street, or 5 to 6 feet from a lane line or center of street and within a lane. The joint pattern for all pavement layers shall be submitted in writing to the Engineer for review and approval 2 weeks in advance of the first lift of pavement to be placed. No exceptions to the specified requirements for joints shall be anticipated, and the Engineer’s decision shall be final. 302-5.9 Measurement and Payment.

Add the following:

Compensation to provide all of the equipment to the site and operated as specified, including all rollers specified regardless of rolling pattern elected by Contractor, shall be considered included in the bid item price for AC material.

Payment Remove and Construct 7.5-Inch Full Depth AC shall be paid at the contract price per ton (TON) and include full compensation for all labor, materials, tools, equipment and incidentals required to construct full depth AC pavement. This bid item will include furnishing the material, placement, compaction, prime coat, tack coat, asphaltic emulsion coating on vertical surfaces to abut the new pavement, grading and compaction of subgrade, and all other work required to result in an asphalt pavement meeting the requirements of the specifications.
302-9 ASPHALT-RUBBER HOT MIX (ARHM).
302-9.1 General.

Add the following:

All PCC surfaces, to be crossed by trucks used to haul ARHM, that are within 500 feet of the work limits shall be covered with sand or other durable covering prior to applying tack coat.

Contractor shall have sufficient power brooms on site during all periods of distribution and spreading to provide for cleanup of haul routes and work areas. Power broom shall provide miscellaneous cleanup of ARHM spoils as directed by the Engineer.

Power brooms used ahead of paving operations after acceptance of cold milling shall only sweep areas that are accepted as completed for cold milling. Power brooms shall not be operated more than 80 percent full of sweepings. Power brooms that have swept areas not accepted as completed for cold milling shall not enter onto areas that are accepted as completed for cold milling.
302-9.3 Distribution and Spreading.

Add the following:

The temperature of ARHM shall be high enough upon delivery that pavement temperature after two passes with the breakdown roller exceeds 290 degrees Fahrenheit

Page 342 of 672 ends

SECTION F – Page 38

SPECIAL PROVISIONS
(143 degrees Celsius).

To avoid picking up loose rock in the overlay area, the tires of all trucks must be lightly oiled with linseed oil or soybean oil or approved equal. Diesel fuel will not be allowed on the project at all for oil down of any equipment.

Raking of ARHM shall be eliminated as much as possible. ARHM material shall not be cast across the mat under any circumstance. Raking shall be just enough to set up edges for uniform joins without casting material. Screed controls shall be the predominant means of controlling material at joins. In areas where paving machines cannot be used due to space constraints, material shall not be thrown by shovels. Material shall be removed directly from the paving machine hopper and shall be placed directly in its final location, to be distributed with minimal raking. Material may be dumped directly from a truck, but further material distribution shall be by shovel directly to its final location with minimal raking. A small rubber tire tractor with a screed type attachment may be used to spread a pile dumped from a truck, but raking shall be minimized after spreading.

The paving machine screed shall not be pulled across an area already paved with ARHM, even adjacent to narrow areas to be paved. Such narrow areas shall have ARHM distributed by methods specified by shovel or rubber tire tractor, unless the adjacent area has hardened enough and will not be significantly marred by passing the screed over it.

Even if hardened adequately, Contractor shall spread rock dust by hand tools to avoid cohesion of the ARHM in the screed to the existing surface of such areas of freshly cured ARHM.

Contractor shall maintain a functioning infrared heat measurement device in close proximity to each paving machine at all times. The infrared device shall be correlated by thermometer to the actual mat temperature prior to use. The correlation difference shall be applied to all readings thereafter. Contractor shall provide a pavement temperature reading, with an infrared heat measurement instrument, when requested by the Engineer.

Inaccessibility of a heat measurement shall be cause for termination of paving operations.

Transverse cold joints shall be provided such that longitudinal joints are not left exposed at the end of the workday.
302-9.4 Rolling.

Add the following:

Initial breakdown rolling shall be vibratory. Rolling in vibratory mode shall not be performed after ARHM material temperature falls below 290 degrees F (143 degrees C), due to disturbance of the bonds beginning to set up in the binder at lower temperatures.

An intermediate roller of the same or greater width than the breakdown roller shall be rolling directly behind the breakdown roller at all times, and paving shall cease if intermediate rolling is terminated for any reason. Additional intermediate rollers may be necessary depending on production rates.

Once a rolling pattern is elected by Contractor, the rolling pattern shall remain consistent, unless conditions change and/or a modified rolling pattern is needed to conform to specification.

Page 343 of 672 ends

SECTION F – Page 39

SPECIAL PROVISIONS
All finish rolling shall be performed by a separate finish roller.

To ensure optimum quality control, the use of more than one paver will require notification 3 days in advance to the Engineer, and will generally require one foreman, one sweeper, and a full complement of rollers per Subsection 302-5 of the Standard Specifications and this Subsection 302-9.4 for each paving machine.

An extra breakdown roller shall be on site at all times, free of defects.

Add the following Subsections:
302-9.4.1 Density and Smoothness. Density and smoothness shall conform to Subsection 302-5.6.2, except the second and third paragraph of Subsection 302-5.6.2 shall not apply to ARHM.

The compaction after rolling shall be 95 percent of density obtained with the California Kneading Compactor, California Test 304 as modified and measured in conformance to this Subsection 302-9.4.1.

The field density of compacted ARHM shall be determined by:
1) A nuclear asphalt testing device, calibrated in conformance with California Test 375, except as modified in this Subsection 302-9.4.1, in the field designed to measure the density of pavement of the thickness being constructed; or 2) Core with density determined as follows:
a) Saw the ARHM lift of pavement from the top of the core approximately perpendicular to the axis of the core, just above any underlying pavement or as necessary to obtain a clean flat surface at the bottom of the sample. b) Clean and dry the sample as described in ASTM 1188.
c) Perform California DOT Test 308 Method A step a.
d) Prior to proceeding to steps 308A b., 308A c., 308A d. and 308A e., place the core, top surface down, firmly into a flat pan of hot liquid paraffin approximately 1/4 inches deep. Allow the sample and paraffin to cool to firm solid state and remove the sample from the pan by cutting around the perimeter. Trim the edges of paraffin parallel to the side of the sample cylinder, and weigh the cylinder to obtain:

G = Mass in grams of level sealed paraffin-treated specimen in air. e) Perform 308A b., 308A c., and 308A d on the sample from D) above. f) Complete the remainder of Test 308A, except replace the formula in 308A e. with the following:

Bulk Specific Gravity =
A
(D – E) – (D – G) / F

Page 344 of 672 ends

SECTION F – Page 40

SPECIAL PROVISIONS
In case of dispute, 1) shall be used, except Contractor may elect to use 2), but all costs for such procedures shall be borne by the Contractor to provide the full set of coring, tests and documentation in conformance with the Standard Specifications, except all test methods shall be modified as specified in these Special Provisions. Also, Contractor shall notify the Engineer at least 3 days in advance of coring operations, and immediately after core testing is complete Contractor shall deliver cores to the Agency for verification.

Nuclear test procedures, including correlation with core densities, shall be in conformance with California Test 375, except as follows:

If a test section is placed and compacted for that purpose, rolling shall be provided as follows: 1) 2 passes with a vibratory breakdown roller above 290 degrees F; and 2) 4 passes with a static roller above 200 degrees F. Core locations for correlation with cores shall be selected based on appearance of relatively tight surface texture, and the test strip shall be selected on this basis. If a test location is determined to have a significantly open texture relative to other areas within the test strip, the location shall not be used. This selection criteria are not to be considered significant to the outcome of, but only as a guideline towards obtaining samples that are relatively well compacted to yield results with minimum standard deviation. The locations shall be well clear of grade breaks and joints. One core centered on the gauge will be used instead of two at each location. Use method 2) in this Subsection 302-9.4.1 to determine density of cores. Surface voids shall not be filled with sand.

Contractor will be notified in writing at least 5 days in advance of such correlation testing and will be invited to have a nuclear gauge onsite to correlate a second gauge. If not independently calibrating at that time, Contractor shall bear the full expense of performing correlation for his nuclear gauge under the specified procedures, but shall notify the City 5 days in advance of such correlation testing, such that the City can correlate with the Contractor’s gauge, if Contractor disagrees with City’s test results.

TABLE 302-9.4.1A

REDUCED COMPENSATION FACTORS
Relative
Compaction
(Percent)
Reduced
Compensation
Factor
Relative
Compaction
(Percent)
Reduced
Compensation
Factor

95.0 0.000 93.4 0.062

94.9 0.002 93.3 0.068

94.8 0.004 93.2 0.075

94.7 0.006 93.1 0.082

94.6 0.009 93.0 0.090

94.5 0.012 92.9 0.098

94.4 0.015 92.8 0.108

94.3 0.018 92.7 0.118

94.2 0.022 92.6 0.129

94.1 0.026 92.5 0.142

94.0 0.030 92.4 0.157

93.9 0.034 92.3 0.175

93.8 0.039 92.2 0.196

93.7 0.044 92.1 0.225

Page 345 of 672 ends

SECTION F – Page 41

SPECIAL PROVISIONS

93.6 0.050 92.0 0.300

93.5 0.056
302-9.4.2 Compaction Payment Reductions.

Based on laboratory tests on AC pavements revealing a highly significant loss of life span for each 1 percent reduction of compaction, and the well known catastrophic effect of oxidation and stripping of asphalt products due to interconnected voids that develop below 95 percent compaction, and the extreme expense of removing and replacing pavement not compacted to the specified minimum, a nominal deduction of payment will be applied for under-compacted ARHM pavement. The bidder in submitting a bid fully accepts the provisions in this Subsection 302-9.4.2 and agrees that the nominal payment deduction is acceptable and reasonable for these purposes.

Payment reductions will be applied to ARHM compacted less than 95 percent of maximum density, the specified minimum, and greater than 91.9 percent of the maximum density based on nuclear testing with Part 3 Test Site Selection of California Test 375 modified as follows:

A lot will be one day’s production or other lesser area of paving as determined by the Agency to be deficient in terms of compaction, and a pull will be the width between joints or edge of pavement as the lot is placed.

Test site selection will conform to California Test 375 Part 3, except the number of tests shall be the area of the lot in square feet divided by 400 and any test site within .5m of a grade break or pavement joint shall be relocated laterally towards the center of the pull to .5m from such joint or grade break.

The mathematical mean average of percent of maximum density represented by all these tests shall be calculated, except any test results outside of this mean plus two standard deviations based on all tests, shall be rejected. The mean average shall be calculated directly from the remaining values. A compensation reduction in conformance with Table 302-9.4.1A will be applied to the contract unit price for ARHM for material within any lot determined to be below minimum relative compaction, except any lot with tests indicating compaction 91.9 percent or less shall be removed and replaced at Contractor’s expense.
302-9.7 Rock Dust Blotter.

Add the following:

Lack of uniformity of application of rock dust shall be cause to terminate paving operations. Rock dust blotter shall not be applied until intermediate rolling is complete, except as approved by the Engineer based on a fine uniform layer of rock dust, or at major intersections and access points.
302-9.9 Payment.

Replace the first sentence of the first paragraph with the following:

Payment for Construct 1.5-Inch ARHM Overlay Uniform Depth shall be paid at the

Page 346 of 672 ends

SECTION F – Page 42

SPECIAL PROVISIONS
contract price per ton (TN) and shall include, but not limited to, full compensation for furnishing all labor, materials, tools, equipment, transportation, crack sealing, tack coat, rock dust blotter, and other incidentals for doing all work, complete, and in place, involved in constructing ARHM overlay as indicated in the contract documents and no additional compensation will be allowed therefor.

SECTION 303 - CONCRETE AND MASONRY CONSTRUCTION
303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY

INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS
303-5.1 Requirements.
303-5.1.1 General.

Replace the second paragraph with the following:

Concrete areas behind sidewalks, driveways and right-of-way shall be considered as walks. The Contractor shall protect all new concrete installations from damage by others (subcontractors or the general public such as, blemishes, water stains, stress cracks, graffiti markings, etc.). The removal and replacement of damaged concrete work shall be performed and no additional cost to the Agency (City). Concrete sidewalk shall be a minimum 4” thick over native soil compacted to a minimum of 95 % relative compaction.

Actual limit of concrete removal shall extend to nearest score mark or joint, if nearest score mark or joint is within 30” limit of removal. Residual from any saw-cutting shall be removed by vacuum. The downstream drain inlet shall be protected. In no case shall the residual be allowed to enter the storm drain system.

Sawcutting shall be accomplished by the use of a power driven saw. The depth of the cut shall be deep enough to provide a clean, straight break without loosening, cracking, or damaging adjoining asphalt or concrete. A clean sawcut edge shall be maintained until new concrete sidewalk is constructed. The exact location of sidewalk removal shall be approved by the City Engineer in the field. Generally, sawcuts shall be on existing joints or score mark.

All necessary sawcutting of existing concrete sidewalks shall be to the lines as required by the City Engineer. Sawcutting shall be included in the unit price and no further compensation shall be made.

It is Contractor’s responsibility to protect all existing adjacent features such as landscaping, irrigation system, property’s fence/wall/gates, curb and gutter, pull boxes, utility boxes, and etc. in place per Section 400. All damages to these items shall be fixed to the satisfaction of City Engineer without any additional compensation.

Concrete sidewalk shall be constructed to the line, grades and designs shown on the plans or as ordered by the City Engineer. Existing surfaces to be joined shall be sawcut on a neat, straight line at the join location. The Contractor shall remove and replace any new concrete work with graffiti markings and blemishes at no additional cost to the City.

Page 347 of 672 ends

SECTION F – Page 43

SPECIAL PROVISIONS
Unless otherwise specified, soil in subgrade for curb and gutter shall be compacted to a relative compaction of ninety-five (95) percent in the top six (6) inches of subgrade.

Detectable warning surface (truncated domes) for curb ramps shall be Cast-in-Place System per Armor Tile Part No. ADA-C-3648 or approved equal, unless otherwise noted.

Color shall be yellow.

Payment of detectable warning surface for new ramps shall be included in the unit price bid for removal and construction of new curb ramps per SPPWC Std Plan 111-5. 303-5.1.2 Drainage Outlets Through Curb.

Replace the second paragraph with the following:

Prior to removal of concrete curb and gutter, Contractor shall identify all curb drains that will be disturbed by the removal and construction of curb and gutter and shall provide locations and quantity of curb drains to the City inspector. Approximate locations of impacted curb drains are shown on the plans but do not represent locations of all impacted curb drains. Contractor is responsible to replace all impacted curb drains, whether shown or not shown on plans. Any curb and gutter that is poured without prior approval from the City inspector may be subject to removal and replacement at the Contractor’s expense and no additional compensation will be allowed. 303-5.9 Measurement and Payment.

Add the following:

Payment for Remove and Construct Curb and Gutter per SPPWC Std Plan 120-3, Match Existing shall be paid per other items and shall include full compensation and include but not limited to furnishing all labor, materials, tools, equipment, saw cutting, hauling, disposing, restoring landscape and irrigation, and incidentals, for the removal of existing curb and gutter and construction of curb and gutter per SPPWC Std Plan 120-3 and no additional compensation will be made therefor.

Payment for Remove and Construct 4-inch Thick PCC Sidewalk per SPPWC Std Plan 113-2 shall be paid per other items and shall include full compensation and include but not limited to furnishing all labor, materials, tools, equipment, saw cutting, hauling, disposing, restoring landscape and irrigation, and incidentals for the removal of existing surface and construction of 4-inch thick PCC sidewalk per SPPWC Std Plan No. 113-2 and no additional compensation will be made therefor.

Payment for Remove and Construct Curb Drain per SPPWC Std Plan 150-3 shall be paid at the contract price per each (EA) and shall include full compensation and include but not limited to furnishing all labor, materials, tools, equipment, sidewalk replacement, saw cutting, hauling, disposing, and incidentals for the removal of existing curb drain and construction of curb drain in-kind per SPPWC Std Plan 150-3 and no additional compensation will be made therefor.

Payment for Remove and Replace Curb Ramp, Type per Plan will be paid for at the contract price per EACH and shall include removal and reconstruction of curb, gutter and sidewalk and installation of truncated domes. Said payment shall include sawcutting, removal and disposal of existing improvements, subgrade preparation, aggregate base,

Page 348 of 672 ends

SECTION F – Page 44

SPECIAL PROVISIONS
expansion joints, forming, pouring, paving, and backfill, complete in place, as shown on the PLANS.

Page 349 of 672 ends

SECTION F – Page 45

SPECIAL PROVISIONS
PART 4 – EXISTING IMPROVEMENTS
400 PROTECTION AND RESTORATION
401-1 GENERAL
Replace the second paragraph with the following:

The Contractor shall relocate, repair, replace or reestablish all existing improvements within the project limits (e.g., curbs, sidewalks, driveways, fences, walls, sprinkler systems, signs, utility installations, pavements, structures, survey monuments, landscaping, etc.) that are damaged or removed as a result of the Contractor’s operations or as required by the plans and specifications.

All existing improvements, either within the right-of-way or not, including irrigation lines that are damaged by actions of the Contractor, shall be restored by the Contractor to their original or better condition at the Contractor’s expense.

The Contractor shall mark, as approved by the Engineer, all survey monuments, manholes, valves, substructures, or other items that are visible on the surface and will be covered by his operations. This shall be completed prior to the start of that operation and approved by the Engineer.

Existing traffic striping, pavement markings, and curb markings shall also be considered as existing improvements and the Contractor shall repaint or replace, at the Contractor’s expense, such striping or markings (except for traffic striping and pavement markings within the limits of the Work) if damaged or if their reflectivity is reduced due to construction operations. 400-3 PAYMENT
Replace the last sentence of the first paragraph with the following:

All costs to the Contractor for protecting, removing, restoring, relocating, repairing, replacing, or reestablishing existing improvements shall be included in the Bid.

SECTION 401 – REMOVAL
401-2 ASPHALT CONCRETE PAVEMENT
Add the following:

Bituminous pavement shall be removed to neatly sawed edges. Saw cuts shall be to a minimum depth of 3 inches. Where only the surface of existing bituminous pavement is to be removed, the method of removal shall be approved by the Engineer, and a minimum laying depth of 1 inch of new pavement material shall be provided at the join line. Where bituminous pavement adjoins a trench, the edges adjacent to the trench shall be saw cut to neat straight lines before resurfacing to ensure that all areas to be resurfaced are accessible to the rollers used to compact the subgrade or paving materials.

Bituminous pavement on curb and gutter, sidewalk or drive approaches shall be removed by heating with a torch to soften the pavement without creating smoke. Softening shall be performed until the bituminous material can be easily scraped away down to the underlying PCC surface. The blade used for scraping shall be maintained straight along its edge and clean.

Bituminous material shall be scraped in this manner until it is completely removed.

Page 350 of 672 ends

SECTION F – Page 46

SPECIAL PROVISIONS
401-3 CONCRETE AND MASONRY IMPROVEMENTS.
401-3.1 Concrete Pavement.

Replace this subsection with the following:

Concrete pavement shall be removed to neatly sawed edges. Saw cuts shall be made to a minimum depth of 3 inches. If a saw cut in concrete pavement falls within 3 feet of a construction joint, cold joint, expansion joint or edge, the concrete shall be removed to the joint or edge. The edges of existing concrete pavement adjacent to trenches, where damaged subsequent to saw cutting of the pavement, shall again be saw cut to neat straight lines for the purpose of removing the damaged pavement areas.
401-3.2 Concrete Curb, Walk, Gutters, Cross Gutters, Curb Ramps, Driveway, and Alley Intersections.

Replace this subsection with the following:

Concrete shall be removed to neatly sawed edges with saw cuts made to a minimum depth of 1½- inches. Concrete sidewalk, or driveway to be removed shall be neatly sawed in straight lines either parallel to the curb or at right angles to the alignment of the sidewalk. No section to be replaced shall be smaller than 30 inches in either length or width. If the saw cut in sidewalk, access ramp, or driveway would fall within 30 inches of a construction joint, expansion joint, or edge, the concrete shall be removed to the joint or edge, except that where the saw cut would fall within 12 inches of a score mark, the saw cut shall be made in and along the score mark. Curb and gutter shall be sawed to a depth of 1½-inches on a neat line at right angles to the curb face. 402 UTILITIES
Add the following Subsections:
402-1.1.1 MANDATORY NOTIFICATION PRIOR TO EXCAVATION
The Contractor’s attention is direct to Section 4215.5 through 4217 of the Government Code of the State of California. This requires that two (2) working days prior to commencing any excavation “Underground Service Alert of Southern California” (USA) shall be notified by phone, toll free 1-800-227-2600, for the assignment of an Inquiry Identification Number.

Construction Contractor shall contact all utility companies (e.g. gas company, electric company, telephone company, cable company, water company, and refuse collectors) at least five (5) working days prior to commencing work and shall verify the location of any known utilities and determine whether or not a representative of each company will be present during excavation:

Additionally, the Contractor shall also notify local entities of his/her schedule fourteen (14) days prior to commencing work, including, local law enforcement agencies, the Post Office, Public Schools, and Bus Companies.

No excavation shall commence unless the Contractor has obtained the USA Inquiry Identification Number.

Page 351 of 672 ends

SECTION F – Page 47

SPECIAL PROVISIONS
402-1.1.2 ACCURACY OF UTILITIES INFORMATION
The locations of known existing major utilities, whether above ground or underground, are indicated on the plans. Information and data reflected in the Contract Documents with respect to underground and above ground utilities at or contiguous to the site is based upon information and data furnished to the City and the Engineer by the owners of such utilities, and the City does not assume responsibility for the accuracy or completeness thereof. The Contractor shall take all possible precautions for the protection of unforeseen utility lines to provide for uninterrupted service and to provide such special protection as may be necessary.

The Contractor shall be responsible for determining the location and depth of all underground facilities, including service connections, which may affect or be affected by his/her operations and he/she shall include the cost to pothole all utilities within the limits of work in his/her bid. If an existing utility line, which has been marked by Underground Service Alert or is shown on the plans, is damaged by the Contractor, the Contractor shall repair the line and bear the cost thereof.

Contractor shall be aware that electrical conduits between street and traffic lights may exist beneath pavement and/or sidewalk in areas where such lights are in place and that said conduits are not shown on these plans.

In the event that the Contractor damages any existing utility lines that are not shown, shown incorrectly or the locations of which are not made known to the Contractor prior to excavation, a telephone call and written report shall be made immediately to the Utility owner, the Engineer, and to the City. If directed by the City, the Contractor shall make repairs under the provisions for changes and extra work contained in SECTION 3 – CONTROL OF THE WORK of the SSPWC Standard Specification.
402-2 PROTECTION
Delete the following text from the last sentence of the fourth paragraph of Section 402-2:
“if located in accordance with 402-1”.
402-4 RELOCATION
Replace the second sentence of the fourth paragraph with the following:

When not otherwise required by the plans and specifications and when directed by the Engineer, the Contractor shall arrange for the relocation of service connections as necessary between the meter and property line, or between the meter and limits of construction. 402-5 DELAYS DUE TO UTILITY CONFLICTS
Delete the last paragraph of this section.
403 MANHOLE ADJUSTMENT AND RECONSTRUCTION
403-1 GENERAL
Add the following Subsections:
403-1.1 Adjustment of Los Angeles County Flood Control District Manhole

Page 352 of 672 ends

SECTION F – Page 48

SPECIAL PROVISIONS
Frame and Cover Sets to Grade.

Adjustments to grade of Los Angeles County Flood Control District Manhole Frame and Cover sets do not require a District permit. However, the Contractor shall notify the Inspection Department at (818) 458-3129, 24 hours in advance of any work in the area of the manhole.
403-1.2 Adjustment of Water Valve Box Frame and Cover.

Water valve box frame and cover within the area to be paved or graded shall be set to finish grade with a concrete collar by the Contractor as required by the Plans and Specifications. In the case of portland cement concrete pavement, water valve box frame and cover shall be set to finish grade by the Contractor before paving.
403-3 MANHOLES IN ASPHALT CONCRETE PAVEMENT
Add the following:

Pavement patch material around all frame and covers shall conform to the finish pavement layer specifications; PG 64-10 Class C/D and/or ARHM GG-C/D. 403-5 PAYMENT
Add the following:

Payment for protection of existing surface utilities shall be included in other items of work and no additional payment will be made therefore, unless separate bid item is provided
Payment for Adjust to Grade (Item as Noted) shall be paid at the contract price per each (EA) and shall include full compensation and include but not limited to furnishing all labor, materials, tools, equipment, and incidentals for adjusting Utility Cover to grade and no additional compensation will be made therefor.

