PREPARED BY: Nicolle Burnham
Parks and Public Works Director
Reviewed by: Town Manager
110 E. Main Street Los Gatos, CA 95030 ● (408) 354-6832 www.losgatosca.gov

TOWN OF LOS GATOS

COUNCIL AGENDA REPORT
MEETING DATE: 11/19/2024
ITEM NO: 1

ADDENDUM
DATE: November 18, 2024
TO: Mayor and Town Council
FROM: Chris Constantin, Town Manager
SUBJECT: Receive an Introductory Report on the Capital Infrastructure Needs of the Town of Los Gatos
REMARKS:

Attachment 5 contains the staff presentation.

Attachments Previously Received with the Staff Report:

1. History of Capital Funding

2. Current Projects

3. Facilities Needs

4. Roads, Parks and Other Projects
Attachments Received with this Addendum:

5. Staff Presentation
This Page Intentionally Left Blank
Capital Improvement Program
Study Session
Town Council
November 19, 2024
Item 1
ATTACHMENT 5

PURPOSE AND INTENT
• Initial discussion regarding capital infrastructure needs of the Town.
• Overall goal is to develop a look ahead of required annual costs to maintain existing infrastructure: roads, buildings, parks, etc. • Current information identifies a 10-year look forward

CAPITAL BUDGETING
• Refer to Staff Report Attachment 1
• 10-year source and use of funds support capital projects:
gas tax, utility undergrounding, traffic mitigation, storm drain funds, grants and general fund appropriated reserve (GFAR)
• Trends and observations
Ending fund balances remain high in many funds
Grant sources increased dramatically in 2021/22
Storm drain and utility undergrounding sources have increased with little use of funds
GFAR is the only source that includes unrestricted capital funds

CURRENT PROJECT DELIVERY
• Refer to Staff Report Attachment 2
• Spending lags projections at end of Q1 due to:
Spending on certain projects was not expected until later in FY 2024/25 (e.g., Shannon Road Repair, Townwide Vegetation Management)
Billing and processing lags performance of work (e.g., Shannon Road Ped and Bikeway Project, Annual Curb Gutter Sidewalk, Annual Street Repair and Resurfacing, Parking Program Implementation)
Some project schedules have shifted due to staffing constraints (e.g., Roadside Fire Fuel Reduction, Pinehurst Community Garden, Lynn Avenue Walkway) FACILITIES NEED PROJECTION 25/26 TO 35/36
• Refer to Staff Memorandum Attachment 2
• Based on 2022 facility condition assessments and American with Disabilities Act Assessment of all Town assets
• Preliminary projection of required annual spending to maintain existing building assets
FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 FY 32/33 FY 33/34 FY 34/35 FY 35/36 Annual Total 2022
Dollars 3,153,045 3,030,045 1,750,045 1,806,545 1,498,045 1,618,045 1,266,045 1,343,545 606,545 2,249,045 428,045 Annual Total Escalated
to 2024 Dollars at 4% 3,410,333 3,277,297 1,892,849 1,953,959 1,620,285 1,750,077 1,369,354 1,453,178 656,039 2,432,567 462,973

STREETS AND PARKS
• Refer to Staff Report Attachment 4
• Summary of currently known needs
• From field conditions and staff knowledge
• Bicycle and Pedestrian Master Plan
• General Plan 2024 (various adopted elements)

SUMMARY OF NEED
Items / Need
Current Opinion of
Potential Costs (2024$)
Town Owned Buildings - Maintenance $ 20,278,913
Town Owned Buildings – Capital Needs $ 1,490,000
Parks $ 28,189,000
Storm Drainage $ 23,126,500
Streets and Roads $ 166,037,000
IT Needs $ 310,000

POTENTIAL FUTURE MAJOR NEEDS
• Police Operations Consolidation
• Civic Center Upgrades
• Projects in 2040 General Plan

NEXT STEPS
• Refine project lists in Staff Report Attachments 3 and 4 to reflect required spending year over year
• This may require additional studies (e,g., playground condition assessments, facility assessment of Civic Center, etc.)
• Return to Council with refined projections and assessment of fiscal impacts
• Align annual CIP budget efforts to what can be funded and completed with a focus on sustaining capital assets that are currently in use. • Work towards establishing annual contribution necessary for current capital and determining funding available to reserve for future capital