SECTION 404 – COLD MILLING
404-2 MILLING MACHINES
404-2.2 Milling to a Specified Elevation.

Add the following:
b) The straight edge grade along the edge of the cold plane area shall not deviate more than ¼-inch below nor 1/8-inch above the grade specified in the Plans or Specifications. 404-7 WORK SITE MAINTENANCE
Add the following:

Cold milling will not be considered complete until all loosened material is removed from the project site. Paving shall not commence until the day after cold milling is complete.

Page 353 of 672 ends

SECTION F – Page 49

SPECIAL PROVISIONS
Cold milled streets shall be approved by the Engineer as completed for cold milling prior to paving. Sweepers used for cold mill sweeping shall not enter on the streets approved as completed for cold milling.
404-11 PAYMENT
Add the following:

Payment for Cold Mill Existing AC Pavement 1.5-Inch Uniform Depth shall be paid at the contract price per square foot (SF) and include full compensation for all labor, materials, tools, equipment, and incidentals required to Cold Mill Existing Asphalt Concrete Pavement. This bid item will shall include, but not limited to, full compensation for furnishing all labor, materials, tools, equipment, transportation, hauling, disposal, and other incidentals for doing all work, complete, and in place, involved in cold milling as indicated in the contract documents, and no additional compensation will be allowed therefor.

Page 354 of 672 ends

SECTION F – Page 50

SPECIAL PROVISIONS
PART 6 – TEMPORARY TRAFFIC CONTROL
600 ACCESS
600-1 General
Add the following:

The Contractor will be required to maintain at least one lane of traffic in each direction through the project area at all times in a manner satisfactory to the Engineer in the form of an engineered traffic control plan. The engineered traffic control plans must be signed by a California registered civil and/or traffic engineer. The plan is a required submittal for review at the pre-construction meeting.

All traffic control on the project shall be implemented by a sub-contractor who specializes in Traffic Control and is approved by the City Engineer.

All drop-offs on the pavement over 1 inch in height that are perpendicular to the direction of traffic, including driveway approach, and will remain overnight shall be ramped with temporary AC pavement. The cost to construct temporary AC pavement shall be included in price paid for other items of work, and no additional payment thereof.

All open trenches shall be covered with non-skid steel plates or temporary asphalt pavement before and after work hours, unless otherwise directed by the Engineer.

Add the following Subsection:
600-1.1 Parking Restrictions and Posting for Tow Away
No Parking signs, posted by the Contractor, shall be of heavy card stock and not less than 1.75 square feet of surface area on the face. Background color shall be white and letters shall be printed in red water resistant ink except day, date, and time of restriction may be printed in black water resistant ink. The signs shall be printed with the words “Tow Away” and “No Parking” with a character height of not less than 2.75 inches and a stroke width of not less than

0.5 inches. The day, dated, and time of the particular restriction shall be printed or attached below the above mentioned wording in characters of not less than 2.0 inches in height and 0.4 inches in stroke width. The day of the week shall be written out or properly abbreviated with three to four letters; date or dates or restriction shall be listed completely; the beginning and ending times shall be clearly listed on the sign.

Signs shall be mounted such that the wording “No Parking” are at an elevation at least three feet above the adjacent flowline. Signs may be tied with string to trees and power poles, taped to existing sign poles, or mounted to stakes or barricades as provided by the Contractor. The signs shall be placed as needed to control the parking of cars within the construction zone; signs shall be placed at intervals of 75 feet or less along each side of the roadway.

Signs shall be posted and maintained by the Contractor for a period of 72 hours prior to the restrictions becoming effective. The Contractor may only post parking restrictions that are effective for the duration of the Work. Upon completion of the Work, the Contractor shall promptly and completely remove and dispose all signs, stakes, and barricades. The Contractor shall promptly reset or replace all damaged or defective signs.

The Contractor shall be fully responsible for the adequate removal of all parked cars. The Contractor shall coordinate the removal of all vehicles with the Sheriff Department. The

Page 355 of 672 ends

SECTION F – Page 51

SPECIAL PROVISIONS
Contractor shall notify the Sheriff Communications Center upon posting of the parking restrictions for a particular street. For removal of parked vehicles, the Contractor shall notify the Sheriff Communications Center not less than two hours prior to the needed removal, stating the address nearest the parked vehicle, make, model, color and license number. The City shall not be responsible for any delay or additional costs associated with the removal of parked cars that obstruct the construction operation.

If a vehicle owner successfully contests a towing citation in court, and their citation is dismissed for causes related to the Contractor’s failure to perform the requirements of this section, the Contractor shall reimburse the City for the cost of any claims associated with the towing citation.

DEVIATIONS FROM THE REQUIREMENTS OF THIS SUBSECTION WILL BE PERMITTED ONLY ON PRIOR CONSENT OF THE ENGINEER. FAILURE OF THE

CONTRACTOR TO ADHERE TO THE REQUIREMENTS OF THIS SUBSECTION, OR

FAILURE OF THE CONTRACTOR TO COMPLETE HIS DAILY SCHEDULE ONCE “TEMPORARY NO PARKING” SIGNS HAVE BEEN POSTED, WILL RESULT IN DAMAGES BEING SUSTAINED BY THE CITY. SUCH DAMAGES ARE, AND WILL

CONTINUE TO BE, IMPRACTICABLE AND EXTREMELY DIFFICULT TO DETERMINE. FOR EACH OCCURRENCE OF A VIOLATION, AS PROVIDED HEREIN,

THE CONTRACTOR SHALL PAY TO THE AGENCY, OR HAVE WITHHELD FROM MONIES DUE TO IT, THE SUM OF $1,000.00.

EXECUTION OF THE CONTRACT SHALL CONSTITUTE AGREEMENT BY THE AGENCY AND CONTRACTOR THAT $1,000.00 PER VIOLATION IS THE MINIMUM

VALUE OF THE COST AND ACTUAL DAMAGE CAUSED, THAT SUCH SUM SHALL

NOT BE CONSTRUED AS A PENALTY, AND THAT SUCH SUM MAY BE DEDUCTED FROM PAYMENTS DUE THE CONTRACTOR.
600-1.2 STREET CLOSURE, DETOURS, BARRICADES
Add the following:

All traffic control barricades, signs and devices used by the Contractor shall, as a minimum, conform to the “Manual of Traffic Controls for Construction and Maintenance Work Zones,” adopted by and in current use by the State of California, Department of Transportation.

Channelization devices shall be spaced no greater than fifty (50) feet apart. The Contractor shall take additional precautions as he/she may find necessary under the circumstances.

Should the Contractor fail to provide adequate traffic control or safety barricades, and in the event a responsible individual cannot be located or refuses to perform, the Agency will at its option place needed devices or engage a private firm to place and maintain said barricades, which will be charged to the Contractor directly.

Temporary traffic channelization shall be accomplished with delineators. Temporary striping will not be allowed unless specifically permitted by the Engineer. The Contractor shall prepare any plans that may be required for temporary striping to the satisfaction of the Engineer. In no event will temporary striping be allowed on finished pavement surfaces which are to remain.

Full street closures will not be allowed prior to City Council approval. 601-1.3 Measurement and Payment.

Measurement and Payment for Traffic Control shall be at the lump sum (LS) bid price and shall

Page 356 of 672 ends

SECTION F – Page 52

SPECIAL PROVISIONS
include but not limited to furnishing all labor, tools, material, equipment, signage, TTC zone devices, channelizing devices, changeable message sign, and incidentals for doing all work involved in preparing traffic control plans and implementing traffic control, and no additional compensation will be allowed therefore.

Page 357 of 672 ends

SECTION G – Page 1

SPECIAL PROVISIONS

SECTION G

BLOOMFIELD STREET IMPROVEMENT PROJECT
CIP NO. 22/23-06

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

SPECIAL PROVISIONS

SIGNING, STRIPING, AND PAVEMENT MARKERS
All equipment, materials, and components for signing and striping, and the installation thereof, shall conform to the 2018 Caltrans Revised Standard Plans, and Revised Standard Specifications, Section 81, “Miscellaneous Traffic Control Devices,” Section 82 “Signs and Markers”, and Section 84, "Markings", unless otherwise noted in these Special Provisions and on the Plans. These Plans and Specifications are hereinafter referred to as State Standard Plans and State Standard Specifications. Copies of these documents are available from Caltrans, District 12 office at 7150 e 4 TH St #100, Santa Ana, California
92705 or from Caltrans, 6002 Folsom Boulevard, Sacramento, California 95819, (916) 445-3520.

All materials required for the completion of work as shown on the Plans shall be provided by the Contractor.

SECTION 81 - MISCELLANEOUS TRAFFIC CONTROL DEVICES
81-3 PAVEMENT MARKERS
81-3.02 Materials.
81-3.02E Epoxy Adhesive. Adhesive for raised pavement markers shall be rapid set type epoxy.

Removal of pavement markers shall be per Section 81-8.03B, "Remove Pavement Markers," of the State Standard Specifications.
81-3.04 Payment. Payment for pavement markers shall be included in the lump-sum price bid for signing and striping, and no additional compensation will be allowed therefor.

SECTION 82 – SIGNS AND MARKERS
82-3 ROADSIDE SIGNS
82-3.03 Construction. Relocated signs shall be installed using existing posts at new locations and shall be set at a minimum 30-inch depth and at a minimum 12-inch square portland cement concrete (PCC). The post depth of the concrete footing shall be sufficient to extend at least 6- inches below the bottom of the posts. ¼-inch expansion paper shall be placed between the sign foundation and sidewalk.

Page 358 of 672 ends

SECTION G – Page 2

SPECIAL PROVISIONS
New signs shall be installed using metal posts set at a minimum of 30-inch depth in a minimum 12-inch square PCC, except as specified otherwise, the metal post shall be 2-inch square “Qwik Punch” posts. The length of the metal post shall be sufficient to extend from the top of the sign to 30-inches below the top of the concrete footing and provide a 7-foot clearance between the finished grade and the bottom of the sign. The depth of the concrete footings shall be sufficient to extend at least 6-inches below the bottom of the posts. ¼-inch expansion paper shall be placed between the sign foundation and sidewalk.

Drill holes for bolts, threaded rods, or expansion anchorage devices drilled in existing concrete by a method that will not shatter the concrete adjacent to the holes.

Repair any spalling or chipping of concrete structures at contractor’s expense.

Marker and delineators shall conform to the provision in Section 81, "Miscellaneous Traffic Control Devices."
82-3.04 Payment. Payment for signing shall be included in the lump sum price bid for signing and striping, and no additional compensation will be allowed therefor.

SECTION 84 - MARKINGS
84-2 TRAFFIC STRIPES AND PAVEMENT MARKINGS
84-2.02 Materials.
84-2.02A General. Traffic stripes, pavement markings, crosswalks, and arrow markings shall be thermoplastic, unless otherwise shown on the Plans. Curb markings shall be paint, two (2) coats. Contractor shall repaint all curb markings within the project limits.

All crosswalks shall be paint, three (3) coats.
84-2.02C Paint. Curb markings shall be paint. Paint shall be ready-mixed rapid dry type.

Ready-mixed paints shall be suitable for use on either asphalt concrete or Portland cement concrete.
84-2.02E Thermoplastic Traffic Stripes and Pavement Markings shall be thermoplastic including glass beads for striping and pavement markings. 84-2.03 Construction.
84-2.03A General. The Contractor shall furnish the necessary control points for all striping and markings and shall be responsible for the completeness and accuracy thereof to the satisfaction of the Engineer.

Page 359 of 672 ends

SECTION G – Page 3

SPECIAL PROVISIONS
The Contractor shall establish all traffic striping between these points by stringline or other method to provide striping that will vary less than ½-inch in 50-feet from the specified alignment.

When no previously applied figures, markings, or traffic striping are available to serve as a guide, suitable layouts shall be spotted in advance of the permanent paint application.

Traffic lines may be spotted by using a rope as a guide for marking spots every 5-feet, by using a marking wheel mounted on a vehicle, or by any other means satisfactory to the Engineer.

The Contractor shall mark or otherwise delineate the traffic lanes in the new roadway or portion of roadway, or detour before opening it to traffic.

The Contractor shall provide an experienced technician to supervise the location, alignment, layout, dimensions, and application of the paint.

Spotting shall be completed prior to the removal of any existing stripes. Existing stripes and markings shall be removed prior to painting new stripes and markings, but in no case shall any section of street be left without the proper striping for more than 24 hours, or over weekends or holidays.

The installation of traffic stripes includes placement of raised pavement markers when called for on the plans.

Adhesive for raised pavement markers shall be per Section 81, “Pavement Markers.” Existing traffic stripes (including raised pavement markers), pavement legends, and markings that do not conform to the plans shall be removed by grinding method per Section 81-8.03B, “Remove Pavement Markers,” and Section 84-9.03B, "Remove Traffic Stripes and Pavement Markings" of the State Standard Specifications. 84-2.03C Application of Stripes and Markings
84-2.03C(3) Painted Traffic Stripes and Pavement Markings. Paint shall be applied in three coats. For those locations where raised pavement markers are to be installed on painted stripes, paint shall be applied prior to installation.

The second coat of paint shall be applied no less than 24 hours from application of first coat.

The third coat of paint shall be applied no less than 24 hours from the application of the second coat.

Each coat of paint shall include glass beads.

Page 360 of 672 ends

SECTION G – Page 4

SPECIAL PROVISIONS
84-2.04 Payment. Payment for striping details, pavement markings, and curb markings shall be included in the lump sum price bid for signing and striping, and no additional compensation will be allowed therefor.

Page 361 of 672 ends

SECTION H – Page 1

SPECIAL PROVISIONS

SECTION H

BLOOMFIELD STREET IMPROVEMENT PROJECT
CIP NO. 22/23-06

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

SPECIAL PROVISIONS

SIGNALS, LIGTHING, AND ELECTRICAL SYSTEMS
All equipment, materials, and components for traffic signal loop replacement shall conform to the 2018 Caltrans Revised Standard Plans and Revised Standard Specifications, Section 86, "Electrical Work" and Section 87 “Electrical Systems” unless otherwise noted in these Special Provisions and on the Plans.

These Plans and Specifications are hereinafter referred to as State Standard Plans and State Standard Specifications. Copies of these documents are available from the Caltrans, District 7 office at 100 South Main Street, Los Angeles, California 90012 or from Caltrans, 6002 Folsom Boulevard, Sacramento, California 95819, (916) 445-3520.

All materials required for the completion of work as shown on the Plans shall be provided by the Contractor.

SECTION 86 – GENERAL
86-1.01 General.
86-1.01C Submittals. The schedule of values (cost breakdown) shall be submitted to the Engineer in conjunction with equipment list and drawings.

Equipment List and Drawings shall be submitted to the Engineer within ten (10) working days after the date of the Notice of Contract Approval.

Materials lists, manufacturer's data, brochures, technical data, etc., shall be labeled and identified, and shall be submitted in bound booklet form.

The Contractor shall retain one copy of all approved material lists and samples at the job site, readily accessible for inspection by the Engineer. Said materials lists and samples shall be the basis for approval or rejection of work.

The Contractor shall guarantee the entire work constructed under this contract and will fully meet all requirements as to quality of workmanship and materials furnished by him.

The Contractor shall make, at the Contractor’s expense, any repairs or replacements made necessary by defects in workmanship or materials that becomes evident within 1 year after acceptance of work by the Agency and to restore to full compliance with the requirements of these Specifications, any part of the work which during the 1-year period is found to be deficient with respect to any provision of the Plans and Specifications. The Contractor shall make all repairs and replacements promptly upon receipt of written

Page 362 of 672 ends

SECTION H – Page 2

SPECIAL PROVISIONS
orders from the Engineer. If the Contractor fails to make the repairs and replacements promptly, the City may do the work and the Contractor and his surety shall be liable to the City for the cost.

Whenever any work or equipment is to be guaranteed or maintained by a manufacturer, supplier, or subcontractor, said obligation shall be that of the Contractor.

All guarantees shall be in writing and delivered to the Engineer by the Contractor prior to final acceptance of the work.
86-1.01D Quality Assurance.
86-1.01D(3) Department Acceptance. Materials and equipment furnished by the Contractor shall be tested at an independent testing facility designated by the City. Cost for testing and delivery to and from the test site shall be considered as included in the lump-sum price bid for traffic signal installation/modification, and no additional compensation will be allowed.
86-1.02 Materials.
86-1.02F Conductors and Cables.
86-1.02F(2) Conductors.
86-1.02F(2)(c) Copper Conductors.
86-1.02F(2)(c)(i) General. Circuit conductors shall be THW PVC type.

SECTION 87 – ELECTRICAL SYSTEMS
87-1 GENERAL
87-1.03 Construction.
87-1.03A General.

No work shall commence and no material or equipment shall be stored at the jobsite until such time that the Contractor notifies the Engineer in writing of the date that all electrical materials and equipment are to be received. Upon receipt of said notification by the Engineer, the Contractor may commence work within 5-working days prior to said delivery date.

Where the Contractor-installed facilities are damaged prior to final acceptance by the Engineer, the Contractor shall repair or replace such facilities at his own expense.

Page 363 of 672 ends

SECTION H – Page 3

SPECIAL PROVISIONS
The job site shall be maintained in a neat and orderly condition at all times and areas of sidewalk removal to be left open for less than 5 days shall be covered with plywood sheeting and barricades. Areas to be left open more than 5 days shall be patched with temporary AC pavement, smoothed to provide a level finished walking surface. 87-1.03F Conductors and Cable Installations.
87-1.03F(2) Cables.
87-1.03F(2)(c) Copper Cables.
87-1.02F(2)(c)(ii) Detector Lead-in Cables. Loop detector leadin cable shall be Type B. 87-1.03F(3) Conductors.
87-1.03F(3)(c) Copper Conductors.
87-1.03F(3)(c)(ii) Inductive Loop Conductors. Loop wire shall be Type 2.
87-1.03H Conductor and Cables Splices.
87-1.03H(2) Splice Insulation Methods. Splices shall be Type C insulated by Method B, as shown on State Standard Plan ES-13A, except detector conductor (video, loop, et cetera) splices shall be Type S or T insulated by Method B, as shown on Standard Plan ES-13A, and shall also be soldered. 87-1.03L Utility Service. Electrical service equipment installation and conduit run details shall be as specified by the serving utility company, and written proof of their approval by the utility shall be submitted to the Engineer prior to installation. The Contractor shall be responsible for all service details, expenses, and scheduling far in advance of need.

The Contractor shall pay all service connection fees.
87-1.03V Detectors.
87-1.03V(1) General. Vehicle detectors shall be of the inductive loop, Type E.

Limit line loop detectors shall be modified inductive loop Type D Bicycle Detector Loop.

Detector loop locations shall be approved by Engineer in the field prior to installation.

Page 364 of 672 ends

SECTION H – Page 4

SPECIAL PROVISIONS
PVC conduit per Standard Plan ES-5E, Curb Termination Detail, Type B, shall be installed wherever a loop-wire saw cut crosses an expansion joint or pavement type change.

The sides of the loop saw cut slots shall be vertical and the minimum radius of the slot entering and leaving the circular part of the loop shall be 1½-inches. Slot width shall be a maximum of ¾-inch.

Slots of circular loops shall be filled with elastometric sealant.

Loops shall be installed on the same day in which the loop slots are cut. This shall include placement of the loop conductors and sealant. 86-8 PAYMENT
86-8.01 Payment. The second paragraph of Section 86-8.01, “Payment,” of the State Standard Specifications, is superseded by the following:

Payment for inductive loops and the installation thereof shall be paid per unit price bid for each inductive loop as shown on the Plans, and no additional compensation will be allowed therefor.

Page 365 of 672 ends

APPENDIX – PART 1

FEDERAL PROVISIONS
APPENDIX – PART 1
Federal Provision

Page 366 of 672 ends

NOTICE TO BIDDERS

FEDERAL REQUIREMENTS
Proposal Phase
For your bid to be considered responsive, you must submit the following forms, either with your bid or by 4:00 p.m. on the fifth calendar day following bid opening:
 Construction Contract DBE Commitment, Exhibit 15-G (p. F-26)  DBE Commitment form, Exhibit 9-I (p. F-28), plus copy of quote/contract from each DBE In addition, you are strongly encouraged, and may be required, to submit the following form as a supplement to Exhibit 15-G:
 Proposer/Contractor – Good Faith Efforts, Exhibit 15-H (p. F-29) Upon execution and submission of your bid, you are agreeing to be bound by the following (but do not need to return the forms unless a disclosure is required):
• Equal Employment Opportunity Certification (p. F-20)
• Public Contract Code Requirements (p. F-21)
• Debarment and Suspension Certification (p. F-22)
• Nonlobbying Certification for Federal-Aid Contracts (p. F-23) If applicable, the following form must be submitted with the bid:
 Disclosure of Lobbying Activities (p. F-24)
Construction Phase
Contractors who are awarded a public works project must submit electronic payroll records to the DIR’s Compliance Monitoring Unit (CMU) in addition to providing wet-ink original copies to the City or its designated labor compliance enforcement officer.

You will be required to submit the following forms each month or quarter, as instructed, during construction:
 Disadvantaged Business Enterprise Running Tally of Payments, Exhibit 9-F  Disadvantaged Business Enterprise Commercially Useful Function Evaluation, Exhibit 9-J  Prompt Payment Certification, Exhibit 9-P
 Monthly DBE Trucking Verification, Exhibit 16-Z1
Excel or fillable pdf versions of these documents are available at https://dot.ca.gov/programs/local-assistance/forms/local-assistance-procedures-manual-forms.

Post-Construction Phase
When construction is completed, you will be required to submit the following forms to the City:
 Final Report – Utilization of Disadvantaged Businesses (DBE) and First-Tier Subcontractors, Exhibit 17-F
 Disadvantaged Business Enterprises (DBE) Certification Status Change, Exhibit 17-O

Page 367 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-1 Page 1 of 21
October 2023
EXHIBIT 12-G REQUIRED FEDERAL-AID CONTRACT LANGUAGE
(For Local Assistance Construction Projects)
The following language must be incorporated into all Local Assistance Federal-aid construction contracts.

The following language, with minor edits, was taken from the Code of Federal Regulations.

MAINTAIN RECORDS AND SUBMIT REPORTS DOCUMENTING YOUR PERFORMANCE UNDER THIS

SECTION

1. DISADVANTAGED BUSINESS ENTERPRISES (DBE)............................................................................ 2 A. Nondiscrimination Statement .......................................................................................................... 3 B. Contract Assurance .......................................................................................................................... 3 C. Prompt Progress Payment ............................................................................................................... 3 D. Prompt Payment of Withheld Funds to Subcontractors ............................................................... 3 E. Termination and Replacement of DBE Subcontractors ................................................................ 4 F. Commitment and Utilization ............................................................................................................. 6 G. Running Tally of Attainments .......................................................................................................... 7 H. Commercially Useful Function ........................................................................................................ 7 I. Use of Joint Checks .......................................................................................................................... 8

2. BID OPENING ............................................................................................................................................ 9

3. BID RIGGING ............................................................................................................................................. 9

4. CONTRACT AWARD ................................................................................................................................. 9

5. CONTRACTOR LICENSE .......................................................................................................................... 9

6. CHANGED CONDITIONS .......................................................................................................................... 9 A. Differing Site Conditions .................................................................................................................. 9 B. Suspensions of Work Ordered by the Engineer ............................................................................ 9 C. Significant Changes in the Character of Work ............................................................................. 10

7. BEGINNING OF WORK, TIME OF COMPLETION, AND LIQUIDATED DAMAGES ............................. 10

8. BUY AMERICA ......................................................................................................................................... 10

9. QUALITY ASSURANCE .......................................................................................................................... 11

10. PROMPT PAYMENT ................................................................................................................................ 11

11. FORM FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID CONTRACTS ................ 12

12. FEMALE AND MINORITY GOALS .......................................................................................................... 12

13. TITLE VI ASSURANCES ......................................................................................................................... 14

14. FEDERAL TRAINEE PROGRAM ............................................................................................................ 18

15. PROHIBITIONS OF CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE EQUIPMENT AND SERVICES ................................................................................................................. 19

Page 368 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-2 Page 2 of 21
October 2023

1. DISADVANTAGED BUSINESS ENTERPRISES (DBE)
The contractor, subrecipient, or subcontractor shall take necessary and reasonable steps to ensure that DBEs have opportunity to participate in the contract (49 CFR 26). To ensure equal participation of DBEs provided in 49 CFR 26.5, the Agency shows a contract goal for DBEs. The prime contractor shall make work available to DBEs and select work parts consistent with available DBE subcontractors and suppliers.

The prime contractor shall meet the DBE goal shown elsewhere in these special provisions or demonstrate that they made adequate good faith efforts to meet this goal. An adequate GFE means that the bidder must show that it took all necessary and reasonable steps to achieve a DBE goal that, by their scope, intensity, and appropriateness to the objective, could reasonably be expected to meet the DBE goal.

If the DBE goal is not met, the contractor needs to complete and submit the DBE GFE documentation as described in Local Assistance Procedures Manual (LAPM) Chapter 9, Section 9.8 within 5 (five) days of bid opening.

It is the prime contractor’s responsibility to verify at date of bid opening that the DBE firm is certified as a DBE by using the California Unified Certification Program (CUCP) database and possesses the most specific available North American Industry Classification System (NAICS) codes and work code applicable to the type of work the firm will perform on the contract. Additionally, the prime contractor is responsible to document the verification record by printing out the CUCP data for each DBE firm. A list of DBEs certified by the CUCP can be found at https://californiaucp.dbesystem.com/.

DBE participation will only count toward the California Department of Transportation’s federally mandated statewide overall DBE goal if the DBE performs a commercially useful function under 49 CFR 26.55.

Credit for materials or supplies the prime contractor purchases from DBEs counts toward the goal in the following manner:
 100 percent counts if the materials or supplies are obtained from a DBE manufacturer.  60 percent counts if the materials or supplies are obtained from a DBE regular dealer.  Only fees, commissions, and charges for assistance in the procurement and delivery of materials or supplies count if obtained from a DBE that is neither a manufacturer nor regular dealer. 49 CFR 26.55 defines "manufacturer" and "regular dealer." The prime contractor receives credit toward the goal if they employ a DBE trucking company that performs a commercially useful function as defined in 49 CFR 26.55(d)(1) as follows:
 The DBE must be responsible for the management and supervision of the entire trucking operation for which it is responsible on a particular contract, and there cannot be a contrived arrangement for the purpose of meeting DBE goals.
 The DBE must itself own and operate at least one fully licensed, insured, and operational truck used on the contract.
 The DBE receives credit for the total value of the transportation services it provides on the contract using trucks it owns, insures, and operates using drivers it employs.  The DBE may lease trucks from another DBE firm, including an owner-operator who is certified as a DBE. The DBE who leases trucks from another DBE receives credit for the total value of the transportation services the lessee DBE provides on the contract.  The DBE may also lease trucks from a non-DBE firm, including from an owner-operator. The DBE that leases trucks equipped with drivers from a non-DBE is entitled to credit for the total value of transportation services provided by non-DBE leased trucks equipped with drivers not to exceed the value of transportation services on the contract provided by DBE-owned trucks or leased trucks with DBE employee drivers. Additional participation by non-DBE owned trucks equipped with drivers receives credit only for the fee or commission it receives as a result of the lease arrangement.  The DBE may lease trucks without drivers from a non-DBE truck leasing company. If the DBE leases trucks from a non-DBE truck leasing company and uses its own employees as drivers, it is entitled to credit for the total value of these hauling services.
 A lease must indicate that the DBE has exclusive use of and control over the truck. This does not preclude the leased truck from working for others during the term of the lease with the consent of the

Page 369 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-3 Page 3 of 21
October 2023
DBE, so long as the lease gives the DBE absolute priority for use of the leased truck. Leased trucks must display the name and identification number of the DBE.

A. Nondiscrimination Statement
The contractor, subrecipient, or subcontractor will never exclude any person from participation in, deny any person the benefits of, or otherwise discriminate against anyone in connection with the award and performance of any contract covered by 49 CFR 26 on the basis of race, color, sex, or national origin. In administering the Local Agency components of the DBE Program Plan, the contractor, subrecipient, or subcontractor will not, directly, or through contractual or other arrangements, use criteria or methods of administration that have the effect of defeating or substantially impairing accomplishment of the objectives of the DBE Program Plan with respect to individuals of a particular race, color, sex, or national origin.

B. Contract Assurance
Under 49 CFR 26.13(b), the contractor, subrecipient, or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR 26 in the award and administration of federal-aid contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate, which may include, but is not limited to:
(1) Withholding monthly progress payments;
(2) Assessing sanctions;
(3) Liquidated damages; and/or
(4) Disqualifying the contractor from future bidding as non-responsible.

C. Prompt Progress Payment
In accordance with California Business and Professions Code Section 7108.5, the prime contractor or subcontractor shall pay to any subcontractor, not later than seven days after receipt of each progress payment, unless otherwise agreed to in writing, the respective amounts allowed the contractor on account of the work performed by the subcontractors, to the extent of each subcontractor’s interest therein. In the event that there is a good faith dispute over all or any portion of the amount due on a progress payment from the prime contractor or subcontractor to a subcontractor, the prime contractor or subcontractor may withhold no more than 150 percent of the disputed amount. Any violation of this requirement shall constitute a cause for disciplinary action and shall subject the licensee to a penalty, payable to the subcontractor, of 2 percent of the amount due per month for every month that payment is not made.

In any action for the collection of funds wrongfully withheld, the prevailing party shall be entitled to his or her attorney’s fees and costs. The sanctions authorized under this requirement shall be separate from, and in addition to, all other remedies, either civil, administrative, or criminal. This clause applies to both DBE and non-DBE subcontractors.

D. Prompt Payment of Withheld Funds to Subcontractors
The Agency may hold retainage from the prime contractor and shall make prompt and regular incremental acceptances of portions, as determined by the Agency, of the contract work, and pay retainage to the prime contractor based on these acceptances. The Agency shall designate one of the methods below in the contract to ensure prompt and full payment of any retainage kept by the prime contractor or subcontractor to a subcontractor. The Agency shall include either Method 1, Method 2, or Method 3 below and delete the other two.

Method 1: No retainage will be held by the Agency from progress payments due to the prime contractor.

Prime contractors and subcontractors are prohibited from holding retainage from subcontractors. Any delay or postponement of payment may take place only for good cause and with the Agency’s prior written approval. Any violation of these provisions shall subject the violating contractor or subcontractor to the penalties, sanctions, and other remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the

Page 370 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-4 Page 4 of 21
October 2023
contractor, deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.

Method 2: No retainage will be held by the Agency from progress payments due to the prime contractor.

Any retainage kept by the prime contractor or by a subcontractor must be paid in full to the earning subcontractor within seven (7) days after the subcontractor’s work is satisfactorily completed. Any delay or postponement of payment may take place only for good cause and with the Agency’s prior written approval. Any violation of these provisions shall subject the violating contractor or subcontractor to the penalties, sanctions, and remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor, deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.

Method 3: The Agency shall hold retainage from the prime contractor and shall make prompt and regular incremental acceptances of portions, as determined by the Agency, of the contract work and pay retainage to the prime contractor based on these acceptances. The prime contractor or subcontractor shall return all monies withheld in retention from all subcontractors within seven (7) days after receiving payment for work satisfactorily completed and accepted including incremental acceptances of portions of the contract work by the Agency. Any delay or postponement of payment may take place only for good cause and with the Agency’s prior written approval. Any violation of these provisions shall subject the violating prime contractor or subcontractor to the penalties, sanctions, and other remedies specified in Section 7108.5 of the California Business and Professions Code and Section 10262 of the California Public Contract Code. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor; deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.

Any violation of these provisions of Prompt Progress Payment and Prompt Payment of Withheld Funds to Subcontractors shall subject the violating prime contractor or subcontractor to the penalties, sanctions, and other remedies specified therein. These requirements shall not be construed to limit or impair any contractual, administrative, or judicial remedies otherwise available to the prime contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the prime contractor, deficient subcontractor performance, or noncompliance by a subcontractor.

E. Termination and Replacement of DBE Subcontractors
The prime contractor shall utilize the specific DBEs listed to perform the work and supply the materials for which each is listed unless the contractor obtains the Agency’s written consent. The prime contractor shall not terminate or replace a listed DBE for convenience and perform the work with their own forces or obtain materials from other sources without prior written authorization from the Agency. Unless the Agency’s prior written consent is provided, the contractor shall not be entitled to any payment for work or material unless it is performed or supplied by the listed DBE on the Exhibit 15-G Construction Contract DBE Commitment form, included in the Bid.

Termination of DBE Subcontractors
After a contract with a specified DBE goal has been executed, termination of a DBE may be allowed for the following, but not limited to, justified reasons with prior written authorization from the Agency:

1. Listed DBE fails or refuses to execute a written contract based on plans and specifications for the project.

2. The Local Agency stipulated that a bond is a condition of executing the subcontract, and the listed DBE fails to meet the Local Agency’s bond requirements.

3. Work requires a contractor's license and listed DBE does not have a valid license under Contractors License Law, or DBE is not properly registered with the California Department of Industrial Relations as a public works contractor.

4. Listed DBE fails or refuses to perform the work or furnish the listed materials (failing or refusing to perform is not an allowable reason to remove a DBE if the failure or refusal is a result of bad faith or discrimination).

Page 371 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-5 Page 5 of 21
October 2023

5. Listed DBE's work is unsatisfactory and not in compliance with the contract.

6. Listed DBE is ineligible to work on the project because of suspension or debarment.

7. Listed DBE becomes bankrupt or insolvent or exhibits credit unworthiness.

8. Listed DBE voluntarily withdraws with written notice from the Contract.

9. Listed DBE is ineligible to receive credit for the type of work required.

10. Listed DBE owner dies or becomes disabled resulting in the inability to perform the work on the Contract.

11. The Agency determines other documented good cause.

To terminate a DBE or to terminate a portion of a DBE's work, the contractor must use the following procedures:

1. Send a written notice to the DBE of Contractor’s intent to use other forces or material sources and include one or more justifiable reasons listed above. Simultaneously send a copy of this written notice to the Agency. The written notice to the DBE must request they provide any response within five (5) business days to both the Contractor and the Agency by either acknowledging their agreement or documenting their reasoning as to why the use of other forces or sources of materials should not occur.

2. If the DBE does not respond within 5 business days, Contractor may move forward with the request as if the DBE had agreed to Contractor’s written notice.

3. Submit Contractor’s DBE termination request by written letter to the Agency and include:
• One or more above listed justifiable reasons along with supporting documentation • Contractor’s written notice to the DBE regarding the request, including proof of transmission and tracking documentation of Contractor’s written notice
• The DBE's response to Contractor’s written notice, if received. If a written response was not provided, provide a statement to that effect.

The Agency shall respond in writing to Contractor’s DBE termination request within 5 business days.

Replacement of DBE Subcontractors
After receiving the Agency’s written authorization of DBE termination request, the Contractor must obtain the Agency’s written agreement for DBE replacement. The Contractor must find or demonstrate GFEs to find qualified DBE replacement firms to perform the work to the extent needed to meet the DBE commitment.

The following procedures shall be followed to request authorization to replace a DBE firm:

1. Submit a request to replace a DBE with other forces or material sources in writing to the Agency which must include:
a. Description of remaining uncommitted work items made available for replacement DBE solicitation and participation.
b. The proposed DBE replacement firm's business information, the work they have agreed to perform, and the following:
• Quote for bid item work and description of work to be performed • Proposed subcontract agreement and written confirmation of agreement to perform on the Contract
• Revised Subcontracting Request form
• Revised Exhibit 15-G: Construction Contract DBE Commitment

2. If Contractor has not identified a DBE replacement firm, submit documentation of the Contractor’s GFEs to use DBE replacement firms within 7 days of Agency's authorization to terminate the DBE.

The Contractor may request the Agency's approval to extend this submittal period to a total of 14 days. Submit documentation of actions taken to find a DBE replacement firm, such as:
• Search results of certified DBEs available to perform the original DBE work identified and/or other work the Contractor had intended to self-perform, to the extent needed to meet the DBE commitment
• Solicitations of DBEs for performance of work identified

Page 372 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-6 Page 6 of 21
October 2023
• Correspondence with interested DBEs that may have included contract details and requirements • Negotiation efforts with DBEs that reflect why an agreement was not reached • If a DBE's quote was rejected, provide Contractor’s reasoning for the rejection, such as why the DBE was unqualified for the work, or why the price quote was unreasonable or excessive • Copies of each DBE's and non-DBE's price quotes for work identified, as the Agency may contact the firms to verify solicitation efforts and determine if the DBE quotes are substantially higher • Additional documentation that supports the GFE
The Agency shall respond in writing to the Contractor’s DBE replacement request within five (5) business days. The Contractor must submit a revised Subcontracting Request form if the replacement plan is authorized by the Agency.

F. Commitment and Utilization
The Agency’s DBE program must include a monitoring and enforcement mechanism to ensure that DBE commitments reconcile to DBE utilization.

The bidder shall complete and sign Exhibit 15-G Construction Contract DBE Commitment included in the contract documents regardless of whether DBE participation is reported. The bidder shall provide written confirmation from each DBE that the DBE is participating in the Contract. LAPM Exhibit 9-I: DBE Confirmation or equivalent form and DBE’s quote must be submitted. The written confirmation must be submitted no later than 4pm on the 5th day after bid opening. If a DBE is participating as a joint venture partner, the bidder shall submit a copy of the joint venture agreement.

If the DBE Commitment form, Exhibit 15-G, is not submitted with the bid, it must be completed and submitted by all bidders to the Agency within five (5) days of bid opening. If the bidder does not submit the DBE Commitment form within the specified time, the Agency will find the bidder’s bid nonresponsive.

The prime contractor shall use each DBE subcontractor as listed on Exhibit 15-G: Construction Contract DBE Commitment unless they receive written authorization for a termination or replacement from the Agency.

The Agency shall request the prime contractor to:

1. Notify the Resident Engineer or Inspector of any changes to its anticipated DBE participation

2. Provide this notification before starting the affected work

3. Maintain records including:
• Name and business address of each 1st-tier subcontractor • Name and business address of each DBE subcontractor, DBE vendor, and DBE trucking company, regardless of tier
• Date of payment and total amount paid to each DBE (see Exhibit 9-F Monthly Disadvantaged Business Enterprise Payment)
If the prime contractor is a DBE contractor, they shall include the date of work performed by their own forces and the corresponding value of the work.

Before the 15th of each month, the prime contractor shall submit a Monthly DBE Trucking Verification (LAPM Exhibit 16-Z1) form.

If a DBE is decertified before completing its work, the DBE must notify the prime contractor in writing of the decertification date. If a business becomes a certified DBE before completing its work, the business must notify the prime contractor in writing of the certification date. The prime contractor shall submit the notifications. Upon work completion, the prime contractor shall complete a Disadvantaged Business Enterprises (DBE) Certification Status Change, Exhibit 17-O, form and submit the form within 30 days of contract acceptance.

Upon work completion, the prime contractor shall complete Exhibit 17-F Final Report – Utilization of Disadvantaged Business Enterprises (DBE), First-Tier Subcontractors and submit it within 90 days of contract acceptance. The Agency will withhold $10,000 until the form is submitted. The Agency releases the withhold upon submission of the completed form.

Page 373 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-7 Page 7 of 21
October 2023
G. Running Tally of Attainments
For projects awarded on or after March 1, 2020, but before September 1, 2023:

After submitting an invoice for reimbursement that includes a payment to a DBE, but no later than the 10th of the following month, the prime contractor/consultant must complete and email the Exhibit 9-F: Disadvantaged Business Enterprise Running Tally of Payments to [email protected] with a copy to local administering agencies.

For projects that are awarded on or after September 1, 2023:

Exhibit 9-F is no longer required. Instead, by the 15th of the month following the month of any payment(s), the prime contractor must now submit Exhibit 9-P to the Local Agency administering the contract. If the Contractor does not make any payments to subcontractors, supplier(s) and/or manufacturers they must report “no payments were made to subs this month” and write this visibly and legibly on Exhibit 9-P.

H. Commercially Useful Function
DBEs must perform a commercially useful function (CUF) under 49 CFR 26.55 when performing work or supplying materials listed on the DBE Commitment form. The DBE value of work will only count toward the DBE commitment if the DBE performs a CUF. A DBE performs a CUF when it is responsible for execution of the work on the contract and is carrying out its responsibilities by actually performing, managing, and supervising the work involved. If a DBE does not perform or exercise responsibility for at least 30% of the total cost of its contract with its own work force, or the DBE subcontracts a greater portion of the work of a contract than would be expected on the basis of normal industry practice for the type of work involved, it will be presumed that the DBE is not performing a CUF. Additionally, the DBE must also be responsible, with respect to materials and supplies used on the contract, for negotiating price, determining quality and quantity, ordering the material and installing (where applicable), and paying for the material itself.

The Contractor must perform CUF evaluation for each DBE company working on a federal-aid contract, with or without a DBE goal. Perform a CUF evaluation at the beginning of the DBE’s work and continue to monitor the performance of CUF for the duration of the project.

The Contractor must provide written notification to the AGENCY at least 15 days in advance of each DBE's initial performance of work or supplying materials for the Contract. The notification must include the DBE's name, work the DBE will perform on the contract, and the location, date, and time of where their work will take place.

Within 10 (ten) days of a DBE initially performing work or supplying materials on the contract, the Contractor shall submit to the LPA the initial evaluation and validation of DBE performance of a CUF using the LAPM 9- J: Disadvantaged Business Enterprise Commercially Useful Function Evaluation. Include the following information with the submittal:
• Subcontract agreement with the DBE
• Purchase orders
• Bills of lading
• Invoices
• Proof of payment
The Contractor must monitor all DBE’s performance of CUF by conducting quarterly evaluations and validations throughout their duration of work on the contract using the LAPM 9-J: DBE Commercially Useful Function Evaluation. The Contractor must submit to the AGENCY these quarterly evaluations and validations by the 5th of the month for the previous three (3) months of work.

The Contractor must notify the AGENCY immediately if the Contractor believes the DBE may not be performing a CUF.

Page 374 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-8 Page 8 of 21
October 2023
The AGENCY will verify DBEs performance of CUF by reviewing the initial and quarterly submissions of LAPM 9-J: DBE Commercially Useful Function Evaluation, submitted supporting information, field observations, and through any additional AGENCY evaluations. The AGENCY must evaluate DBEs and their CUF performance throughout the duration of a Contract. The AGENCY will provide written notice to Contractor and DBE at least two (2) business days prior to any evaluation. The Contractor and DBE must participate in the evaluation. Upon completing the evaluation, the AGENCY must share the evaluation results with the Contractor and DBE. An evaluation could include items that must be remedied upon receipt. If the AGENCY determines the DBE is not performing a CUF the Contractor must suspend performance of the noncompliant work.

The Contractor and DBEs must submit any additional CUF related records and documents within five (5) business days of AGENCY’s request such as
• Proof of ownership or lease and rental agreements for equipment • Tax records
• Employee rosters
• Certified payroll records
• Inventory rosters
Failure to submit required DBE Commercially Useful Function Evaluation forms or requested records and documents can result in withholding of payment for the value of work completed by the DBE.

If the Contractor and/or the AGENCY determine that a listed DBE is not performing a CUF in performance of their DBE committed work, immediately suspend performance of the noncompliant portion of the work. The AGENCY may deny payment for the noncompliant portion of the work. The AGENCY will ask the Contractor to submit a corrective action plan (CAP) to the AGENCY within five (5) days of the noncompliant CUF determination. The CAP must identify how the Contractor will correct the noncompliance findings for the remaining portion of the DBE's work. The AGENCY has five (5) days to review the CAP in conjunction with the prime contractor’s review. The Contractor must implement the CAP within five (5) days of the AGENCY's approval. The AGENCY will then authorize the prior noncompliant portion of work for the DBE's committed work.

If corrective actions cannot be accomplished to ensure the DBE performs a CUF on the Contract, then the Contractor may have good cause to request termination of the DBE.

I. Use of Joint Checks
A joint check may be used between the Contractor or lower-tier subcontractor and a DBE subcontractor purchasing materials from a material supplier if the contractor obtains prior approval from the LPA for the proposed use of joint check upon submittal of the LAPM 9-K: DLA Disadvantaged Business Enterprises (DBE) Joint Check Agreement Request form.

To use a joint check, the following conditions must be met:
• All parties, including the Contractor, must agree to the use of a joint check • Entity issuing the joint check acts solely to guarantee payment • DBE must release the check to the material supplier
• LPA must authorize the request before implementation
• Any party to the agreement must provide requested documentation within 10 days of the LPA's request for the documentation
• Agreement to use a joint check must be short-term, not to exceed 1 year, allowing sufficient time needed to establish or increase a credit line with the material supplier A request for a joint check agreement may be initiated by any party. If a joint check is used, the DBE remains responsible for all elements of 49 CFR 26.55(c)(1).

Page 375 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-9 Page 9 of 21
October 2023
Failure to comply with the above requirements disqualifies DBE participation and results in no credit and no payment to the Contractor for DBE participation.

A joint check may not be used between the Contractor or subcontractor and a DBE regular dealer, bulk material supplier, manufacturer, wholesaler, broker, trucker, packager, manufacturer’s representative, or other persons who arrange or expedite transactions.

2. BID OPENING
The Agency publicly opens and reads bids at the time and place shown on the Notice to Contractors.

3. BID RIGGING
The U.S. Department of Transportation (DOT) provides a toll-free hotline to report bid rigging activities. Use the hotline to report bid rigging, bidder collusion, and other fraudulent activities. The hotline number is (800) 424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT's effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General.

4. CONTRACT AWARD
If the Agency awards the contract, the award is made to the lowest responsible and responsive bidder.

5. CONTRACTOR LICENSE
The Contractor must be properly licensed as a contractor from contract award through contract acceptance (23 CFR 635.110).

6. CHANGED CONDITIONS
A. Differing Site Conditions

1. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.

2. Upon written notification, the engineer will investigate the conditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly. The engineer will notify the contractor of the determination whether or not an adjustment of the contract is warranted.

3. No contract adjustment which results in a benefit to the contractor will be allowed unless the contractor has provided the required written notice.

4. No contract adjustment will be allowed under this clause for any effects caused on unchanged work. [This provision may be omitted by the Local Agency, at their option.] B. Suspensions of Work Ordered by the Engineer

1. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment.

2. Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly.

Page 376 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-10 Page 10 of 21
October 2023
The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted.

3. No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed.

4. No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.

C. Significant Changes in the Character of Work

1. The engineer reserves the right to make, in writing, at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project.

Such changes in quantities and alterations shall not invalidate the contract nor release the surety, and the contractor agrees to perform the work as altered.

2. If the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character, an adjustment, excluding anticipated profit, will be made to the contract. The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the contractor in such amount as the engineer may determine to be fair and equitable.

3. If the alterations or changes in quantities do not significantly change the character of the work to be performed under the contract, the altered work will be paid for as provided elsewhere in the contract.

4. The term “significant change” shall be construed to apply only to the following circumstances:
• When the character of the work as altered differs materially in kind or nature from that involved or included in the original proposed construction; or
• When a major item of work, as defined elsewhere in the contract, is increased in excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase in quantity shall apply only to that portion in excess of 125 percent of original contract item quantity, or in case of a decrease below 75 percent, to the actual amount of work performed.

7. BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES The Contractor shall begin work within 15 calendar days after the issuance of the Notice to Proceed.

This work shall be diligently prosecuted to completion before the expiration of 20 WORKING DAYS beginning on the fifteenth calendar day after the date shown on the Notice to Proceed.

The Contractor shall pay to the City of Los Alamitos the sum of $1,500 per day, for each and every calendar day’s delay in finishing the work in excess of the number of working days prescribed above.

8. BUY AMERICA
Buy America requirements apply to steel and iron, manufactured products, and construction materials permanently incorporated into the project.

Steel and Iron Materials
All steel and iron materials must be melted and manufactured in the United States except:

1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials [60 Fed Reg 15478 (03/24/1995)];

2. If the total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total contract amount or $2,500, materials produced outside the U.S. may be used if authorized.

Furnish steel and iron materials to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured. All melting and manufacturing processes for these materials, including an application of a coating, must occur in

Page 377 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-11 Page 11 of 21
October 2023
the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.

Manufactured Products
Iron and steel used in precast concrete manufactured products must meet the requirements of the above section (Steel and Iron Materials) regardless of the amount used. Iron and steel used in other manufactured products must meet the requirements of the above section (Steel and Iron Materials) if the weight of steel and iron components constitutes 90 percent or more of the total weight of the manufactured product.

Construction Materials
Buy America requirements apply to the following construction materials that are or consist primarily of:

1. Non-ferrous metals

2. Plastic and polymer-based products such as:

2.1 Polyvinylchloride

2.2 Composite Building Materials

3. Glass

4. Fiber optic cable (including drop cable)

5. Optical fiber

6. Lumber

7. Engineered wood

8. Drywall
All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United States.

Where one or more of these construction materials have been combined by a manufacturer with other materials through a manufacturing process, Buy America requirements do not apply unless otherwise specified.

Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where he construction material was manufactured and attest specifically to Buy America compliance.

Buy America requirements do not apply to the following:

1. Tools and construction equipment used in performing the work’

2. Temporary work that is not incorporated into the finished project Waivers
If Buy America waivers are granted, use the following language to include in the contract:

The following steel and iron products, manufactured products, or construction materials have received an approved Buy America waiver for this contract and, therefore, are not subject to Buy America requirements:

1. 2.

9. QUALITY ASSURANCE
The Local Agency uses a Quality Assurance Program (QAP) to ensure a material is produced to comply with the Contract. The Local Agency may examine the records and reports of tests the prime contractor performs if they are available at the job site. Schedule work to allow time for QAP.

10. PROMPT PAYMENT
A. From the Agency to the Contractors
The Local Agency shall make all project progress payment within 30 days after receipt of an undisputed and properly submitted payment request from the Contractor on a construction contract. If the Local Agency fails to pay promptly, the Local Agency shall pay interest to the Contractor, which accrues at the rate of 10 percent per annum on the principal amount of a money judgment remaining unsatisfied and pro-rated as necessary. Upon receipt of the payment request, the Local Agency shall act in accordance with both of the following:

Page 378 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-12 Page 12 of 21
October 2023

1. The Local Agency shall review each payment request as soon as feasible after receipt to verify it is a proper payment request.

2. The Local Agency must return any payment request deemed improper by the Local Agency to the Contractor as soon as feasible, but not later than seven (7) days, after receipt. A request returned pursuant to this paragraph shall include documentation setting forth in writing the reasons why it is an improper payment request.

B. Submittal of Exhibit 9-P
For projects awarded on or after September 1, 2023:

The Contractor must submit Exhibit 9-P to the Local Agency administering the contract by the 15th of the month following the month of any payment(s). If the Contractor does not make any payments to subcontractors, supplier(s) and/or manufacturers they must report “no payments were made to subs this month” and write this visibly and legibly on Exhibit 9-P.

The Local Agency must verify all Exhibit 9-P information, monitor compliance with prompt payment requirements for DBE and non-DBE firms, and address any shortfall to the DBE commitment and prompt payment issues until the end of the project. The Local Agency must email a copy of Exhibit 9-P to [email protected] before the end of the month after receiving the Exhibit 9-P from the Contractor.

11. FORM FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID CONTRACTS [Form FHWA-1273 must be physically inserted into the contract without modification, excluding

ATTACHMENT A - EMPLOYMENT AND MATERIALS PREFERENCE FOR APPALACHIAN DEVELOPMENT HIGHWAY SYSTEM OR APPALACHIAN LOCAL ACCESS ROAD CONTRACTS] [The current version of Form FHWA-1273 is accessible at FHWA’s website:
https://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf]

12. FEMALE AND MINORITY GOALS
To comply with Section II, "Nondiscrimination," of "Required Contract Provisions Federal-Aid Construction Contracts," the following are for female and minority utilization goals for Federal-aid construction contracts and subcontracts that exceed $10,000:

The nationwide goal for female utilization is 6.9 percent.

The goals for minority utilization [45 Fed Reg 65984 (10/3/1980)] are as follows:

MINORITY UTILIZATION GOALS
Economic Area Goal
(Percent)
174
Redding CA:

Non-SMSA (Standard Metropolitan Statistical Area) Counties:

CA Lassen; CA Modoc; CA Plumas; CA Shasta; CA Siskiyou; CA Tehama

6.8 175
Eureka, CA
Non-SMSA Counties:

CA Del Norte; CA Humboldt; CA Trinity

6.6

Page 379 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-13 Page 13 of 21
October 2023
176
San Francisco-Oakland-San Jose, CA:

SMSA Counties:
7120 Salinas-Seaside-Monterey, CA
CA Monterey
7360 San Francisco-Oakland
CA Alameda; CA Contra Costa; CA Marin; CA San Francisco; CA San Mateo 7400 San Jose, CA
CA Santa Clara, CA
7485 Santa Cruz, CA
CA Santa Cruz
7500 Santa Rosa
CA Sonoma
8720 Vallejo-Fairfield-Napa, CA
CA Napa; CA Solano
Non-SMSA Counties:

CA Lake; CA Mendocino; CA San Benito

28.9 25.6

19.6 14.9

9.1 17.1

23.2 177
Sacramento, CA:

SMSA Counties:
6920 Sacramento, CA
CA Placer; CA Sacramento; CA Yolo
Non-SMSA Counties
CA Butte; CA Colusa; CA El Dorado; CA Glenn; CA Nevada; CA Sierra; CA Sutter; CA Yuba

16.1 14.3
178
Stockton-Modesto, CA:

SMSA Counties:
5170 Modesto, CA
CA Stanislaus
8120 Stockton, CA
CA San Joaquin
Non-SMSA Counties
CA Alpine; CA Amador; CA Calaveras; CA Mariposa; CA Merced; CA Tuolumne

12.3 24.3

19.8 179
Fresno-Bakersfield, CA
SMSA Counties:
0680 Bakersfield, CA
CA Kern
2840 Fresno, CA
CA Fresno
Non-SMSA Counties:

CA Kings; CA Madera; CA Tulare

19.1 26.1

23.6 180
Los Angeles, CA:

SMSA Counties:
0360 Anaheim-Santa Ana-Garden Grove, CA
CA Orange
4480 Los Angeles-Long Beach, CA
CA Los Angeles
6000 Oxnard-Simi Valley-Ventura, CA
CA Ventura
6780 Riverside-San Bernardino-Ontario, CA
CA Riverside; CA San Bernardino
7480 Santa Barbara-Santa Maria-Lompoc, CA
CA Santa Barbara
Non-SMSA Counties
CA Inyo; CA Mono; CA San Luis Obispo

11.9 28.3

21.5 19.0

19.7 24.6

Page 380 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-14 Page 14 of 21
October 2023
For the last full week of July during which work is performed under the contract, the prime contractor and each non-material-supplier subcontractor with a subcontract of $10,000 or more must complete Form FHWA PR-1391 (Appendix C to 23 CFR 230). Submit the forms by August 15.

13. TITLE VI ASSURANCES
[The U.S. Department of Transportation Order No. 1050.2A requires all federal-aid Department of Transportation contracts between an agency and a contractor to contain Appendix A and Appendix E. Note:

Appendix B is required only if the contract impacts deeds effecting or recording the transfer of real property, structures, or improvements thereon, or granting interest therein. Appendices C and D are required only if the contract impacts deeds, licenses, leases, permits, or similar instruments entered into by the recipient.]

APPENDIX A
During the performance of this Agreement, the contractor, for itself, its assignees, and successors in interest (hereinafter collectively referred to as CONTRACTOR) agrees as follows:
a. Compliance with Regulations: CONTRACTOR shall comply with the regulations relative to nondiscrimination in federally assisted programs of the Department of Transportation, Title 49, Code of Federal Regulations, Part 21, as they may be amended from time to time, (hereinafter referred to as the REGULATIONS), which are herein incorporated by reference and made a part of this agreement. b. Nondiscrimination: CONTRACTOR, with regard to the work performed by it during the AGREEMENT, shall not discriminate on the grounds of race, color, sex, national origin, religion, age, or disability in the selection and retention of sub-applicants, including procurements of materials and leases of equipment.

CONTRACTOR shall not participate either directly or indirectly in the discrimination prohibited by Section

21.5 of the Regulations, including employment practices when the agreement covers a program set forth in Appendix B of the Regulations.
c. Solicitations for Sub-agreements, Including Procurements of Materials and Equipment: In all solicitations either by competitive bidding or negotiation made by CONTRACTOR for work to be performed under a Sub-agreement, including procurements of materials or leases of equipment, each potential sub-applicant or supplier shall be notified by CONTRACTOR of the CONTRACTOR’S obligations under this Agreement and the Regulations relative to nondiscrimination on the grounds of race, color, or national origin. d. Information and Reports: CONTRACTOR shall provide all information and reports required by the Regulations, or directives issued pursuant thereto, and shall permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by the California Department of Transportation or FHWA to be pertinent to ascertain compliance with such Regulations or directives. Where any information required of CONTRACTOR is in the exclusive possession of another who fails or refuses to furnish this information, CONTRACTOR shall so certify to the California Department of Transportation or the FHWA as appropriate and shall set forth what efforts CONTRACTOR has made to obtain the information.
e. Sanctions for Noncompliance: In the event of CONTRACTOR’s noncompliance with the nondiscrimination provisions of this agreement, the California Department of Transportation shall impose such agreement sanctions as it or the FHWA may determine to be appropriate, including, but not limited to:
i. withholding of payments to CONTRACTOR under the Agreement within a reasonable period of time, not to exceed 90 days; and/or
ii. cancellation, termination or suspension of the Agreement, in whole or in part. 181
San Diego, CA:

SMSA Counties
7320 San Diego, CA
CA San Diego
Non-SMSA Counties
CA Imperial

16.9 18.2

Page 381 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-15 Page 15 of 21
October 2023
f. Incorporation of Provisions: CONTRACTOR shall include the provisions of paragraphs (1) through (6) in every sub-agreement, including procurements of materials and leases of equipment, unless exempt by the Regulations, or directives issued pursuant thereto.

CONTRACTOR shall take such action with respect to any sub-agreement or procurement as the California Department of Transportation or FHWA may direct as a means of enforcing such provisions including sanctions for noncompliance, provided, however, that, in the event CONTRACTOR becomes involved in, or is threatened with, litigation with a sub-applicant or supplier as a result of such direction, CONTRACTOR may request the California Department of Transportation enter into such litigation to protect the interests of the State, and, in addition, CONTRACTOR may request the United States to enter into such litigation to protect the interests of the United States.

APPENDIX B

CLAUSES FOR DEEDS TRANSFERRING UNITED STATES PROPERTY
The following clauses will be included in deeds effecting or recording the transfer of real property, structures, or improvements thereon, or granting interest therein from the United States pursuant to the provisions of Assurance 4:

NOW THEREFORE, the U.S. Department of Transportation as authorized by law and upon the condition that the recipient will accept title to the lands and maintain the project constructed thereon in accordance with Title 23 U.S.C., the regulations for the administration of the preceding statute, and the policies and procedures prescribed by the FHWA of the U.S. Department of Transportation in accordance and in compliance with all requirements imposed by Title 49, Code of Federal Regulations, U.S. Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Non-discrimination in Federally-assisted programs of the U.S. Department of Transportation pertaining to and effectuating the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252; 42 U.S.C. § 2000d to 2000d-4), does hereby remise, release, quitclaim and convey unto the recipient all the right, title and interest of the U.S. Department of Transportation in and to said lands described in Exhibit A attached hereto and made a part hereof.
(HABENDUM CLAUSE)
TO HAVE AND TO HOLD said lands and interests therein unto the recipient and its successors forever, subject, however, to the covenants, conditions, restrictions and reservations herein contained as follows, which will remain in effect for the period during which the real property or structures are used for a purpose for which Federal financial assistance is extended or for another purpose involving the provision of similar services or benefits and will be binding on the recipient, its successors and assigns. The recipient, in consideration of the conveyance of said lands and interest in lands, does hereby covenant and agree as a covenant running with the land for itself, its successors and assigns, that (1) no person will on the grounds of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination with regard to any facility located wholly or in part on, over, or under such lands hereby conveyed [,] [and]* (2) that the recipient will use the lands and interests in lands and interest in lands so conveyed, in compliance with all requirements imposed by or pursuant to Title 49, Code of Federal Regulations, U.S. Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federally-assisted programs of the U.S. Department of Transportation, Effectuation of Title VI of the Civil Rights Act of 1964, and as said Regulations and Acts may be amended[, and (3) that in the event of breach of any of the above-mentioned non-discrimination conditions, the Department will have a right to enter or re-enter said lands and facilities on said lands, and that above described land and facilities will thereon revert to and vest in and become the absolute property of the U.S. Department of Transportation and its assigns as such interest existed prior to this instruction].* (*Reverter clause and related language to be used only when it is determined that such a clause is necessary in order to make clear the purpose of Title VI.)

APPENDIX C

CLAUSES FOR TRANSFER OF REAL PROPERTY ACQUIRED OR IMPROVED

UNDER THE ACTIVITY, FACILITY, OR PROGRAM
The following clauses will be included in deeds, licenses, leases, permits, or similar instruments entered into by the recipient pursuant to the provisions of Assurance 7(a):

Page 382 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-16 Page 16 of 21
October 2023
A. The (grantee, lessee, permittee, etc. as appropriate) for himself/herself, his/her heirs, personal representatives, successors in interest, and assigns, as a part of the consideration hereof, does hereby covenant and agree [in the case of deeds and leases add “as a covenant running with the land”] that:

1. In the event facilities are constructed, maintained, or otherwise operated on the property described in this (deed, license, lease, permit, etc.) for a purpose for which a U.S. Department of Transportation activity, facility, or program is extended or for another purpose involving the provision of similar services or benefits, the (grantee, licensee, lessee, permittee, etc.) will maintain and operate such facilities and services in compliance with all requirements imposed by the Acts and Regulations (as may be amended) such that no person on the grounds of race, color, or national origin, will be excluded from participation in, denied the benefits of, or be otherwise subjected to discrimination in the use of said facilities.

B. With respect to licenses, leases, permits, etc., in the event of breach of any of the above Nondiscrimination covenants, the recipient will have the right to terminate the (lease, license, permit, etc.) and to enter, re-enter, and repossess said lands and facilities thereon, and hold the same as if the (lease, license, permit, etc.) had never been made or issued.*
C. With respect to a deed, in the event of breach of any of the above Non-discrimination covenants, the recipient will have the right to enter or re-enter the lands and facilities thereon, and the above described lands and facilities will there upon revert to and vest in and become the absolute property of the recipient and its assigns.*
(*Reverter clause and related language to be used only when it is determined that such a clause is necessary to make clear the purpose of Title VI.)

APPENDIX D

CLAUSES FOR CONSTRUCTION/USE/ACCESS TO REAL PROPERTY

ACQUIRED UNDER THE ACTIVITY, FACILITY OR PROGRAM
The following clauses will be included in deeds, licenses, permits, or similar instruments/agreements entered into by the recipient pursuant to the provisions of Assurance 7(b):

A. The (grantee, licensee, permittee, etc., as appropriate) for himself/herself, his/her heirs, personal representatives, successors in interest ,and assigns, as a part of the consideration hereof, does hereby covenant and agree (in the case of deeds and leases add, “as a covenant running with the land”) that (1) no person on the ground of race, color, or national origin, will be excluded from participation in, denied the benefits of, or be otherwise subjected to discrimination in the use of said facilities, (2) that in the construction of any improvements on, over, or under such land, and the furnishings of services thereon, no person on the ground of race, color, or national origin, will be excluded from participation in, denied the benefits of, or otherwise be subjected to discrimination, (3) that the (grantee, licensee, lessee, permittee, etc.) will use the premises in compliance with all other requirements imposed by or pursuant to the Acts and Regulations, as amended, set forth in this Assurance.

B. With respect to (licenses, leases, permits, etc.) in the event of breach of any of the above of the above Non-discrimination covenants, the recipient will have the right to terminate the (license, permits, etc., as appropriate) and to enter or re-enter and repossess said land and the facilities thereon, and hold the same as if said (license, permit, etc., as appropriate) had never been made or issued.* C. With respect to deeds, in the event of breach of any of the above Non-discrimination covenants, the recipient will thereupon revert to and vest in and become the absolute property of the recipient and its assigns.
(*Reverter clause and related language to be used only when it is determined that such a clause is necessary to make clear the purpose of Title VI.)

Page 383 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-17 Page 17 of 21
October 2023

APPENDIX E
During the performance of this contract, the contractor, for itself, its assignees, and successors in interest (hereinafter referred to as the “contractor”) agrees to comply with the following non-discrimination statutes and authorities, including, but not limited to:

Pertinent Non-Discrimination Authorities:
• Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252), prohibits discrimination on the basis of race, color, national origin); and 49 CFR Part 21; • The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42 U.S.C. § 4601), (prohibits unfair treatment of persons displaced or whose property has been acquired because of Federal or Federal-aid programs and projects);
• Federal-Aid Highway Act of 1973, (23 U.S.C. § 324 et seq.), prohibits discrimination on the basis of sex; • Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et seq.), as amended, (prohibits discrimination on the basis of disability); and 49 CR Part 27; • The Age Discrimination Act of 1975, as amended, (42 U.S.C. § 6101 et seq.), prohibits discrimination on the basis of age);
• Airport and Airway Improvement Act of 1982, (49 U.S.C. § 471, Section 47123), as amended, (prohibits discrimination based on race, creed, color, national origin, or sex); • The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened the scope, coverage and applicability of Title VI of the Civil Rights Act of 1964, The Age Discrimination Act of 1975 and Section 504 of the Rehabilitation Act of 1973, by expanding the definition of the terms “programs or activities” to include all of the programs or activities of the Federal-aid recipients, sub-recipients and contractors, whether such programs or activities are Federally funded or not);
• Titles II and III of the Americans with Disabilities Act, which prohibit discrimination of the basis of disability in the operation of public entities, public and private transportation systems, places of public accommodation, and certain testing entities (42 U.S.C. §§ 12131 – 12189) as implemented by Department of Transportation regulations 49 C.F.R. parts 37 and 38; • The Federal Aviation Administration’s Non-discrimination statute (49 U.S.C. § 47123) (prohibits discrimination on the basis of race, color, national origin, and sex); • Executive Order 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, which ensures discrimination against minority populations by discouraging programs, policies, and activities with disproportionately high and adverse human health or environmental effects on minority and low-income populations;
• Executive Order 13166, Improving Access to Services for Persons with Limited English Proficiency, and resulting agency guidance, national origin discrimination includes discrimination because of limited English proficiency (LEP). To ensure compliance with Title VI, you must take reasonable steps to ensure that LEP persons have meaningful access to your programs (70 Fed. Reg. at 74087 to 74100); • Title IX of the Education Amendments of 1972, as amended, which prohibits you from discriminating because of sex in education programs or activities (20 U.S.C. 1681 et seq.).

Page 384 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-18 Page 18 of 21
October 2023
Federal Trainee Program Special Provisions
(to be used when applicable)

14. FEDERAL TRAINEE PROGRAM
For the Federal training program, the number of trainees or apprentices is 0.

This section applies if a number of trainees or apprentices is specified in the special provisions.

As part of the prime contractor’s equal opportunity affirmative action program, provide on-the-job training to develop full journeymen in the types of trades or job classifications involved.

The prime contractor has primary responsibility for meeting this training requirement.

If the prime contractor subcontracts a contract part, they shall determine how many trainees or apprentices are to be trained by the subcontractor. Include these training requirements in each subcontract.

Where feasible, 25 percent of apprentices or trainees in each occupation must be in their 1st year of apprenticeship or training.

Distribute the number of apprentices or trainees among the work classifications on the basis of the prime contractor’s needs and the availability of journeymen in the various classifications within a reasonable recruitment area.

Before starting work, the prime contractor shall submit to the City:

1. Number of apprentices or trainees to be trained for each classification

2. Training program to be used

3. Training starting date for each classification
The prime contractor shall obtain approval from the City for this submitted information before the prime contractor starts work. The City credits the prime contractor for each apprentice or trainee the prime contractor employs on the job who is currently enrolled or becomes enrolled in an approved program.

The primary objective of this section is to train and upgrade minorities and women toward journeymen status.

The prime contractor shall make every effort to enroll minority and women apprentices or trainees, such as conducting systematic and direct recruitment through public and private sources likely to yield minority and women apprentices or trainees, to the extent they are available within a reasonable recruitment area and show that they have made the efforts. In making these efforts, the prime contractor shall not discriminate against any applicant for training.

The prime contractor shall not employ as an apprentice or trainee an employee:

1. In any classification in which the employee has successfully completed a training course leading to journeyman status or in which the employee has been employed as a journeyman

2. Who is not registered in a program approved by the US Department of Labor, Bureau of Apprenticeship and Training
The prime contractor shall ask the employee if the employee has successfully completed a training course leading to journeyman status or has been employed as a journeyman. The prime contractor’s records must show the employee's answers to the questions.

In the training program, the prime contractor shall establish the minimum length and training type for each classification. The City and FHWA approve a program if one of the following is met:

1. It is calculated to:
 Meet equal employment opportunity responsibilities
 Qualify the average apprentice or trainee for journeyman status in the classification involved by the end of the training period

2. It is registered with the U.S. Department of Labor, Bureau of Apprenticeship and Training, and it is administered in a way consistent with the equal employment responsibilities of Federal-aid highway construction contracts
The prime contractor shall obtain the State's approval for their training program before they start work involving the classification covered by the program.

Page 385 of 672 ends

Local Assistance Procedures Manual Exhibit 12-G
Required Federal-Aid Contract Language
F-19 Page 19 of 21
October 2023
The prime contractor shall provide training in the construction crafts, not in clerk-typist or secretarial-type positions. Training is allowed in lower-level management positions such as office engineers, estimators, and timekeepers if the training is oriented toward construction applications. Training is allowed in the laborer classification if significant and meaningful training is provided and approved by the division office.

Off-site training is allowed if the training is an integral part of an approved training program and does not make up a significant part of the overall training.

The City reimburses the prime contractor 80 cents per hour of training given an employee on this contract under an approved training program:

1. For on-site training

2. For off-site training if the apprentice or trainee is currently employed on a Federal-aid project and the prime contractor does at least one of the following:
 Contribute to the cost of the training
 Provide the instruction to the apprentice or trainee
 Pay the apprentice's or trainee's wages during the off-site training period

3. If the prime contractor complies with this section.

Each apprentice or trainee must:

1. Begin training on the project as soon as feasible after the start of work involving the apprentice's or trainee's skill

2. Remain on the project as long as training opportunities exist in the apprentice's or trainee's work classification or until the apprentice or trainee has completed the training program The prime contractor shall furnish the apprentice or trainee with a:

1. Copy of the training plan approved by the U.S. Department of Labor or a training plan for trainees approved by both Caltrans and FHWA

2. Certification showing the type and length of training satisfactorily completed.

Maintain records and submit reports documenting contractor’s performance under this section.

15. PROHIBITION OF CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE

EQUIPMENT AND SERVICES
In response to significant national security concerns, the agency shall check the prohibited vendor list before making any telecommunications and video surveillance purchase because recipients and subrecipients of federal funds are prohibited from obligating or expending loan or grant funds to:
• Procure or obtain;
• Extend or renew a contract to procure or obtain; or
• Enter into a contract (or extend or renew a contract) to procure or obtain equipment, services, or systems that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

The prohibited vendors (and their subsidiaries or affiliates) are:
• Huawei Technologies Company;
• ZTE Corporation;
• Hytera Communications Corporation;
• Hangzhou Hikvision Digital Technology Company;
• Dahua Technology Company; and
• Subsidiaries or affiliates of the above-mentioned companies.

In implementing the prohibition, the agency administering loan, grant, or subsidy programs shall prioritize available funding and technical support to assist affected businesses, institutions and organizations as is reasonably necessary for those affected entities to transition from covered communications equipment and services, to procure replacement equipment and services, and to ensure that communications service to users and customers is sustained.

Page 386 of 672 ends

Local Assistance Procedures Manual Exhibit 12-H
Sample Bid
January 2019
F-20

THE BIDDER'S EXECUTION ON THE SIGNATURE PORTION OF THIS PROPOSAL SHALL

ALSO CONSTITUTE AN ENDORSEMENT AND EXECUTION OF THIS CERTIFICATION, WHICH IS A PART OF THIS PROPOSAL.)

EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
The □bidder / □proposed subcontractor hereby certifies that he □has / □has not participated in a previous contract or subcontract subject to the equal opportunity clauses, as required by Executive Orders 10925, 11114, or 11246, and that, where required, has filed with the Joint Reporting Committee, the Director of the Office of Federal Contract Compliance, a Federal Government contracting or administering agency, or the former President's Committee on Equal Employment Opportunity, all reports due under the applicable filling requirements.

Note: The above certification is required by the Equal Employment Opportunity Regulations of the Secretary of Labor (41 CFR 60-1.7(b) (1)), and must be submitted by bidders and proposed subcontractors only in connection with contracts and subcontracts which are subject to the equal opportunity clause. Contracts and subcontracts which are exempt from the equal opportunity clause are set forth in 41 CFR 60-1.5. (Generally only contracts or subcontracts of $10,000 or under are exempt.) Currently, Standard Form 100 (EEO-1) is the only report required by the Executive Orders or their implementing regulations.

Proposed prime contractors and subcontractors who have participated in a previous contract or subcontract subject to the Executive Orders and have not filed the required reports should note that 41 CFR 60-1.7(b) (1) prevents the award of contracts and subcontracts unless such contractor submits a report covering the delinquent period or such other period specified by the Federal Highway Administration or by the Director, Office of Federal Contract Compliance, U.S. Department of Labor.

Page 387 of 672 ends

Local Assistance Procedures Manual Exhibit 12-H
Sample Bid
January 2019
F-21
(THE BIDDER'S EXECUTION ON THE SIGNATURE PORTION OF THIS PROPOSAL SHALL

ALSO CONSTITUTE AN ENDORSEMENT AND EXECUTION OF THIS CERTIFICATION, WHICH IS A PART OF THIS PROPOSAL.)

PUBLIC CONTRACT CODE
Public Contract Code Section 10285.1 Statement
In conformance with Public Contract Code Section 10285.1 (Chapter 376, Stats. 1985), the bidder hereby declares under penalty of perjury under the laws of the State of California that the Bidder has / has not been convicted within the preceding three (3) years of any offenses referred to in that section, including any charge of fraud, bribery, collusion, conspiracy, or any other act in violation of any state or federal antitrust law in connection with the bidding upon, award of, or performance of, any public works contract, as defined in Public Contract Code Section 1101, with any public entity, as defined in Public Contract Code Section 1100, including the Regents of the University of California or the Trustees of the California State University. The term “bidder” is understood to include any partner, member, officer, director, responsible managing officer, or responsible managing employee thereof, as referred to in Section 10285.1.

Note: The Bidder must place a checkmark before “has” or “has not” in one of the check boxes provided.

Public Contract Code Section 10162 Questionnaire
In conformance with Public Contract Code Section 10162, the Bidder shall complete, under penalty of perjury, the following questionnaire:

Has the Bidder, any officer of the Bidder, or any employee of the Bidder who has a proprietary interest in the Bidder, ever been disqualified, removed, or otherwise prevented from bidding on, or completing a federal, state, or local government project because of a violation of law or a safety regulation? Yes No
If the answer is yes, explain the circumstances in the following space:

Public Contract Code Section 10232 Statement
In conformance with Public Contract Code Section10232, the Contractor hereby states under penalty of perjury that no more than one (1) final unappealable finding of contempt of court by a federal court has been issued against the Contactor within the immediately preceding two-year period because of the Contractor’s failure to comply with an order of a federal court which orders the Contractor to comply with an order of the National Labor Relations Board.

Page 388 of 672 ends

Local Assistance Procedures Manual Exhibit 12-H
Sample Bid
January 2019
F-22
(THE BIDDER'S EXECUTION ON THE SIGNATURE PORTION OF THIS PROPOSAL SHALL

ALSO CONSTITUTE AN ENDORSEMENT AND EXECUTION OF THIS CERTIFICATION, WHICH IS A PART OF THIS PROPOSAL.)

DEBARMENT AND SUSPENSION CERTIFICATION
TITLE 49, CODE OF FEDERAL REGULATIONS, PART 29
The bidder, under penalty of perjury, certifies that, except as noted below, he/she or any other person associated therewith in the capacity of owner, partner, director, officer, manager:
• is not currently under suspension, debarment, voluntary exclusion, or determination of ineligibility by any Federal agency;
• has not been suspended, debarred, voluntarily excluded, or determined ineligible by any Federal agency within the past 3 years;
• does not have a proposed debarment pending; and
• has not been indicted, convicted, or had a civil judgment rendered against it by a court of competent jurisdiction in any matter involving fraud or official misconduct within the past 3 years.

If there are any exceptions to this certification, insert the exceptions in the following space.

Exceptions will not necessarily result in denial of award, but will be considered in determining bidder responsibility. For any exception noted above, indicate below to whom it applies, initiating agency, and dates of action.

Note: Providing false information may result in criminal prosecution or administrative sanctions.

Page 389 of 672 ends

Local Assistance Procedures Manual Exhibit 12-H
Sample Bid
January 2019
F-23
(THE BIDDER'S EXECUTION ON THE SIGNATURE PORTION OF THIS PROPOSAL SHALL

ALSO CONSTITUTE AN ENDORSEMENT AND EXECUTION OF THIS CERTIFICATION, WHICH IS A PART OF THIS PROPOSAL.)

NONLOBBYING CERTIFICATION

FOR FEDERAL-AID CONTRACTS
The prospective participant certifies, by signing and submitting this bid or proposal, to the best of his or her knowledge and belief, that:
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.
(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard FormLLL, "Disclosure of Lobbying Activities," in conformance with its instructions.

This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

The prospective participant also agrees by submitting his or her bid or proposal that he or she shall require that the language of this certification be included in all lower tier subcontracts, which exceed $100,000 and that all such subrecipients shall certify and disclose accordingly.

Page 390 of 672 ends

Local Assistance Procedures Manual Exhibit 12-H
Sample Bid
January 2019
F-24

DISCLOSURE OF LOBBYING ACTIVITIES
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352

1. Type of Federal Action: 2. Status of Federal Action: 3. Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post-award
d. loan For Material Change Only:
e. loan guarantee
year ___________ quarter ___________
f. loan insurance date of last report _________________

4. Name and Address of Reporting Entity 5. If Reporting Entity in No. 4 is Subawardee, Enter Name and Address of Prime:

Prime Subawardee
Tier _______ , if known
Congressional District, if known: Congressional District, if known:

6. Federal Department/Agency: 7. Federal Program Name/Description:

CFDA Number, if applicable

8. Federal Action Number, if known: 9. Award Amount, if known:
$

10. a. Name and Address of Lobbying Registrant b. Individuals Performing Services (including (If individual, last name, first name, MI): address if different from No. 10a) (last name, first name, MI):
(attach Continuation Sheet(s) if necessary)

11. Amount of Payment (check all that apply) 13. Type of Payment (check all that apply)

$ Actual planned a. retainer
b. one-time fee

12. Form of Payment (check all that apply): c. commission a. cash d. contingent fee
b. in-kind; specify: nature e deferred
Value f. other, specify

14. Brief Description of Services Performed or to be performed and Date(s) of Service, including officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 11:
(attach Continuation Sheet(s) if necessary)

15. Continuation Sheet(s) attached: Yes No

16. Information requested through this form is authorized by Title 31 U.S.C. Section 1352. This disclosure of lobbying reliance was placed by the tier above when his transaction was made or entered into. This disclosure is required pursuant to 31 U.S.C. 1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any person who fails to file the required disclosure shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

Signature: ___________________________________
Print Name: _________________________________
Title: _______________________________________
Telephone No.: _________________ Date: _________
Authorized for Local Reproduction
Federal Use Only: Standard Form – LLL

Page 391 of 672 ends

Local Assistance Procedures Manual Exhibit 12-H
Sample Bid
January 2019
F-25

INSTRUCTIONS FOR COMPLETION OF SF-LLL,

DISCLOSURE OF LOBBYING ACTIVITIES
This disclosure form shall be completed by the reporting entity, whether subawardee or prime Federal recipient, at the initiation or receipt of covered Federal action or a material change to previous filing pursuant to title 31 U.S.C. section 1352. The filing of a form is required for such payment or agreement to make payment to lobbying entity for influencing or attempting to influence an officer or employee of any agency, a Member of Congress an officer or employee of Congress or an employee of a Member of Congress in connection with a covered Federal action. Attach a continuation sheet for additional information if the space on the form is inadequate. Complete all items that apply for both the initial filing and material change report. Refer to the implementing guidance published by the Office of Management and Budget for additional information.

1. Identify the type of covered Federal action for which lobbying activity is and/or has been secured to influence, the outcome of a covered Federal action.

2. Identify the status of the covered Federal action.

3. Identify the appropriate classification of this report. If this is a follow-up report caused by a material change to the information previously reported, enter the year and quarter in which the change occurred. Enter the date of the last, previously submitted report by this reporting entity for this covered Federal action.

4. Enter the full name, address, city, state, and zip code of the reporting entity. Include Congressional District if known.

Check the appropriate classification of the reporting entity that designates if it is or expects to be a prime or subaward recipient. Identify the tier of the subawardee, e.g., the first subawardee of the prime is the first tier. Subawards include but are not limited to subcontracts, sub-grants, and contract awards under grants.

5. If the organization filing the report in Item 4 checks "Subawardee," then enter the full name, address, city, state, and zip code of the prime Federal recipient. Include Congressional District, if known.

6. Enter the name of the Federal agency making the award or loan commitment. Include at least one organization level below agency name, if known (e.g., Department of Transportation, United States Coast Guard).

7. Enter the Federal program name or description for the covered Federal action (item 1). If known, enter the full Catalog of Federal Domestic Assistance (CFDA) number for grants, cooperative agreements, loans, and loan commitments.

8. Enter the most appropriate Federal identifying number available for the Federal action identification in item 1 (e.g., Request for Proposal (RFP) number, Invitation for Bid (IFB) number, grant announcement number, the contract grant or loan award number, the application/proposal control number assigned by the Federal agency). Include prefixes, e.g., "RFP-DE-90-001."

9. For a covered Federal action where there has been an award or loan commitment by the Federal agency, enter the Federal amount of the award/loan commitments for the prime entity identified in item 4 or 5.

10. (a) Enter the full name, address, city, state, and zip code of the lobbying entity engaged by the reporting entity identified in item 4 to influence the covered Federal action. (b) Enter the full names of the individual(s) performing services and include full address if different from 10 (a). Enter Last Name, First Name, and Middle Initial (Ml).

11. Enter the amount of compensation paid or reasonably expected to be paid by the reporting entity (item 4) to the lobbying entity (item 10). Indicate whether the payment has been made (actual) or will be made (planned). Check all boxes that apply. If this is a material change report, enter the cumulative amount of payment made or planned to be made.

12. Check the appropriate box(es). Check all boxes that apply. If payment is made through an in-kind contribution, specify the nature and value of the in-kind payment.

13. Check the appropriate box(es). Check all boxes that apply. If other, specify nature.

14. Provide a specific and detailed description of the services that the lobbyist has performed or will be expected to perform and the date(s) of any services rendered. Include all preparatory and related activity not just time spent in actual contact with Federal officials. Identify the Federal officer(s) or employee(s) contacted or the officer(s) employee(s) or Member(s) of Congress that were contacted.

15. Check whether or not a continuation sheet is attached.

16. The certifying official shall sign and date the form, print his/her name title and telephone number.

Public reporting burden for this collection of information is estimated to average 30 minutes per response, including time for reviewing instruction, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding the burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Office of Management and Budget, Paperwork Reduction Project (0348-0046), Washington, D.C. 20503.

Page 392 of 672 ends

Local Assistance Procedures Manual Exhibit 15-G
Construction Contract DBE Commitment
F-26 January 2023
Exhibit 15-G: Construction Contract DBE Commitment

1. Local Agency: City of Los Alamitos 2. Contract DBE Goal: 17 %

3. Project Description: Street Improvements on Bloomfield Street

4. Project Location: Bloomfield Street from Katella Avenue to Florista Street

5. Bidder's Name: 6. Prime Certified DBE:  7. Bid Amount: $

8. Total Dollar Amount for ALL Subcontractors: 9. Total Number of ALL Subcontractors:

10. Bid
Item
Number

11. Description of Work, Service, or Materials Supplied

12. NAICS or
Work Category
Codes

13. DBE
Certification
Number

14. DBE Contact Information
(Must be certified on the date bids are opened)

15. DBE
Dollar
Amount

Local Agency to Complete this Section upon Execution of Award 16. TOTAL CLAIMED DBE PARTICIPATION $

22. Local Agency Contract Number:

23. Federal-Aid Project Number:
%

24. Bid Opening Date:

25. Contract Award Date:

IMPORTANT: Identify all DBE firms being claimed for credit, regardless of tier. Names of the First Tier DBE Subcontractors and their respective item(s) of work listed above must be consistent, where applicable with the names and items of the work in the "Subcontractor List" submitted with your bid. Written confirmation of each listed DBE is required.

26. Award Amount:

Local Agency certifies that all DBE certifications are valid and information on this form is complete and accurate.

27. Local Agency Representative's Signature 28. Date 17. Preparer's Signature 18. Date

29. Local Agency Representative's Name 30. Phone 19. Preparer's Name 20. Phone

31. Local Agency Representative's Title 21. Preparer's Title

DISTRIBUTION: 1. Original – Local Agency

2. Copy – Caltrans District Local Assistance Engineer (DLAE). Failure to submit to DLAE within 30 days of contract execution may result in de-obligation of federal funds on contract.

3. Include additional copy with award package.

Page 393 of 672 ends

Local Assistance Procedures Manual Exhibit 15-G
Construction Contract DBE Commitment
F-27 January 2023
INSTRUCTIONS – CONSTRUCTION CONTRACT DBE COMMITMENT

CONTRACTOR SECTION

1. Local Agency - Enter the name of the local or regional agency that is funding the contract.

2. Contract DBE Goal - Enter the contract DBE goal percentage as it appears on the project advertisement.

3. Project Description - Enter the project description as it appears on the project advertisement (Bridge Rehab, Seismic Rehab, Overlay, Widening, etc.).

4. Project Location - Enter the project location(s) as shown on the project advertisement.

5. Bidder’s Name - Enter the contractor’s firm name.

6. Prime Certified DBE - Check box if prime contractor is a certified DBE.

7. Bid Amount - Enter the total contract bid dollar amount for the prime contractor.

8. Total Dollar Amount for ALL Subcontractors - Enter the total dollar amount for all subcontracted contractors. SUM = (DBEs + all Non-DBEs). Do not include the prime contractor information in this count.

9. Total number of ALL subcontractors - Enter the total number of all subcontracted contractors. SUM = (DBEs + all Non-DBEs). Do not include the prime contractor information in this count.

10. Bid Item Number - Enter bid item number for work, services, or materials supplied to be provided.

11. Description of Work, Services, or Materials Supplied - Enter description of work, services, or materials to be provided. Indicate all work to be performed by DBEs including work performed by the prime contractor’s own forces, if the prime is a DBE. If 100% of the item is not to be performed or furnished by the DBE, describe the exact portion to be performed or furnished by the DBE. See LAPM Chapter 9 to determine how to count the participation of DBE firms.

12. NAICS or Work Category Codes - Enter NAICS or Work Category Codes from the California Unified Certification Program database.

13. DBE Certification Number - Enter the DBE’s Certification Identification Number. All DBEs must be certified on the date bids are opened.

14. DBE Contact Information - Enter the name, address, and phone number of all DBE subcontracted contractors. Also, enter the prime contractor’s name and phone number, if the prime is a DBE.

15. DBE Dollar Amount - Enter the subcontracted dollar amount of the work to be performed or service to be provided. Include the prime contractor if the prime is a DBE. See LAPM Chapter 9 for how to count full/partial participation.

16. Total Claimed DBE Participation - $: Enter the total dollar amounts entered in the “DBE Dollar Amount” column. %: Enter the total DBE participation claimed (“Total Claimed DBE Participation Dollars” divided by item “Bid Amount”). If the total % claimed is less than item “Contract DBE Goal,” an adequately documented Good Faith Effort (GFE) is required (see Exhibit 15-H DBE Information - Good Faith Efforts of the LAPM).

17. Preparer’s Signature - The person completing the DBE commitment form on behalf of the contractor’s firm must sign their name.

18. Date - Enter the date the DBE commitment form is signed by the contractor’s preparer.

19. Preparer’s Name - Enter the name of the person preparing and signing the contractor’s DBE commitment form.

20. Phone - Enter the area code and phone number of the person signing the contractor’s DBE commitment form.

21. Preparer’s Title - Enter the position/title of the person signing the contractor’s DBE commitment form.

LOCAL AGENCY SECTION

22. Local Agency Contract Number - Enter the Local Agency contract number or identifier.

23. Federal-Aid Project Number - Enter the Federal-Aid Project Number(s).

24. Bid Opening Date - Enter the date contract bids were opened.

25. Contract Award Date - Enter the date the contract was executed.

26. Award Amount - Enter the contract award amount as stated in the executed contract.

27. Local Agency Representative’s Signature - The person completing this section of the form for the Local Agency must sign their name to certify that the information in this and the Contractor Section of this form is complete and accurate.

28. Date - Enter the date the DBE commitment form is signed by the Local Agency Representative.

29. Local Agency Representative’s Name - Enter the name of the Local Agency Representative certifying the contractor’s DBE commitment form.

30. Phone - Enter the area code and phone number of the person signing the contractor’s DBE commitment form.

31. Local Agency Representative Title - Enter the position/title of the Local Agency Representative certifying the contractor’s DBE commitment form.

Page 394 of 672 ends

Local Assistance Procedures Manual Exhibit 9-I
DBE Confirmation
F-28 January 2023
EXHIBIT 9-I: DISADVANTAGED BUSINESS ENTERPRISE (DBE) CONFIRMATION

FEDERAL PROJECT NUMBER
CRAL-5363(013)

NAME OF DBE BUSINESS

NAME OF DBE REPRESENTATIVE

DBE CERTIFICATION NUMBER

NAME OF BIDDER

NAME OF PRIME CONTRACTOR IF DIFFERENT FROM THE BIDDER

NAME OF REPRESENTATIVE OF PRIME CONTRACTOR
DATE
Bid Item Number Item of work and description of services to be subcontracted or materials to be provided1 Amount ($)

1 If 100% of an item is not to be performed or furnished by the DBE, describe the exact portion of the item to be performed or furnished.

DBE firms can use this form as a written confirmation or use an equivalent form. Written confirmation must be submitted no later than 4 pm on the 5th day after bid opening.

Total
As an authorized representative of a certified disadvantaged business enterprise, I confirm if the bidder is awarded the contract, my business will enter into a contractual agreement with the bidder or prime contractor to perform the type and dollar amount of work shown on the DBE Commitment form.

Signature of DBE’s Authorized Representative
Printed Name of DBE’s Authorized Representative
Title of DBE’s Authorized Representative

Date

Page 395 of 672 ends

Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Efforts
July 23, 2015
F-29
EXHIBIT 15-H: PROPOSER/CONTRACTOR GOOD FAITH EFFORTS
Cost Proposal Due Date ___________________ PE/CE
Federal-aid Project No(s). CRAL-5363(013) Bid Opening Date ___________________ CON The City of Los Alamitos established a Disadvantaged Business Enterprise (DBE) goal of 17% for this contract. The information provided herein shows the required good faith efforts to meet or exceed the DBE contract goal.

Proposers or bidders submit the following information to document their good faith efforts within five (5) calendar days from cost proposal due date or bid opening. Proposers and bidders are recommended to submit the following information even if the Exhibit 10-O1: Consultant Proposal DBE Commitments or Exhibit 15-G: Construction Contract DBE Commitment indicate that the proposer or bidder has met the DBE goal. This form protects the proposer’s or bidder’s eligibility for award of the contract if the administering agency determines that the bidder failed to meet the goal for various reasons, e.g., a DBE firm was not certified at bid opening, or the bidder made a mathematical error.

The following items are listed in the Section entitled “Submission of DBE Commitment” of the Special Provisions, please attach additional sheets as needed:

A. The names and dates of each publication in which a request for DBE participation for this project was placed by the bidder (please attach copies of advertisements or proofs of publication):

Publications Dates of Advertisement

B. The names and dates of written notices sent to certified DBEs soliciting bids for this project and the dates and methods used for following up initial solicitations to determine with certainty whether the DBEs were interested (please attach copies of solicitations, telephone records, fax confirmations, etc.):

Names of DBEs Solicited Date of Initial Solicitation Follow Up Methods and Dates

Page 396 of 672 ends

Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Efforts
July 23, 2015
F-30
C. The items of work made available to DBE firms including those unbundled contract work items into economically feasible units to facilitate DBE participation. It is the bidder's responsibility to demonstrate that sufficient work to facilitate DBE participation in order to meet or exceed the DBE contract goal.

D. The names, addresses and phone numbers of rejected DBE firms, the reasons for the bidder's rejection of the DBEs, the firms selected for that work (please attach copies of quotes from the firms involved), and the price difference for each DBE if the selected firm is not a DBE:

Names, addresses and phone numbers of rejected DBEs and the reasons for the bidder's rejection of the DBEs:

Names, addresses and phone numbers of firms selected for the work above:

E. Efforts (e.g., in advertisements and solicitations) made to assist interested DBEs in obtaining information related to the plans, specifications and requirements for the work which was provided to DBEs:

Items of
Work
Proposer or Bidder
Normally Performs Item
(Y/N)
Breakdown of
Items
Amount
($)
Percentage
Of
Contract

Page 397 of 672 ends

Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Efforts
July 23, 2015
F-31
F. Efforts (e.g., in advertisements and solicitations) made to assist interested DBEs in obtaining bonding, lines of credit or insurance, necessary equipment, supplies, materials, or related assistance or services, excluding supplies and equipment the DBE subcontractor purchases or leases from the prime contractor or its affiliate:

G. The names of agencies, organizations or groups contacted to provide assistance in contacting, recruiting and using DBE firms (please attach copies of requests to agencies and any responses received, i.e., lists, Internet page download, etc.):

Name of Agency/Organization Method/Date of Contact Results H. Any additional data to support a demonstration of good faith efforts:

Page 398 of 672 ends

SIGNING AND STRIPING GENERAL NOTES: R E V I S I O N S R E F E R E N C E S 2401 East Katella Ave, Suite 450, Anaheim, California 92806 714/978-8200 fax 714/978-8299 USER: kevin.smith
FILE: W:\WE-CA\Los Alamitos, City of\110184.12-Bloomfield\900-PS&E\901-Plans\PL-01-TITLE.NEW.dwg DATE: Oct 30, 2023 - 12:59pm Know what'sbelow. Callbefore you dig. R ________

Page 399 of 672 ends

CONSTRUCTION NOTES: LEGEND E D D SS SS S S R E V I S I O N S R E F E R E N C E S 2401 East Katella Ave, Suite 450, Anaheim, California 92806 714/978-8200 fax 714/978-8299 USER: kevin.smith
FILE: W:\WE-CA\Los Alamitos, City of\110184.12-Bloomfield\900-PS&E\901-Plans\PL-01-BLOOMFIELD.dwg DATE: Oct 30, 2023 - 1:17pm Know what'sbelow. Callbefore you dig. R ________

Page 400 of 672 ends

CONSTRUCTION NOTES: LEGEND R E V I S I O N S R E F E R E N C E S 2401 East Katella Ave, Suite 450, Anaheim, California 92806 714/978-8200 fax 714/978-8299 USER: kevin.smith
FILE: W:\WE-CA\Los Alamitos, City of\110184.12-Bloomfield\900-PS&E\901-Plans\PL-02-DETAIL.dwg DATE: Oct 30, 2023 - 1:14pm Know what'sbelow. Callbefore you dig. R ________

Page 401 of 672 ends

E
D
D

R E V I S I O N S R E F E R E N C E S
2401 East Katella Ave, Suite 450, Anaheim, California 92806 714/978-8200 fax 714/978-8299 USER: kevin.smith FILE: W:\WE-CA\Los Alamitos, City of\110184.12-Bloomfield\900-PS&E\901-Plans\PL-STRIPE-04-BLOOMFIELD.dwg DATE: Oct 30, 2023 - 1:18pm Know what'sbelow.

Callbefore you dig.

R
LEGEND

STRIPING CONSTRUCTION NOTES SIGNING AND STRIPING GENERAL NOTES

KATELLA AVE BLOOMFIELD ST FLORISTA ST

KATELLA AVE

Page 402 of 672 ends

City of Los Alamitos

CITY COUNCIL AGENDA REPORT
MEETING DATE: November 20, 2023 ITEM NUMBER: 11L
To: Mayor Tanya Doby & Members of the City Council
Presented By: Chris Kelley, City Engineer
Subject: Award of Plans and Specifications for the Demolition of Los Alamitos Television Production (LATV) Building at 10921 Oak Street Project (CIP No. 22/23-04)

SUMMARY
This item recommends awarding a bid to begin the demolition of the Los Alamitos Television (LATV)/Public Works (PW) Building at 10921 Oak Street Project (CIP No. 22/23-04).

RECOMMENDATION

1. Award construction for the LATV/PW Building at 10921 Oak Street Project (CIP No. 22/23-04) in the amount of $104,671.00 to Unlimited Environmental, Inc.; and,

2. Authorize the Mayor to execute the contract with Unlimited Environmental, Inc. for the LATV/PW Building at 10921 Oak Street Project (CIP No. 22/23-04); and

3. Authorize the City Engineer to add work and execute change orders in an amount not to exceed the contingency reserve of 20% or $20,935.00.

BACKGROUND
The City-owned LATV/PW building located at 10921 Oak Street will be developed in the future and the City desires to have the existing single-story building demolished.

Page 403 of 672 ends

The demolition of the site will occur in one phase, involving the demolition of the existing building and the demolition of substructures, foundations, and underground utility service lines.

The existing surface will be restored with a secured gravel surface. Abatement of asbestos and lead has already been performed and the site is ready for demolition.

After the LATV/PW building is removed, the City will explore options for the use of the site. The project will also include the installation of an 8-foot-high chain link fence with black plastic slats around the perimeter of the existing building footprint to secure the site. Landscape-grade gravel rocks will be installed to stabilize the ground surface.

DISCUSSION
Project Bid Results
Notices announcing the solicitation of bids for this project were posted in the local publications, consisting of the Event News-Enterprise and F.W. Dodge Publication.

Bids for the project were publicly opened on October 19, 2023 at 11:00 a.m. From the three (9) total bids received, it was determined that the lowest responsible bid submitted was from Unlimited Environmental, Inc. with a total bid amount of $104,671.00. The bid results are provided below:

Page 404 of 672 ends

Unlimited Environmental, Inc $ 104,671.00
ASR Demolition $ 109,803.92
Balandra Demolition $ 119,000.00
Resource Environmental, Inc $ 122,000.00
3M Construction Corporation $ 112,755.46
TVR Construction Engineering $ 130,510.00
LCR Earthwork & Engineering $ 131,800.00
Interior Demolition $ 132,786.00
UBD Inc $ 155,777.00
Average $ 124,344.82
The following represents an approximate timeline for the completion of the project, which consists of building demolition and soil stabilization. • 11/20/2023 Award of Contract – Council Meeting
• 12/11/2023 Start of construction
• 02/19/2024 End of construction

FISCAL IMPACT
The total budget for the project is $225,000.00 The budget for the project was bid at $104,671.00 with a 20% contingency of $20,935 for a total of $125,606. An additional $99,394 for abatement, design/engineering support, contingency, advertisement, and construction management brings the total project cost to $225,000.

Budget Fiscal Year Source Amount
2022-2023 Building Fund $ 75,000.00
2023-2025 General Fund $150,000.00
Project Total $225,000.00
Attachment: 1. CIP 22-23-04 DEMOLITION OF LATV - CONTRACT AND SPECIFICATIONS

2. CIP 22-23-04 DEMOLITION OF LATV - PLANS

3. CIP 22-23-04 BID PROPOSAL - Unlimited Environmental, Inc.

4. CIP 22-23-04 DEMOLITION OF LATV - BID ANALYSIS

5. CIP 22-23-04 DEMOLITION OF LATV - AGREEMENT

Page 405 of 672 ends

CITY OF LOS ALAMITOS

CONTRACT DOCUMENTS AND SPECIFICATIONS
FOR

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
AUGUST 2023
NOTICE TO THE BIDDERS:

1. Bids will be received electronically through BidNet Direct (http://cityoflosalamitos.org/517/Bid-Opportunities).

2. Bid bond required – 10% of bid amount to be submitted to the City Clerk’s Office.

3. Bids must be received by 11:00 a.m. on the 19th day of October 2023

Page 406 of 672 ends

This page is intentionally left blank.

Page 407 of 672 ends

CITY OF LOS ALAMITOS

SPECIFICATIONS FOR

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

GENERAL REQUIREMENTS AND TECHNICAL PROVISIONS
PREPARED BY:

Willdan Engineering
2401 East Katella Avenue, Suite 300
Anaheim, Ca 92806
(714) 978-8200

FOR THE CITY OF LOS ALAMITOS

PUBLIC WORKS DIVISION

DEVELOPMENT SERVICES DEPARTMENT

Page 408 of 672 ends

This page is intentionally left blank.

Page 409 of 672 ends

TABLE OF CONTENTS

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

SECTION
NOTICE INVITING BIDS .......................................................................................................................... A INSTRUCTIONS TO BIDDERS .................................................................................................................. B PROPOSAL INFORMATION AND DOCUMENTS .................................................................................. C CONTRACT INFORMATION AND DOCUMENTS ................................................................................ D STANDARD SPECIFICATIONS ................................................................................................................. E SPECIAL PROVISIONS .............................................................................................................................. F RECYCLING OF MATERIALS ................................................................................................................. G DEMOLITION AND IMPROVEMENTS PLANS ................................................................. APPENDIX A

Page 410 of 672 ends

This page is intentionally left blank.

Page 411 of 672 ends

SECTION A – Page 1

NOTICE INVITING BID

SECTION A

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

NOTICE INVITING BIDS

Page 412 of 672 ends

SECTION A – Page 2

NOTICE INVITING BID
This page is intentionally left blank.

Page 413 of 672 ends

SECTION A – Page 3

NOTICE INVITING BID

NOTICE INVITING BIDS

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
PUBLIC NOTICE IS HEREBY GIVEN that the City of Los Alamitos as AGENCY, invites electronic bids for the above stated project. Bids will be received electronically through BidNet Direct (http://cityoflosalamitos.org/517/Bid-Opportunities). A bid received after the time set for the bid opening shall not be considered. Bidders are required to submit (upload) all items listed in SECTION C including acknowledgement of all addendums.

Bids will be received up to the hour of 11:00 a.m., on the 19th day of October, 2023 and will be opened virtually at that time. If you would like to attend the bid opening, it will be accessible through Teams Meet using Meeting ID 259 612 665 032 and Passcode i4SuHv.

The City of Los Alamitos proposes to demolish the Los Alamitos Television Production Building located at 10921 Oak Street, install chain link fence with slats, site grading, and placement of ¾” pea gravel.

In accordance with the provisions of California Public Contract Code § 3300, and Business and Professions Code § 7028.15(e), the Agency has determined that the contractor shall possess a valid Class A or Class C21 contractor’s license at the time that the contract is awarded. Failure to possess the specified license shall render a bidder’s bid as non-responsive and shall bar award of the contract to any bidder not possessing the specified license at the time of the award.

CONTRACTORS ARE REQUIRED BY LAW TO BE LICENSED AND REGULATED BY THE CONTRACTORS’ STATE LICENSE BOARD. ANY QUESTIONS CONCERNING A CONTRACTOR MAY BE REFERRED TO THE REGISTRAR, CONTRACTORS’ STATE LICENSE BOARD, P.O. BOX 2600, SACRAMENTO, CA 95826. At the time the contract is awarded, the contractor shall be properly licensed in accordance with the laws of this state. The first payment for work or material shall not be made unless and until the Registrar of Contractors verifies to the Agency that the records of the Contractors’ State License Board indicate that the contractor was properly licensed at the time the contract was awarded. Any bidder or contractor not so licensed shall be subject to all legal penalties imposed by law including, but not limited to, any appropriate disciplinary action by the Contractors’ State Board. Failure of the bidder to obtain proper and adequate licensing for an award of a contract shall constitute a failure to execute the contract and shall result in the forfeiture of the security of the bidder. (Public Contract Code § 20103.5)
Bids must be prepared on the approved bid forms in conformance with INSTRUCTIONS TO BIDDERS and must be submitted electronically on BidNet Direct (BidNet) , accessible through the Agency’s webpage at http://cityoflosalamitos.org/517/Bid-Opportunities where each prospective bidder must first register as a vendor through the Agency’s BidNet portal. Contract documents, plans, and specifications will be available for review on BidNet. All relevant materials shall be obtained from the link above. The Agency’ is not responsible for and accepts no liability in the event a response is late due to any network, internet or any other technical problem or interruption. The bidder is solely responsible for “on time” submission of their electronic bid. The Agency will only consider bids that have been transmitted successfully and have been issued an e-bid confirmation number. Bidders experiencing any technical difficulties with the bid submission process may contact BidNet at (800)835-4603.

Page 414 of 672 ends

SECTION A – Page 4

NOTICE INVITING BID
A bid guarantee in the amount of 10% of the total must be submitted to the City Clerk prior to the bid submission deadline. ORIGINAL SEALED COPY OF BIDDER’S BOND MUST BE SUBMITTED TO THE CITY CLERK’S OFFICE, ATTN. WINDMERA QUINTANAR, 3191 KATELLA AVENUE, LOS ALAMITOS, CA 90720. SEALED ENVELOPE BEARING THE BID BOND SHOULD BE CLEARLY MARKED “ON-CALL SERVICES FOR CONCRETE REMEDIATION.” The bid bond shall be ten percent (10%) of the bid in the following form: (a) cash; (b) a cashier’s check made payable to the City of Los Alamitos; (c) a certified check made payable to the City of Los Alamitos; or (d) a bidder’s bond executed by an admitted surety insurer made payable to the City of Los Alamitos. Bidder may upload electronic bond that meets Agency requirements. Such security shall be forfeited should the successful bidder to whom the contract is awarded fails to timely execute the contract and to deliver the necessary bonds and insurance certificates as specified in the contract documents.

To the extent applicable, at any time during the term of the Agreement for the proposed project, the successful bidder may, at its own expense, substitute securities equivalent to the amount withheld as retention (or the retained percentage) in accordance with Public Contract Code § 22300.

Pursuant to California Civil Code § 3247, a payment bond is required to be submitted for all projects estimated in excess of $25,000.00. The Agency has determined that the proposed project is a public works subject to the provisions of Labor Code § 1720 thereby requiring the Contractor to pay the prevailing wage rates for all work performed under the Contract.

The Agency reserves the right to reject any and all bids.

Questions or Requests for Information (RFIs) or interpretations are due ten (10) days before the time announced for the opening of the bids and shall be submitted on the BidNet portal. If you have any questions, please contact Chris Kelley, at (562) 357-5411 or via email [email protected] or Vandine Ouk at (562) 357- 4511 or via email at [email protected].

BY ORDER OF the City Council of the City of Los Alamitos, California.

Page 415 of 672 ends

SECTION B – Page 1

INSTRUCTION TO BIDDERS

SECTION B

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

INSTRUCTIONS TO BIDDERS

Page 416 of 672 ends

SECTION B – Page 2

INSTRUCTION TO BIDDERS

INSTRUCTIONS TO BIDDERS

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
B1.01 INSPECTION OF SITE OF WORK
Bidders are required to inspect the site of the work in order to satisfy themselves, by personal examination or by such other means as they may prefer, of the location of the proposed work and as to the actual conditions of and at the site of work. If, during the course of his/her examination, a bidder finds facts or conditions which appear to him/her to conflict with the letter or spirit of the contract documents, or with any other data furnished him/her, he/she may apply to the Agency in writing in accordance with B1.04 INTERPRETATION OF CONTRACT DOCUMENTS for additional information and explanation before submitting his/her bid.

The submission of a proposal by the bidder shall constitute the acknowledgment that, if awarded the contract, he/she has relied and is relying on his/her own examination of (a) the site of the work, (b) the access to the site, and (c) all other data, matters, and things requisite to the fulfillment of the work and on his/her own knowledge of existing services and utilities on and in the vicinity of the site of the work to be constructed under the contract, and not on any representation or warranty of the Agency. No claim for additional compensation will be allowed which is based upon a lack of knowledge of these items.

B1.02 EXAMINATION OF CONTRACT DOCUMENTS
Each bidder shall thoroughly examine and be familiar with legal and procedural documents, general conditions, specifications, drawings, and addenda (if any). The submission of a proposal shall constitute an acknowledgment upon which the Agency may rely that the bidder has thoroughly examined and is familiar with the contract documents. The bidders’ attention is directed to the need, if any, for special invoicing for this project. The failure or neglect of a bidder to receive or examine any of the contract documents shall in no way relieve him/her from any obligations with respect to his/her proposal or to the contract. No claim for additional compensation will be allowed which is based upon a lack of knowledge of any contract document.

B1.03 CONTRACT PERIOD/CONSTRUCTION COMPLETION DATE
Bidder’s attention is called to the provisions set forth in SECTION E, STANDARD SPECIFICATIONS, particularly those pertaining to the contract period and liquidated damages for avoidable delays.

The Contractor shall begin work within fifteen (15) calendar days after the date of the Notice to Proceed and shall diligently prosecute said work to completion before the expiration 25 WORKING DAYS. The Contractor shall pay to the Agency the sum of $500.00 per day, for each and every calendar days delay in finishing the work in excess of the number of working days prescribed above.

B1.04 INTERPRETATION OF CONTRACT DOCUMENTS
No oral interpretations will be made to any bidder as to the meaning of the contract documents. Requests for an interpretation shall be made in writing and delivered to the Agency at least ten (10) days before the time announced for opening the proposals. Interpretations by the Agency will be in the form of addenda to the contract documents and, when issued, will be sent as promptly as is practical to all parties to whom the contract documents have been issued. Agency makes no guarantee that all bidders will receive all addenda.

Page 417 of 672 ends

SECTION B – Page 3

INSTRUCTION TO BIDDERS
Copies of addenda will be made available for inspection at the office where contract documents are on file for inspection as indicated on the Invitation for Bids. All such addenda shall become part of the contract.

All questions shall be addressed to Chris Kelley, City of Los Alamitos, (562)357-5411.

B1.05 SOIL INFORMATION
Soil reports have not been prepared for this project.

B1.06 PROPOSAL
Proposals shall be made on the forms enclosed in SECTION C of these specifications with or without removal from the bound contract documents. All proposals shall give the prices proposed, both in words and in numbers, shall give all other information requested herein, and shall be signed by the bidder or his/her authorized representative, with his/her address. If the proposal is made by an individual, his/her name, signature and mailing address must be shown; if made by firm or partnership, the name and mailing address of the firm or partnership and the signature of at least one of the general partners must be shown; if made by a corporation, the proposal shall show the name of the state under the laws of which the corporation is chartered, the name and mailing address of the corporation, and the name and title of the person who signs on behalf of the corporation. If the proposal is made by a corporation, a certified copy of the bylaws or resolution of the board of directors of the corporation shall be furnished demonstrating the authority of the officer signing the proposal to execute contracts on behalf of the corporation.

Bidders are warned against making erasures or alterations of any kind, and proposals which contain omissions, erasures or irregularities of any kind may be rejected. No oral, telegraphic, or telephonic proposals or modifications will be considered.

In conformance with the Business and Profession Code, § 7028.15, the Contractor must state clearly his/her license number and expiration date. In addition, he/she shall sign a statement that these representations were made under the penalty of perjury. This statement shall be made on the EXPERIENCE STATEMENT in SECTION C.

The contractor will be required to pay prevailing wage pursuant to California Law, including California Labor Code §§ 1770 et seq. Copies of the prevailing rate of per diem wages are on file at the offices of the Agency.

B1.07 ADDENDA
Each proposal shall include specific acknowledgment in the space provided on SECTION C - BID PROPOSAL of receipt of all addenda issued during the bidding period. Failure to so acknowledge may result in the proposal being rejected as not responsive.

B1.08 BID PRICES
Bid prices shall include everything necessary for the completion of construction and fulfillment of the contract including, but not limited to, furnishing all materials, equipment, tools, plant and other facilities and all management, superintendence, labor, and services, except as may be provided otherwise in the contract documents. In the event of a difference between a price quoted in words and a price quoted in numbers for the same quotation, the words shall be the amount bid.

In preparing bid prices, bidder represents that he/she has carefully examined the Contract Documents and the site where the work is to be performed and that he/she has familiarized himself with all local conditions

Page 418 of 672 ends

SECTION B – Page 4

INSTRUCTION TO BIDDERS
and federal, state, and local laws, ordinances, rules, and regulations that may affect the performance of the work in any manner. The bidder further represents that he/she has studied all surveys and investigation reports about subsurface and physical conditions pertaining to the job site, that he/she has performed such additional surveys and investigations as he/she deems necessary to complete the work at his/her bid price, and that he/she has correlated the results of all such data with the requirements of the Contract Documents.

The submittal of a bid shall be conclusive evidence that the bidder has investigated and is satisfied as to the conditions to be encountered, including locality, uncertainty of weather and all other contingencies, and as to the character, quality, quantities, and scope of the work.

The plans and specifications for the work show subsurface conditions or otherwise hidden conditions as the Design Engineer supposes or believes them to exist but is not intended or to be inferred that the conditions as shown thereon constitute a representation that such conditions are actually existent. Except as otherwise specifically provided in the Contract Documents, the Agency, the Design Engineer and their consultants or agents shall not be liable for any loss sustained by the Contractor as a result of any variance of such conditions as shown on the plans and the actual conditions revealed during the progress of the work or otherwise.

The Contractor shall perform an independent take-off of the plans and bid accordingly. Quantities listed in the BID SCHEDULE in SECTION C are intended only as a guide for the Contractor as to the anticipated order of magnitude of work. Contractor shall be responsible for verifying all estimated quantities.

Contractor will be reimbursed for the quantity of items actually installed as required by the Contract Documents and shown on the plans to neat line and grade.

The Contractor will not be reimbursed for unauthorized work performed outside of that required by the Contract Documents.

B1.09 TAXES
No mention shall be made in the proposal of sales tax, use tax, or any other tax, as all amounts bid will be deemed and held to include any such taxes which may be applicable.

B1.10 RECOGNITION OF BONDING COMPANIES
All bonding companies used by the Contractor in this contract must be recognized by the Federal Government within Circular 570. All proposals or contracts received that include bonds posted by bonding companies not recognized in Circular 570 will result in the disqualification of the bid proposal and forfeiture of the bid bond.

B1.11 QUALIFICATION OF BIDDERS
Each bidder shall be skilled and regularly engaged in the general class or type of work called for under the contract. A statement setting forth his/her experience shall be submitted by each bidder on the EXPERIENCE STATEMENT form provided in SECTION C.

Each bidder shall possess a valid Contractor’s License issued by the Contractor’s State License Board at the time his/her bid is submitted. The class of license shall be applicable to the work specified in the contract. Each bidder shall also have no less than five (5) years’ experience in the magnitude and character of the work bid.

It is the intention of the Agency to award a contract to a bidder who furnished satisfactory evidence that he/she has the requisite experience and ability, and that he/she has sufficient capital, facilities, and plant to enable him/her to prosecute the work successfully and properly, and to complete it within the time stated in the contract.

Page 419 of 672 ends

SECTION B – Page 5

INSTRUCTION TO BIDDERS
To determine the degree of responsibility to be credited to the bidder, the Agency will weigh any evidence that the bidder has performed satisfactorily other contracts of like nature, magnitude and comparable difficulty and comparable rates of progress. If in the opinion of the Agency, a bidder is determined to be insufficiently qualified, then that bidder will not be considered for award of the contract.

B1.12 DESIGNATION OF SUPPLIERS AND SUBCONTRACTORS
Each proposal shall have listed on the DESIGNATION OF SUPPLIERS AND SUBCONTRACTORS form provided in SECTION C the name and address of each subcontractor to whom the bidder proposes to sublet portions of the work in excess of one-half percent of the total amount of his/her bid. For the purpose of this paragraph, a subcontractor is defined as one who contracts with the Contractor to furnish materials and labor, or labor only for the performance of work at the site of the work or who will specially fabricate a portion of the work off the site pursuant to detailed drawings in the contract documents.

Public Contract Code § 4104 requires all bidders to list subcontractors who will perform work in excess of ½% of the total bid, or in the case of streets and highways, ½% or $10,000, whichever is greater.

Public Contract Code § 6109 prohibits a contractor from performing work with a subcontractor who is debarred pursuant to Labor Code §§ 1777.1 or 1777.7.

B1.13 PROPOSAL GUARANTEE
The proposal shall be accompanied by a proposal guarantee bond duly completed on the form provided herewith by a guarantee company authorized to carry on business in the State of California for payments to the Agency in the sum of at least 10% of the total amount of the bid proposal, or alternatively by a certified or cashier’s check payable to the Agency, or cash, in the sum of at least 10% of the total amount of the bid proposal. The amount payable to the Agency under the proposal guarantee shall be forfeited to the Agency in case of failure or neglect of the bidder to furnish, execute and deliver to the Agency the required bonds, evidence of insurance and to enter into, execute and deliver to the Agency the agreement on the form provided herewith, within ten (10) days after being notified in writing by the Agency that the award has been made and the agreement is ready for execution.

B1.14 MODIFICATION OF PROPOSAL
A modification of a bid proposal already received will be considered only if the modification is received before the time announced for the opening of bids. All modifications shall be made in writing, executed, and submitted in the same form and manner as the original bid proposal.

B1.15 WITHDRAWAL OF PROPOSAL
A proposal may be withdrawn by a written request signed by the bidder. Such requests must be delivered to the Agency’s designated official prior to the bid opening hour stipulated in SECTION A – NOTICE INVITING SEALED BIDS. Proposals may not be withdrawn after that time without forfeiture of the proposal guarantee. The withdrawal of a proposal will not prejudice the right of the bidder to submit a new proposal, providing there is time to do so.

B1.16 POSTPONEMENT OF BID OPENING
The Agency reserves the right to postpone the date and time for opening of bids at any time prior to the date and time announced in SECTION A–NOTICE INVITING SEALED BIDS.

B1.17 DISQUALIFICATION OF BIDDERS

Page 420 of 672 ends

SECTION B – Page 6

INSTRUCTION TO BIDDERS
If there is reason to believe that collusion exists among the bidders, none of the bids of the participants in such collusion will be considered. In the event that any bidder acting as a prime Contractor has an interest in more than one proposal, all such proposals will be rejected, and the bidder will be disqualified. This restriction does not apply to subcontractors or suppliers who may submit quotations to more than one bidder, and while doing so, may also submit a formal proposal as a prime Contractor.

B1.18 REJECTION OF PROPOSALS
The Agency reserves the right to reject any and all proposals, to waive any irregularity, and to reject any proposals which are incomplete, obscure or irregular; any proposals which omit a bid on any one or more items on which bids are required; which omit unit prices if unit prices are required; in which unit prices are unbalanced in the opinion of the Agency; which are accompanied by insufficient or irregular bid security; or which are from bidders who have previously failed to perform properly or to timely complete contracts of any nature.

B1.19 AWARD OF CONTRACT
The Contract will be awarded, if at all, to the lowest responsible and responsive bidder, whose bid proposal is not rejected for cause by the Agency. However, until an award is made, the Agency reserves right will be reserved to reject any or all bids, and to waive technical errors or discrepancies, if to do so is deemed to best serve the interests of the Agency. In no event will an award be made until all necessary investigations are made as to the responsibility and qualifications of the bidder to whom it is proposed to make such an award.

Each bidder’s attention is directed to the possibility that the award of the project may be delayed for various reasons. The Agency reserves the right to delay the award of the project for 45 calendar days. After 45 calendar days, the low bidder may at any time request release from its bid without penalty.

The acceptance of a proposal will be evidenced by a Notice of Award of Contract in writing, delivered by mail to the bidder whose proposal is accepted. No other act of the Agency shall constitute acceptance of a proposal. The award of contract shall obligate the bidder whose proposal is accepted to furnish a performance bond, payment bond and maintenance bond, as well as evidence of insurance and to execute the contract set forth herein.

B1.20 RETURN OF PROPOSAL GUARANTEES
Within ten (10) calendar days after the bids are opened, the Agency will release the proposal guarantees accompanying the proposals which are not to be considered in making the award. Proposal guarantees for the two lowest bidders will be held until the contract has been fully executed, after which they will be returned to the respective bidders.

B2.21 EXECUTION OF CONTRACT
The contract agreement shall be executed in duplicate by the successful bidder and returned, together with the contract bonds and evidence of insurance, within ten (10) calendar days after the notification of the contract award by the Agency in writing. In case of failure of the successful bidder to execute the contract agreement within ten (10) calendar days after such notice, or any subsequent extension approved by Agency, the Agency at its option may consider the bidder in default, in which case the bid bond or proposal guarantee accompanying the bid shall become the property of the Agency. After execution by the Agency, one original contract shall be returned to the Contractor.

Page 421 of 672 ends

SECTION B – Page 7

INSTRUCTION TO BIDDERS
B1.22 FLEXIBILITY OF BID SCHEDULE
It is the intent of the Agency to award a contract to the lowest responsible and responsive bidder and the flexibility shown in the bid schedule is necessary to ensure a project within the Agency’s budget limits and constraints.

B1.23 SB 854
• No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
• No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
• This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

Page 422 of 672 ends

SECTION C

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

PROPOSAL INFORMATION AND DOCUMENTS

PROPOSAL INFORMATION AND DOCUMENTS

BID PROPOSAL

BID SCHEDULE

BID BOND

BID GUARANTEE

NON-COLLUSION AFFIDAVIT

BIDDER INFORMATION

EXPERIENCE STATEMENT

DESIGNATION OF SUPPLIERS AND SUBCONTRACTORS
SECTION C – Page 1

PROPOSAL INFORMATION AND DOCUMENT

Page 423 of 672 ends

BID PROPOSAL

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
The undersigned, as bidder, declares that he/she has examined all of the contract documents and specifications contained in this project manual for the above referenced project, and that he/she will contract with the Agency on the form of contract provided herewith to do everything necessary for the fulfillment of this contract at the price, and on the terms and conditions therein contained.

The following are included and are to be considered as forming a part of this proposal: BID PROPOSAL, BID SCHEDULE, BID BOND, NONCOLLUSION AFFIDAVIT, BID GUARANTEE (if submitted in lieu of Bid Bond), BIDDER INFORMATION, EXPERIENCE STATEMENT, DESIGNATION OF SUPPLIERS & SUBCONTRACTORS, BIDDER’S STATEMENT REGARDING INSURANCE COVERAGE, and STATEMENT REGARDING CONTRACTOR’S LICENSING LAWS.

Contractor acknowledges receipt and inclusion of addenda to into this bid proposal and the contract documents.

Attached is a Bid Bond duly completed by a guarantee company authorized to carry on business in the State of California in the amount of at least 10% of the total amount of this proposal, or alternatively, there is attached a certified or cashier’s check payable to the Agency or evidence of a cash payment to the Agency, in the amount of at least 10% of the total amount of our proposal.

If this proposal is accepted, we agree to sign the contract form and to furnish the Performance Bond and the Payment Bond (each to be 100% of the bid amount), the Maintenance Bond (to be 50% of the bid amount), and the required evidence of insurance within ten (10) calendar days after receiving written Notice of Award of Contract.

We further agree if our proposal is accepted and a contract for the performance of the work is entered into with the Agency, to so plan the work and to prosecute it with such diligence that all of the work shall be completed within the time stipulated in SECTION E - TIME OF COMPLETION.

NAME OF BIDDER:

MAILING ADDRESS:

STATE OF INCORPORATION:

AUTHORIZED SIGNATURE:

TITLE:

DATE:
(If Company is a corporation, provide corporate resolution per B 1.06 PROPOSAL.) SECTION C – Page 2

PROPOSAL INFORMATION AND DOCUMENT

Page 424 of 672 ends

BID SCHEDULE

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
The cost of all labor, services, material, equipment, and installation necessary for the completion of the work itemized under this schedule, even though not shown, or specified, shall be included in the unit price for the various items shown herein. For a description of the work associated with each bid item, see SECTION E–SPECIAL PROVISIONS. The Agency reserves the right to increase or decrease the quantity of any item or omit items as may be necessary, and the same shall in no way affect or void the contract, except those appropriate additions or deductions from the contract total price will be made at the stipulated unit price in accordance with these Contract Documents.

The Agency reserves the right to reject any and all bids, to waive any informality in a bid, and to make awards in the interest of the Agency.

The Contractor shall perform an independent take-off of the plans and bid accordingly. Quantities listed in this Bid Schedule are intended only as a guide for the Contractor asto the anticipated order of magnitude of work. The Contractor shall be responsible for verifying all estimated quantities. The Contractor will be reimbursed for the quantity of items actually installed as required by the Contract Documents, including addenda, and shown on the plans to neat line and grade.

The Contractor will not be reimbursed for work performed for his convenience, or as required to adapt to field conditions, or for unauthorized work performed outside of that required by the Contract Documents.

The Contractor shall be responsible for calculating and providing totals for the bid schedule. The proposal schedule shall include all costs for labor, services, material, equipment, and installation associated with completing the work in place per the plans, specifications, and details.

NAME OF BIDDER:

CONTRACTOR’S LICENSE NO.:

AUTHORIZED SIGNATURE:

TITLE:

DATE:

SECTION C – Page 3

PROPOSAL INFORMATION AND DOCUMENT

Page 425 of 672 ends

BID SCHEDULE (Continued)

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

BID SCHEDULE A
No. Item Description Estimated
Quantity
Unit Unit Price Item
Amount
1 Mobilization 1 LS $ $
2 Water Pollution Control 1 LS $ $
3 Irrigation System Modifications 1 LS $ $
4 Clearing and Grubbing 1 LS $ $
5 Demolition of the TV Production Building 1 LS $ $
6 Temporary 6' Chain Link Fence with Privacy
Screen & Straw Rolls 195 LF $ $
7 Grading (Flatten to 4" below reference point,
90% compaction) 1 LS $ $
8 Vegetation Control Fabric 4140 SQFT $ $
9 3/4" Size Landscape Grade Rocks, 4" Thick
(Locally Available) 80 TON $ $
10 Restore Lawn 430 SQFT $ $
11 8' High Chain Link Fence with Black Plastic
Slats 148 LF $ $
12 6' - 2"x2"x .25" Steel Square Tube /
Anchored to Block Wall / Field Welded to
Existing Steel Bars
12 LF $ $
Total
Bid Schedule A Total $ ______________________________________ Bid Schedule A Total (in words): __________________________________________________________ _______________________________________________________________________________________

The Contractor shall be responsible for calculating and providing unit prices for the schedule. The proposal schedule shall include all costs for services, labor, materials, equipment, and installation associated with completing the work in place per the plans, specifications, and details.

The City has the option to reject all bids with or without cause. The City also has the option to remove bid items at its discretion. If the City chooses to remove bid items, no bid price adjustment will be allowed.

For the purposes of determining the lowest responsible bidder, the Bid Schedule A Total shall be considered.
(Company Name of Bidder) (Date)
SECTION C – Page 4

PROPOSAL INFORMATION AND DOCUMENT

Page 426 of 672 ends

BID BOND

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
KNOW ALL MEN BY THESE PRESENTS that Bidder , as PRINCIPAL, and , as SURETY, are held and firmly bound unto the City of Los Alamitos as AGENCY, in the penal sum of
dollars ($ ), which is ten percent (10%) of the total amount bid by PRINCIPAL to AGENCY for the above stated project, for the payment of which sum, PRINCIPAL and SURETY agree to be bound, jointly and severally, firmly by these presents.

The SURETY, for value received, hereby stipulates, and agrees that the obligations of said SURETY and its BOND shall be in no way impaired or affected by any extension of the time within which the AGENCY may accept such Bid; and said SURETY does hereby waive notice of any such extension.

THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas PRINCIPAL is about to submit a bid to AGENCY for the above stated project, if said bid is rejected, or if said bid is accepted and a contract is awarded and entered into by PRINCIPAL in the manner and time specified, and PRINCIPAL provides the required payment and performance bonds and insurance coverages to AGENCY, then this obligation shall be null and void, otherwise it shall remain in full force and effect in favor of AGENCY.

IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seals this day of ., 2023.

PRINCIPAL*
SURETY*
*Provide BIDDER and SURETY name, address and telephone number and the name, title, address, and telephone number for their authorized representatives. Power of Attorney must be attached.

Subscribed and sworn to this day of , 2023.

NOTARY PUBLIC (SEAL)
SECTION C – Page 5

PROPOSAL INFORMATION AND DOCUMENT

Page 427 of 672 ends

BID GUARANTEE

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
Note: The following statement shall be used if other than a bid surety bond accompanies bid. “Accompanying this proposal is a money order*, certified check*, cashier’s check*, cash*, payable to the order of the City of Los Alamitos in the amount of
Dollars ($ ) which is at
least ten percent (10%) of the total amount of this bid. The proceeds of this bid guarantee shall become the property of the City of Los Alamitos provided this bid is accepted by said City, through action of its legally constituted contracting authorities, and the undersigned fails to execute a contract and furnish the required bonds and insurance within the stipulated time. Otherwise, the proceeds of this bid guarantee shall be returned to the undersigned.”
NAME OF BIDDER:

MAILING ADDRESS:

AUTHORIZED SIGNATURE:

TITLE:

DATE:
(*Delete the inapplicable words)
SECTION C – Page 6

PROPOSAL INFORMATION AND DOCUMENT

Page 428 of 672 ends

NON-COLLUSION AFFIDAVIT
The undersigned declares:

I am the of , the party making the foregoing
bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly, or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on [date], at [city], [state].

Signature of Declarant
Printed Name of Declarant
SECTION C – Page 7

PROPOSAL INFORMATION AND DOCUMENT

Page 429 of 672 ends

BIDDER INFORMATION

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
BIDDER certifies that the following information is true and correct:

Name of Bidder:
...........................................................................................................................................................

Business Address:
...........................................................................................................................................................

Telephone: .FAX:

E-mail:

Contractor’s License No.: Date License Issued: .

License Expiration Date:

The following are the names, titles, addresses, and phone numbers of all individuals, firm members, partners, joint venturers, and/or corporate officers having a principal interest in this proposal: (Name / Title / Address / Telephone)
Any voluntary or involuntary bankruptcy judgments against any principal having an interest in this proposal are as follows: (Type of Judgment / Date)
All current and prior DBA’s, aliases, and/or fictitious business names for any principal having an interest in this proposal are as follows: (Principal / DBA’s / Applicable Dates) Prior Disqualification
SECTION C – Page 8

PROPOSAL INFORMATION AND DOCUMENT

Page 430 of 672 ends

Has your firm ever been disqualified from performing work for any City, County, Public or Private Contracting entity? Yes / No . If yes, provide the following information. (If more than once, use separate sheets):

Date: Entity:

Location:

Reason:

Provide Status and any Supplemental Statement:

Has your firm been reinstated by this entity? Yes / No
Violations of Federal or State Law
A. Has your firm or its officers been assessed any penalties by any agency for noncompliance, violations of Federal or State labor laws and/or business or licensing regulations within the past five (5) years relating to your construction projects?
Yes / No: Federal / State:

If “yes”, identify and describe, (including status):

Have the penalties been paid? Yes / No:

B. Does your firm or its officers have any ongoing investigations by any AGENCY regarding violations of the State Labor Code, California Business and Professions Code or State Licensing laws? Yes / No: Codes / Laws: Section / Article:
................................................

If “yes”, identify and describe (including status):
........................................................................................................................................................... ...........................................................................................................................................................

SECTION C – Page 9

PROPOSAL INFORMATION AND DOCUMENT

Page 431 of 672 ends

I declare under penalty of perjury under the laws of the State of California that all of the representations made in this BIDDER INFORMATION are true and correct. Executed this day of , 2023, at ,
California.

Authorized Representative Signature and Title
SECTION C – Page 10

PROPOSAL INFORMATION AND DOCUMENT

Page 432 of 672 ends

EXPERIENCE STATEMENT

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
Pursuant to this BID PROPOSAL and QUALIFICATION OF BIDDERS, the following is a record of the Bidder’s experience in construction of a type similar in magnitude and character to that contemplated under this contract. Included in this section should be a complete list of references for similar projects in terms of scope of work, value of work, and time constraints. The Contractor must demonstrate that he/she has experience with this type of project and can manage this project effectively. If necessary, additional numbered pages can be attached to this page. The Contractor must be properly licensed to perform the work in this project as determined by the State Contractor’s License Board.

Project Title: Client:

Date: Project Value: Contact: Tel #
Description:

Subject to Federal Labor Standards: Yes No
Project Title: Client:

Date: Project Value: Contact: Tel #
Description:

Subject to Federal Labor Standards: Yes No
SECTION C – Page 11 PROPOSAL INFORMATION AND DOCUMENT

Page 433 of 672 ends

EXPERIENCE STATEMENT (Continued)

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
Project Title: Client:

Date: Project Value: Contact: Tel
#
Description:

Subject to Federal Labor Standards: Yes No
Project Title: Client:

Date: Project Value: Contact: Tel #
Description:

Subject to Federal Labor Standards: Yes No
I declare under penalty of perjury under the laws of the State of California that all of the representations made in this EXPERIENCE STATEMENT are true and correct. Executed this day of , 20 , at ,
California.

Authorized Representative Signature and Title
SECTION C – Page 12 PROPOSAL INFORMATION AND DOCUMENT

Page 434 of 672 ends

DESIGNATION OF SUPPLIERS AND SUBCONTRACTORS

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
The following is a list of subcontractors and suppliers, as defined in 2-3 SUBCONTRACTS of the Standard Specifications, who will perform work or provide materials of value in excess of one-half percent of the total bid price or $10,000, whichever is greater.

No subcontractor shall perform work in excess of the amount specified in 2-3 SUBCONTRACTS of the Standard Specifications, without the written approval of the Agency.

The Contractor is responsible to ensure that appropriate provisions are to be inserted in all subcontracts to bind subcontractors to the contract requirements as contained herein.

Each subcontractor must agree to comply with all applicable Federal, State, and local requirements.

Name and Address of
Subcontractor
Employer
Tax Id #
MBE/
WBE
(Y/N)
Work Subcontracted Portion of Work (% of Contract
Price)
These representations are made under the penalty of perjury under the laws of the State of California. The undersigned hereby certifies that each subcontractor has been notified in writing of its equal opportunity obligations.

NAME OF BIDDER:

AUTHORIZED SIGNATURE: Date:

SECTION C – Page 13 PROPOSAL INFORMATION AND DOCUMENT

Page 435 of 672 ends

SECTION D – Page 1

CONTRACT INFORMATION AND DOCUMENT

SECTION D

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

CONTRACT INFORMATION AND DOCUMENTS

CONTRACT INFORMATION AND DOCUMENTS

CONTRACT AGREEMENT

PAYMENT BOND

FAITHFUL PERFORMANCE BOND

MAINTENANCE BOND
WORKER’S COMPENSATION INSURANCE CERTIFICATE

INSURANCE ENDORSEMENT

STATEMENT REGARDING INSURANCE COVERAGE
STATEMENT REGARDING THE CONTRACTOR’S LICENSING LAWS

Page 436 of 672 ends

SECTION D – Page 2

CONTRACT INFORMATION AND DOCUMENT

ARTICLES OF AGREEMENT

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA

THIS DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC WORKS BUILDING , SPECIFICATION NO. CIP 22/23-04 AGREEMENT (“AGREEMENT”) is made and entered into for the above-stated project this day of _____ , 2023 (City Council Action Date Here), BY AND BETWEEN the City of Los Alamitos, a municipal corporation, hereafter designated as “AGENCY”, and CONTRACTOR’S BUSINESS NAME, a (State) (corporation,
partnership, limited liability company, or other business form), hereafter designated as “CONTRACTOR.”
WITNESSETH that AGENCY and CONTRACTOR have mutually agreed as follows:

ARTICLE I: Contract Documents
The contract documents for the DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC WORKS BUILDING, SPECIFICATION NO. CIP 22/23- 04 shall consist of the Notice Inviting Sealed Bids, Instructions To Bidders, Bid Proposal, Bid Schedule, Standard Specifications, Special Provisions, and all referenced specifications, details, standard drawings, and appendices; together with two signed copies of the AGREEMENT, two signed copies of required bonds; one copy of the insurance certificates, permits, notices, and affidavits; and also including any and all addenda or supplemental agreements clarifying, amending, or extending the work contemplated as may be required to ensure its completion in an acceptable manner (collectively referred to herein as the “Contract Documents”). All of the provisions of the Contract Documents are made a part hereof as though fully set forth herein.

ARTICLE II: Scope of Work
For and in consideration of the payments and agreements to be made and performed by AGENCY, CONTRACTOR agrees to furnish all materials and equipment and perform all work required for the above-stated project, and to fulfill all other obligations as set forth in the aforesaid contract documents.

AGENCY hereby employs CONTRACTOR to provide the materials, do the work, and fulfill the obligations according to the terms and conditions herein contained and referred to, for the prices provided herein, and hereby contracts to pay the same at the time, in the manner, and upon the conditions set forth in this AGREEMENT.

In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to this AGREEMENT, CONTRACTOR offers and agrees to assign to the AGENCY all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 (Section 16700, et seq.) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of

Page 437 of 672 ends

SECTION D – Page 3

CONTRACT INFORMATION AND DOCUMENT
goods, services, or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time the awarding body tenders final payment to CONTRACTOR, without further acknowledgment by the parties.

ARTICLE III: Compensation
A. CONTRACTOR agrees to receive and accept the prices set forth in the Bid Proposal and Bid Schedule as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder. In no event shall the total compensation and costs payable to CONTRACTOR under this Agreement exceed the sun of Dollars ($................... ,) unless specifically approved in advance and in writing by AGENCY Such compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the aforesaid Contract Documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work.

B. This AGREEMENT is subject to the provisions of Article 1.7 (commencing at Section 20104.50) of Division 2, Part 3 of the Public Contract Code regarding prompt payment of contractors by local governments. Article 1.7 mandates certain procedures for the payment of undisputed and properly submitted payment requests within 30 days after receipt, for the review of payment requests, for notice to Contractor of improper payment requests, and provides for the payment of interest on progress payment requests which are not timely made in accordance with that Article. This AGREEMENT hereby incorporates the provisions of Article 1.7 as though fully set forth herein.

C. At the request and expense of CONTRACTOR, securities equivalent to the amount withheld shall be deposited with AGENCY, or with a state or federally chartered bank in this state as the escrow agent, who shall then pay those moneys to CONTRACTOR upon Agency’s confirmation of CONTRACTOR’S satisfactory completion of this AGREEMENT. At any time during the term of this AGREEMENT CONTRACTOR may, at its own expense, substitute securities for funds otherwise withheld as retention (or the retained percentage) in accordance with Public Contract Code § 22300.

ARTICLE IV: Labor Code
AGENCY and CONTRACTOR acknowledge that this AGREEMENT is subject to the provisions of Division 2, Part 7, Chapter 1 (commencing with Section 1720) of the California Labor Code relating to public works and public agencies and agree to be bound by all the provisions thereof as though set forth fully herein. Full compensation for conforming to the requirements of the Labor Code and with other Federal, State, and local laws related to labor, and rules, regulations and ordinances which apply to any work performed pursuant to this AGREEMENT is included in the price for all contract items of work involved.

This AGREEMENT is further subject to prevailing wage law, including, but not limited to, the following:

A. The CONTRACTOR shall pay the prevailing wage rates for all work performed

Page 438 of 672 ends

SECTION D – Page 4

CONTRACT INFORMATION AND DOCUMENT
under the AGREEMENT. When any craft or classification is omitted from the general prevailing wage determinations, the CONTRACTOR shall pay the wage rate of the craft or classification most closely related to the omitted classification. The CONTRACTOR shall forfeit as a penalty to AGENCY $200.00, or any greater penalty provided in the Labor Code for each Calendar Day, or portion thereof, for each worker paid less than the prevailing wage rates for any work done under the AGREEMENT in violation of the provisions of the Labor Code whether such worker is employed in the execution of the work by CONTRACTOR or by any Subcontractor under CONTRACTOR. In addition, CONTRACTOR shall pay each worker the difference between such prevailing wage rates and the amount paid to each worker for each Calendar Day, or portion thereof, for which each worker was paid less than the prevailing wage rate.

B. CONTRACTOR shall comply with the provisions of Labor Code Section 1777.5 concerning the employment of apprentices on public works projects, and further agrees that CONTRACTOR is responsible for compliance with Section 1777.5 by all of its subcontractors.

C. Pursuant to Labor Code § 1776, CONTRACTOR and any subcontractor shall keep accurate payroll records, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with this AGREEMENT. Each payroll record shall contain or be verified by a written declaration that it is made under penalty of perjury, stating both of the following:
(1) The information contained in the payroll record is true and correct; and (2) The employer has complied with the requirements of Labor Code §§ 1811, and 1815 for any work performed by his or her employees on the public works project. The payroll records enumerated under subdivision (a) shall be certified and shall be available for inspection at all reasonable hours as required by Labor Code § 1776.

D. This AGREEMENT is further subject to 8-hour workday and wage and hour penalty law, including, but not limited to, Labor Code Sections 1810 and 1813, as well as California nondiscrimination laws, as follows:

CONTRACTOR shall strictly adhere to the provisions of the Labor Code regarding the 8-hour day and the 40-hour week, overtime, Saturday, Sunday and holiday work and nondiscrimination on the basis of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, sex, or sexual orientation, except as provided in Section 12940 of the Government Code. Pursuant to the provisions of the Labor Code, eight hours’ labor shall constitute a legal day’s work. Work performed by CONTRACTOR’s employees in excess of eight hours per day, and 40 hours during any one week, must include compensation for all hours worked in excess of eight hours per day, or 40 hours during any one week, at not less than one and one-half times the basic rate of pay.

CONTRACTOR shall forfeit as a penalty to AGENCY $25.00, or any greater penalty set forth in the Labor Code for each worker employed in the execution of the work by CONTRACTOR or by any Subcontractor of CONTRACTOR, for each Calendar Day during which such worker is required or permitted to the work more than eight hours in one Calendar Day or more than 40 hours in any one calendar week in violation of the Labor Code.

E. This AGREEMENT is subject to Public Contract Code Section 6109:

CONTRACTOR shall be prohibited from performing work on this project with a subcontractor who is ineligible to perform work on the project pursuant to Sections 1777.1 or 1777.7 of the Labor Code.

Page 439 of 672 ends

SECTION D – Page 5

CONTRACT INFORMATION AND DOCUMENT
ARTICLE V: Work Site Conditions
A. In compliance with and pursuant to Government Code Section 4215, AGENCY shall assume the responsibility, as between the parties to this AGREEMENT, for the timely removal, relocation, or protection of existing main- or trunk-line utility facilities located on the site of any construction project that is a subject of this AGREEMENT, if such utilities are not identified by AGENCY in the plans and specifications made a part of the invitation for bids.

The Contract Documents shall include provisions to compensate CONTRACTOR for the costs of locating, repairing damage not due to the failure of CONTRACTOR to exercise reasonable care, and removing or relocating such utility facilities not indicated in the plans and specifications with reasonable accuracy, and for equipment on the project necessarily idled during such work. CONTRACTOR shall not be assessed liquidated damages for delay in completion of the project, when such delay was caused by the failure of AGENCY or the owner of a utility to provide for removal or relocation of such utility facilities.

B. To the extent that the work requires trenches in excess of five feet (5’) and is estimated to cost more than $25,000, prior to any excavation, CONTRACTOR must provide the AGENCY, or a registered civil or structural engineer employed by the AGENCY to whom authority has been delegated to acceptsuch plans, a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer. Nothing in this section shall be deemed to allow the use of a shoring, sloping, or protective system less effective than that required by the Construction Safety Orders.

C. This AGREEMENT is further subject to Public Contract Code Section 7104 with regard to any trenches deeper than four feet (4’) involved in the proposed work as follows:

CONTRACTOR shall promptly, and before the following conditions are disturbed, notify AGENCY, in writing, of any:
(1) Material that CONTRACTOR believes may be hazardous waste, as defined in Section 25117 of the Health and Safety Code, which is required to be removed to a Class I, Class II, or Class III disposal site in accordance with existing law. (2) Subsurface or latent physical conditions at the site differing from those indicated by all available information provided prior to the deadline for submission of bids. (3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.

AGENCY shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or involve hazardous waste, and cause a decrease or increase in CONTRACTOR’s cost of, or the time required for, performance of any part of the work, AGENCY shall issue a change order under the procedures described in this AGREEMENT.

Page 440 of 672 ends

SECTION D – Page 6

CONTRACT INFORMATION AND DOCUMENT
In the event that a dispute arises between AGENCY and CONTRACTOR whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in CONTRACTOR’s cost of, or time required for, performance of any part of the work, CONTRACTOR shall not be excused from any scheduled completion date provided in the AGREEMENT but shall proceed with all work to be performed under the AGREEMENT.

CONTRACTOR shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties.

ARTICLE VI: Insurance
A. With respect to performance of work under this AGREEMENT, CONTRACTOR shall maintain, and shall require all of its subcontractors to maintain, insurance as required by Section E “Standard Specifications” of the Contract Documents.

B. This AGREEMENT is further subject to Workers’ Compensation obligations, including, but not limited to, California Labor Code Sections 1860 and 1861 as follows:

CONTRACTOR shall take out and maintain, during the life of this contract, Worker’s Compensation Insurance for all of CONTRACTOR’s employees employed at the site of improvement; and, if any work is sublet, CONTRACTOR shall require the subcontractor similarly to provide Worker’s Compensation Insurance for all of the latter’s employees, unless such employees are covered by the protection afforded by CONTRACTOR. CONTRACTOR and any of CONTRACTOR’s subcontractors shall be required to provide AGENCY with a written statement acknowledging its obligation to secure payment of Worker’s Compensation Insurance as required by Labor Code § 1861; to wit: ‘I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.’ If any class of employees engaged in work under this AGREEMENT at the site of the Project is not protected under any Worker’s Compensation law, CONTRACTOR shall provide and shall cause each subcontractor to provide adequate insurance for the protection of employees not otherwise protected. CONTRACTOR shall indemnify and hold harmless AGENCY for any damage resulting from failure of either CONTRACTOR or any subcontractor to take out or maintain such insurance.

ARTICLE VII: Indemnification
To the fullest extent permitted by law, CONTRACTOR shall, at its sole cost and expense, fully defend, indemnify and hold harmless AGENCY, its authorized representatives and their respective subsidiaries, affiliates, members, directors, officers, employees and agents (collectively, the “Indemnitees”) from and against any and all claims, actions, demands, costs, judgments, liens, penalties, liabilities, damages, losses, and expenses, including but not limited to any fees of accountants, attorneys or other professionals (collectively “Liabilities”), arising out of, in connection with, resulting from or related to, any act, omission, fault or negligence of CONTRACTOR, CONTRACTOR’s Representative, or any of its officers, agents, employees, Subcontractors or Suppliers, or any person or organization directly or indirectly employed by any of them (Collectively, the “Indemnitors”), in connection with or relating to or claimed to be in connection with or relating to the work performed under this AGREEMENT.

Page 441 of 672 ends

SECTION D – Page 7

CONTRACT INFORMATION AND DOCUMENT
If CONTRACTOR is a joint venture or partnership, each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of CONTRACTOR that are assumed under or arise out of this AGREEMENT. Each of such venturers or partners waives notice of the breach or non-performance of any undertaking or obligation of CONTRACTOR contained in, resulting from, or assumed under this AGREEMENT, and the failure to give any such notice shall not affect or impair such venturer’s or partner’s joint and several liability hereunder.

ARTICLE VIII: Binding Effect
AGENCY and CONTRACTOR each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto and to its partners, successors, assigns, and legal representatives in respect of all covenants, agreements, and obligations contained in the Contract Documents. This AGREEMENT is not assignable nor the performance of either party’s duties delegable without the prior written consent of the other party. Any attempted or purported assignment or delegation of any of the rights of obligations of either party without the prior written consent of the other shall be void and of no force and effect.

ARTICLE IX: Dispute Resolution
A. In the event of a dispute arising out of the terms of this AGREEMENT, including any action brought to declare the rights granted herein or to enforce any of the terms of this AGREEMENT, the party prevailing in such dispute shall be entitled to all reasonable costs and litigation expenses actually incurred, including fees of attorneys and expert witnesses. Any court action arising out of this AGREEMENT shall be filed in the Los Angeles County Superior Court. Any alternative dispute resolution proceeding arising out of this AGREEMENT shall be heard in the City of Los Angeles or the City of Los Alamitos, California.

B. AGENCY shall have full authority to compromise or otherwise settle any claim relating to this AGREEMENT or any part hereof at any time. AGENCY shall provide timely notification to CONTRACTOR of the receipt of any third-party claim relating to this AGREEMENT. AGENCY shall be entitled to recover its reasonable costs incurred in providing the notification required by this section.

C. This AGREEMENT is further subject to the provisions of Article 1.5 (commencing at Section 20104) of Division 2, Part 3 of the Public Contract Code regarding the resolution of public works claims of less than $375,000. Article 1.5 mandates certain procedures for the filing of claims and supporting documentation by Contractor, for the response to such claims by the Agency, for a mandatory meet and confer conference upon the request of Contractor, for mandatory nonbinding mediation in the event litigation is commenced, and for mandatory judicial arbitration upon the parties’ failure to resolve the dispute through mediation. This AGREEMENT hereby incorporates the provisions of Article 1.5 as though fully set forth herein.

ARTICLE X: Independent Contractor
CONTRACTOR is and shall at all times remain as to AGENCY, a wholly independent contractor. Neither AGENCY nor any of its agents shall have control of the conduct of CONTRACTOR or any of CONTRACTOR’s employees, except as herein set forth.

CONTRACTOR shall not at any time or in any manner represent that it or any of its agents or employees are in any manner agents or employees of AGENCY.

Page 442 of 672 ends

SECTION D – Page 8

CONTRACT INFORMATION AND DOCUMENT
ARTICLE XI: Taxes
CONTRACTOR is responsible for paying all retail, sales and use, transportation, export, import, special or other taxes and duties applicable to, and assessable against any work, materials, equipment, services, processes, and operations incidental to or involved in this AGREEMENT. The CONTRACTOR is responsible for ascertaining and arranging to pay such taxes and duties. The prices established in this AGREEMENT shall include compensation for any taxes the CONTRACTOR is required to pay by laws and regulations in effect as of the execution of this AGREEMENT.

ARTICLE XII: Notices
All notices and communications shall be sent in writing to the parties at the following addresses:

AGENCY: Chris Kelley CONTRACTOR: [INSERT CONTACT]
CITY OF LOS ALAMITOS CONTRACTOR’S BUSINESS NAME
3191 Katella Avenue Mailing Street Address
Los Alamitos, CA 90720 City, State Zip Code
ARTICLE XIII: Entire Agreement
This AGREEMENT supersedes any and all other agreements, either oral or written, between the parties and contains all of the covenants and agreements between the parties pertaining to the work of improvements described herein. Each party to this AGREEMENT acknowledges that no representations, inducements, promises or agreements, orally or otherwise, have been made by any party, or anyone acting on behalf of any party, which are not embodied herein, and that any other agreement, statement or promise not contained in this AGREEMENT shall not be valid or binding. Any modification of this AGREEMENT will be effective only if signed by the party to be charged.

The benefits and obligations of this AGREEMENT shall inure to and be binding upon the representatives, agents, partners, heirs, successors and assigns of the parties hereto. This AGREEMENT shall be construed pursuant to the laws of the State of California.

ARTICLE XIV: Authority to Contract
The signatories hereto represent that they are authorized to sign on behalf of the respective parties they represent and are competent to do so, and each of the parties hereto hereby irrevocably waives any and all rights to challenge signatures on these bases.

ARTICLE XV: General Provisions
A. All reports, documents, or other written material (“written products” herein) developed by CONTRACTOR in the performance of this Agreement shall be and remain the

Page 443 of 672 ends

SECTION D – Page 9

CONTRACT INFORMATION AND DOCUMENT
property of AGENCY without restriction or limitation upon its use or dissemination by AGENCY. CONTRACTOR may take and retain copies of such written products as desired, but no such written products shall be the subject of a copyright application by CONTRACTOR.

B. In the performance of this Agreement, CONTRACTOR shall not discriminate against any employee, subcontractor, or applicant for employment because of race, color, creed, religion, sex, marital status, sexual orientation, national origin, ancestry, age, physical or mental disability, medical condition, or any other unlawful basis.

C. The captions appearing at the commencement of the sections hereof, and in any paragraph thereof, are descriptive only and for convenience in reference to this Agreement.

Should there be any conflict between such heading, and the section or paragraph at the head of which it appears, the section or paragraph hereof, as the case may be, and not such heading, shall control and govern in the construction of this Agreement. Masculine or feminine pronouns shall be substituted for the neuter form and vice versa, and the plural shall be substituted for the singular form and vice versa, in any place or places herein in which the context requires such substitution(s).

D. The waiver by AGENCY or CONTRACTOR of any breach of any term, covenant or condition herein contained shall not be deemed to be a waiver of such term, covenant, or condition or of any subsequent breach of the same or any other term, covenant or condition herein contained. No term, covenant or condition of this Agreement shall be deemed to have been waived by AGENCY or CONTRACTOR unless in writing.

E. Each right, power and remedy provided for herein or now or hereafter existing at law, in equity, by statute, or otherwise shall be cumulative and shall be in addition to every other right, power, or remedy provided for herein or now or hereafter existing at law, in equity, by statute, or otherwise. The exercise, the commencement of the exercise, or the forbearance of the exercise by any party of any one or more of such rights, powers or remedies shall not preclude the simultaneous or later exercise by such party of any of all of such other rights, powers, or remedies.

IN WITNESS WHEREOF the parties hereto for themselves, their heirs, executors, administrators, successors, and assigns do hereby agree to the full performance of the covenants herein contained and have caused this AGREEMENT to be executed in duplicate by setting hereunto their names, titles, hands, and seals this Xth day of Month, 20XX (Council Action Date Here)
CONTRACTOR: Contractor’s Business Name
Contractor’s Sign Name, Title
Contractor’s License No. XXXXXX
Subscribed and sworn to this day of , 20 .

Page 444 of 672 ends

SECTION D – Page 10

CONTRACT INFORMATION AND DOCUMENT

NOTARY PUBLIC (SEAL)
AGENCY:

Mayor
City of Los Alamitos
Date
ATTESTED:

Windmera Quintanar, MMC, City Clerk
City of Los Alamitos
Date

APPROVED AS
TO FORM:

Michael S. Daudt, City Attorney
City of Los Alamitos
Date
( E X E C U T E I N D U P L I C A T E )

Page 445 of 672 ends

SECTION D – Page 11

CONTRACT INFORMATION AND DOCUMENT

PAYMENT BOND

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
WHEREAS, the City of Los Alamitos, as AGENCY has awarded to Contractor’s Business Name, as CONTRACTOR, a contract for the above-stated project.

AND WHEREAS, CONTRACTOR is required to furnish a bond in connection with the contract, to secure the payment of claims of laborers, mechanics, material persons, and other persons as provided by law.

NOW THEREFORE, we, the undersigned CONTRACTOR and SURETY, are held and firmly bound unto AGENCY in the sum of [DESCRIBE VERBALLY; 100% OF TOTAL CONTRACT AMOUNT—TO BE INSERTED BY CONTRACTOR]Dollars ($XXX,XXX.XX) which is one hundred percent (100%) of the total contract amount for the above-stated project, for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITIONS OF THIS OBLIGATION IS SUCH that if CONTRACTOR, its heirs, executors, administrators, successors, assigns or subcontractors, shall fail to pay any of the persons named in Civil Code Section 3181, or amounts due under the Unemployment Insurance Code with respect to work or labor withheld, and to pay over to the Employment Development Department from the wages of employees of the CONTRACTOR and its subcontractors pursuant to Section 13020 of the Unemployment Insurance Code, with respect to such work and labor, that the surety or sureties herein will pay for the same in an amount not exceeding the sum specified in this bond, otherwise the above obligation shall be void. In case suit is brought upon this bond, SURETY will pay reasonable attorneys’ fees to the plaintiffs and AGENCY in an amount to be fixed by the court.

This bond shall inure to the benefit to any of the persons named in Civil Code Section 3181 as to give a right of action to such persons or their assigns in any suit brought upon this bond.

The SURETY hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the contract or the specifications accompanying it shall in any manner affect SURETY’s obligations on this bond. The SURETY hereby waives notice of any such change, extension, alteration, or addition and hereby waives the requirements of Section 2845 of the Civil Code as a condition precedent to any remedies AGENCY may have.

IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seals this day of , 20 .

Contractor* Contractor’s Signer’s Name, Title
Contractor’s Business Name
Mailing Street Address
City, State, Zip Code
Telephone #
Surety*
*Provide CONTRACTOR and SURETY name, address and telephone number and the name, title, address, and telephone number for the respective authorized representatives. Power of Attorney must be attached.

Subscribed and sworn to this day of , 20 .

NOTARY PUBLIC........................................................................................................ . ...................................................................................................................................... (SEAL) (E X E C U T E I N D U P L I C A T E)

Page 446 of 672 ends

SECTION D – Page 12

CONTRACT INFORMATION AND DOCUMENT

FAITHFUL PERFORMANCE BOND

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
KNOW ALL PERSONS BY THESE PRESENTS That Contractor’s Business Name, hereinafter referred to as “CONTRACTOR” as PRINCIPAL, and , a corporation duly organized and doing business under and by virtue of the laws of the State of California and duly licensed for the purpose of making, guaranteeing, or becoming sole surety upon bonds or undertakings as Surety, are held and firmly bound unto the CITY OF LOS ALAMITOS, CALIFORNIA, hereinafter referred to as the “AGENCY” in the sum of [DESCRIBE VERBALLY; 100% OF TOTAL CONTRACT AMOUNT—TO BE INSERTED BY CONTRACTOR]Dollars ($XXX,XXX.XX); which is one hundred percent (100%) of the total contract amount for the above stated project; lawful money of the United States of America for the payment of which sum, well and truly to be made, we bind ourselves, our heirs, executors, administrators, assigns and successors, jointly and severally, firmly by these presents.

THE CONDITIONS OF THIS OBLIGATION ARE SUCH, that whereas CONTRACTOR has been awarded and is about to enter into a Contract with AGENCY to perform all work required pursuant to the contract documents for the project entitled: DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC WORKS BUILDING, SPECIFICATION NO. CIP 22/23- 04 CONTRACT which Contract is by this reference incorporated herein, and is required by AGENCY to give this Bond in connection with the execution of the Contract; NOW, THEREFORE, if CONTRACTOR and his or her Subcontractors shall well and truly do and perform all the covenants and obligations of the Contract on his or her part to be done and performed at the times and in the manner specified herein including compliance with all Contract specifications and quality requirements, then this obligation shall be null and void, otherwise it shall be and remain in full force and effect.

PROVIDED, that any alterations in the work to be done, or in the material to be furnished, which may be made pursuant to the terms of the Contract, shall not in any way release CONTRACTOR or the Surety thereunder, nor shall any extensions of time granted under the provisions of the Contract release either CONTRACTOR or said Surety, and notice of such alterations of extensions of the Contract is hereby waived by said Surety.

In the event suit is brought upon this Bond by AGENCY and judgment is recovered, said Surety shall pay all costs incurred by AGENCY in such suit, including a reasonable attorney’s fee to be fixed by the Court.

IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seals this day of , 20
Contractor* Name, Title of Signer
SURETY*………………………………………….

Contractor’s Business Name ……………………………………………
Mailing Street Address ……………………………………………
City, State, Zip Code ……………………………………………
Telephone #
……………………………………………
*Provide CONTRACTOR and SURETY name, address and telephone number and the name, title, address, and telephone number for their respective authorized representatives. Power of Attorney must be attached.

Subscribed and sworn to this day of , 20

Page 447 of 672 ends

SECTION D – Page 13

CONTRACT INFORMATION AND DOCUMENT

NOTARY PUBLIC (SEAL)
(E X E C U T E I N D U P L I C A T E)

Page 448 of 672 ends

SECTION D – Page 14

CONTRACT INFORMATION AND DOCUMENT

MAINTENANCE BOND

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
KNOW ALL PERSONS BY THESE PRESENTS THAT WHEREAS, the City of Los Alamitos, as AGENCY has awarded to Contractor’s Business Name, as CONTRACTOR, a contract for the abovestated project.

AND WHEREAS, CONTRACTOR is required to furnish a bond in connection with the contract guaranteeing maintenance thereof.

NOW, THEREFORE, we, the undersigned CONTRACTOR and SURETY, are held firmly bound unto AGENCY in the sum of DESCRIBE VERBALLY; 50% OF TOTAL CONTRACT AMOUNT—TO BE INSERTED BY CONTRACTOR]Dollars ($XXX,XXX.XX), which is fifty percent (50%) of the total contract amount for the above-stated project to be paid to AGENCY, its successors and assigns, for which payment well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITIONS OF THIS OBLIGATION ARE SUCH that if CONTRACTOR shall remedy without cost to AGENCY any defects which may develop during a period of one (1) year from the date of recordation of the Notice of Completion of the work performed under the contract, provided such defects are caused by defective or inferior materials or work, then this obligation shall be void; otherwise, it shall be and remain in full force and effect. In case suit is brought upon this bond, SURETY will pay reasonable attorneys’ fees to the AGENCY in an amount to be fixed by the court.

IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seals this day of
. ..................................... , 20 .

Contractor* Contractor’s Signer’s Name, Title
Contractor’s Business Name
Mailing Street Address
City, State, Zip Code
Telephone #
SURETY*
*Provide CONTRACTOR and SURETY name, address and telephone number and the name, title, address, and telephone number for their respective authorized representatives. Powers of Attorney must be attached.

Subscribed and sworn to this ........... day of ............................... , 20 .

NOTARY PUBLIC.................................................................................................. . ................................................................................................................................ (SEAL) (EXECUTE IN DUPLICATE)

Page 449 of 672 ends

SECTION D – Page 15

CONTRACT INFORMATION AND DOCUMENT
WORKERS’ COMPENSATION INSURANCE CERTIFICATE
The Contractor shall execute the following form as required by the California Labor Code, Sections 1860 and 1861:

I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

DATE: Contractor’s Business Name .
(Contractor)
By:
(Signature)
(Title)
Attest:

By:
(Signature)
(Title)
Note: See Section 5 Legal Relations and Responsibilities, Subsection 5-4 of the Standard Specifications for insurance carrier rating requirements.

Page 450 of 672 ends

SECTION D – Page 16

CONTRACT INFORMATION AND DOCUMENT

ENDORSEMENTS TO INSURANCE POLICY
Name of Insurance Company:

Policy Number:

Effective Date:

The following endorsements are hereby incorporated by reference into the attached Certificate of Insurance as though fully set forth thereon:

1. The naming of an additional insured as herein provided shall not affect any recovery to which such additional insured would be entitled under this policy if not named as such additional insured, and

2. The additional insured named herein shall not be held liable for any premium or expense of any nature on this policy or any extensions thereof, and

3. The additional insured named herein shall not by reason of being so named be considered a member of any mutual insurance company for any purpose whatsoever, and

4. The provisions of the policy will not be changed, suspended, canceled, or otherwise terminated as to the interest of the additional insured named herein without first giving such additional insured twenty (20) days’ written notice.

5. Any other insurance held by the additional insured shall not be required to contribute anything toward any loss or expense covered by the insurance, which is referred to by this certificate.

6. The company provided insurance for this certificate is a company licensed to do business in the State of California with a Best’s rating of A+ VIII or greater.

It is agreed that the City of Los Alamitos, its officers, and employees, are included as Additional Insureds under the contracts of insurance for which the Certificate of Insurance is given.

Authorized Insurance Agent
Date:

Page 451 of 672 ends

SECTION D – Page 17

CONTRACT INFORMATION AND DOCUMENT

STATEMENT REGARDING INSURANCE COVERAGE

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
The undersigned representative of Bidder hereby certifies that he/she has reviewed the insurance coverage requirements specified in 5.4 LIABILITY INSURANCE of Section E, Standard Specifications. Should Bidder be awarded the contract for the work, the undersigned further certifies that Bidder can meet all of these specification requirements for insurance including insurance coverage of his/her subcontractors.

NAME OF BIDDER: .......................................................................................................

MAILING ADDRESS: ....................................................................................................... ....................................................................................................... .......................................................................................................

AUTHORIZED SIGNATURE: .......................................................................................................

TITLE: .......................................................................................................

DATE: .......................................................................................................

Page 452 of 672 ends

SECTION D – Page 18

CONTRACT INFORMATION AND DOCUMENT
STATEMENT REGARDING CONTRACTOR’S LICENSING LAWS

DEMOLITION OF LOS ALAMITOS TELEVISION PRODUCTION BUILDING / PUBLIC

WORKS BUILDING
AT 10921 OAK STREET
SPECIFICATION NO. CIP 22/23-04

IN THE CITY OF LOS ALAMITOS, CALIFORNIA
[Business & Professions Code § 7028.15]
[Public Contract Code § 20103.5]
I, the undersigned, certify that I am aware of the following provisions of California law and that I, or the entity on whose behalf this certification is given, hold a currently valid California contractor’s license as set forth below:

Business & Professions Code § 7028.15:
a) It is a misdemeanor for any person to submit a bid to a public agency to engage in the business or act in the capacity of a contractor within this state without having a license therefor, except in any of the following cases:
(1)The person is particularly exempted from this chapter. (2)The bid is submitted on a state project governed by Section 10164 of the Public Contract Code or on any local agency project governed by Section 20104 [now § 20103.5] of the Public Contract Code.
b) If a person has been previously convicted of the offense described in this section, the court shall impose a fine of 20 percent of the price of the contract under which the unlicensed person performed contracting work, or four thousand five hundred dollars ($4,500), whichever is greater, or imprisonment in the county jail for not less than 10 days nor more than six months, or both.

In the event the person performing the contracting work has agreed to furnish materials and labor on an hourly basis, “the price of the contract” for the purposes of this subdivision means the aggregate sum of the cost of materials and labor furnished and the cost of completing the work to be performed.
c) This section shall not apply to a joint venture license, as required by Section 7029.1.

However, at the time of making a bid as a joint venture, each person submitting the bid shall be subject to this section with respect to his/her individual licenser. d) This section shall not affect the right or ability of a licensed architect, land surveyor, or registered professional engineer to form joint ventures with licensed contractors to render services within the scope of their respective practices. e) Unless one of the foregoing exceptions applies, a bid submitted to a public agency by a contractor who is not licensed in accordance with this chapter shall be considered nonresponsive and shall be rejected by the public agency. Unless one of the foregoing exceptions applies, a local public agency shall, before awarding a contract or issuing a purchase order, verify that the contractor was properly licensed when the contractor submitted the bid. Notwithstanding any other provision of law, unless one of the foregoing exceptions applies, the registrar may issue a citation to any public officer or employee of a public entity who knowingly awards a contract or issues a purchase order to a contractor who is not licensed pursuant to this chapter. The amount of civil penalties, appeal, and finality of such citations shall be subject to Sections 7028.7 to 7028.13, inclusive. Any contract awarded to, or any purchase order issued to, as contractor who is not licensed pursuant to this chapter is void.

Page 453 of 672 ends

SECTION D – Page 19

CONTRACT INFORMATION AND DOCUMENT
f) Any compliance or noncompliance with subdivision (e) of this section, as added by Chapter 863 of the Statutes of 1989, shall not invalidate any contract or bid awarded by a public agency during which time that subdivision was in effect. g) A public employee or officer shall not be subject to a citation pursuant to this section if the public employee, officer, or employing agency made an inquiry to the board for the purposes of verifying the license status of any person or contractor and the board failed to respond to the inquiry within three business days. For purposes of this section, a telephone response by the board shall be deemed sufficient.

Public Contract Code § 20103.5:

In all contracts subject to this part where federal funds are involved, no bid submitted shall be invalidated by the failure of the bidder to be licensed in accordance with the laws of this state.

However, at the time the contract is awarded, the contractor shall be properly licensed in accordance with the laws of this state. The first payment for work or material under any contract shall not be made unless and until the Registrar of Contractors verifies to the agency that the records of the Contractors’ State License Board indicate that the contractor was properly licensed at the time the contract was awarded. Any bidder or contractor not so licensed shall be subject to all legal penalties imposed by law, including, but not limited to, any appropriate disciplinary action by the Contractors’ State License Board. The agency shall include a statement to that effect in the standard form of pre-qualification questionnaire and financial statement. Failure of the bidder to obtain proper and adequate licensing for an award of a contract shall constitute a failure to execute the contract and shall result in the forfeiture of the security of the bidder.

Contractor’s License Number:

License Expiration Date:

Authorized Signature:

Date: