§ Non-Right-of-Way Update - Staff then developed the draft update to Chapter

17.46. On April 12, 2021, the Council adopted Resolution No. 21-17, establishing engineering, design and location standards, conditions of approval, and application requirements for facilities permitted under Chapter 17.46. and on April 26, 2021, the Council adopted Ordinance No. 484, revising that chapter.

Public recommendations, including those from residents and their legal counsel, Mr.

McCollough; and input from the Center for Municipal Solutions (CMS), the City’s current wireless consultant; informed the development of the requirements for both the public right-of-way and non-right-of-way wireless standards. The City selected the technical reviewer (CMS) recommended by the public through a competitive Request for Proposals process, and CMS currently reviews wireless applications for compliance alongside City Staff during application review. No wireless permit is approved without review and input from CMS.

Design Standards Adopted by Resolution
MMC Chapters 12.02 and 17.46 each authorize the City Council to establish engineering, design, and location standards, and standard conditions of approval, by resolution. Resolutions are external documents to the Municipal Code but supplement it and specify technical requirements. This structure allows the City to adapt its regulations as law and technology change. The Wireless Design Standards for both right-of-way and non-right-of-way were adopted by Council through Resolutions 20-65 (ROW) and 21-17 (Non-ROW). They require stealth (concealed) design, establish residential spacing standards, and contain standard permit conditions.

Wireless Application Activity
The City has recently processed a number of wireless applications; however, most of these applications involve modifications to existing facilities or “eligible facilities requests” (EFRs). EFRs are proposed changes to existing wireless facilities, a category of applications federal law and FCC regulations requires the City to approve when specified criteria established by Federal Communications Commission (FCC) are met. Over the past year, the Planning Division issued decisions approving 39 wireless applications, all processed as EFRs. Twelve of those decisions have been appealed administratively.

The City has not approved a new (non-EFR) wireless facility in approximately three and a half years. Staff believes that is due to the requirements of the existing wireless regulations and the fulsome limitations and regulations imposed by the City. The subject amendments are a prospective change to the Council’s location standards. These changes do not (and cannot) affect EFR applications.

Page 4 of 10 ends

Applicable Federal Law
There are two common application types in Malibu, and different regulatory standards govern each.

TABLE 1 – WIRELESS APPLICATION TYPES
Type of Request Overview City Authority
Eligible Facilities
Request (EFR)
A modification to an existing wireless site,
such as replacing antennas or adding
equipment, that does not substantially
change the facility according to FCC
criteria.

Federal law requires approval if the request
does not substantially change the facility
under criteria set by the FCC. Review is
limited to those criteria, which incorporate the
facility’s approved concealment elements
and conditions of approval; the City cannot
require relocation or impose new design
standards.

New Wireless
Facility / Non-EFR
A new wireless location on an existing
structure with no wireless, a new or
replacement pole, or a modification that
exceeds the federal EFR limits.

Subject to the City’s local review standards to
the extent allowed under federal law. This
may include being subject to the Local
Coastal Program.

DISCUSSION: The amendments restrict new (non-EFR) wireless facilities in residential areas, both in the public rights-of-way and on private property by prohibiting their location in these areas unless an exception is needed and granted to ensure compliance with state and federal law. A new non-EFR facility may be approved in residential areas, as defined, only through the existing exception provisions of Chapter 12.02 and the parallel provision of Chapter 17.46, and the Resolutions.1 The Planning Commission, Director, or Hearing Officer may grant an exception to locate in residential areas only if the applicant demonstrates through clear and convincing evidence that an exception should be granted2. Staff anticipates applicants will be discouraged from seeking sites in residential areas, but may from time to time seek an exception on the basis that denial of an application would, within the meaning of federal law, (1) prohibit or effectively prohibit the provision of personal wireless services, or (2) otherwise violate applicable laws or regulations.
3 If an exception is granted, the standards are waived only to the minimum extent required to avoid the prohibition or violation. In plain terms, the waiver process exists because federal law does not allow the City to apply its standards in a way that leaves a carrier unable to provide personal wireless services, in conflict with federal law limits on local authority; this may be considered an “effective prohibition” which is disallowed.
1 Exception provisions appear in Reso. No. 20-65, § 9; and Reso. No. 21-17, § 7, implementing MMC Sections

12.02.050(E) and 17.46.060(D), respectively. 2 Waiver authority is the Planning Commission for facilities outside the right-of-way and the Director or Hearing Officer for right-of-way facilities. 3 MMC Sections 12.02.050(E), 17.46.060(D), Reso. No. 20-65, § 9(A)(1); and Reso. No. 21-17, § 7(A)(1).

Page 5 of 10 ends

A new definition of “residential areas” establishes where the new siting restriction applies. Utility poles along PCH or other major arterial roads as depicted in Figure CI-1 of the City’s General Plan remain available as preferred and allowed locations for wireless siting. The practical effect is to strengthen the direction to site new facilities on PCH and arterial roads where the City’s location preferences have channeled them since 2020, while preserving the availability of the waiver process to avoid case-by-case conflicts with federal law. Attachments 3 and 4 include redlines showing each amendment in context.

The following summarizes the changes, and Table 2 compares current and proposed standards.
§ Resolution No. 26-53 (amending and replacing Resolution No. 20-65, Public ROW) adds the definition of residential areas. The “residential areas” definition expressly excludes utility poles along PCH and the Figure CI-1 arterials. The amendment increases the 600-foot facility spacing standard to 1,000 feet, retaining the arterial exception. It also renumbers and amends the location preferences and adds the residential restriction under the Subsection 5.C (Discouraged and Disallowed Locations/Zones). § Resolution No. 26-54 (amending and replacing Resolution No. 21-17, NonROW) adds the “residential areas” definition for parcels, removes residential from the least appropriate locations designation in Section 5.C.6, and adds new Subsection 5.D (Disallowed Locations) containing the parallel restriction.

TABLE 2 – CURRENT AND PROPOSED STANDARDS
Standard Current Proposed
Residential siting
(Reso. 20-65 and 21-17)
Location preferences disfavor
residential siting. New facilities may be
approved in residential areas through
discretionary review. EFRs are
excluded.

Residential areas are designated
disallowed locations for new facilities.

Approval is available only through an
exception. EFRs are excluded.

Definition of “residential
areas” (new)
Not defined. The resolutions refer to
areas “adjacent to any residential zone
district.”
Defined terms. Non-ROW: Parcel zoning
under MMC Chapter 17.06. ROW: a
parcel abutting or fronting the right-of-way
within 300 feet of the proposed facility.

Utility poles along PCH and arterials
excluded.

Spacing
(Reso. 20-65 § 5.A)
600 feet between facilities adjacent to
residential zones. PCH and arterials
excepted.

Increased to 1,000 feet. PCH and arterial
poles excepted; does not apply adjacent
to commercial zone districts.

Location preferences Favor arterials, non-residential property, One new preference inserted: adjacency

Page 6 of 10 ends

TABLE 2 – CURRENT AND PROPOSED STANDARDS
Standard Current Proposed
(Reso. 20-65 § 5.B) and existing structures. to non-residentially designated property (Item 2). List renumbered.

Exceptions
(MMC Chs. 12.02 and

17.46; Reso.20-65 § 9;
(Reso. 21-17 § 7)
Exceptions to standards may be granted
upon clear and convincing evidence.

Basis for an exception is that denial
would effectively prohibit service under
federal law, or otherwise violate
applicable laws or regulations.

The generally applicable exception
process in each resolution continues to be
available to applicants, including as
applied to the new residential restriction.

Scope and Applicability
The restriction applies only to new (non-EFR) facilities in residential areas, both in the public rights-of-way and on private property. It does not require relocation of existing facilities or apply to EFRs. If adopted, the amendments take effect immediately and apply to applicable applications submitted after the effective date. Pending applications are reviewed under the standards in effect when each application was submitted.

Health and Safety
The amendments do not change the Wireless Design Standards’ existing health and safety standards. The Standards require compliance with the California Building, Electrical, and Fire Codes, along with backup power consistent with Fire Code Section 1206.2.2, seismic and site-hardening standards, and operational noise limits. The Standards also require the applicant to obtain third-party verification that the facility complies with the FCC’s radiofrequency exposure standards. Federal law preempts local regulation of radiofrequency (RF) emissions for compliant facilities (47 U.S.C. § 332(c)(7)(B)(iv)). In practice, the City may verify compliance with the FCC’s exposure standards, but it may not regulate the placement of a compliant facility based on the environmental effects of RF emissions.

Comparison with the City of Calabasas
Commentary from members of the public claimed that the Calabasas had a more robust ordinance than Malibu. The City Council directed staff to examine how the City of Calabasas wireless facilities regulates wireless facilities under their Municipal Code Chapter 17.31 (Ordinance No. 2021-391) and Wireless Facility Design Guidelines adopted by Council resolution. Unlike Malibu, Calabasas is not in the coastal zone, and many of its residential areas lie within homeowners associations.

Calabasas adopted its current regulations partly in response to the 2018 Woolsey Fire.

Its 2019 citywide survey found a majority of respondents dissatisfied with wireless

Page 7 of 10 ends

service, including its reliability during the fire, and willing to accept new sites, including in neighborhoods, if appropriately disguised or screened. Calabasas designed the 2021 update to encourage such deployment, and the ordinance included an 18-month fee reduction for new facilities.

Under Calabasas’ updated regulations, for new facilities, there are two permit tiers.4 A new stealth facility qualifies for a Tier 1 permit, an administrative review with no public hearing. Tier 1 facilities are allowed in residential and open space zones (which are the least desirable in Malibu’s laws) on developed properties under common ownership, such as a homeowners association. Tier 1 facilities are also exempt from the 1,000-foot residential, school, and park setback that applies to Tier 2 facilities. Under Calabasas’ design guidelines, for example, a new freestanding macro-tower designed as a faux tree with screened or disguised antennas and underground equipment qualifies as stealth (Tier 1) (See Exhibit 1). In Malibu, such applications would be subject to the full application of the City’s wireless laws (which limit placement in residential and open space areas) and would be subject to a coastal development permit (CDP) (which requires further scrutiny and discretion in order comply with the City’s Local Coastal Program). In Calabasas, Tier 2 permits are required for new facilities that do not qualify for Tier 1, and only a Tier 2 permit requires a public hearing. As explained above, stealth facilities do not require the Tier 2 process.

For new facilities in residential areas, Malibu’s current and newly proposed amendments are more restrictive than Calabasas’ regulations. Calabasas permits large macro-tower stealth facilities administratively on qualifying residential properties. In contrast, the amendments restrict new facilities in residential areas unless an exception is granted.

The current Malibu design standards designate residential areas as the least desirable for wireless siting. Both approaches are lawful policy choices within the federal framework described in Table 1.
[Remainder of page left intentionally blank]
4 The City of Calabasas processes modifications to existing facilities under a separate permit type.

Page 8 of 10 ends

Exhibit 1 – Calabasas’ Wireless Facilities Design Guidelines, Figures 12 and 13: a non-stealth faux tree facility on the left (Tier 2, requiring discretionary review) and a stealth faux tree facility on the right (Tier 1, eligible for administrative approval even in residential areas). What would be allowed as an administrative approval in Calabasas would require a CDP and a public hearing in Malibu under the current laws.

Coastal Zone and Local Coastal Program
The entire City is within the coastal zone. The amendments revise engineering, design and location standards adopted by City Council resolution pursuant to MMC Chapters

12.02 and 17.46, and do not amend the City’s certified Local Coastal Program (LCP).

The Wireless Design Standards operate in addition to, and not in place of, the LCP.

Coastal development permit requirements apply to new wireless facilities where applicable. The amendments do not affect coastal resources. A waiver granted under the Wireless Design Standards does not exempt a facility from any required coastal review, and nothing in the amendments authorizes development inconsistent with the certified LCP.

The LCP itself addresses wireless facilities. The Council approved Local Coastal Program Amendment (LCPA) No. 16-007, amending the Local Implementation Plan (LIP) provisions regulating wireless communications facilities, concurrently with Ordinance No. 484 in April 2021. Since the last Council meeting, staff has reinstated discussions with the California Coastal Commission to finalize the certification process.

ENVIRONMENTAL REVIEW: The Resolutions are not a project within the meaning of Section 15378 of CEQA Guidelines, because they have no potential for resulting in physical change in the environment, directly or indirectly. The Resolutions do not

Page 9 of 10 ends

authorize any specific development or installation on any specific piece of property within the City’s boundaries. Moreover, when and if an application for installation is submitted, the City will at that time conduct a preliminary review of the application in accordance with CEQA.

Alternatively, if the Resolutions are a “project” within the meaning of CEQA Guidelines Section 15378, the Resolutions are exempt from CEQA on multiple grounds. First, the Resolutions are exempt because the City Council’s adoption of the Resolutions is covered by the general rule that CEQA applies only to projects which have the potential for causing a significant effect on the environment (CEQA Guidelines, § 15061(b)(3)).

That is, adoption of the Resolutions has no potential to cause a significant effect on the environment as it does not approve any development and limits the potential for development more than currently exists under the City’s regulations. Second, the Resolution is categorically exempt under State CEQA Guidelines §§ 15307 and 15308 as an action taken by a regulatory agency, as authorized by local ordinance (MMC Chapters 12.02 and 17.46), to assure the protection of natural resources and the environment. The Resolutions strengthen the City’s location and design standards for new wireless facilities. They do not weaken any existing standard and do not authorize any construction or development. The City’s wireless permitting process involves procedures for protection of the environment, including discretionary review of each application and coastal development permit review under the certified Local Coastal Program where applicable. None of the exceptions in CEQA Guidelines § 15300.2 applies.

In order to install a facility in accordance with the Resolutions, the wireless provider would have to submit an application for installation of the wireless facility. At that time, the City will have specific and definite information regarding the facility to review in accordance with CEQA.

PUBLIC NOTICE: The agenda for this item was posted consistent with the Brown Act at least 72 hours before the meeting. Staff sent a courtesy email with the meeting date and participation instructions to the interested parties list for wireless matters and updated the City’s wireless facilities webpage with notification of this meeting. The City also maintains a Pending Applications page on its website and earlier this year published a Wireless Facilities FAQ and fact sheet explaining the City’s review process.5 Public comments on this item have been received both at public meetings and through general correspondence since February 2026.

SUMMARY: Staff recommends that the City Council adopt Resolution Nos. 26-53 and 26-54, amending Resolution Nos. 20-65 and 21-17. The amendments restrict new wireless facilities in residential areas (both in ROW and non-ROW), define “residential 5 Visit malibucity.org/pendingwireless to read the Wireless Fact Sheet and the Pending Applications Report.

Page 10 of 10 ends

areas,” and make conforming changes in the ROW to the spacing, separation, and location preference standards.

ATTACHMENTS:

1. Resolution No. 26-53 Amending and Replacing Resolution No. 20-65 (Public Right-of-Way)

2. Resolution No. 26-54 Amending and Replacing Resolution No. 21-17 (NonRight-of-Way)

3. Redline of Resolution No. 20-65

4. Redline of Resolution No. 21-17

5. Figure CI-1 of the City’s General Plan (Map of Major Arterial Roadways) Attachment 1
RESOLUTION NO. 26-53

A RESOLUTION OF THE CITY OF MALIBU AMENDING AND REPLACING RESOLUTION NO. 20-65 (WIRELESS FACILITIES IN THE PUBLIC RIGHTOF-WAY) TO RESTRICT NEW WIRELESS FACILITIES IN RESIDENTIAL AREAS, DEFINE “RESIDENTIAL AREAS,” AND REVISE THE RELATED SPACING, SEPARATION, AND LOCATION PREFERENCE STANDARDS;

AND FINDING THAT THIS RESOLUTION IS NOT SUBJECT TO THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT AND, IN THE

ALTERNATIVE, IS EXEMPT FROM CEQA
The City Council of the City of Malibu does hereby find, resolve and order as follows:

SECTION 1. Recitals
A. Chapter 12.02 of the Malibu Municipal Code (MMC) governs the permitting, installation, and regulation of personal wireless services facilities in the City’s public right-of-way (ROW);
B. MMC Section 12.02.050(D) provides that “[a]ll applicants shall engineer, design and locate the wireless facilities in accordance with the standards and wireless regulations set forth separately though the resolution adopted by the City Council;” C. The City’s public rights-of-way are a uniquely valuable public resource, closely linked with the City’s character, making the regulation of wireless installations in the public rightsof-way necessary to protect and preserve the aesthetics in the community; D. Being authorized to do so, the City wishes to establish engineering, design and development standards applicable to wireless installations in the public rights-of-way; E. The City also wishes to set standard conditions of approval applicable to wireless ROW permits; and
F. On December 9, 2020 the City Council conducted a duly noticed public hearing and received testimony from City staff and all interested parties regarding the engineering, design and development standards.

G. On July 13, 2026 the City Council a duly noticed meeting and received testimony from City staff and all interested parties regarding the residential restriction.

Purpose.

The purpose of this document is to (1) establish design and location standards (Standards) for wireless facilities in the public right-of-way (ROW) within the City; and (2) set standard conditions of approval for Wireless ROW Permits (WRPs).

Resolution No. 26-53

Page 2 of 24 ends

_____________________
Definitions.

For the purposes of these Standards, the definitions set forth in Malibu Municipal Code (MMC) Section 12.02.020 are incorporated by reference into this Resolution and in addition the following definitions apply:

A. “Pole-mounted facility” means a wireless facility that is, or is proposed to be, attached to or contained in a pole.

B. “Residential areas” means the portion of the public right-of-way, excluding utility poles along Pacific Coast Highway or other major arterial roadways as depicted in Figure CI-1 of the City’s General Plan, where any parcel abutting or fronting the right-of-way within three hundred (300) feet of the proposed facility is zoned RR, SF, MF, MFBF, or MH, or is a Planned Development parcel whose principal use is residential, under MMC Chapter 17.06. Distance shall be measured from the farthest projection of the proposed wireless facility to the nearest such residential parcel line.

C. “Stealth facility” (or “stealth facilities”) means a wireless facility designed to look like something other than a wireless tower or base station.

General Standards for all Facilities.

The following standards shall apply to all wireless facilities in the ROW:

A. All wireless facilities shall be engineered and designed to minimize the visual impact by means of placement, screening, camouflaging, painting and texturing and to be compatible with existing architectural elements, building materials and other site characteristics. The applicant shall use the smallest and least visible antenna possible to accomplish the facility’s objectives. All antennas and support structures shall be painted and/or textured to achieve architectural compatibility with the structures for which they are attached and/or located.

B. Prohibition of Generators. Permanent generators are prohibited.

C. General Orders. All installations shall comply with applicable California Public Utilities Commission (“CPUC”) General Orders, including, but not limited to General Order 95, and, if stricter, the pole owner’s safety standards. None of the engineering or design standards are meant to conflict with or cause a violation of CPUC General Orders. Accordingly, the Standards can be adjusted on a case-by-case basis if it is demonstrated that adjustment is necessary to ensure compliance with CPUC rules on safety.

Resolution No. 26-53

Page 3 of 24 ends

_____________________
D. Electric Service. The permittee shall request that the permittee’s electric service provider apply flat-rate billing for any proposed electric service, wireless smart metering or other alternative metering option that would obviate the need for an above-grade electric meter. If flat-rate service is not available, applicants may install a shrouded “smart meter” that shall not exceed the width of the pole; provided, however that such smart meter shall be placed at least ten (10) feet above ground level. If the proposed project involves a ground-mounted equipment cabinet, an electric meter may be integrated with and recessed into the cabinet, but the Director shall not approve a separate ground-mounted electric meter pedestal unless (1) the separate ground-mounted meter pedestal would be placed off the sidewalk and (2) the applicant demonstrates with clear and convincing evidence that all other alternatives for the electric meter are not available. All support equipment located within cabinets, shelters, or similar structures shall be screened from public view to the maximum extent feasible.

Undergrounding of support equipment is required wherever practicable.

E. Security. All equipment and facilities shall be installed in a manner to avoid being an attractive nuisance and to prevent unauthorized access, climbing, and graffiti.

F. Safety. All wireless facilities, including each piece of equipment, shall be located and placed in a manner so as to not interfere with the public use of the ROW; impede the flow of vehicular or pedestrian traffic; impair the primary use and purpose of poles/signs/traffic signals or other infrastructure; interfere with outdoor dining areas or emergency facilities; or otherwise obstruct the accessibility of the ROW. Further, all wireless facilities and associated equipment shall comply with Americans with Disabilities Act (ADA) requirements.

G. Fire and Electrical Safety Standards. All wireless facilities shall contain:

1. A power shut off readily accessible to fire service personnel for emergencies;

2. Surge protection for lightning discharge or other significant electrical disturbances;

3. Signage as required by the permit conditions, the National Electric Code or the Los Angeles County Fire Department Chief or his or her designee; and

4. Instructions for first responders to de-energize the equipment.

H. Noise. Wireless facilities and equipment must comply with the City’s noise ordinance in MMC 8.24, or any successor provisions, and be designed to Resolution No. 26-53

Page 4 of 24 ends

_____________________
prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

I. Lighting. Lighting of antenna structures and their electrical support equipment is prohibited, except as required by any order or regulation of the Federal Communications Commission (FCC) or the Federal Aviation Administration (FAA) and except for manually operated emergency lights for use when official operating personnel are on site.

J. Signs. No facility may display any signage or advertisement unless it is expressly allowed by this paragraph or required by law or a permit condition. Every facility shall at all times display signage that accurately identifies the facility owner and provides the owner’s unique site number and a local or toll-free telephone number to contact the facility owner’s operations center.

K. Landscaping. Where appropriate, facilities shall be installed so as to maintain and enhance existing landscaping on the site, including trees, foliage and shrubs, whether or not utilized for screening. In addition to any landscaping used for concealment or screening purposes, the applicant shall replace any existing landscaping displaced during construction or installation of the applicant’s facility. The applicant’s landscaping plan shall be subject to the City’s review and approval but shall, at a minimum, match the existing landscaping and foliage surrounding the installation site consistent with MMC Section 17.53.090.

Location Standards for All Facilities.

The location standards for all wireless facilities, other than those that qualify as eligible facilities requests, in the ROW are as follows:

A. Spacing. Wireless facilities located in residential areas, except for those facilities placed on utility poles located along Pacific Coast Highway or other major arterial roadways as depicted in Figure CI-1 of the City’s General Plan, shall not be located within one thousand (1,000) feet of any other wireless facility. This provision does not apply to wireless facilities located adjacent to any commercial zone district.

B. Location preference for wireless facilities should be given to the following:

1. Installations along major arterial roadways as depicted in Figure CI1 of the City’s General Plan.

2. Locations adjacent to property designated non-residential (except for public open space and recreational vehicle park zoning districts), unless otherwise prohibited pursuant to this title.

Resolution No. 26-53

Page 5 of 24 ends

_____________________

3. Facilities attached to existing utility poles or street lights, or sited adjacent to existing structures not used for human habitation or school grounds or to playgrounds or parks. Whenever possible, facilities shall be located on and/or inside existing structures.

4. Sites that are not highly visible from adjacent roadways and do not obstruct views of impressive scenes off the Pacific Ocean, offshore islands, the Santa Monica Mountains, canyons, valleys, or ravines.

5. Unless otherwise indicated in this title, no wireless facility shall be installed on an exposed ridgeline unless the facility blends with the surrounding existing natural and man-made environment and a finding is made that no other location is technically feasible.

C. Discouraged and Disallowed Locations/Zones.

1. Wireless facilities that are within 250 feet from the property line of an open space or recreational area.

2. The City expressly designates residential areas, as defined in Section 3, as disallowed locations for new wireless facilities.

3. Wireless facilities that are less than five hundred (500) feet from school grounds, playgrounds or parks.

4. Wireless facilities that are less than four hundred fifty (450) feet from any other existing wireless facility within or adjacent to any residential zone district, except for those facilities placed on utility poles located along Pacific Coast Highway or other major arterial roadways as depicted in Figure CI-1 of the City’s General Plan.

D. Placements shall not be in front of dwelling units or schools.

Undergrounding Standards for All Facilities.

With regard to undergrounding wireless facilities, the following standards apply:

A. Equipment, including remote radio units (RRUs) that cannot be placed with the antenna in the shroud, must be placed underground, subject to Section 7(B) below. Vaults and pull boxes shall be installed flush to grade.

B. Ground-mounted equipment is prohibited unless required for technical reasons.

1. If required, ground-mounted wireless facilities shall be located near existing structures or trees at similar heights for screening purposes.

The equipment shall be enclosed in cabinets, sized only for the Resolution No. 26-53

Page 6 of 24 ends

_____________________
necessary equipment. Further, if ground mounted, the antennas, equipment, cabinet and support structure shall be painted, textured, landscaped or otherwise camouflaged as much as possible to integrate the structure into the environment. Colors and materials for facilities shall be non-reflective and chosen to minimize visibility.

As such, ground-mounted equipment shall be stealth.

2. The ground-mounted equipment must not obstruct ocean views.

3. Not more than one ground-mounted antenna shall be permitted on each site.

Design Standards for all Facilities.

The general design standards for wireless facilities in the ROW are as follows:

A. Materials. The materials used shall be non-reflective and non-flammable.

B. Cabinet doors must be designed to stay securely closed, and openings in all facilities shall be shielded or made the smallest size feasible to protect against fire and wind-blown embers.

C. The pole, or other support structure, and all equipment shall be designed to withstand forces from seismic events.

D. All connections between various components of the facility, power lines, and conduit shall be designed in a manner to protect against damage by a natural disaster, a vehicular accident, an act of vandalism or similar external forces.

E. Stealth. The wireless facility shall be stealth. Stealth elements and techniques should be used to blend the facility with surrounding materials and colors of the support structure and make the facility appear to be something other than a wireless facility. Stealth elements include, but are not limited to, the following:

1. Radio frequency (RF) transparent screening or shrouds;

2. Matching the color of the existing support structure by painting, coating, or otherwise coloring the wireless facility, equipment, mounting brackets, and cabling;

3. Placing cables and wires inside the pole or beneath conduit of the smallest size possible;

4. Minimizing the size of the site;
Resolution No. 26-53

Page 7 of 24 ends

_____________________

5. Installing new infrastructure that matches existing infrastructure in the area surrounding the proposed site; and

6. Using paint of durable quality.

F. Curb Setback Requirements. New or replacement poles shall be a minimum of 18 inches from the face of the curb.

G. Collocation. The City has a preference for the use of existing infrastructure.

Wireless facilities shall be collocated on existing poles or other facilities when possible. No permittee shall restrict access to an existing antenna location if required to collocate by the City and if possible to do so.

H. Minimum Height. All antennas shall be located such that: (1) any person walking adjacent to the transmitting surface of the antenna will be walking on a grade that is a minimum of eight and one-half feet below the transmitting surface; and (2) no person at ground level will be exposed to an exposure level that is higher than allowed by the FCC’s general population exposure rules.

I. Strand-mounted Facilities. Strand-mounted facilities are encouraged. The facilities must be stealth and of the smallest size that is technically feasible to reduce aesthetic impacts.

Engineering and Design Standards for Pole-Mounted Facilities.

In addition to the generally applicable standards set forth above, the design standards for polemounted facilities in the ROW are as follows:

A. Facilities on Streetlight Poles.

1. Stealth. The facility shall be engineered, designed, painted, coated, and otherwise made to maintain the look of a streetlight pole rather than a wireless facility, tower, or base station.

2. Antennas and RRUs. Antennas shall be top-mounted in a shroud, and RRUs and other equipment shall be placed underground. If RRUs and equipment cannot be underground, then they shall be placed within the shroud with the antenna. RRUs attached to the side of the pole or ground-mounted are discouraged, but if they are required due to technical reasons, they should use the smallest RRU volume possible and be stacked vertically and close together with minimal distance from the pole.

3. Dimensions. Antennas shall be of the smallest possible size, but in no case more than three cubic feet in volume. Pole-top wireless Resolution No. 26-53

Page 8 of 24 ends

_____________________
facilities, including shroud, shall be no more than 60 inches in height and 14.5 inches in diameter.

4. Cables and Wiring. All cables and wiring must be within the pole.

B. Facilities on Wood Utility Poles.

1. Stealth. The facility shall be engineered, designed, painted, coated, and otherwise made to maintain the look of a utility pole rather than a wireless facility, tower, or base station.

2. Antennas. The preferred mounting type for wireless facilities on wood utility poles is side-mounting.
a. Side-mounted Facilities. Antennas and RRUs shall be midpole mounted (i.e., mid-pole mounted) in a shroud. If RRUs are attached to the side of the pole, the facility should use the smallest RRU volume possible, and the RRUs should be
stacked vertically and close together with minimal distance from the pole.
(1) Antennas shall be of the smallest possible size, but in no case more than three cubic feet in volume.
(2) Side-mounted wireless facilities shall be of the
smallest size technically feasible and shall not
project from the pole more than 30 inches. The
diameter of the shroud shall be no greater than the
diameter of the pole or 14.5 inches, whichever is less.

Side-mounted facilities shall only extend out on one
side of the pole.
b. Top-mounted Facilities. Antennas and RRUs shall be topmounted in a shroud. (1) Dimensions. Antennas shall be of the smallest
possible size, but in no case more than three cubic
feet in volume.
(a) Pole-top wireless facilities, including shroud,
shall be no more than 72 inches in height and

14.5 inches in diameter.

3. Cables and Wiring. All cables and wiring must be within the conduit on the exterior of the pole. The conduit must be a color that matches the pole and of the smallest size technically feasible.

Resolution No. 26-53

Page 9 of 24 ends

_____________________
C. Replacement Poles. If an applicant proposes or is required to install a replacement pole to accommodate the proposed facility:

1. Placement. A replacement pole must be in the same location as the pole that it is replacing or as close to the original location as possible, taking into account pole owner safety-related requirements and all applicable location and placement standards herein.

2. Design. Replacement poles should match the design (e.g., color, dimensions, height, style, and materials) of the existing pole that is being replaced.

3. Cables and Wiring. All cables and wiring on non-wood poles must be within the structure. All cables and wiring on wood poles must be within conduit on the exterior of the pole. The conduit must be a color that matches the pole and of the smallest size technically feasible.

4. Stealth. The facility should be stealth, as defined above in Section 4(B).

D. New (Non-Replacement) Poles.

1. Waiver Required. New poles are prohibited, unless a waiver is approved by the City to prevent a prohibition of service.

2. Design. New poles (including antenna) shall have a maximum height of 28 feet and a maximum diameter of 14 inches, and any base enclosure shall not exceed 24 inches in width or height. If existing poles are present in the surrounding area, then the new pole shall be designed to resemble the existing poles in appearance, color, materials, and distribution pattern/spacing.

3. New wooden poles are prohibited, unless required to match existing poles in the area surrounding the proposed installation site.

4. Cables and Wiring. All cables and wiring on non-wood poles must be within the pole. All cables and wiring on wood poles must be within the conduit on the exterior of the pole. The conduit must be a color that matches the pole and of the smallest size technically feasible.

5. Antennas and RRUs. Antennas and RRUs shall be contained within the pole and its base or underground.

6. Stealth. The facility must be stealth, as defined above in Section 4(B).

Resolution No. 26-53

Page 10 of 24 ends

_____________________
Exceptions to These Standards.

A. An exception may be granted to one or more of these Standards in the following circumstances:

1. Pursuant to MMC Section 12.02.050(E), if an applicant demonstrates to the Director or Hearing Officer in writing with clear and convincing evidence that denial of an application would, within the meaning of federal law, prohibit or effectively prohibit the provision of personal wireless services, or otherwise violate applicable laws or regulations. All waivers approved pursuant to MMC Section 12.02.050(E) shall be (1) granted only on a case-bycase basis, and (2) narrowly-tailored so that the requirements of these Standards are waived only to the minimum extent required to avoid the prohibition or violation.

2. If an applicant demonstrates to the Director or Hearing Officer with clear and convincing evidence set forth in a feasibility study that compliance with a requirement of the policy would be technically infeasible and the proposed wireless facility complies with the requirements of this policy to the greatest extent technically feasible.

For example, an exception to a requirement to conceal antennas in a shroud may be granted if shrouding is shown to be technically infeasible and an alternative concealment such as a colored film wrap is proposed. As another example, an exception to the volume limitation for antennas in a single shroud may be granted if the applicant can demonstrate that a greater volume is technically required, and that it is using the smallest, technically feasible engineering and design for providing personal wireless services, taking into account the other requirements of these Standards; or

3. If an applicant demonstrates to the Director or Hearing Officer in writing and based on clear and convincing evidence that the particular engineering, design or location proposed involves only minor non-compliance with a requirement of these Standards but such non-compliance either results in no increase in visual harms to the community or provides other benefits. For example, an exception to the antenna or equipment size or volume limitations may be granted when the applicant can demonstrate that because of the proposed location of the wireless facility away from viewsheds of residences or shielded by vegetation or existing infrastructure (such as barriers) in the public ROW, any additional visual and physical impacts of the larger wireless facility would be insignificant. As another example, an exception to the wireless facility location limitations may be granted when the applicant can demonstrate that the placement is less visible from viewsheds of Resolution No. 26-53

Page 11 of 24 ends

_____________________
residences or shielded by vegetation or existing infrastructure (such as barriers) in the public right-of-way, or is less physically intrusive (for example, less impactful to tree roots or reduces noise), or the applicant can demonstrate that in a multi-site deployment, the placement would reduce the overall number of sites needed and be no more visible or physically intrusive than placement in accordance with the wireless location criteria. Among other factors, in deciding whether or not to grant an exception, the Director may consider the impact of expansions to the facility that the applicant would be entitled to make as of right if granted.

B. Factors to be addressed in a feasibility study requesting an exception to undergrounding requirements based on feasibility shall include but are not limited to construction impacts (including duration and extent of excavation and soil disturbance); traffic and pedestrian impacts (including impediments to access during construction and maintenance, or permanent impediments due to the nature of particular equipment); operational challenge (such as water, heat, or maintenance complications affecting network reliability); noise impacts (such as venting and pumping which may be required in some instances); cost impacts; aesthetic considerations; and permanent impacts to the integrity and future capacity of public ROW.

C. Exceptions must be requested at the time an application is initially submitted for a WRP. The request must include both the specific provision(s) from which exception is sought and the basis of the request, including all supporting evidence on which the applicant relies. Any request for exception after the Director has deemed an application complete constitutes a material change to the proposed wireless facility and shall be considered a new application. A request for exception from one or more requirements does not relieve the applicant from compliance with all other applicable provisions of law or of these Standards.

Standard Conditions of Approval for Permits Under MMC Chapter 12.02.

A. Generally. In addition to any supplemental conditions imposed by the Director of Planning or the Hearing Officer, as the case may be, all permits under MMC Chapter 12.02 shall be subject to the following conditions, unless modified by the approving authority:

1. The permittee, and their successors in interest, shall indemnify and defend the City of Malibu and its officers, employees and agents from and against all liability and costs relating to the City's actions concerning this project, including (without limitation) any award of litigation expenses in favor of any person or entity who seeks to challenge the validity of any of the City's actions or decisions in connection with this project or seeks to hold the City liable in whole Resolution No. 26-53

Page 12 of 24 ends

_____________________
or in part as a result of the engineering, design, construction or operation of the facility. The City shall have the sole right to choose its counsel and property owners shall reimburse the City’s expenses incurred in its defense of any lawsuit challenging the City’s actions concerning this project.

2. Subsequent submittals for this project shall be in substantial compliance with the plans date-stamped received by the Planning Department on _____________. The project shall comply with all conditions of approval stipulated in the referral sheets attached to the agenda report for this project. In the event the project plans conflict with any condition of approval, the condition shall take precedence and revised plans shall be submitted and approved by the Planning Director prior to the Environmental Sustainability Department for plan check.

3. The permit and rights conferred in this approval shall not be effective until the permittee signs, notarizes and returns the Acceptance of Conditions Affidavit accepting the conditions set forth herein. The applicant shall file this form with the Planning Department within 30 days of this decision or prior to issuance of any wireless ROW, building, electrical or encroachment permit.

4. The applicant shall digitally submit a complete set of plans, including the items required in Condition No. 5 to the Planning Department for consistency review and approval prior to plan check and again prior to the issuance of any building or development permits.

5. This Notice of Decision (including the signed and notarized Acceptance of Conditions Affidavit) shall be copied in its entirety and placed directly onto a separate plan sheet(s) to be included in the development plans prior to submitting any development permits from the City of Malibu Environmental Sustainability Department and encroachment permit.

6. A WRP shall be valid for a period of ten (10) years from issuance, unless pursuant to another provision of the Code or these conditions, it expires sooner or is terminated. At the end of ten (10) years from the date of issuance, such wireless ROW permit shall automatically expire, unless an extension or renewal has been granted. A person holding a WRP must either (1) remove the facility within thirty (30) days following the permit’s expiration (provided that removal of support structure owned by City, a utility, or another entity authorized to maintain a support structure in the right of way need not be removed, but must be restored to its prior condition, except Resolution No. 26-53

Page 13 of 24 ends

_____________________
as specifically permitted by the City); or (2) prior to expiration, submit an application to renew the permit, which application must, among all other requirements, demonstrate that the impact of the wireless facility cannot be reduced. The wireless facility must remain in place until it is acted upon by the City and all appeals from the City’s decision exhausted.

7. The installation and construction authorized by a WRP shall be completed within three (3) years after its approval, or it will expire without further action by the City unless prior to the three (3) years the applicant submit an extension request and the City, in its sole discretion, grants a time extension for due cause. The installation and construction authorized by a wireless ROW permit shall conclude, including any necessary post-installation repairs and/or restoration to the ROW, within thirty (30) days following the day construction commenced. The permittee must provide written notice to City within ten (10) days after completing construction. The expiration date shall be suspended until an appeal and/or litigation regarding the subject permit is resolved.

8. The Planning Director may grant up to four one-year extensions of the timeline, in Condition 7 above, for completing the installation and construction authorized by a WRP, if the Planning Director finds that the conditions, including but not limited to changes in the wireless ordinance under which the WRP approval was issued, have not significantly changed.

9. Any questions of intent or interpretation of any condition of approval will be resolved by the Planning Director upon written request of such interpretation.

10. All structures shall conform to the requirements of the Environmental Sustainability Department, City Public Works Department, FCC and Los Angeles County Fire Department
requirements, as applicable. Notwithstanding this review, all required permits, including but not limited to an encroachment permit from the City, shall be secured.

11. Minor changes to the approved plans or the conditions of approval may be approved by the Planning Director, provided such changes achieve substantially the same results and the project is still in compliance with the MMC. An application with all required materials and fees shall be required.

Resolution No. 26-53

Page 14 of 24 ends

_____________________
Cultural Resources

12. In the event that potentially important cultural resources are found in the course of geologic testing, work shall immediately cease until a qualified archaeologist can provide an evaluation of the nature and significance of the resources and until the Planning Director can review this information. Where, as a result of this evaluation, the Planning Director determines that the project may have an adverse impact on cultural resources, a Phase II Evaluation of cultural resources shall be required pursuant to MMC Section

17.54.040(D)(4)(b).

13. If human bone is discovered, the procedures described in Section 7050.5 of the California Health and Safety Code shall be followed.

These procedures require notification of the coroner. If the coroner determines that the remains are those of a Native American, the applicant shall notify the Native American Heritage Commission by phone within 24 hours. Following notification of the Native American Heritage Commission, the procedures described in Section 5097.94 and Section 5097.98 of the California Public Resources Code shall be followed.

Wireless Facility Conditions

14. All antennas shall meet the minimum siting distances to public/uncontrolled areas required for compliance with the FCC regulations and standards governing the environmental effects of radio frequency emissions. Permittee shall keep up-to-date on current information from the FCC in regards to maximum
permissible radio frequency exposure levels. In the event that the FCC changes its guidelines for human exposure to radio frequency, permittee shall, within 30 days after any such change, submit to the Planning Director a report prepared by a qualified engineer that demonstrates actual compliance with such changed guidelines. The Director may, at permittee’s sole cost, retain an independent consultant to evaluate the compliance report and any potential modifications to the permit necessary to conform to the FCC’s guidelines. Failure to submit the compliance report required under this condition, or failure to maintain compliance with the FCC’s guidelines for human exposure to radio frequency at all times shall constitute grounds for permit revocation.

15. All antennas shall be located so that any person walking adjacent to the transmitting surface of the antenna will be walking on a grade, which is a minimum of eight and one-half feet below the transmitting surface.

Resolution No. 26-53

Page 15 of 24 ends

_____________________

16. All antennas, equipment, and support structures shall be engineered and designed to prevent unauthorized climbing.

17. The wireless facility shall be erected, operated, and maintained in compliance with the general requirements set forth in the Standards.

18. The antenna and electrical support equipment shall, at all times, be operated in a manner that conforms to the applicable federal health and safety standards.

19. Wireless facilities and equipment must comply with the City’s noise ordinance in MMC 8.24, or any successor provisions, and prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

20. The installation of a permanent onsite generator and/or other equipment is prohibited. The Planning Director’s approval is required if a generator is to be placed onsite for temporary or permanent use.

21. All pole-mounted equipment associated with the application shall be located no lower than eight feet above grade or ground level on the utility pole.

22. The City or its designee may enter onto the facility area to inspect the facility upon 48 hours prior notice to the permittee. The permittee shall cooperate with all inspections and may be present for any inspection of its facility by the City. The City reserves the right to enter or direct its designee to enter the facility and support, repair, disable, or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

The City shall make an effort to contact the permittee prior to disabling or removing any facility elements, but in any case, shall notify permittee within 24 hours of doing so.

23. Testing of any equipment shall take place on weekdays only, and only between the hours of 8:30 a.m. and 4:30 p.m., except that testing is prohibited on holidays that fall on a weekday. In addition, testing is prohibited on weekend days.

24. Permittee shall obtain and maintain throughout the term of the permit commercial general liability insurance with a limit of five million dollars ($5,000,000) per occurrence for bodily injury and property damage and six million dollars ($6,000,000) general aggregate including premises operations, contractual liability, personal injury, and products completed operations. The relevant Resolution No. 26-53

Page 16 of 24 ends

_____________________
policy(ies) shall name the City, its elected/appointed officials, commission members, officers, representatives, agents, and employees as additional insureds. Permittee shall use its best efforts to provide thirty (30) days’ prior notice to the City of to the cancellation or material modification of any applicable insurance policy.

25. Prior to issuance of a wireless encroachment permit, the permittee shall file with the City, and shall maintain in good standing throughout the term of the approval, a performance bond or other surety or another form of security for the removal of the facility in the event that the use is abandoned or the permit expires, or is revoked, or is otherwise terminated. The security shall be in the amount equal to the cost of physically removing the facility and all related facilities and equipment on the site, based on the higher of two contractor’s quotes for removal that are provided by the permittee. The permittee shall reimburse the city for staff time associated with the processing and tracking of the bond, based on the hourly rate adopted by the City Council. Reimbursement shall be paid when the security is posted and during each administrative review.

26. Permittee shall not move, alter, temporarily relocate, change, or interfere with any existing structure, improvement, or property without the prior consent of the owner of that structure, improvement, or property. No structure, improvement, or property owned by the City shall be moved to accommodate a permitted activity or encroachment, unless the City determines that such movement will not adversely affect the City or any surrounding businesses or residents, and the Permittee pays all costs and expenses related to the relocation of the City's structure, improvement, or property. Prior to commencement of any work pursuant to a WRP, the permittee shall provide the City with documentation establishing to the city's satisfaction that the permittee has the legal right to use or interfere with any other structure, improvement, or property within the public right-of-way or City utility easement to be affected by permittee's facilities.

27. The permission granted by a WRP shall not in any event constitute an easement on or an encumbrance against the ROW. No right, title, or interest (including franchise interest) in the ROW, or any part thereof, shall vest or accrue in permittee by reason of a WRP or the issuance of any other permit or exercise of any privilege given thereby.

Resolution No. 26-53

Page 17 of 24 ends

_____________________

28. No possessory interest is created by a WRP. However, to the extent that a possessory interest is deemed created by a governmental entity with taxation authority, permittee acknowledges that City has given to permittee notice pursuant to California Revenue and Taxation Code Section 107.6 that the use or occupancy of any public property pursuant to a WRP may create a possessory interest which may be subject to the payment of property taxes levied upon such interest.

Permittee shall be solely liable for, and shall pay and discharge prior to delinquency, any and all possessory interact taxes or other taxes, fees, and assessments levied against permittee’s right to possession, occupancy, or use of any public property pursuant to any right of possession, occupancy, or use created by this WRP.

29. If not already completed, permittee shall enter into the appropriate agreement with the City, as determined by the City, prior to constructing, attaching, or operating a facility on municipal infrastructure. This permit is not a substitute for such agreement.

30. For all facilities located within the ROW, the permittee shall remove or relocate, at its expense and without expense to the City, any or all of its facilities when such removal or relocation is deemed necessary by the City by reason of any change of grade, alignment, or width of any right-of-way, for installation of services, water pipes, drains, storm drains, power or signal lines, traffic control devices, right-ofway improvements, or for any other construction, repair, or improvement to the right-of-way.

31. If a facility is not operated for a continuous period of three (3) months, the WRP and any other permit or approval therefore shall be deemed abandoned and terminated automatically, unless before the end of the three (3) month period (i) the Director has determined that the facility has resumed operations, or (ii) the City has received an application to transfer the permit to another service provider. No later than ninety (90) days from the date the facility is determined to have ceased operation or the permittee has notified the Director of its intent to vacate the site, the permittee shall remove all equipment and improvements associated with the use and shall restore the site to its original condition to the satisfaction of the Director. The permittee shall provide written verification of the removal of the facilities within thirty (30) days of the date the removal is completed. If the facility is not removed within thirty (30) days after the permit has been discontinued pursuant to this subsection, the site shall be deemed to be a nuisance, and the City may cause the facility to be removed at permittee’s expense or by calling any bond or other financial assurance to pay for removal. If there are two (2) or more Resolution No. 26-53

Page 18 of 24 ends

_____________________
users of a single facility or support structure, then this provision shall apply to the specific elements or parts thereof that were abandoned but will not be effective for the entirety thereof until all users cease use thereof.

32. In the event the City determines that it is necessary to take legal action to enforce any of these conditions, or to revoke a permit, and such legal action is taken, the permittee shall be required to pay any and all costs of such legal action, including reasonable attorney’s fees, incurred by the City, even if the matter is not prosecuted to a final judgment or is amicably resolved, unless the City should otherwise agree with permittee to waive said fees or any part thereof.

The foregoing shall not apply if the permittee prevails in the enforcement proceeding.

Construction

33. Installation hours shall be limited to Monday through Friday from 7:00 a.m. to 7:00 p.m. and Saturdays from 8:00 a.m. to 5:00 p.m. No installation activities shall be permitted on Sundays and Citydesignated holidays. The restricted work hours described in this condition do not apply to emergency maintenance necessary to protect health or property. The City of Malibu may issue a Stop Work Order if permittee violates this condition. Construction activities shall be conducted in compliance with, and abide by, all applicable safety codes.

Site Specific Conditions

34. In the event that the electric service provider does not currently offer an alternative metering option, the permittee shall remove the above-grade electric meter when such option becomes available.

Prior to removing the above-grade electric meter, the permittee shall apply for any encroachment and/or other ministerial permit(s) required to perform the removal. Upon removal, the permittee shall restore the affected area to its original condition that existed prior to installation of the equipment.

35. The permittee acknowledges that the City specifically includes conditions of approval related to (a) painting, coloring or finishing the equipment to match the pole; (b) undergrounding all equipment to the extent possible; and (c) installing equipment within shrouds, conduits and risers as concealment elements engineered and designed to integrate the wireless facility with the surrounding built and natural environment. Any future modifications to the Resolution No. 26-53

Page 19 of 24 ends

_____________________
permittee’s wireless facility must maintain or improve all concealment elements.

36. Before the permittee submits any applications for construction, encroachment, excavation or other required permits in connection with this permit, the permittee must incorporate a true and correct copy of this permit, all conditions associated with this permit and any approved photo simulations into the project plans (collectively, the “Approved Plans”). The permittee must construct, install and operate the wireless facility in substantial compliance with the Approved Plans as determined by the Director or the Director’s designee. Any substantial or material alterations, modifications or other changes to the Approved Plans, whether requested by the permittee or required by other departments or public agencies with jurisdiction over the wireless facility, must be submitted in a written request subject to the Director’s prior review and approval, who may refer the request to the original approval authority if the Director finds that the requested alteration, modification or other change substantially deviates from the Approved Plans or implicates a significant or substantial land-use concern.

37. The permittee shall install and at all times maintain in good condition a “Network Operations Center Information” and “RF Caution” sign on the utility pole no less than three (3) feet below the antenna (measured from the top of the sign) and no less than nine (9) feet above the ground line (measured from the bottom of the sign). Signs required under this condition shall be installed so that a person can clearly see the sign as he or she approaches within three (3) feet of the antenna structure. If any person on or within the public ROW is or may be exposed to emissions that exceed applicable FCC uncontrolled/general population limits at any time the sign shall expressly so state and provide instructions on how persons can avoid any such exposure. The sign shall also include the name(s) of the facility owner(s), equipment owner(s) and operator(s)/carrier(s) of the antenna(s), property owner name, as well as emergency phone number(s) for all such parties. The sign shall not be lighted, unless applicable law, rule or regulation requires lighting. No signs or advertising devices other than required certification, warning, required seals or signage, other signage required by law, this Chapter, any City or applicable state code or the Los Angeles County Fire Department Chief or his or her designee shall be permitted. The sign shall be no larger than two (2) square feet.

38. The permittee shall ensure that all signage complies with FCC Office of Engineering and Technology Bulletin 65, CPUC General Resolution No. 26-53

Page 20 of 24 ends

_____________________
Order 95 or American National Standards Institute C95.2 for color, symbol, and content conventions. All such signage shall at all times provide a working local or toll-free telephone number to its network operations center, and such telephone number shall be able to reach a live person who can exert transmitter power-down control over this site as required by the FCC.

39. In the event that the FCC changes any of radio frequency signage requirements that are applicable to the project site approved herein or ANSI Z535.1, ANSI Z535.2, and ANSI C95.2 standards that are applicable to the project site approved herein are changed, the permittee, within 30 days of each such change, at its own cost and expense, shall replace the signage at the project site to comply with the current standards.

40. The permittee shall maintain the paint, color and finish of the facility in good condition at all times.

41. All improvements, including foundations, and appurtenant ground wires, shall be removed from the property and the site restored to its original pre-installation conditions within 90 days of cessation of operation or abandonment of the facility.

42. Build-Out Conditions.
a. Permittee shall not commence any excavation, construction, installation or other work on the project site until and unless it demonstrates to the City Public Works Department that the project complies with all generally applicable laws,
regulations, codes and other rules related to public health and safety, including without limitation all applicable provisions in California Public Utilities Commission General Order 95 and MMC Chapters 8.12, 8.24 and 15.08.
b. To the extent that the pole owner requires greater or more restrictive standards than contained in California Public Utilities Commission General Order 95, those standards
shall control.

43. Permittee shall at all times maintain compliance with all applicable federal, State and local laws, regulations, ordinances and other rules, including Americans with Disabilities Act (ADA) requirements.

44. The permittee shall cooperate with all inspections. The City and its designees reserves the right to support, repair, disable or remove any Resolution No. 26-53

Page 21 of 24 ends

_____________________
elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

45. Permittee shall at all times maintain accurate contact information for all parties responsible for the facility, which shall include a phone number, street mailing address and email address for at least one natural person. All such contact information for responsible parties shall be provided to the Planning Department at the time of permit issuance and within one business day of permittee’s receipt of City staff’s written request.

46. Permittee shall undertake all reasonable efforts to avoid undue adverse impacts to adjacent properties and/or uses that may arise from the construction, operation, maintenance, modification and removal of the facility.

47. The site and the facility must be maintained in a neat and clean manner and in accordance with all approved plans and conditions of approval.

48. Permittee shall promptly remove any graffiti on the wireless facility at permittee’s sole expense within 48 hours after notice.

Prior to Operation

49. The applicant shall request a final Planning Department inspection immediately after the wireless facility has been installed and prior to the commencement of services and final electrical inspection by the City of Malibu Environmental Sustainability Department.

50. Within thirty (30) calendar days following the installation of any wireless facilities, the applicant shall provide to the Planning Department with a field report prepared by a qualified engineer verifying that the unit has been inspected, tested, and is operating in compliance with FCC standards. Specifically, the on-site postinstallation radiofrequency (RF) emissions testing must demonstrate actual compliance with the FCC OET Bulletin 65 RF emissions safety guidelines for general population/uncontrolled RF exposure in all sectors. For this testing, the transmitter shall be operating at maximum operating power, and the testing shall occur outwards to a distance where the RF emissions no longer exceed the
uncontrolled/general population limit. Such report and
documentation shall include the make and model (or other identifying information) of the unit tested, the date and time of the inspection, a certification that the unit is properly installed and working within applicable FCC limits, and a specific notation of the Resolution No. 26-53

Page 22 of 24 ends

_____________________
distance from the transmitter at which the emissions are equal to or less than the uncontrolled/general population limit.

51. The operation of the approved facility shall commence no later than one (1) month after the City completes its post-installation inspection of the facility, any issues with the facility are resolved, and the City receives the RF testing report required in the condition of approval above, or the wireless ROW permit will expire without further action by the City.

Fixed Conditions

52. Violation of any of the conditions of this approval shall be cause for revocation and termination of all rights thereunder.

Eligible Facilities Requests
In addition to all of the other conditions of approval placed on a WRP, all permits for an eligible facilities request under MMC Chapter 12.02 shall be subject to the following additional conditions, unless modified by the approving authority:

53. Any permit granted in response to an application qualifying as an eligible facilities request shall be subject to the terms and conditions of the underlying permit.

54. The City’s grant or grant by operation of law of an eligible facilities request permit constitutes a federally-mandated modification to the underlying permit or approval for the subject tower or base station.

Notwithstanding any permit duration established in another permit condition, the City’s grant or grant by operation of law of a eligible facilities request permit will not extend the permit term for the underlying permit or any other underlying regulatory approval, and its term shall be coterminous with the underlying permit or other regulatory approval for the subject tower or base station.

55. The City’s grant or grant by operation of law of an eligible facilities request does not waive, and shall not be construed to waive, any standing by the City to challenge Section 6409(a) of the Spectrum Act, any FCC rules that interpret Section 6409(a) of the Spectrum Act, or any modification to Section 6409(a) of the Spectrum Act.

Small Cell Facilities
In addition to the other conditions of approval placed on a WRP, all permits for a small cell facility under MMC Chapter 12.02 shall be subject to the following additional condition, unless modified by the approving authority:

Resolution No. 26-53

Page 23 of 24 ends

_____________________

56. The City’s grant of a permit for a small cell facility request does not waive, and shall not be construed to waive, any standing by the city to challenge any FCC orders or rules related to small cell facilities, or any modification to those FCC orders or rules.

SECTION 11. Environmental Review.

This Resolution is not a project within the meaning of Section 15378 of the State of California Environmental Quality Act (CEQA) Guidelines, because it has no potential for resulting in physical change in the environment, directly or indirectly. The Resolution does not authorize any specific development or installation on any specific piece of property within the City’s boundaries.

Moreover, when and if an application for installation is submitted, the City will at that time conduct preliminary review of the application in accordance with CEQA.

Alternatively, even if the Resolution is a “project” within the meaning of State CEQA Guidelines section 15378, the Resolution is exempt from CEQA on multiple grounds. First, the Resolution is exempt CEQA because the City Council’s adoption of the Resolution is covered by the general rule that CEQA applies only to projects which have the potential for causing a significant effect on the environment. (State CEQA Guidelines, § 15061(b)(3)). That is, approval of the Resolution will not result in the actual installation of any facilities in the City. In order to install a facility in accordance with this Resolution, the wireless provider would have to submit an application for installation of the wireless facility. At that time, the City will have specific and definite information regarding the facility to review in accordance with CEQA. And, in fact, the City will conduct preliminary review under CEQA at that time. Second, the Resolution is categorically exempt under CEQA Guidelines §§ 15307 and 15308 as an action taken by a regulatory agency, as authorized by local ordinance (MMC Chapter 12.02), to assure the protection of natural resources and the environment. The Resolution strengthens the City’s location and design standards for new wireless facilities. It does not weaken any existing standard and does not authorize any construction or development. The City’s wireless permitting process involves procedures for protection of the environment, including discretionary review of each application and coastal development permit review under the certified Local Coastal Program where applicable. None of the exceptions in CEQA Guidelines § 15300.2 applies.

Moreover, in the event that the Resolution is interpreted so as to permit installation of wireless facilities on a particular site, the installation would be exempt from CEQA review in accordance with either State CEQA Guidelines section 15302 (replacement or reconstruction), State CEQA Guidelines section 15303 (new construction or conversion of small structures), and/or State CEQA Guidelines section 15304 (minor alterations to land).

SECTION 12. This Resolution shall become effective immediately upon is passage and adoption.

SECTION 13. The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

Resolution No. 26-53

Page 24 of 24 ends

_____________________
PASSED, APPROVED, and ADOPTED this 13th day of July 2026. _____________________________
BRUCE SILVERSTEIN, Mayor
ATTEST:
___________________________
KELSEY PETTIJOHN, City Clerk
(seal)
APPROVED AS TO FORM:
_____________________________
TREVOR RUSIN, Interim City Attorney
Attachment 2
RESOLUTION NO. 26-54

A RESOLUTION OF THE CITY OF MALIBU AMENDING AND REPLACING RESOLUTION NO. 21-17 (WIRELESS FACILITIES ON LAND OTHER THAN

THE PUBLIC RIGHT-OF-WAY) TO RESTRICT NEW WIRELESS
FACILITIES IN RESIDENTIAL AREAS AND DEFINE “RESIDENTIAL AREAS”; AND FINDING THAT THIS RESOLUTION IS NOT SUBJECT TO

THE CALIFORNIA ENVIRONMENTAL QUALITY ACT AND, IN THE

ALTERNATIVE, IS EXEMPT FROM CEQA
The City Council of the City of Malibu does hereby find, resolve and order as follows:

SECTION 1. Recitals.

A. Malibu Municipal Code (MMC) Chapter 17.46 governs the permitting, installation, and regulation of wireless communications facilities in the City, other than those in the public right-of-way, which are subject to MMC Chapter 12.02.

B. Section 17.46.060(D) provides that “[a]ll applicants shall engineer, design and locate the wireless communications facilities in accordance with the standards and wireless regulations set forth separately though the resolution adopted by the City Council.” C. Being authorized to do so, the City wishes to establish engineering, design and development standards applicable to wireless installations.

D. The City also wishes to set standard conditions of approval and basic application requirements applicable to wireless permits.

E. On April 12, 2021 the City Council conducted a duly noticed public hearing and received testimony from City staff and all interested parties regarding the standards, conditions and requirements.

F. On July 13, 2026 the City Council conducted a duly noticed public hearing and received testimony from City staff and all interested parties regarding the residential restriction.

Purpose.

The purpose of this document is to (1) establish design and location standards (Standards) for wireless communications facilities on land other than public right-of-way; (2) set standard conditions of approval for Wireless Permits (WPs); and (3) set basic application requirements for WPs.

Definitions.

For the purposes of these Standards, the definitions set forth in Malibu Municipal Code (MMC) Section 17.46.040 are incorporated by reference into this Resolution and in addition the following definitions apply:

Resolution No. 26-54

Page 2 of 27 ends

_____________________
A. “Park” A parcel, parcels of land or a portion of a parcel intended for active public recreation uses. Parks may include sports fields, playgrounds community buildings and unique or specialized activity areas. Land dedicated for open space and trails are not considered parks for the purposes of this Chapter.

B. “Playground” A portion of land used for and equipped with public facilities for recreation specially by children. A playground includes the sand or rubberized floor around the apparatus.

C. “Pole-mounted facility” means a wireless communications facility that is, or is proposed to be, attached to or contained in a pole.

D. “Residential areas” means any parcel zoned RR, SF, MF, MFBF, or MH, or a Planned Development parcel whose principal use is residential, under MMC Chapter 17.06.

E. “School” any building, campus or sports field which is designed, constructed or used for education, instruction or school sports, whether public or private, in any branch of knowledge.

F. “Stealth facility” (or “stealth facilities”) means a wireless communications facility designed to look like something other than a wireless tower or base station.

General Standards for all Facilities.

The following general requirements apply at all times to all wireless communications facilities located in all zoning districts:

A. All wireless communications facilities shall be engineered and designed to minimize the visual impact by means of placement, screening, camouflaging, painting and texturing and to be compatible with existing architectural elements, building materials and other site characteristics. The applicant shall use the smallest and least visible antenna possible to accomplish the facility’s objectives. All antennas and support structures shall be painted and/or textured to achieve architectural compatibility with the structures for which they are attached and/or located.

B. Each facility must comply with any and all applicable provisions of the Malibu Municipal Code, including but not limited to provisions of the California Building Code, California Electric Code, California Plumbing Code, California Mechanical Code, and California Fire Code, and any conditions of approval imposed as part of the approval process.

C. Each facility must comply with any and all applicable regulations and standards promulgated or imposed by any state or federal agency, including, Resolution No. 26-54

Page 3 of 27 ends

_____________________
but not limited to, the Federal Communications Commission (FCC) and the Federal Aviation Administration (FAA). Further, all wireless communications facilities, associated equipment and services shall comply with Americans with Disabilities Act (ADA) requirements.

D. Fire and Electrical Safety Standards. All wireless communications facilities shall contain:

1. Surge protection for lightning discharge or other significant electrical disturbances; and

2. Signage as required by the permit conditions, the National Electric Code or the Los Angeles County Fire Department Chief or their designee.

E. The facility must at all times comply with all applicable health requirements and standards pertaining to radio frequency emissions.

F. All antennas shall meet the minimum siting distances to habitable structures required for compliance with FCC regulations and standards governing the environmental effects of radio frequency emissions.

G. Noise. Wireless communications facilities and equipment must comply with the City’s noise ordinance in MMC Chapter 8.24, or any successor provisions, and be designed to prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

H. Signs. No facility may display any signage or advertisement unless it is expressly allowed by this paragraph, necessary for stealth concealment purposes, or required by law or a permit condition. Every facility shall at all times display signage that accurately identifies the facility owner and provides the owner’s unique site number and a local or toll-free telephone number to contact the facility owner’s operations center.

I. Landscaping. Where appropriate, facilities shall be installed so as to maintain and enhance existing landscaping on the site, including trees, foliage and shrubs, whether or not utilized for screening. In addition to any landscaping used for concealment or screening purposes, the applicant shall replace any existing landscaping displaced during construction or installation of the applicant’s facility. The applicant’s landscaping plan shall be subject to the City’s review and approval but shall, at a minimum, match the existing landscaping and foliage surrounding the installation site consistent with MMC Section 17.53.090. The permittee shall ensure that any vegetation allowed to remain in place under the Fire Code, including vegetation provided for screening, is properly maintained and watered.

Resolution No. 26-54

Page 4 of 27 ends

_____________________
J. All electrical support equipment located within cabinets, shelters, or similar structures shall be screened from public view. Roof-mounted electrical support equipment shall be discouraged. Ground-mounted electrical support equipment shall be encouraged. In addition, under grounding of support equipment is required wherever practicable.

K. All antennas shall be located such that any person walking adjacent to the transmitting surface of the antenna will be walking on a grade that is a minimum of eight and one-half feet below the transmitting surface.

L. Lighting of antenna structures and their electrical support equipment is prohibited, except as required by any order or regulation of the FCC or the FAA and except for manually operated emergency lights for use when official operating personnel are on site.

M. A backup power supply must be required for all new wireless communications facilities to the extent allowed by law and in compliance with California Fire Code 1206.2.2.

Location Standards for All Facilities.

The location standards for all wireless communications facilities, other than those that qualify as eligible facilities requests, are as follows:

A. No wireless telecommunication facility shall be located within five hundred (500) feet of any school, playground, or park unless a finding is made, based on technical evidence acceptable to the reviewing authority showing a clear need for the facility and that no technically feasible alternative site exists.

Except for facilities installed on the same pole or tower as an existing wireless telecommunication facility, wireless telecommunication facilities located within any residential zone district shall not be located within one thousand (1,000) feet of any other wireless communications facility, except from those facilities placed on utility poles along Pacific Coast Highway, unless a waiver is granted.

B. All new freestanding wireless communications facilities and monopoles shall be set back a minimum distance of at least one hundred and twenty (120) percent of the height of the facility or monopole from any property line abutting a residentially zoned property. This minimum setback is not subject to the waivers allowed under Section 7 of this Resolution.

C. Location preference for wireless communications facilities should be given to the following:

Resolution No. 26-54

Page 5 of 27 ends

_____________________

1. Property designated non-residential (except for public open space and recreational vehicle park zoning districts), unless otherwise prohibited pursuant to this title.

2. Facilities attached or sited adjacent to existing structures. Whenever possible, facilities shall be located on and/or inside existing structures. Appropriate types of existing structures may include, but are not limited to: buildings, water tanks, telephone poles and utility towers and poles, sign standards, light standards and roadway overpasses.

3. Sites with minimum separation. Sites that are more than five hundred (500) feet from school, playgrounds, and parks.

4. Sites that are not highly visible from adjacent roadways.

5. Unless otherwise indicated in MMC Chapter 17.46 or these Standards, no wireless facility shall be installed on an exposed ridgeline unless the facility blends with the surrounding existing natural and man-made environment and a finding is made that no other location is technically feasible.

6. The City expressly designates public open space and recreational vehicle park zoning districts, parks and schools as the least appropriate possible locations, and the absolute last choices for siting.

D. Disallowed Locations. The City expressly designates residential areas, as defined in Section 3, as disallowed locations for new wireless facilities.

Engineering and Design Standards for all Facilities.

The general design standards for wireless communications facilities subject to MMC Chapter

17.46 are as follows:

A. Basic Requirements. The proposed wireless facility and its supporting structure (if needed) shall be limited to the minimum size necessary to serve the defined service objectives of the wireless service provider or providers that will be using the facility, except where a larger facility has superior concealment elements.

B. Materials. The materials used shall be non-reflective and non-flammable.

C. Cabinet doors and other openings must be designed to stay securely closed, and openings in all facilities shall be shielded or made the smallest size feasible to protect against fire and wind-blown embers.

Resolution No. 26-54

Page 6 of 27 ends

_____________________
D. The tower, or other support structure, and all equipment shall be designed to withstand forces from seismic events. To that end, all wireless facility sites must be built to the applicable standards of Hardening Requirements including but not limited to APCO ANSI 2.106.1–2019, or their replacements. The telecommunications tower, pole or structure when fully loaded with antennas, transmitters, and other equipment and camouflaging shall be designed as determined by the Building Official. All equipment mounting racks and equipment used shall be anchored in such a manner that such a quake will not tip them over, throw the equipment off its shelves, or otherwise act to damage it.

E. All connections between various components of the facility, power lines, and conduit shall be designed in a manner to protect against damage by a natural disaster, a vehicular accident, an act of vandalism or similar external forces.

F. Stealth. The wireless facility shall be stealth. Stealth elements and techniques should be used to blend the facility with surrounding materials and colors of the support structure and make the facility appear to be something other than a wireless facility. Stealth elements include, but are not limited to, the following:

1. Radio frequency (RF) transparent screening or shrouds;

2. Matching the color of the existing support structure by painting, coating, or otherwise coloring the wireless facility, equipment, mounting brackets, and cabling;

3. Placing cables and wires inside the pole or beneath conduit of the smallest size possible;

4. Minimizing the size of the site;

5. Installing new infrastructure that matches existing infrastructure in the area surrounding the proposed site; and

6. Using paint of durable quality.

7. Built with weather-resistant materials while permitting weathered treatment for aesthetic reasons and to avoid reflective material.

G. Minimum Height. All antennas shall be located such that: (1) any person walking adjacent to the transmitting surface of the antenna will be walking on a grade that is a minimum of eight and one-half feet below the transmitting surface; and (2) no person at ground level will be exposed to Resolution No. 26-54

Page 7 of 27 ends

_____________________
an exposure level that is higher than allowed by the FCC’s general population exposure rules.

H. Facade-Mounted Equipment. Facade-mounted antennas and equipment shall be architecturally integrated into the building, or other support structure, design and otherwise made as unobtrusive as possible so that the facility does not appear to be a wireless facility. Antennas and equipment should be located entirely within an existing or newly created architectural feature so as to be completely screened from view. Facade-mounted facilities shall generally not extend more than eighteen (18) inches out from and may not project above the building face. Façade-mounted wireless telecommunication facilities shall not exceed twenty-eight (28) feet in height above the ground. However, antenna elements, mounted flush on the facade of an existing structure that exceeds twenty-eight (28) feet, may have a height equal to the height of the building.

I. Ground-Mounted Equipment.Outdoor ground-mounted equipment associated with base stations shall be avoided whenever feasible. In locations visible or accessible to the public, applicants shall conceal outdoor ground-mounted equipment, including ancillary power generation equipment, with opaque fences or landscape features that mimic the adjacent structure(s) (including, but not limited to, dumpster corrals and other accessory structures) and by painting, texturing, or otherwise concealing the facility as much as possible. Ground-mounted wireless communications facilities shall be located near existing structures or trees at similar heights for screening purposes where feasible. Not more than one ground-mounted antenna, provided that licensed amateur radio station antennas consistent with MMC 17.46.020(B)(2), shall also be permitted on each site.

J. Roof-Mounted Facilities. Roof-mounted antennas and necessary equipment shall be screened from above if visible from higher elevations. Rooftopmounted wireless telecommunication facilities shall not exceed twentyeight (28) feet in height or three (3) feet above the roof parapet from which they are attached, whichever is less restrictive. Associated roof-mounted equipment cabinets shall not extend more than three (3) feet above the roof from which it is attached and shall be set back a minimum of ten (10) feet from the edge of the roof. All roof-mounted equipment cabinets shall be located behind a mechanical screen wall. In the event that a roof parapet wall screens the equipment cabinets, a mechanical screen wall will not be required.

K. Freestanding Facilities. Freestanding facilities requiring a new monopole or other new support structure shall be stealth facilities. Further, they shall be located as close as possible to existing above-ground utilities, such as electrical towers or utility poles (which are not scheduled for removal or Resolution No. 26-54

Page 8 of 27 ends

_____________________
under grounding for at least 18 months after the date of application), light poles, trees of comparable heights, and in areas where they will not detract from the appearance of the City.

1. Freestanding wireless telecommunication facilities, including monopoles, shall not exceed twenty-eight (28) feet in height and shall not extend higher than the top of the ridgeline nearest the antenna. The height of a freestanding facility shall be measured from the natural undisturbed ground surface below the center of the base of the tower itself to the tip of the highest antenna or piece of equipment attached thereto.

2. Aside from the antenna itself, no additional equipment may be visible. All cables, including, but not limited to, electrical and utility cables, shall be run within the interior of the freestanding facility and shall be camouflaged or hidden to the fullest extent feasible without jeopardizing the physical integrity of the facility.

3. Monopole installations shall be situated so as to utilize existing natural or man-made features including topography, vegetation, buildings, or other structures to provide the greatest amount of visual screening.

4. All antenna components and accessory wireless equipment shall be treated with exterior coatings of a color and texture to match the predominant visual background or existing architectural elements so as to visually blend in with the surrounding development. Subdued colors and non-reflective materials that blend with surrounding materials and colors shall be used.

5. Monopoles shall be no greater in diameter or other cross-sectional dimensions than is necessary for the proper functioning of the facility.

L. All wireless telecommunication facilities shall be designed to prevent unauthorized climbing and graffiti.

M. Fire Safety Standards. All wireless facilities designs shall include:

1. a power shut off, such as by means of rapid entry Knox or similar type systems shall be installed;

2. surge protection devices capable of mitigating a direct or partial direct lightning discharge; and
Resolution No. 26-54

Page 9 of 27 ends

_____________________

3. surge protection devices capable of mitigating significant electrical disturbances that may enter the facility via conductive cables.

N. Satellite dish or parabolic antennas shall be situated as close to the ground as possible to reduce visual impact without compromising their function.

O. Support equipment pads, cabinets, shelters and buildings require architectural, landscape, color, fencing, or other camouflage treatment to minimize visual impacts to the extent deemed necessary by the Planning Director. Landscaping screening should also be provided if irrigation water is available.

P. No freestanding facility or ancillary support equipment may be located between the face of a building and a public street, bikeway, park or residence.

Waivers of These Standards.

A. A waiver of one or more of these Standards may be granted in the following circumstances:

1. Pursuant to MMC Section 17.46.060(D), if an applicant demonstrates to the Planning Commission through clear and convincing evidence that denial of an application would, within the meaning of federal law, prohibit or effectively prohibit the provision of personal wireless services, or otherwise violate applicable laws or regulations;

2. If an applicant demonstrates to the Planning Commission through clear and convincing evidence set forth in a feasibility study that compliance with a requirement of these Standards would be technically infeasible and the proposed wireless facility complies with the requirements of these Standards to the greatest extent technically feasible. For example, an exception to a requirement to conceal antennas in a shroud may be granted if shrouding is shown to be technically infeasible and an alternative concealment such as a colored film wrap is proposed; or

3. If an applicant demonstrates to the Planning Commission with clear and convincing evidence that the particular engineering, design or location proposed involves an alternative that better meets the purposes of Chapter 17.46 and only minor non-compliance with a requirement of these design Standards and results in no increase in public visual impact to the community or provides other benefits.

For example, an exception to the wireless facility location limitations may be granted when the applicant can demonstrate that Resolution No. 26-54

Page 10 of 27 ends

_____________________
the placement is less visible from viewsheds of residences or shielded by vegetation or existing infrastructure (such as barriers), or is less physically intrusive (for example, less impactful to tree roots or reduces noise). Among other factors, in deciding whether or not to grant an exception, the Planning Commission may consider the impact of expansions to the facility that the applicant would be entitled to make as of right if granted.

B. Waivers may only be requested at the time an application is initially submitted for a discretionary permit. The request must include both the specific provision(s) from which waiver is sought and the basis of the request, including all supporting evidence on which the applicant relies.

Any request for waiver after the City has deemed an application complete constitutes a material change to the proposed wireless facility and shall be considered a new application. A request for waiver from one or more requirements does not relieve the applicant from compliance with all other applicable provisions of law or of MMC Section 17.46.060.

Standard Conditions of Approval for Permits Under MMC Chapter 17.46.

A. Generally. In addition to any supplemental conditions imposed by the Planning Director or Planning Commission, as the case may be, all development permits or conditional use permits granted for wireless communications facilities subject to this Chapter 17.46 shall be subject to the following conditions, unless modified by the approving authority:

1. The permittee shall defend, indemnify, and hold harmless the city or any of its boards, commissions, agents, officers, and employees from any claim, action or proceeding against the city, its boards, commission, agents, officers, or employees to attack, set aside, void, or annul, the approval of the project, or to hold the City liable in whole or in part as a result of the engineering, design, construction or operation of the facility. The City shall promptly notify the provider(s) of any such claim, action or proceeding if the city bears its own attorney’s fees and costs, and the city defends the action in good faith.

2. The permittee shall be strictly liable for interference caused by its facilities with city communications systems. The permittee shall be responsible for costs for determining the source of the interference, all costs associated with eliminating the interference (including but not limited to filtering, installing cavities, installing directional antennas, powering down systems, and engineering analysis), and all costs arising from third party claims against the city attributable to the interference.

Resolution No. 26-54

Page 11 of 27 ends

_____________________

3. Subsequent submittals for this project shall be in substantial compliance with the plans date-stamped received by the Planning Department on _____________. The project shall comply with all conditions of approval stipulated in the referral sheets attached to the agenda report for this project. In the event the project plans conflict with any condition of approval, the condition shall take precedence and revised plans shall be submitted and approved by the Planning Director prior to the Environmental Sustainability Department for plan check.

4. The permit and rights conferred in this approval shall not be effective until the permittee signs, notarizes and returns the Acceptance of Conditions Affidavit accepting the conditions set forth herein. The applicant shall file this form with the Planning Department within 30 days of this decision or prior to issuance of any development, conditional use, building, electrical or encroachment permit.

5. The applicant shall digitally submit a complete set of plans, including the items required in Condition No. 6 to the Planning Department for consistency review and approval prior to plan check and again prior to the issuance of any building or development permits.

6. The Notice of Decision (including the signed and notarized Acceptance of Conditions Affidavit) shall be copied in its entirety and placed directly onto a separate plan sheet(s) to be included in the development plans prior to submitting any development permits from the City of Malibu Environmental Sustainability Department and encroachment permit.

7. A development permit or conditional use permit, as applicable, shall be valid for a period of ten (10) years from issuance, unless pursuant to another provision of the Code or these conditions, it expires sooner or is terminated. At the end of ten (10) years from the date of issuance, such development or conditional use permit shall automatically expire, unless an extension or renewal has been granted. A person holding a development permit or conditional use permit must either (1) remove the facility within thirty (30) days following the permit’s expiration (provided that removal of support structure owned by City, a utility, or another entity authorized to maintain a support structure need not be removed, but must be restored to its prior condition, except as specifically permitted by the City); or (2) prior to expiration, submit an application to renew the permit, which application must, among all other requirements, demonstrate that the impact of the wireless facility cannot be Resolution No. 26-54

Page 12 of 27 ends

_____________________
reduced. The wireless facility must remain in place until it is acted upon by the City and all appeals from the City’s decision exhausted.

8. The installation and construction authorized by a permit shall be completed within three (3) years after its approval, or it will expire without further action by the City unless prior to the three (3) years the applicant submit an extension request and the City, in its sole discretion, grants a time extension for due cause. The installation and construction authorized by a permit shall conclude, including any necessary post-installation repairs and/or restoration to the property, within thirty (30) days following the day construction commenced. The permittee must provide written notice to City within ten (10) days after completing construction, and may not begin operations until all City and Fire Department (if applicable) inspections have been completed and the project is found to be consistent with the permit. The expiration date shall be suspended until an appeal and/or litigation regarding the subject permit is resolved.

9. The Planning Director may grant up to four one-year extensions of the timeline, in Condition 7 above, for completing the installation and construction authorized by a development or condition use permit, if the Planning Director finds that the conditions, including but not limited to changes in the wireless ordinance under which the permit approval was issued, have not significantly changed.

10. Any questions of intent or interpretation of any condition of approval will be resolved by the Planning Director upon written request of such interpretation.

11. All structures shall conform to the requirements of the Environmental Sustainability Department, City Public Works Department, FCC and Los Angeles County Fire Department
requirements, as applicable. Notwithstanding this review, all required permits, including but not limited to an encroachment permit from the City, shall be secured.

12. Minor changes to the approved plans or the conditions of approval may be approved by the Planning Director, provided such changes achieve substantially the same results and the project is still in compliance with the MMC. An application with all required materials and fees shall be required.

Resolution No. 26-54

Page 13 of 27 ends

_____________________
Cultural Resources

13. In the event that potentially important cultural resources are found in the course of geologic testing, work shall immediately cease until a qualified archaeologist can provide an evaluation of the nature and significance of the resources and until the Planning Director can review this information. Where, as a result of this evaluation, the Planning Director determines that the project may have an adverse impact on cultural resources, a Phase II Evaluation of cultural resources shall be required pursuant to MMC Section

17.54.040(D)(4)(b).

14. If human bone is discovered, the procedures described in Section 7050.5 of the California Health and Safety Code shall be followed.

These procedures require notification of the coroner. If the coroner determines that the remains are those of a Native American, the applicant shall notify the Native American Heritage Commission by phone within 24 hours. Following notification of the Native American Heritage Commission, the procedures described in Section 5097.94 and Section 5097.98 of the California Public Resources Code shall be followed.

Wireless Facility Conditions

15. All antennas shall meet the minimum siting distances to public/uncontrolled areas required for compliance with the FCC regulations and standards governing the environmental effects of radio frequency emissions. Permittee shall keep up-to-date on current information from the FCC in regards to maximum
permissible radio frequency exposure levels. In the event that the FCC changes its guidelines for human exposure to radio frequency, permittee shall, within 30 days after any such change, submit to the Planning Director a report prepared by a qualified engineer that demonstrates actual compliance with such changed guidelines. The Director may, at permittee’s sole cost, retain an independent consultant to evaluate the compliance report and any potential modifications to the permit necessary to conform to the FCC’s guidelines. Failure to submit the compliance report required under this condition, or failure to maintain compliance with the FCC’s guidelines for human exposure to radio frequency at all times shall constitute grounds for permit revocation.

16. All antennas shall be located so that any person walking adjacent to the transmitting surface of the antenna will be walking on a grade, which is a minimum of eight and one-half feet below the transmitting surface.

Resolution No. 26-54

Page 14 of 27 ends

_____________________

17. All antennas, equipment, and support structures shall be engineered and designed to prevent unauthorized climbing.

18. The wireless facility shall be erected, operated, and maintained in compliance with the general requirements set forth in the Standards and any specific requirements in the permit.

19. The antenna and electrical support equipment shall, at all times, be operated in a manner that conforms to the applicable health and safety standards, including those imposed by MMC Chapter 17.46 and this Resolution.

20. Wireless communications facilities and equipment must comply with the City’s noise ordinance in MMC 8.24, or any successor provisions, and prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

21. The Planning Director’s approval is required if a generator is to be placed onsite for temporary or permanent use.

22. All non-ground-mounted equipment associated with the application shall be located no lower than eight feet above grade or ground level on the monopole or support structure.

23. The City or its designee may enter onto the facility area to inspect the facility upon 48 hours prior notice to the permittee. The permittee shall cooperate with all inspections and may be present for any inspection of its facility by the City. The City reserves the right to enter or direct its designee to enter the facility and support, repair, disable, or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

The City shall make an effort to contact the permittee prior to disabling or removing any facility elements, but in any case, shall notify permittee within 24 hours of doing so.

24. Testing of any equipment shall take place on weekdays only, and only between the hours of 8:30 a.m. and 4:30 p.m., except that testing is prohibited on holidays that fall on a weekday. In addition, testing is prohibited on weekend days.

25. Permittee shall obtain and maintain throughout the term of the permit commercial general liability insurance with a limit of five million dollars ($5,000,000) per occurrence for bodily injury and property damage and six million dollars ($6,000,000) general aggregate including premises operations, contractual liability, Resolution No. 26-54

Page 15 of 27 ends

_____________________
personal injury, and products completed operations. The relevant policy(ies) shall name the City, its elected/appointed officials, commission members, officers, representatives, agents, and employees as additional insureds. A true and correct copy of the policy of insurance shall constitute proof of insurance required by this Subsection. Permittee shall use its best efforts to provide thirty (30) days’ prior notice to the City of to the cancellation or material modification of any applicable insurance policy. Failure to maintain insurance consistent with this Condition shall automatically void the permit, and the permittee shall immediately deenergize and remove the facility from operation. The policy shall not have a pollution or other exclusion which excludes injuries or damages from EMF/RF exposures.

26. Prior to issuance of a City permit or encroachment permit, the permittee shall file with the City, and shall maintain in good standing throughout the term of the approval, a performance bond or other surety or another form of security for the removal of the facility in the event that the use is abandoned or the permit expires, or is revoked, or is otherwise terminated. The security shall be in the amount equal to the cost of physically removing the facility and all related facilities and equipment on the site, based on the higher of two contractor’s quotes for removal that are provided by the permittee. The permittee shall reimburse the city for staff time associated with the processing and tracking of the bond, based on the hourly rate adopted by the City Council. Reimbursement shall be paid when the security is posted and during each administrative review.

27. Permittee shall not move, alter, temporarily relocate, change, or interfere with any existing structure, improvement, or property without the prior consent of the owner of that structure, improvement, or property. No structure, improvement, or property owned by the City shall be moved to accommodate a permitted activity or encroachment, unless the City determines that such movement will not adversely affect the City or any surrounding businesses or residents, and the Permittee pays all costs and expenses related to the relocation of the City's structure, improvement, or property. Prior to commencement of any work pursuant to any permit, the permittee shall provide the City with documentation establishing to the city's satisfaction that the permittee has the legal right to use or interfere with any other structure, improvement, or property to be affected by permittee's facilities.

Resolution No. 26-54

Page 16 of 27 ends

_____________________

28. No possessory interest is created by a Wireless Permit. However, to the extent that a possessory interest is deemed created by a governmental entity with taxation authority, permittee
acknowledges that City has given to permittee notice pursuant to California Revenue and Taxation Code Section 107.6 that the use or occupancy of any public property pursuant to a development or conditional use permit may create a possessory interest which may be subject to the payment of property taxes levied upon such interest. Permittee shall be solely liable for, and shall pay and discharge prior to delinquency, any and all possessory interact taxes or other taxes, fees, and assessments levied against permittee’s right to possession, occupancy, or use of any public property pursuant to any right of possession, occupancy, or use created by this development or conditional use permit.

29. If not already completed, permittee shall enter into the appropriate agreement with the City, as determined by the City, prior to constructing, attaching, or operating a facility on municipal infrastructure. This permit is not a substitute for such agreement.

30. If a facility is not operated for a continuous period of three (3) months, the Wireless Permit and any other permit or approval therefor shall be deemed abandoned and terminated automatically, unless before the end of the three (3) month period (i) the Director has determined that the facility has resumed operations, or (ii) the City has received an application to transfer the permit to another service provider. No later than ninety (90) days from the date the facility is determined to have ceased operation, or the permittee has notified the Director of its intent to vacate the site, the permittee shall remove all equipment and improvements associated with the use and shall restore the site to its original condition to the satisfaction of the Director. The permittee shall provide written verification of the removal of the facilities within thirty (30) days of the date the removal is completed. If the facility is not removed within thirty (30) days after the permit has been discontinued pursuant to this subsection, the site shall be deemed to be a nuisance, and the City may cause the facility to be removed at permittee’s expense or by calling any bond or other financial assurance to pay for removal. If there are two (2) or more users of a single facility or support structure, then this provision shall apply to the specific elements or parts thereof that were abandoned but will not be effective for the entirety thereof until all users cease use thereof.

31. In the event the City determines that it is necessary to take legal action to enforce any of these conditions, or to revoke a permit, and Resolution No. 26-54

Page 17 of 27 ends

_____________________
such legal action is taken, the permittee shall be required to pay any and all costs of such legal action, including reasonable attorney’s fees, incurred by the City, even if the matter is not prosecuted to a final judgment or is amicably resolved, unless the City otherwise agrees, in its complete discretion, to waive said fees or any part thereof.

32. Interference with city communications systems and other governmental emergency systems is prohibited. Further, no permits issued pursuant to this chapter of the City Code establish any guarantee or warranty that Licensee’s facility will be free from interference from city or third-party communication systems.

Construction

33. Installation hours shall be limited to Monday through Friday from 7:00 a.m. to 7:00 p.m. and Saturdays from 8:00 a.m. to 5:00 p.m. No installation activities shall be permitted on Sundays and Citydesignated holidays. The restricted work hours described in this condition do not apply to emergency maintenance necessary to protect health or property. The City of Malibu may issue a Stop Work Order if permittee violates this condition. Construction activities shall be conducted in compliance with, and abide by, all applicable safety codes and permit conditions.

34. All sites must be designed and build to the standards of ANSI/APCO Public Safety Grade Site Hardening Requirements, also referred to as “APCO ANSI 2.106.1-2019”.

Site Specific Conditions

35. In the event that the electric service provider does not currently offer an alternative metering option, the permittee shall remove the above-grade electric meter when such option becomes available.

Prior to removing the above-grade electric meter, the permittee shall apply for any encroachment and/or other ministerial permit(s) required to perform the removal. Upon removal, the permittee shall restore the affected area to its original condition that existed prior to installation of the equipment.

36. The permittee acknowledges that the City specifically includes conditions of approval related to (a) painting, coloring or finishing the equipment to match the monopole or support structure; (b) undergrounding all equipment to the extent possible; (c) installing equipment within shrouds, conduits and risers as concealment elements engineered and designed to integrate the wireless facility Resolution No. 26-54

Page 18 of 27 ends

_____________________
with the surrounding built and natural environment; and (d) specific structural, seismic, electrical, fire and operating/maintenance requirements. Any future modifications to the permittee’s wireless facility must maintain or improve all concealment elements and safety precautions.

37. Before the permittee submits any applications for construction, encroachment, excavation or other required permits in connection with this permit, the permittee must incorporate a true and correct copy of this permit, all conditions associated with this permit and any approved photo simulations into the project plans (collectively, the “Approved Plans”). The permittee must construct, install and operate the wireless facility in substantial compliance with the Approved Plans as determined by the Director or the Director’s designee. Any substantial or material alterations, modifications or other changes to the Approved Plans, whether requested by the permittee or required by other departments or public agencies with jurisdiction over the wireless facility, must be submitted in a written request subject to the Director’s prior review and approval, who may refer the request to the original approval authority if the Director finds that the requested alteration, modification or other change substantially deviates from the Approved Plans or implicates a significant or substantial land-use concern.

38. The permittee shall install and at all times maintain in good condition a “Network Operations Center Information” and “RF Caution” sign on the utility pole no less than three (3) feet below the antenna (measured from the top of the sign) and no less than nine (9) feet above the ground line (measured from the bottom of the sign). Signs required under this condition shall be installed so that a person can clearly see the sign as he or she approaches within three (3) feet of the antenna structure. If any person on or within the property is or may be exposed to emissions that exceed applicable FCC uncontrolled/general population limits at any time the sign shall expressly so state, and provide instructions on how persons can avoid any such exposure. The sign shall also include the name(s) of the facility owner(s), equipment owner(s) and operator(s)/carrier(s) of the antenna(s), property owner name, as well as emergency phone number(s) for all such parties. The sign shall not be lighted, unless applicable law, rule or regulation requires lighting. No signs or advertising devices other than required certification, warning, required seals or signage, other signage required by law, this Chapter, any City or applicable state code or the Los Angeles County Fire Department Chief or his or her designee shall be permitted. The sign shall be no larger than two (2) square feet.

Resolution No. 26-54

Page 19 of 27 ends

_____________________

39. The permittee shall ensure that all signage complies with FCC Office of Engineering and Technology Bulletin 65, CPUC General Order 95 or American National Standards Institute C95.2 for color, symbol, and content conventions. All such signage shall at all times provide a working local or toll-free telephone number to its network operations center, and such telephone number shall be able to reach a live person who can exert transmitter power-down control over this site as required by the FCC.

40. In the event that the FCC changes any of radio frequency signage requirements that are applicable to the project site approved herein or ANSI Z535.1, ANSI Z535.2, and ANSI C95.2 standards that are applicable to the project site approved herein are changed, the permittee, within 30 days of each such change, at its own cost and expense, shall replace the signage at the project site to comply with the current standards.

41. The permittee shall maintain the paint, color and finish of the facility in good condition at all times.

42. All improvements, including foundations, and appurtenant ground wires, shall be removed from the property and the site restored to its original pre-installation conditions within 90 days of cessation of operation or abandonment of the facility.

43. Build-Out Conditions.
a. Permittee shall not commence any excavation, construction, installation or other work on the project site until and unless it demonstrates to the City Public Works Department that the project complies with these Conditions along with all
applicable laws, regulations, codes and other rules related to public health and safety, including without limitation all applicable provisions in California Public Utilities
Commission General Order 95 and MMC Chapters 8.12,

8.24 and 15.08.
b. To the extent that a pole owner or any provision in the MMC or this resolution require greater or more restrictive
standards than California Public Utilities Commission
General Order 95, if applicable, those standards shall
control.

44. Permittee shall at all times maintain compliance with all applicable federal, State and local laws, regulations, ordinances and other rules, including Americans with Disabilities Act (ADA) requirements.

Resolution No. 26-54

Page 20 of 27 ends

_____________________

45. The permittee shall cooperate with all inspections. The City and its designees reserve the right to support, repair, disable or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

46. Permittee shall at all times maintain accurate contact information for all parties responsible for the facility, which shall include a phone number, street mailing address and email address for at least one natural person. All such contact information for responsible parties shall be provided to the Planning Department at the time of permit issuance and within one business day of permittee’s receipt of City staff’s written request.

47. Permittee shall undertake all reasonable efforts to avoid undue adverse impacts to adjacent properties and/or uses that may arise from the construction, operation, maintenance, modification and removal of the facility.

48. The site and the facility must be maintained in a neat and clean manner and in accordance with all approved plans and conditions of approval.

49. Permittee shall promptly remove any graffiti on the wireless facility at permittee’s sole expense within 48 hours after notice.

Prior to Operation

50. The applicant shall request a final Planning Department inspection and final building inspection by the City of Malibu Environmental Sustainability Department immediately after the wireless facility has been installed and prior to the commencement of services.

51. Within thirty (30) calendar days following the installation of any wireless communications facilities, the applicant shall provide to the Planning Department with a field report prepared by a qualified engineer verifying that the unit has been inspected, tested, and is operating in compliance with FCC standards. Specifically, the onsite post-installation radiofrequency (RF) emissions testing must demonstrate actual compliance with the FCC OET Bulletin 65 RF emissions safety guidelines for general population/uncontrolled RF exposure in all sectors. For this testing, the transmitter shall be operating at maximum operating power, and the testing shall occur outwards to a distance where the RF emissions no longer exceed the uncontrolled/general population limit. Such report and
documentation shall include the make and model (or other identifying information) of the unit tested, the date and time of the Resolution No. 26-54

Page 21 of 27 ends

_____________________
inspection, a certification that the unit is properly installed and working within applicable FCC limits, and a specific notation of the distance from the transmitter at which the emissions are equal to or less than the uncontrolled/general population limit.

52. The operation of the approved facility shall commence no later than one (1) month after the City completes its post-installation inspections of the facility, any issues with the facility are resolved, and the City receives the RF testing report required in the condition of approval above, or the development or conditional use permit will expire without further action by the City.

Fixed Conditions

53. Violation of any of the conditions of this approval shall be cause for revocation and termination of all rights thereunder.

Eligible Facilities Requests
All permits for an eligible facilities requests under MMC Chapter 17.46 shall be subject to the following conditions and all of the other conditions of approval placed on a Wireless Permit, unless modified by the approving authority:

54. Any permit granted in response to an application qualifying as an eligible facilities request shall be subject to the terms and conditions of the underlying permit.

55. The City’s grant or grant by operation of law of an eligible facilities request permit constitutes a federally-mandated modification to the underlying permit or approval for the subject tower or base station.

Notwithstanding any permit duration established in another permit condition, the City’s grant or grant by operation of law of a eligible facilities request permit will not extend the permit term for the underlying permit or any other underlying regulatory approval, and its term shall be coterminous with the underlying permit or other regulatory approval for the subject tower or base station.

56. The City’s grant or grant by operation of law of an eligible facilities request does not waive, and shall not be construed to waive, any standing by the City to challenge Section 6409(a) of the Spectrum Act, any FCC rules that interpret Section 6409(a) of the Spectrum Act, or any modification to Section 6409(a) of the Spectrum Act.

Resolution No. 26-54

Page 22 of 27 ends

_____________________
Small Cell Facilities
In addition to the other conditions of approval placed on a Wireless Permit, all permits for a small cell facility under MMC Chapter 17.46 shall be subject to the following additional condition, unless modified by the approving authority:

57. The City’s grant of a permit for a small cell facility request does not waive, and shall not be construed to waive, any standing by the city to challenge any FCC orders or rules related to small cell facilities, or any modification to those FCC orders or rules.

Basic Application Requirements for Permits Under MMC Chapter 17.46.

A. Generally. In addition to providing all required fees, all wireless telecommunication facility carriers or providers shall provide the information required by a separate application form published, and updated from time to time, by the City. If no such form is available, then the applicant must submit all documents, information, and any other materials necessary to allow the City to make required findings and ensure that the proposed facility will comply with applicable laws and not endanger the public health, safety, or welfare. Such information may include:

1. Contact information for:
a. Applicant and their representatives
b. Owner of proposed wireless communications facility
c. If different from facility owner, the identity of the person or entity responsible for operating the proposed wireless
facility
d. The property owner or owner of the structure on which the proposed wireless facility would be installed
e. Names, addresses, telephone numbers, and email addresses of anyone acting on behalf of the applicant with regard to the application;
f. The name, address and phone number of all persons that prepared or assisted in preparing the application and any required reports;
g. The postal address, parcel number, or utility pole identifier of the property;
h. The location of the schools, playgrounds and parks within 500 feet of the project site;
i. Local contact person for emergencies
j. Assessor’s Parcel Number

2. Purpose of new wireless communications facility or amendment

3. Type of Application (Select all that apply)
a. Eligible Facilities Request
b. Small Cell – Collocation
Resolution No. 26-54

Page 23 of 27 ends

_____________________
c. Small Cell – New Structure
d. Collocation (Non-Small Cell)
e. All Other Wireless Communications Facilities
f. Permit Renewal
g. Waiver

4. Letter of authorization signed by the property owner authorizing the applicant to submit and process the application, including executed copies of any leases, letters of agency, or proof of ownership, of private property involved in the project.

5. Authorizations, and Licenses

6. Provide previous approvals, if applicable, and Certificate of Completion. Site inspection fees may apply if a final inspection was never requested

7. Identify all other required permits and approvals for the subject facility.

8. Electrical and Structural Safety Information. The following engineering documents prepared under the responsible charge of and sealed by a California licensed Professional Engineer must be included in the application:
a. A short circuit and coordination study (“SCCS”) calculated pursuant to the IEEE 551-2006: Recommended Practice for Calculating AC Short-Circuit Currents in Industrial and Commercial Power Systems or the latest version of that
standard. The study must demonstrate the protection devices will ensure the equipment enclosure will not be breached.

The SCCS must include analysis of Voltage Transient
Surges due to contact of conductors of different voltages; b. A one-line diagram of the electrical system;
c. Voltage Drop & Load Flow Study;
d. Load Calculation;
e. Panel Directories;
f. A plot plan showing the location of the mounting structure including address, or structure designation, or GPS location on the front sheet;
g. A plot plan showing the location of the service disconnecting means; and
h. An elevation drawing of the equipment and the service disconnecting means.

9. Structural Safety Information. The structural/civil engineering documents prepared under the responsible charge of and sealed by a California licensed professional civil engineer.
a. Photo simulations, from at least three different angles, showing the pole and streetscape before and after
installation. In some cases, more than three different angles may be required;
Resolution No. 26-54

Page 24 of 27 ends

_____________________
b. The azimuth, size and center-line height location of all proposed and existing antenna(s) on the supporting
structure;
c. The number, type and model of the antenna(s) that will be used with a copy of the specification sheet;
d. The make, model, type and manufacturer of any tower
involved and a design plan stating the tower’s capacity to accommodate multiple users;
e. Site and Construction Plans. Complete and accurate plans, drawn to scale, signed, and sealed by a California-licensed engineer, land surveyor, and/or architect, which include the following items.
(1) A site plan and elevation drawings for the facility as existing and as proposed with all height and width
measurements explicitly stated.
(2) A site plan describing the proposed tower and
antenna(s) and all related fixtures, structures,
appurtenances and apparatus, including height above
pre-existing grade, materials, color and lighting;
(3) A depiction, with height and width measurements
explicitly stated, of all existing and proposed
transmission equipment.
(4) A depiction of all existing and proposed utility runs and points of contact.
(5) A depiction of the leased or licensed area of the site with all rights-of-way and easements for access and
utilities labeled in plan view.
f. Detailed map with locations of the poles or other property on which equipment is to be located, including specific pole identification number, if applicable, and the areas it will service;
g. Description as to why the desired location is superior to other similar locations, from a community perspective, including, but not limited to:
(1) Proximity to residential buildings and descriptions of efforts to prevent any blocking of views of
impressive scenes; and
(2) Written documentation demonstrating a good faith
effort to locate the proposed facility in the least
intrusive location in accordance with the location
requirements of this Resolution.
h. A description in writing and a visual rendering
demonstrating effective screening of all ground-mounted or roof-mounted equipment of the facility from view.

Resolution No. 26-54

Page 25 of 27 ends

_____________________
i. Color-coded carrier-generated RF Coverage (propagation) maps, at a scale no smaller than 1 inch (1”) to a quarter (1/4) mile with all appropriate legends, showing the coverage for the highest and lowest frequencies to be used by the facility.

Frequencies are to be stated numerically, not qualitatively.

Provide a represented value in dB of each colors it
specifically represents.
j. If the project involves, modifies or will use an existing facility or structure, a description of the type of structure (e.g., guyed, self-supporting lattice or monopole), and a report on the physical condition of the facility certified by a professional engineer licensed in the state of California. k. If the application is for a new tower, clear and convincing technical evidence by a carrier or wireless service provider justifying the total height of the proposed facility and the need for such to the exclusion of all reasonable alternatives.

Evidence in the form of propagation studies must include all modeling data and assumptions used to produce the studies at the requested height and should take into consideration the ability to collocate other carriers in the future.
l. A siting analysis which identifies other feasible locations within or outside the City which could serve the area
intended to be served by the facility, unless the applicant provides compelling technical reasons for providing fewer than the minimum.
m. An affirmation, under penalty of perjury, that the proposed installation will be FCC compliant, in that it will not cause members of the general public to be exposed to RF levels that exceed the emissions levels deemed safe by the FCC. A copy of the fully completed FCC form “A Local
Government Official’s Guide to Transmitting Antenna RF
Emission Safety: Rules, Procedures, and Practical Guidance:

Appendix A” titled “Optional Checklist for Determination of Whether a Facility is Categorically Excluded” for each frequency band of RF emissions to be transmitted from the proposed facility upon the approval of the application. All planned radio frequency emissions on all frequency bands must be shown on the Appendix A form(s) attached to the application. All planned radio frequency emissions are to be entered on each Appendix A form only in wattage units of “effective radiated power.”
n. A statement detailing the frequency, modulation and class of service of radio or other transmitting equipment;
o. A copy of the FCC license applicable for the intended use of the proposed facilities;
Resolution No. 26-54

Page 26 of 27 ends

_____________________
p. A HazMat Business Plan for all new generators, and any storage and/or use of hazardous materials during the project, to include:
i. A list of toxic substances that may develop during
arcing or fire that may impede fire suppression
efforts;
ii. A list of hazards that may develop during arcing or fire that may impede fire suppression efforts;
q. A demolition plan, if applicable.
r. A written statement of the applicant’s willingness to allow other carriers to co-locate on the proposed personal wireless service facility where technically and economically feasible and aesthetically desirable, subject to the qualification that colocation should not occur when public exposures from the resulting higher cumulative sources would exceed FCC
limits.
s. Such other information as the Director shall establish. t. A statement signed by a person with legal authority to bind the applicant attesting under penalty of perjury to the accuracy of the information provided in the application. If attester not an authorized employee of the applicant, then the attester must demonstrate that it is an authorized agent of the applicant, with lawful Power of Attorney from the applicant.

SECTION 10. Environmental Review.

This Resolution is not a project within the meaning of Section 15378 of the State of California Environmental Quality Act (CEQA) Guidelines, because it has no potential for resulting in physical change in the environment, directly or indirectly. The Resolution does not authorize any specific development or installation on any specific piece of property within the City’s boundaries.

Moreover, when and if an application for installation is submitted, the City will at that time conduct preliminary review of the application in accordance with CEQA.

Alternatively, even if the Resolution is a “project” within the meaning of State CEQA Guidelines section 15378, the Resolution is exempt from CEQA on multiple grounds. First, the Resolution is exempt CEQA because the City Council’s adoption of the Resolution is covered by the general rule that CEQA applies only to projects which have the potential for causing a significant effect on the environment. (State CEQA Guidelines, § 15061(b)(3)). That is, approval of the Resolution will not result in the actual installation of any facilities in the City. In order to install a facility in accordance with this Resolution, the wireless provider would have to submit an application for installation of the wireless facility. At that time, the City will have specific and definite information regarding the facility to review in accordance with CEQA. And, in fact, the City will conduct preliminary review under CEQA at that time. Second, the Resolution is categorically exempt under CEQA Guidelines §§ 15307 and 15308 as an action taken by a regulatory agency, as authorized by local ordinance (MMC Chapter 17.46), to assure the protection of natural resources Resolution No. 26-54

Page 27 of 27 ends

_____________________
and the environment. The Resolution strengthens the City’s location and design standards for new wireless facilities. It does not weaken any existing standard and does not authorize any construction or development. The City’s wireless permitting process involves procedures for protection of the environment, including discretionary review of each application and coastal development permit review under the certified Local Coastal Program where applicable. None of the exceptions in CEQA Guidelines §15300.2 applies.

Moreover, in the event that the Resolution is interpreted so as to permit installation of wireless communications facilities on a particular site, the installation would be exempt from CEQA review in accordance with either State CEQA Guidelines section 15302 (replacement or reconstruction), State CEQA Guidelines section 15303 (new construction or conversion of small structures), and/or State CEQA Guidelines section 15304 (minor alterations to land).

SECTION 11. This Resolution shall become effective immediately upon its passage and adoption.

SECTION 12. The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

PASSED, APPROVED, and ADOPTED this 13th day of July 2026. ______________________________
BRUCE SILVERSTEIN, Mayor
ATTEST:
__________________________________
KELSEY PETTIJOHN, City Clerk
(seal)
APPROVED AS TO FORM:
__________________________________
TREVOR RUSIN, Interim City Attorney
Attachment 3
RESOLUTION NO. 26-53 20-65

A RESOLUTION OF THE CITY OF MALIBU AMENDING AND REPLACING RESOLUTION NO. 20-65 (WIRELESS FACILITIES IN THE PUBLIC RIGHTOF-WAY) TO RESTRICT NEW WIRELESS FACILITIES IN RESIDENTIAL AREAS, DEFINE “RESIDENTIAL AREAS,” AND REVISE THE RELATED

SPACING, SEPARATION, AND LOCATION PREFERENCE STANDARDS

ADOPTING ENGINEERING, DESIGN AND LOCATION STANDARDS AND

CONDITIONS OF APPROVAL FOR WIRELESS FACILITIES IN THE PUBLIC RIGHT-OF-WAY; AND FINDING THAT THIS RESOLUTION IS NOT

SUBJECT TO THE CALIFORNIA ENVIRONMENTAL QUALITY ACT AND,

IN THE ALTERNATIVE, IS EXEMPT FROM CEQA THE SAME EXEMPT

FROM THE CALIFORNIA ENVIRONMENTAL QUALITY ACT
The City Council of the City of Malibu does hereby find, resolve and order as follows:

SECTION 1. Recitals
A. Chapter 12.02 of the Malibu Municipal Code governs the permitting, installation, and regulation of personal wireless services facilities in the City’s public right-of-way (ROW); B. Section 12.02.050(D) provides that “[a]ll applicants shall engineer, design and locate the wireless facilities in accordance with the standards and wireless regulations set forth separately though the resolution adopted by the City Council;” C. The City’s public rights-of-way are a uniquely valuable public resource, closely linked with the City’s character, making the regulation of wireless installations in the public rightsof-way necessary to protect and preserve the aesthetics in the community; D. Being authorized to do so, the City wishes to establish engineering, design and development standards applicable to wireless installations in the public rights-of-way; E. The City also wishes to set standard conditions of approval applicable to wireless ROW permits; and
F. On December 9, 2020 the City Council conducted a duly noticed public hearing and received testimony from City staff and all interested parties regarding the engineering, design and development standards.

G. On July 13, 2026 the City Council held a duly noticed meeting and received testimony from City staff and all interested parties regarding the residential restriction.

Purpose.

The purpose of this document is to (1) establish design and location standards (Standards) for wireless facilities in the public right-of-way (ROW) within the City; and (2) set standard conditions of approval for Wireless ROW Permits (WRPs).

Resolution No. 26-53 20-65

Page 2 of 24 ends

_____________________
Definitions.

For the purposes of these Standards, the definitions set forth in Malibu Municipal Code (MMC) Section 12.02.020 are incorporated by reference into this Resolution and in addition the following definitions apply:

A. “Pole-mounted facility” means a wireless facility that is, or is proposed to be, attached to or contained in a pole.

B. “Residential areas” means the portion of the public right-of-way, excluding utility poles along Pacific Coast Highway or other major arterial roadways as depicted in Figure CI-1 of the City’s General Plan, where any parcel abutting or fronting the right-of-way within three hundred (300) feet of the proposed facility is zoned RR, SF, MF, MFBF, or MH, or is a Planned Development parcel whose principal use is residential, under MMC Chapter 17.06. Distance shall be measured from the farthest projection of the proposed wireless facility to the nearest such residential parcel line.

BC. “Stealth facility” (or “stealth facilities”) means a wireless facility designed to look like something other than a wireless tower or base station.

General Standards for all Facilities The following standards shall apply to all wireless facilities in the ROW:

A. All wireless facilities shall be engineered and designed to minimize the visual impact by means of placement, screening, camouflaging, painting and texturing and to be compatible with existing architectural elements, building materials and other site characteristics. The applicant shall use the smallest and least visible antenna possible to accomplish the facility’s objectives. All antennas and support structures shall be painted and/or textured to achieve architectural compatibility with the structures for which they are attached and/or located.

B. Prohibition of Generators. Permanent generators are prohibited.

C. General Orders. All installations shall comply with applicable California Public Utilities Commission (“CPUC”) General Orders, including, but not limited to General Order 95, and, if stricter, the pole owner’s safety standards. None of the engineering or design standards are meant to conflict with or cause a violation of CPUC General Orders. Accordingly, the Standards can be adjusted on a case-by-case basis if it is demonstrated that adjustment is necessary to ensure compliance with CPUC rules on safety.

D. Electric Service. The permittee shall request that the permittee’s electric service provider apply flat-rate billing for any proposed electric service, wireless smart metering or other alternative metering option that would Resolution No. 26-53 20-65

Page 3 of 24 ends

_____________________
obviate the need for an above-grade electric meter. If flat-rate service is not available, applicants may install a shrouded “smart meter” that shall not exceed the width of the pole; provided, however that such smart meter shall be placed at least ten (10) feet above ground level. If the proposed project involves a ground-mounted equipment cabinet, an electric meter may be integrated with and recessed into the cabinet, but the Director shall not approve a separate ground-mounted electric meter pedestal unless (1) the separate ground-mounted meter pedestal would be placed off the sidewalk and (2) the applicant demonstrates with clear and convincing evidence that all other alternatives for the electric meter are not available. All support equipment located within cabinets, shelters, or similar structures shall be screened from public view to the maximum extent feasible.

Undergrounding of support equipment is required wherever practicable.

E. Security. All equipment and facilities shall be installed in a manner to avoid being an attractive nuisance and to prevent unauthorized access, climbing, and graffiti.

F. Safety. All wireless facilities, including each piece of equipment, shall be located and placed in a manner so as to not interfere with the public use of the ROW; impede the flow of vehicular or pedestrian traffic; impair the primary use and purpose of poles/signs/traffic signals or other infrastructure; interfere with outdoor dining areas or emergency facilities; or otherwise obstruct the accessibility of the ROW. Further, all wireless facilities and associated equipment shall comply with Americans with Disabilities Act (ADA) requirements.

G. Fire and Electrical Safety Standards. All wireless facilities shall contain:

1. A power shut off readily accessible to fire service personnel for emergencies;

2. Surge protection for lightning discharge or other significant electrical disturbances;

3. Signage as required by the permit conditions, the National Electric Code or the Los Angeles County Fire Department Chief or his or her designee; and

4. Instructions for first responders to de-energize the equipment.

H. Noise. Wireless facilities and equipment must comply with the City’s noise ordinance in MMC 8.24, or any successor provisions, and be designed to prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

Resolution No. 26-53 20-65

Page 4 of 24 ends

_____________________
I. Lighting. Lighting of antenna structures and their electrical support equipment is prohibited, except as required by any order or regulation of the Federal Communications Commission (FCC) or the Federal Aviation Administration (FAA) and except for manually operated emergency lights for use when official operating personnel are on site.

J. Signs. No facility may display any signage or advertisement unless it is expressly allowed by this paragraph or required by law or a permit condition. Every facility shall at all times display signage that accurately identifies the facility owner and provides the owner’s unique site number and a local or toll-free telephone number to contact the facility owner’s operations center.

K. Landscaping. Where appropriate, facilities shall be installed so as to maintain and enhance existing landscaping on the site, including trees, foliage and shrubs, whether or not utilized for screening. In addition to any landscaping used for concealment or screening purposes, the applicant shall replace any existing landscaping displaced during construction or installation of the applicant’s facility. The applicant’s landscaping plan shall be subject to the City’s review and approval but shall, at a minimum, match the existing landscaping and foliage surrounding the installation site consistent with MMC Section 17.53.090.

Location Standards for All Facilities.

The location standards for all wireless facilities, other than those that qualify as eligible facilities requests, in the ROW are as follows:

A. Spacing. Wireless facilities located in residential areas adjacent to any residential zone district, except for those facilities placed on utility poles located along Pacific Coast Highway or other major arterial roadways as depicted in Figure CI-1 of the City’s General Plan, shall not be located within one thousand (1,000) six hundred (600) feet of any other wireless facility, unless a finding is made, based on technical evidence acceptable to the Planning Director, as appropriate, showing a clear need for the facility and that no technically feasible alternative site exists. This provision does not apply to wireless facilities located adjacent to any commercial zone district.

B. Location preference for wireless facilities should be given to the following:

1. Installations along major arterial roadways as depicted in Figure CI1 of the City’s General Plan.

2. Locations adjacent to property designated non-residential (except for public open space and recreational vehicle park zoning districts), unless otherwise Resolution No. 26-53 20-65

Page 5 of 24 ends

_____________________
prohibited pursuant to this title.

23. Facilities attached to existing utility poles or street lights, or sited adjacent to existing structures not used for human habitation or school grounds or to playgrounds or parks. Whenever possible, facilities shall be located on and/or inside existing structures.

3. 4. Sites that are not highly visible from adjacent roadways and do not obstruct views of impressive scenes off the Pacific Ocean, offshore islands, the Santa Monica Mountains, canyons, valleys, or ravines.

4.5. Unless otherwise indicated in this title, no wireless facility shall be installed on an exposed ridgeline unless the facility blends with the surrounding existing natural and man-made environment and a finding is made that no other location is technically feasible.

C. Discouraged and Disallowed Locations/Zones.

1. Wireless facilities that are within 250 feet from the property line of an open space or recreational area.

2. The City expressly designates residential areas, as defined in Section 3, as disallowed locations for new wireless facilities. 2 3. Wireless facilities that are less than five hundred (500) feet from school grounds, playgrounds or parks.
3 4. Wireless facilities that are less than four hundred fifty (450) feet from any other existing wireless facility within or adjacent to any residential zone district, except for those facilities placed on utility poles located along Pacific Coast Highway or other major arterial roadways as depicted in Figure CI-1 of the City’s General Plan.

D. Placements shall not be in front of dwelling units or schools.

Undergrounding Standards for All Facilities.

With regard to undergrounding wireless facilities, the following standards apply:

A. Equipment, including remote radio units (RRUs) that cannot be placed with the antenna in the shroud, must be placed underground, subject to Section 7(B) below. Vaults and pull boxes shall be installed flush to grade.

B. Ground-mounted equipment is prohibited unless required for technical reasons.

Resolution No. 26-53 20-65

Page 6 of 24 ends

_____________________

1. If required, ground-mounted wireless facilities shall be located near existing structures or trees at similar heights for screening purposes.

The equipment shall be enclosed in cabinets, sized only for the necessary equipment. Further, if ground mounted, the antennas, equipment, cabinet and support structure shall be painted, textured, landscaped or otherwise camouflaged as much as possible to integrate the structure into the environment. Colors and materials for facilities shall be non-reflective and chosen to minimize visibility.

As such, ground-mounted equipment shall be stealth.

2. The ground-mounted equipment must not obstruct ocean views.

3. Not more than one ground-mounted antenna shall be permitted on each site.

Design Standards for all Facilities.

The general design standards for wireless facilities in the ROW are as follows:

A. Materials. The materials used shall be non-reflective and non-flammable.

B. Cabinet doors must be designed to stay securely closed, and openings in all facilities shall be shielded or made the smallest size feasible to protect against fire and wind-blown embers.

C. The pole, or other support structure, and all equipment shall be designed to withstand forces from seismic events.

D. All connections between various components of the facility, power lines, and conduit shall be designed in a manner to protect against damage by a natural disaster, a vehicular accident, an act of vandalism or similar external forces.

E. Stealth. The wireless facility shall be stealth. Stealth elements and techniques should be used to blend the facility with surrounding materials and colors of the support structure and make the facility appear to be something other than a wireless facility. Stealth elements include, but are not limited to, the following:

1. Radio frequency (RF) transparent screening or shrouds;

2. Matching the color of the existing support structure by painting, coating, or otherwise coloring the wireless facility, equipment, mounting brackets, and cabling;

3. Placing cables and wires inside the pole or beneath conduit of the smallest size possible;
Resolution No. 26-53 20-65

Page 7 of 24 ends

_____________________

4. Minimizing the size of the site;

5. Installing new infrastructure that matches existing infrastructure in the area surrounding the proposed site; and

6. Using paint of durable quality.

F. Curb Setback Requirements. New or replacement poles shall be a minimum of 18 inches from the face of the curb.

G. Collocation. The City has a preference for the use of existing infrastructure.

Wireless facilities shall be collocated on existing poles or other facilities when possible. No permittee shall restrict access to an existing antenna location if required to collocate by the City and if possible to do so.

H. Minimum Height. All antennas shall be located such that: (1) any person walking adjacent to the transmitting surface of the antenna will be walking on a grade that is a minimum of eight and one-half feet below the transmitting surface; and (2) no person at ground level will be exposed to an exposure level that is higher than allowed by the FCC’s general population exposure rules.

I. Strand-mounted Facilities. Strand-mounted facilities are encouraged. The facilities must be stealth and of the smallest size that is technically feasible to reduce aesthetic impacts.

Engineering and Design Standards for Pole-Mounted Facilities.

In addition to the generally applicable standards set forth above, the design standards for polemounted facilities in the ROW are as follows:

A. Facilities on Streetlight Poles.

1. Stealth. The facility shall be engineered, designed, painted, coated, and otherwise made to maintain the look of a streetlight pole rather than a wireless facility, tower, or base station.

2. Antennas and RRUs. Antennas shall be top-mounted in a shroud, and RRUs and other equipment shall be placed underground. If RRUs and equipment cannot be underground, then they shall be placed within the shroud with the antenna. RRUs attached to the side of the pole or ground-mounted are discouraged, but if they are required due to technical reasons, they should use the smallest RRU volume possible and be stacked vertically and close together with minimal distance from the pole.

Resolution No. 26-53 20-65

Page 8 of 24 ends

_____________________

3. Dimensions. Antennas shall be of the smallest possible size, but in no case more than three cubic feet in volume. Pole-top wireless facilities, including shroud, shall be no more than 60 inches in height and 14.5 inches in diameter.

4. Cables and Wiring. All cables and wiring must be within the pole.

B. Facilities on Wood Utility Poles.

1. Stealth. The facility shall be engineered, designed, painted, coated, and otherwise made to maintain the look of a utility pole rather than a wireless facility, tower, or base station.

2. Antennas. The preferred mounting type for wireless facilities on wood utility poles is side-mounting.
a. Side-mounted Facilities. Antennas and RRUs shall be midpole mounted (i.e., mid-pole mounted) in a shroud. If RRUs are attached to the side of the pole, the facility should use the smallest RRU volume possible, and the RRUs should be
stacked vertically and close together with minimal distance from the pole.
(1) Antennas shall be of the smallest possible size, but in no case more than three cubic feet in volume.
(2) Side-mounted wireless facilities shall be of the
smallest size technically feasible and shall not
project from the pole more than 30 inches. The
diameter of the shroud shall be no greater than the
diameter of the pole or 14.5 inches, whichever is less.

Side-mounted facilities shall only extend out on one
side of the pole.
b. Top-mounted Facilities. Antennas and RRUs shall be topmounted in a shroud. (1) Dimensions. Antennas shall be of the smallest
possible size, but in no case more than three cubic
feet in volume.
(a) Pole-top wireless facilities, including shroud,
shall be no more than 72 inches in height and

14.5 inches in diameter.

Resolution No. 26-53 20-65

Page 9 of 24 ends

_____________________

3. Cables and Wiring. All cables and wiring must be within the conduit on the exterior of the pole. The conduit must be a color that matches the pole and of the smallest size technically feasible.

C. Replacement Poles. If an applicant proposes or is required to install a replacement pole to accommodate the proposed facility:

1. Placement. A replacement pole must be in the same location as the pole that it is replacing or as close to the original location as possible, taking into account pole owner safety-related requirements and all applicable location and placement standards herein.

2. Design. Replacement poles should match the design (e.g., color, dimensions, height, style, and materials) of the existing pole that is being replaced.

3. Cables and Wiring. All cables and wiring on non-wood poles must be within the structure. All cables and wiring on wood poles must be within conduit on the exterior of the pole. The conduit must be a color that matches the pole and of the smallest size technically feasible.

4. Stealth. The facility should be stealth, as defined above in Section 4(B).

D. New (Non-Replacement) Poles.

1. Waiver Required. New poles are prohibited, unless a waiver is approved by the City to prevent a prohibition of service.

2. Design. New poles (including antenna) shall have a maximum height of 28 feet and a maximum diameter of 14 inches, and any base enclosure shall not exceed 24 inches in width or height. If existing poles are present in the surrounding area, then the new pole shall be designed to resemble the existing poles in appearance, color, materials, and distribution pattern/spacing.

3. New wooden poles are prohibited, unless required to match existing poles in the area surrounding the proposed installation site.

4. Cables and Wiring. All cables and wiring on non-wood poles must be within the pole. All cables and wiring on wood poles must be within the conduit on the exterior of the pole. The conduit must be a color that matches the pole and of the smallest size technically feasible.

Resolution No. 26-53 20-65

Page 10 of 24 ends

_____________________

5. Antennas and RRUs. Antennas and RRUs shall be contained within the pole and its base or underground.

6. Stealth. The facility must be stealth, as defined above in Section 4(B).

Exceptions to These Standards
A. An exception may be granted to one or more of these Standards in the following circumstances:

1. Pursuant to MMC Section 12.02.050(E), if an applicant demonstrates to the Director or Hearing Officer in writing with clear and convincing evidence that denial of an application would, within the meaning of federal law, prohibit or effectively prohibit the provision of personal wireless services, or otherwise violate applicable laws or regulations. All waivers approved pursuant to MMC Section 12.02.050(E) shall be (1) granted only on a case-bycase basis, and (2) narrowly-tailored so that the requirements of these Standards are waived only to the minimum extent required to avoid the prohibition or violation.

2. If an applicant demonstrates to the Director or Hearing Officer with clear and convincing evidence set forth in a feasibility study that compliance with a requirement of the policy would be technically infeasible and the proposed wireless facility complies with the requirements of this policy to the greatest extent technically feasible.

For example, an exception to a requirement to conceal antennas in a shroud may be granted if shrouding is shown to be technically infeasible and an alternative concealment such as a colored film wrap is proposed. As another example, an exception to the volume limitation for antennas in a single shroud may be granted if the applicant can demonstrate that a greater volume is technically required, and that it is using the smallest, technically feasible engineering and design for providing personal wireless services, taking into account the other requirements of these Standards; or

3. If an applicant demonstrates to the Director or Hearing Officer in writing and based on clear and convincing evidence that the particular engineering, design or location proposed involves only minor non-compliance with a requirement of these Standards but such non-compliance either results in no increase in visual harms to the community or provides other benefits. For example, an exception to the antenna or equipment size or volume limitations may be granted when the applicant can demonstrate that because of the proposed location of the wireless facility away from viewsheds Resolution No. 26-53 20-65

Page 11 of 24 ends

_____________________
of residences or shielded by vegetation or existing infrastructure (such as barriers) in the public ROW, any additional visual and physical impacts of the larger wireless facility would be insignificant. As another example, an exception to the wireless facility location limitations may be granted when the applicant can demonstrate that the placement is less visible from viewsheds of residences or shielded by vegetation or existing infrastructure (such as barriers) in the public right-of-way, or is less physically intrusive (for example, less impactful to tree roots or reduces noise), or the applicant can demonstrate that in a multi-site deployment, the placement would reduce the overall number of sites needed and be no more visible or physically intrusive than placement in accordance with the wireless location criteria. Among other factors, in deciding whether or not to grant an exception, the Director may consider the impact of expansions to the facility that the applicant would be entitled to make as of right if granted.

B. Factors to be addressed in a feasibility study requesting an exception to undergrounding requirements based on feasibility shall include but are not limited to construction impacts (including duration and extent of excavation and soil disturbance); traffic and pedestrian impacts (including impediments to access during construction and maintenance, or permanent impediments due to the nature of particular equipment); operational challenge (such as water, heat, or maintenance complications affecting network reliability); noise impacts (such as venting and pumping which may be required in some instances); cost impacts; aesthetic considerations; and permanent impacts to the integrity and future capacity of public ROW.

C. Exceptions must be requested at the time an application is initially submitted for a WRP. The request must include both the specific provision(s) from which exception is sought and the basis of the request, including all supporting evidence on which the applicant relies. Any request for exception after the Director has deemed an application complete constitutes a material change to the proposed wireless facility and shall be considered a new application. A request for exception from one or more requirements does not relieve the applicant from compliance with all other applicable provisions of law or of these Standards.

Standard Conditions of Approval for Permits Under MMC Chapter 12.02.

A. Generally. In addition to any supplemental conditions imposed by the Director of Planning or the Hearing Officer, as the case may be, all permits under MMC Chapter 12.02 shall be subject to the following conditions, unless modified by the approving authority:

Resolution No. 26-53 20-65

Page 12 of 24 ends

_____________________

1. The permittee, and their successors in interest, shall indemnify and defend the City of Malibu and its officers, employees and agents from and against all liability and costs relating to the City's actions concerning this project, including (without limitation) any award of litigation expenses in favor of any person or entity who seeks to challenge the validity of any of the City's actions or decisions in connection with this project or seeks to hold the City liable in whole or in part as a result of the engineering, design, construction or operation of the facility. The City shall have the sole right to choose its counsel and property owners shall reimburse the City’s expenses incurred in its defense of any lawsuit challenging the City’s actions concerning this project.

2. Subsequent submittals for this project shall be in substantial compliance with the plans date-stamped received by the Planning Department on _____________. The project shall comply with all conditions of approval stipulated in the referral sheets attached to the agenda report for this project. In the event the project plans conflict with any condition of approval, the condition shall take precedence and revised plans shall be submitted and approved by the Planning Director prior to the Environmental Sustainability Department for plan check.

3. The permit and rights conferred in this approval shall not be effective until the permittee signs, notarizes and returns the Acceptance of Conditions Affidavit accepting the conditions set forth herein. The applicant shall file this form with the Planning Department within 30 days of this decision or prior to issuance of any wireless ROW, building, electrical or encroachment permit.

4. The applicant shall digitally submit a complete set of plans, including the items required in Condition No. 5 to the Planning Department for consistency review and approval prior to plan check and again prior to the issuance of any building or development permits.

5. This Notice of Decision (including the signed and notarized Acceptance of Conditions Affidavit) shall be copied in its entirety and placed directly onto a separate plan sheet(s) to be included in the development plans prior to submitting any development permits from the City of Malibu Environmental Sustainability Department and encroachment permit.

6. A WRP shall be valid for a period of ten (10) years from issuance, unless pursuant to another provision of the Code or these conditions, it expires sooner or is terminated. At the end of ten (10) years from Resolution No. 26-53 20-65

Page 13 of 24 ends

_____________________
the date of issuance, such wireless ROW permit shall automatically expire, unless an extension or renewal has been granted. A person holding a WRP must either (1) remove the facility within thirty (30) days following the permit’s expiration (provided that removal of support structure owned by City, a utility, or another entity authorized to maintain a support structure in the right of way need not be removed, but must be restored to its prior condition, except as specifically permitted by the City); or (2) prior to expiration, submit an application to renew the permit, which application must, among all other requirements, demonstrate that the impact of the wireless facility cannot be reduced. The wireless facility must remain in place until it is acted upon by the City and all appeals from the City’s decision exhausted.

7. The installation and construction authorized by a WRP shall be completed within three (3) years after its approval, or it will expire without further action by the City unless prior to the three (3) years the applicant submit an extension request and the City, in its sole discretion, grants a time extension for due cause. The installation and construction authorized by a wireless ROW permit shall conclude, including any necessary post-installation repairs and/or restoration to the ROW, within thirty (30) days following the day construction commenced. The permittee must provide written notice to City within ten (10) days after completing construction. The expiration date shall be suspended until an appeal and/or litigation regarding the subject permit is resolved.

8. The Planning Director may grant up to four one-year extensions of the timeline, in Condition 7 above, for completing the installation and construction authorized by a WRP, if the Planning Director finds that the conditions, including but not limited to changes in the wireless ordinance under which the WRP approval was issued, have not significantly changed.

9. Any questions of intent or interpretation of any condition of approval will be resolved by the Planning Director upon written request of such interpretation.

10. All structures shall conform to the requirements of the Environmental Sustainability Department, City Public Works Department, FCC and Los Angeles County Fire Department
requirements, as applicable. Notwithstanding this review, all required permits, including but not limited to an encroachment permit from the City, shall be secured.

Resolution No. 26-53 20-65

Page 14 of 24 ends

_____________________

11. Minor changes to the approved plans or the conditions of approval may be approved by the Planning Director, provided such changes achieve substantially the same results and the project is still in compliance with the MMC. An application with all required materials and fees shall be required.

Cultural Resources

12. In the event that potentially important cultural resources are found in the course of geologic testing, work shall immediately cease until a qualified archaeologist can provide an evaluation of the nature and significance of the resources and until the Planning Director can review this information. Where, as a result of this evaluation, the Planning Director determines that the project may have an adverse impact on cultural resources, a Phase II Evaluation of cultural resources shall be required pursuant to MMC Section

17.54.040(D)(4)(b).

13. If human bone is discovered, the procedures described in Section 7050.5 of the California Health and Safety Code shall be followed.

These procedures require notification of the coroner. If the coroner determines that the remains are those of a Native American, the applicant shall notify the Native American Heritage Commission by phone within 24 hours. Following notification of the Native American Heritage Commission, the procedures described in Section 5097.94 and Section 5097.98 of the California Public Resources Code shall be followed.

Wireless Facility Conditions

14. All antennas shall meet the minimum siting distances to public/uncontrolled areas required for compliance with the FCC regulations and standards governing the environmental effects of radio frequency emissions. Permittee shall keep up-to-date on current information from the FCC in regards to maximum
permissible radio frequency exposure levels. In the event that the FCC changes its guidelines for human exposure to radio frequency, permittee shall, within 30 days after any such change, submit to the Planning Director a report prepared by a qualified engineer that demonstrates actual compliance with such changed guidelines. The Director may, at permittee’s sole cost, retain an independent consultant to evaluate the compliance report and any potential modifications to the permit necessary to conform to the FCC’s guidelines. Failure to submit the compliance report required under this condition, or failure to maintain compliance with the FCC’s Resolution No. 26-53 20-65

Page 15 of 24 ends

_____________________
guidelines for human exposure to radio frequency at all times shall constitute grounds for permit revocation.

15. All antennas shall be located so that any person walking adjacent to the transmitting surface of the antenna will be walking on a grade, which is a minimum of eight and one-half feet below the transmitting surface.

16. All antennas, equipment, and support structures shall be engineered and designed to prevent unauthorized climbing.

17. The wireless facility shall be erected, operated, and maintained in compliance with the general requirements set forth in the Standards.

18. The antenna and electrical support equipment shall, at all times, be operated in a manner that conforms to the applicable federal health and safety standards.

19. Wireless facilities and equipment must comply with the City’s noise ordinance in MMC 8.24, or any successor provisions, and prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

20. The installation of a permanent onsite generator and/or other equipment is prohibited. The Planning Director’s approval is required if a generator is to be placed onsite for temporary or permanent use.

21. All pole-mounted equipment associated with the application shall be located no lower than eight feet above grade or ground level on the utility pole.

22. The City or its designee may enter onto the facility area to inspect the facility upon 48 hours prior notice to the permittee. The permittee shall cooperate with all inspections and may be present for any inspection of its facility by the City. The City reserves the right to enter or direct its designee to enter the facility and support, repair, disable, or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

The City shall make an effort to contact the permittee prior to disabling or removing any facility elements, but in any case, shall notify permittee within 24 hours of doing so.

23. Testing of any equipment shall take place on weekdays only, and only between the hours of 8:30 a.m. and 4:30 p.m., except that Resolution No. 26-53 20-65

Page 16 of 24 ends

_____________________
testing is prohibited on holidays that fall on a weekday. In addition, testing is prohibited on weekend days.

24. Permittee shall obtain and maintain throughout the term of the permit commercial general liability insurance with a limit of five million dollars ($5,000,000) per occurrence for bodily injury and property damage and six million dollars ($6,000,000) general aggregate including premises operations, contractual liability, personal injury, and products completed operations. The relevant policy(ies) shall name the City, its elected/appointed officials, commission members, officers, representatives, agents, and employees as additional insureds. Permittee shall use its best efforts to provide thirty (30) days’ prior notice to the City of to the cancellation or material modification of any applicable insurance policy.

25. Prior to issuance of a wireless encroachment permit, the permittee shall file with the City, and shall maintain in good standing throughout the term of the approval, a performance bond or other surety or another form of security for the removal of the facility in the event that the use is abandoned or the permit expires, or is revoked, or is otherwise terminated. The security shall be in the amount equal to the cost of physically removing the facility and all related facilities and equipment on the site, based on the higher of two contractor’s quotes for removal that are provided by the permittee. The permittee shall reimburse the city for staff time associated with the processing and tracking of the bond, based on the hourly rate adopted by the City Council. Reimbursement shall be paid when the security is posted and during each administrative review.

26. Permittee shall not move, alter, temporarily relocate, change, or interfere with any existing structure, improvement, or property without the prior consent of the owner of that structure, improvement, or property. No structure, improvement, or property owned by the City shall be moved to accommodate a permitted activity or encroachment, unless the City determines that such movement will not adversely affect the City or any surrounding businesses or residents, and the Permittee pays all costs and expenses related to the relocation of the City's structure, improvement, or property. Prior to commencement of any work pursuant to a WRP, the permittee shall provide the City with documentation establishing to the city's satisfaction that the permittee has the legal right to use or interfere with any other Resolution No. 26-53 20-65

Page 17 of 24 ends

_____________________
structure, improvement, or property within the public right-of-way or City utility easement to be affected by permittee's facilities.

27. The permission granted by a WRP shall not in any event constitute an easement on or an encumbrance against the ROW. No right, title, or interest (including franchise interest) in the ROW, or any part thereof, shall vest or accrue in permittee by reason of a WRP or the issuance of any other permit or exercise of any privilege given thereby.

28. No possessory interest is created by a WRP. However, to the extent that a possessory interest is deemed created by a governmental entity with taxation authority, permittee acknowledges that City has given to permittee notice pursuant to California Revenue and Taxation Code Section 107.6 that the use or occupancy of any public property pursuant to a WRP may create a possessory interest which may be subject to the payment of property taxes levied upon such interest.

Permittee shall be solely liable for, and shall pay and discharge prior to delinquency, any and all possessory interact taxes or other taxes, fees, and assessments levied against permittee’s right to possession, occupancy, or use of any public property pursuant to any right of possession, occupancy, or use created by this WRP.

29. If not already completed, permittee shall enter into the appropriate agreement with the City, as determined by the City, prior to constructing, attaching, or operating a facility on municipal infrastructure. This permit is not a substitute for such agreement.

30. For all facilities located within the ROW, the permittee shall remove or relocate, at its expense and without expense to the City, any or all of its facilities when such removal or relocation is deemed necessary by the City by reason of any change of grade, alignment, or width of any right-of-way, for installation of services, water pipes, drains, storm drains, power or signal lines, traffic control devices, right-ofway improvements, or for any other construction, repair, or improvement to the right-of-way.

31. If a facility is not operated for a continuous period of three (3) months, the WRP and any other permit or approval therefore shall be deemed abandoned and terminated automatically, unless before the end of the three (3) month period (i) the Director has determined that the facility has resumed operations, or (ii) the City has received an application to transfer the permit to another service provider. No later than ninety (90) days from the date the facility is determined to have ceased operation or the permittee has notified the Director of its intent to vacate the site, the permittee shall remove all equipment Resolution No. 26-53 20-65

Page 18 of 24 ends

_____________________
and improvements associated with the use and shall restore the site to its original condition to the satisfaction of the Director. The permittee shall provide written verification of the removal of the facilities within thirty (30) days of the date the removal is completed. If the facility is not removed within thirty (30) days after the permit has been discontinued pursuant to this subsection, the site shall be deemed to be a nuisance, and the City may cause the facility to be removed at permittee’s expense or by calling any bond or other financial assurance to pay for removal. If there are two (2) or more users of a single facility or support structure, then this provision shall apply to the specific elements or parts thereof that were abandoned but will not be effective for the entirety thereof until all users cease use thereof.

32. In the event the City determines that it is necessary to take legal action to enforce any of these conditions, or to revoke a permit, and such legal action is taken, the permittee shall be required to pay any and all costs of such legal action, including reasonable attorney’s fees, incurred by the City, even if the matter is not prosecuted to a final judgment or is amicably resolved, unless the City should otherwise agree with permittee to waive said fees or any part thereof.

The foregoing shall not apply if the permittee prevails in the enforcement proceeding.

Construction

33. Installation hours shall be limited to Monday through Friday from 7:00 a.m. to 7:00 p.m. and Saturdays from 8:00 a.m. to 5:00 p.m. No installation activities shall be permitted on Sundays and Citydesignated holidays. The restricted work hours described in this condition do not apply to emergency maintenance necessary to protect health or property. The City of Malibu may issue a Stop Work Order if permittee violates this condition. Construction activities shall be conducted in compliance with, and abide by, all applicable safety codes.

Site Specific Conditions

34. In the event that the electric service provider does not currently offer an alternative metering option, the permittee shall remove the above-grade electric meter when such option becomes available.

Prior to removing the above-grade electric meter, the permittee shall apply for any encroachment and/or other ministerial permit(s) required to perform the removal. Upon removal, the permittee shall restore the affected area to its original condition that existed prior to installation of the equipment.

Resolution No. 26-53 20-65

Page 19 of 24 ends

_____________________

35. The permittee acknowledges that the City specifically includes conditions of approval related to (a) painting, coloring or finishing the equipment to match the pole; (b) undergrounding all equipment to the extent possible; and (c) installing equipment within shrouds, conduits and risers as concealment elements engineered and designed to integrate the wireless facility with the surrounding built and natural environment. Any future modifications to the permittee’s wireless facility must maintain or improve all concealment elements.

36. Before the permittee submits any applications for construction, encroachment, excavation or other required permits in connection with this permit, the permittee must incorporate a true and correct copy of this permit, all conditions associated with this permit and any approved photo simulations into the project plans (collectively, the “Approved Plans”). The permittee must construct, install and operate the wireless facility in substantial compliance with the Approved Plans as determined by the Director or the Director’s designee. Any substantial or material alterations, modifications or other changes to the Approved Plans, whether requested by the permittee or required by other departments or public agencies with jurisdiction over the wireless facility, must be submitted in a written request subject to the Director’s prior review and approval, who may refer the request to the original approval authority if the Director finds that the requested alteration, modification or other change substantially deviates from the Approved Plans or implicates a significant or substantial land-use concern.

37. The permittee shall install and at all times maintain in good condition a “Network Operations Center Information” and “RF Caution” sign on the utility pole no less than three (3) feet below the antenna (measured from the top of the sign) and no less than nine (9) feet above the ground line (measured from the bottom of the sign). Signs required under this condition shall be installed so that a person can clearly see the sign as he or she approaches within three (3) feet of the antenna structure. If any person on or within the public ROW is or may be exposed to emissions that exceed applicable FCC uncontrolled/general population limits at any time the sign shall expressly so state and provide instructions on how persons can avoid any such exposure. The sign shall also include the name(s) of the facility owner(s), equipment owner(s) and operator(s)/carrier(s) of the antenna(s), property owner name, as well as emergency phone number(s) for all such parties. The sign shall not be lighted, unless applicable law, rule or regulation requires lighting. No signs or advertising devices other than required certification, warning, Resolution No. 26-53 20-65

Page 20 of 24 ends

_____________________
required seals or signage, other signage required by law, this Chapter, any City or applicable state code or the Los Angeles County Fire Department Chief or his or her designee shall be permitted. The sign shall be no larger than two (2) square feet.

38. The permittee shall ensure that all signage complies with FCC Office of Engineering and Technology Bulletin 65, CPUC General Order 95 or American National Standards Institute C95.2 for color, symbol, and content conventions. All such signage shall at all times provide a working local or toll-free telephone number to its network operations center, and such telephone number shall be able to reach a live person who can exert transmitter power-down control over this site as required by the FCC.

39. In the event that the FCC changes any of radio frequency signage requirements that are applicable to the project site approved herein or ANSI Z535.1, ANSI Z535.2, and ANSI C95.2 standards that are applicable to the project site approved herein are changed, the permittee, within 30 days of each such change, at its own cost and expense, shall replace the signage at the project site to comply with the current standards.

40. The permittee shall maintain the paint, color and finish of the facility in good condition at all times.

41. All improvements, including foundations, and appurtenant ground wires, shall be removed from the property and the site restored to its original pre-installation conditions within 90 days of cessation of operation or abandonment of the facility.

42. Build-Out Conditions.
a. Permittee shall not commence any excavation, construction, installation or other work on the project site until and unless it demonstrates to the City Public Works Department that the project complies with all generally applicable laws,
regulations, codes and other rules related to public health and safety, including without limitation all applicable provisions in California Public Utilities Commission General Order 95 and MMC Chapters 8.12, 8.24 and 15.08.
b. To the extent that the pole owner requires greater or more restrictive standards than contained in California Public Utilities Commission General Order 95, those standards
shall control.

Resolution No. 26-53 20-65

Page 21 of 24 ends

_____________________

43. Permittee shall at all times maintain compliance with all applicable federal, State and local laws, regulations, ordinances and other rules, including Americans with Disabilities Act (ADA) requirements.

44. The permittee shall cooperate with all inspections. The City and its designees reserves the right to support, repair, disable or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

45. Permittee shall at all times maintain accurate contact information for all parties responsible for the facility, which shall include a phone number, street mailing address and email address for at least one natural person. All such contact information for responsible parties shall be provided to the Planning Department at the time of permit issuance and within one business day of permittee’s receipt of City staff’s written request.

46. Permittee shall undertake all reasonable efforts to avoid undue adverse impacts to adjacent properties and/or uses that may arise from the construction, operation, maintenance, modification and removal of the facility.

47. The site and the facility must be maintained in a neat and clean manner and in accordance with all approved plans and conditions of approval.

48. Permittee shall promptly remove any graffiti on the wireless facility at permittee’s sole expense within 48 hours after notice.

Prior to Operation

49. The applicant shall request a final Planning Department inspection immediately after the wireless facility has been installed and prior to the commencement of services and final electrical inspection by the City of Malibu Environmental Sustainability Department.

50. Within thirty (30) calendar days following the installation of any wireless facilities, the applicant shall provide to the Planning Department with a field report prepared by a qualified engineer verifying that the unit has been inspected, tested, and is operating in compliance with FCC standards. Specifically, the on-site postinstallation radiofrequency (RF) emissions testing must demonstrate actual compliance with the FCC OET Bulletin 65 RF emissions safety guidelines for general population/uncontrolled RF exposure in all sectors. For this testing, the transmitter shall be operating at maximum operating power, and the testing shall occur outwards to Resolution No. 26-53 20-65

Page 22 of 24 ends

_____________________
a distance where the RF emissions no longer exceed the
uncontrolled/general population limit. Such report and
documentation shall include the make and model (or other identifying information) of the unit tested, the date and time of the inspection, a certification that the unit is properly installed and working within applicable FCC limits, and a specific notation of the distance from the transmitter at which the emissions are equal to or less than the uncontrolled/general population limit.

51. The operation of the approved facility shall commence no later than one (1) month after the City completes its post-installation inspection of the facility, any issues with the facility are resolved, and the City receives the RF testing report required in the condition of approval above, or the wireless ROW permit will expire without further action by the City.

Fixed Conditions

52. Violation of any of the conditions of this approval shall be cause for revocation and termination of all rights thereunder.

Eligible Facilities Requests
In addition to all of the other conditions of approval placed on a WRP, all permits for an eligible facilities request under MMC Chapter 12.02 shall be subject to the following additional conditions, unless modified by the approving authority:

53. Any permit granted in response to an application qualifying as an eligible facilities request shall be subject to the terms and conditions of the underlying permit.

54. The City’s grant or grant by operation of law of an eligible facilities request permit constitutes a federally-mandated modification to the underlying permit or approval for the subject tower or base station.

Notwithstanding any permit duration established in another permit condition, the City’s grant or grant by operation of law of a eligible facilities request permit will not extend the permit term for the underlying permit or any other underlying regulatory approval, and its term shall be coterminous with the underlying permit or other regulatory approval for the subject tower or base station.

55. The City’s grant or grant by operation of law of an eligible facilities request does not waive, and shall not be construed to waive, any standing by the City to challenge Section 6409(a) of the Spectrum Act, any FCC rules that interpret Section 6409(a) of the Spectrum Act, or any modification to Section 6409(a) of the Spectrum Act.

Resolution No. 26-53 20-65

Page 23 of 24 ends

_____________________
Small Cell Facilities
In addition to the other conditions of approval placed on a WRP, all permits for a small cell facility under MMC Chapter 12.02 shall be subject to the following additional condition, unless modified by the approving authority:

56. The City’s grant of a permit for a small cell facility request does not waive, and shall not be construed to waive, any standing by the city to challenge any FCC orders or rules related to small cell facilities, or any modification to those FCC orders or rules.

SECTION 11. Environmental Review.

This Resolution is not a project within the meaning of Section 15378 of the State of California Environmental Quality Act (CEQA) Guidelines, because it has no potential for resulting in physical change in the environment, directly or indirectly. The Resolution does not authorize any specific development or installation on any specific piece of property within the City’s boundaries.

Moreover, when and if an application for installation is submitted, the City will at that time conduct preliminary review of the application in accordance with CEQA. Alternatively, even if the Resolution is a “project” within the meaning of State CEQA Guidelines section 15378, the Resolution is exempt from CEQA on multiple grounds. First, the Resolution is exempt CEQA because the City Council’s adoption of the Resolution is covered by the general rule that CEQA applies only to projects which have the potential for causing a significant effect on the environment. (State CEQA Guidelines, § 15061(b)(3)). That is, approval of the Resolution will not result in the actual installation of any facilities in the City. In order to install a facility in accordance with this Resolution, the wireless provider would have to submit an application for installation of the wireless facility. At that time, the City will have specific and definite information regarding the facility to review in accordance with CEQA. And, in fact, the City will conduct preliminary review under CEQA at that time. Second, the Resolution is categorically exempt under CEQA Guidelines §§ 15307 and 15308 as an action taken by a regulatory agency, as authorized by local ordinance (MMC Chapter 12.02), to assure the protection of natural resources and the environment. The Resolution strengthens the City’s location and design standards for new wireless facilities. It does not weaken any existing standard and does not authorize any construction or development. The City’s wireless permitting process involves procedures for protection of the environment, including discretionary review of each application and coastal development permit review under the certified Local Coastal Program where applicable. None of the exceptions in CEQA Guidelines §15300.2 applies.

Moreover, in the event that the Resolution is interpreted so as to permit installation of wireless facilities on a particular site, the installation would be exempt from CEQA review in accordance with either State CEQA Guidelines section 15302 (replacement or reconstruction), State CEQA Guidelines section 15303 (new construction or conversion of small structures), and/or State CEQA Guidelines section 15304 (minor alterations to land).

Resolution No. 26-53 20-65

Page 24 of 24 ends

_____________________
SECTION 12. This Resolution shall become effective immediately upon its passage and adoption.

SECTION 13. The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

PASSED, APPROVED, and ADOPTED this 9 13th day of July 2026 December 2020. _____________________________
BRUCE SILVERSTEIN, Mayor
ATTEST:
___________________________
KELSEY PETTIJOHN, City Clerk
(seal)
APPROVED AS TO FORM:
_____________________________
TREVOR RUSIN, Interim City Attorney
Attachment 4
RESOLUTION NO. 26-54 21-17

A RESOLUTION OF THE CITY OF MALIBU AMENDING AND REPLACING RESOLUTION NO. 21-17 (WIRELESS FACILITIES ON LAND OTHER THAN

THE PUBLIC RIGHT-OF-WAY) TO RESTRICT NEW WIRELESS
FACILITIES IN RESIDENTIAL AREAS AND DEFINE “RESIDENTIAL AREAS” ADOPTING ENGINEERING, DESIGN AND LOCATION

STANDARDS, CONDITIONS OF APPROVAL AND BASIC APPLICATION

REQUIREMENTS FOR WIRELESS COMMUNICATIONS FACILITIES ON
LAND OTHER THAN PUBLIC RIGHT-OF-WAY; AND FINDING THAT THIS

RESOLUTION IS NOT SUBJECT TO THE CALIFORNIA ENVIRONMENTAL

QUALITY ACT AND, IN THE ALTERNATIVE, IS EXEMPT FROM CEQA

THE SAME EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL

QUALITY ACT
The City Council of the City of Malibu does hereby find, resolve and order as follows:

SECTION 1. Recitals
A. Malibu Municipal Code (MMC) Chapter 17.46 governs the permitting, installation, and regulation of wireless communications facilities in the City, other than those in the public right-of-way, which are subject to MMC Chapter 12.02.

B. Section 17.46.060(D) provides that “[a]ll applicants shall engineer, design and locate the wireless communications facilities in accordance with the standards and wireless regulations set forth separately though the resolution adopted by the City Council.” C. Being authorized to do so, the City wishes to establish engineering, design and development standards applicable to wireless installations.

D. The City also wishes to set standard conditions of approval and basic application requirements applicable to wireless permits.

E. On April 12, 2021 the City Council conducted a duly noticed public hearing and received testimony from City staff and all interested parties regarding the standards, conditions and requirements.

F. On July 13, 2026 the City Council held a duly noticed meeting and received testimony from City staff and all interested parties regarding the residential restriction.

Purpose. The purpose of this document is to (1) establish design and location standards (Standards) for wireless communications facilities on land other than public right-ofway; (2) set standard conditions of approval for Wireless Permits (WPs); and (3) set basic application requirements for WPs.

Definitions.

Resolution No. 26-54 21-17

Page 2 of 27 ends

_____________________
For the purposes of these Standards, the definitions set forth in Malibu Municipal Code (MMC) Section 17.46.040 are incorporated by reference into this Resolution and in addition the following definitions apply:

A. “Park” A parcel, parcels of land or a portion of a parcel intended for active public recreation uses. Parks may include sports fields, playgrounds community buildings and unique or specialized activity areas. Land dedicated for open space and trails are not considered parks for the purposes of this Chapter.

B. “Playground” A portion of land used for and equipped with public facilities for recreation specially by children. A playground includes the sand or rubberized floor around the apparatus.

C. “Pole-mounted facility” means a wireless communications facility that is, or is proposed to be, attached to or contained in a pole.

D. “Residential areas” means any parcel zoned RR, SF, MF, MFBF, or MH, or a Planned Development parcel whose principal use is residential, under MMC Chapter 17.06.

DE. “School” any building, campus or sports field which is designed, constructed or used for education, instruction or school sports, whether public or private, in any branch of knowledge.

EF. “Stealth facility” (or “stealth facilities”) means a wireless communications facility designed to look like something other than a wireless tower or base station.

General Standards for all Facilities.

The following general requirements apply at all times to all wireless communications facilities located in all zoning districts:

A. All wireless communications facilities shall be engineered and designed to minimize the visual impact by means of placement, screening, camouflaging, painting and texturing and to be compatible with existing architectural elements, building materials and other site characteristics. The applicant shall use the smallest and least visible antenna possible to accomplish the facility’s objectives. All antennas and support structures shall be painted and/or textured to achieve architectural compatibility with the structures for which they are attached and/or located.

B. Each facility must comply with any and all applicable provisions of the Malibu Municipal Code, including but not limited to provisions of the California Building Code, California Electric Code, California Resolution No. 26-54 21-17

Page 3 of 27 ends

_____________________
Plumbing Code, California Mechanical Code, and California Fire Code, and any conditions of approval imposed as part of the approval process.

C. Each facility must comply with any and all applicable regulations and standards promulgated or imposed by any state or federal agency, including, but not limited to, the Federal Communications Commission (FCC) and the Federal Aviation Administration (FAA). Further, all wireless communications facilities, associated equipment and services shall comply with Americans with Disabilities Act (ADA) requirements.

D. Fire and Electrical Safety Standards. All wireless communications facilities shall contain:

1. Surge protection for lightning discharge or other significant electrical disturbances; and

2. Signage as required by the permit conditions, the National Electric Code or the Los Angeles County Fire Department Chief or their designee.

E. The facility must at all times comply with all applicable health requirements and standards pertaining to radio frequency emissions.

F. All antennas shall meet the minimum siting distances to habitable structures required for compliance with FCC regulations and standards governing the environmental effects of radio frequency emissions.

G. Noise. Wireless communications facilities and equipment must comply with the City’s noise ordinance in MMC Chapter 8.24, or any successor provisions, and be designed to prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

H. Signs. No facility may display any signage or advertisement unless it is expressly allowed by this paragraph, necessary for stealth concealment purposes, or required by law or a permit condition. Every facility shall at all times display signage that accurately identifies the facility owner and provides the owner’s unique site number and a local or toll-free telephone number to contact the facility owner’s operations center.

I. Landscaping. Where appropriate, facilities shall be installed so as to maintain and enhance existing landscaping on the site, including trees, foliage and shrubs, whether or not utilized for screening. In addition to any landscaping used for concealment or screening purposes, the applicant shall replace any existing landscaping displaced during construction or installation of the applicant’s facility. The applicant’s landscaping plan shall Resolution No. 26-54 21-17

Page 4 of 27 ends

_____________________
be subject to the City’s review and approval but shall, at a minimum, match the existing landscaping and foliage surrounding the installation site consistent with MMC Section 17.53.090. The permittee shall ensure that any vegetation allowed to remain in place under the Fire Code, including vegetation provided for screening, is properly maintained and watered.

J. All electrical support equipment located within cabinets, shelters, or similar structures shall be screened from public view. Roof-mounted electrical support equipment shall be discouraged. Ground-mounted electrical support equipment shall be encouraged. In addition, under grounding of support equipment is required wherever practicable.

K. All antennas shall be located such that any person walking adjacent to the transmitting surface of the antenna will be walking on a grade that is a minimum of eight and one-half feet below the transmitting surface.

L. Lighting of antenna structures and their electrical support equipment is prohibited, except as required by any order or regulation of the FCC or the FAA and except for manually operated emergency lights for use when official operating personnel are on site.

M. A backup power supply must be required for all new wireless communications facilities to the extent allowed by law and in compliance with California Fire Code 1206.2.2.

Location Standards for All Facilities.

The location standards for all wireless communications facilities, other than those that qualify as eligible facilities requests, are as follows:

A. No wireless telecommunication facility shall be located within five hundred (500) feet of any school, playground, or park unless a finding is made, based on technical evidence acceptable to the reviewing authority showing a clear need for the facility and that no technically feasible alternative site exists.

Except for facilities installed on the same pole or tower as an existing wireless telecommunication facility, wireless telecommunication facilities located within any residential zone district shall not be located within one thousand (1,000) feet of any other wireless communications facility, except from those facilities placed on utility poles along Pacific Coast Highway, unless a waiver is granted.

B. All new freestanding wireless communications facilities and monopoles shall be set back a minimum distance of at least one hundred and twenty (120) percent of the height of the facility or monopole from any property line abutting a residentially zoned property. This minimum setback is not subject to the waivers allowed under Section 7 of this Resolution.

Resolution No. 26-54 21-17

Page 5 of 27 ends

_____________________
C. Location preference for wireless communications facilities should be given to the following:

1. Property designated non-residential (except for public open space and recreational vehicle park zoning districts), unless otherwise prohibited pursuant to this title.

2. Facilities attached or sited adjacent to existing structures. Whenever possible, facilities shall be located on and/or inside existing structures. Appropriate types of existing structures may include, but are not limited to: buildings, water tanks, telephone poles and utility towers and poles, sign standards, light standards and roadway overpasses.

3. Sites with minimum separation. Sites that are more than five hundred (500) feet from school, playgrounds, and parks.

4. Sites that are not highly visible from adjacent roadways.

5. Unless otherwise indicated in MMC Chapter 17.46 or these Standards, no wireless facility shall be installed on an exposed ridgeline unless the facility blends with the surrounding existing natural and man-made environment and a finding is made that no other location is technically feasible.

6. The City expressly designates residential, public open space and recreational vehicle park zoning districts, parks and schools as the least appropriate possible locations, and the absolute last choices for siting.

D. Disallowed Locations. The City expressly designates residential areas, as defined in Section 3, as disallowed locations for new wireless facilities.

Engineering and Design Standards for all Facilities.

The general design standards for wireless communications facilities subject to MMC Chapter

17.46 are as follows:

A. Basic Requirements. The proposed wireless facility and its supporting structure (if needed) shall be limited to the minimum size necessary to serve the defined service objectives of the wireless service provider or providers that will be using the facility, except where a larger facility has superior concealment elements.

B. Materials. The materials used shall be non-reflective and non-flammable.

Resolution No. 26-54 21-17

Page 6 of 27 ends

_____________________
C. Cabinet doors and other openings must be designed to stay securely closed, and openings in all facilities shall be shielded or made the smallest size feasible to protect against fire and wind-blown embers.

D. The tower, or other support structure, and all equipment shall be designed to withstand forces from seismic events. To that end, all wireless facility sites must be built to the applicable standards of Hardening Requirements including but not limited to APCO ANSI 2.106.1–2019, or their replacements. The telecommunications tower, pole or structure when fully loaded with antennas, transmitters, and other equipment and camouflaging shall be designed as determined by the Building Official. All equipment mounting racks and equipment used shall be anchored in such a manner that such a quake will not tip them over, throw the equipment off its shelves, or otherwise act to damage it.

E. All connections between various components of the facility, power lines, and conduit shall be designed in a manner to protect against damage by a natural disaster, a vehicular accident, an act of vandalism or similar external forces.

F. Stealth. The wireless facility shall be stealth. Stealth elements and techniques should be used to blend the facility with surrounding materials and colors of the support structure and make the facility appear to be something other than a wireless facility. Stealth elements include, but are not limited to, the following:

1. Radio frequency (RF) transparent screening or shrouds;

2. Matching the color of the existing support structure by painting, coating, or otherwise coloring the wireless facility, equipment, mounting brackets, and cabling;

3. Placing cables and wires inside the pole or beneath conduit of the smallest size possible;

4. Minimizing the size of the site;

5. Installing new infrastructure that matches existing infrastructure in the area surrounding the proposed site; and

6. Using paint of durable quality.

7. Built with weather-resistant materials while permitting weathered treatment for aesthetic reasons and to avoid reflective material.

G. Minimum Height. All antennas shall be located such that: (1) any person walking adjacent to the transmitting surface of the antenna will be walking Resolution No. 26-54 21-17

Page 7 of 27 ends

_____________________
on a grade that is a minimum of eight and one-half feet below the transmitting surface; and (2) no person at ground level will be exposed to an exposure level that is higher than allowed by the FCC’s general population exposure rules.

H. Facade-Mounted Equipment. Facade-mounted antennas and equipment shall be architecturally integrated into the building, or other support structure, design and otherwise made as unobtrusive as possible so that the facility does not appear to be a wireless facility. Antennas and equipment should be located entirely within an existing or newly created architectural feature so as to be completely screened from view. Facade-mounted facilities shall generally not extend more than eighteen (18) inches out from and may not project above the building face. Façade-mounted wireless telecommunication facilities shall not exceed twenty-eight (28) feet in height above the ground. However, antenna elements, mounted flush on the facade of an existing structure that exceeds twenty-eight (28) feet, may have a height equal to the height of the building.

I. Ground-Mounted Equipment.Outdoor ground-mounted equipment associated with base stations shall be avoided whenever feasible. In locations visible or accessible to the public, applicants shall conceal outdoor ground-mounted equipment, including ancillary power generation equipment, with opaque fences or landscape features that mimic the adjacent structure(s) (including, but not limited to, dumpster corrals and other accessory structures) and by painting, texturing, or otherwise concealing the facility as much as possible. Ground-mounted wireless communications facilities shall be located near existing structures or trees at similar heights for screening purposes where feasible. Not more than one ground-mounted antenna, provided that licensed amateur radio station antennas consistent with MMC 17.46.020(B)(2), shall also be permitted on each site.

J. Roof-Mounted Facilities. Roof-mounted antennas and necessary equipment shall be screened from above if visible from higher elevations. Rooftopmounted wireless telecommunication facilities shall not exceed twentyeight (28) feet in height or three (3) feet above the roof parapet from which they are attached, whichever is less restrictive. Associated roof-mounted equipment cabinets shall not extend more than three (3) feet above the roof from which it is attached and shall be set back a minimum of ten (10) feet from the edge of the roof. All roof-mounted equipment cabinets shall be located behind a mechanical screen wall. In the event that a roof parapet wall screens the equipment cabinets, a mechanical screen wall will not be required.

K. Freestanding Facilities. Freestanding facilities requiring a new monopole or other new support structure shall be stealth facilities. Further, they shall be Resolution No. 26-54 21-17

Page 8 of 27 ends

_____________________
located as close as possible to existing above-ground utilities, such as electrical towers or utility poles (which are not scheduled for removal or under grounding for at least 18 months after the date of application), light poles, trees of comparable heights, and in areas where they will not detract from the appearance of the City.

1. Freestanding wireless telecommunication facilities, including monopoles, shall not exceed twenty-eight (28) feet in height and shall not extend higher than the top of the ridgeline nearest the antenna. The height of a freestanding facility shall be measured from the natural undisturbed ground surface below the center of the base of the tower itself to the tip of the highest antenna or piece of equipment attached thereto.

2. Aside from the antenna itself, no additional equipment may be visible. All cables, including, but not limited to, electrical and utility cables, shall be run within the interior of the freestanding facility and shall be camouflaged or hidden to the fullest extent feasible without jeopardizing the physical integrity of the facility.

3. Monopole installations shall be situated so as to utilize existing natural or man-made features including topography, vegetation, buildings, or other structures to provide the greatest amount of visual screening.

4. All antenna components and accessory wireless equipment shall be treated with exterior coatings of a color and texture to match the predominant visual background or existing architectural elements so as to visually blend in with the surrounding development. Subdued colors and non-reflective materials that blend with surrounding materials and colors shall be used.

5. Monopoles shall be no greater in diameter or other cross-sectional dimensions than is necessary for the proper functioning of the facility.

L. All wireless telecommunication facilities shall be designed to prevent unauthorized climbing and graffiti.

M. Fire Safety Standards. All wireless facilities designs shall include:

1. a power shut off, such as by means of rapid entry Knox or similar type systems shall be installed;

2. surge protection devices capable of mitigating a direct or partial direct lightning discharge; and
Resolution No. 26-54 21-17

Page 9 of 27 ends

_____________________

3. surge protection devices capable of mitigating significant electrical disturbances that may enter the facility via conductive cables.

N. Satellite dish or parabolic antennas shall be situated as close to the ground as possible to reduce visual impact without compromising their function.

O. Support equipment pads, cabinets, shelters and buildings require architectural, landscape, color, fencing, or other camouflage treatment to minimize visual impacts to the extent deemed necessary by the Planning Director. Landscaping screening should also be provided if irrigation water is available.

P. No freestanding facility or ancillary support equipment may be located between the face of a building and a public street, bikeway, park or residence.

Waivers of These Standards.

A. A waiver of one or more of these Standards may be granted in the following circumstances:

1. Pursuant to MMC Section 17.46.060(D), if an applicant demonstrates to the Planning Commission through clear and convincing evidence that denial of an application would, within the meaning of federal law, prohibit or effectively prohibit the provision of personal wireless services, or otherwise violate applicable laws or regulations;

2. If an applicant demonstrates to the Planning Commission through clear and convincing evidence set forth in a feasibility study that compliance with a requirement of these Standards would be technically infeasible and the proposed wireless facility complies with the requirements of these Standards to the greatest extent technically feasible. For example, an exception to a requirement to conceal antennas in a shroud may be granted if shrouding is shown to be technically infeasible and an alternative concealment such as a colored film wrap is proposed; or

3. If an applicant demonstrates to the Planning Commission with clear and convincing evidence that the particular engineering, design or location proposed involves an alternative that better meets the purposes of Chapter 17.46 and only minor non-compliance with a requirement of these design Standards and results in no increase in public visual impact to the community or provides other benefits.

For example, an exception to the wireless facility location limitations may be granted when the applicant can demonstrate that Resolution No. 26-54 21-17

Page 10 of 27 ends

_____________________
the placement is less visible from viewsheds of residences or shielded by vegetation or existing infrastructure (such as barriers), or is less physically intrusive (for example, less impactful to tree roots or reduces noise). Among other factors, in deciding whether or not to grant an exception, the Planning Commission may consider the impact of expansions to the facility that the applicant would be entitled to make as of right if granted.

B. Waivers may only be requested at the time an application is initially submitted for a discretionary permit. The request must include both the specific provision(s) from which waiver is sought and the basis of the request, including all supporting evidence on which the applicant relies.

Any request for waiver after the City has deemed an application complete constitutes a material change to the proposed wireless facility and shall be considered a new application. A request for waiver from one or more requirements does not relieve the applicant from compliance with all other applicable provisions of law or of MMC Section 17.46.060.

Standard Conditions of Approval for Permits Under MMC Chapter 17.46.

A. Generally. In addition to any supplemental conditions imposed by the Planning Director or Planning Commission, as the case may be, all development permits or conditional use permits granted for wireless communications facilities subject to this Chapter 17.46 shall be subject to the following conditions, unless modified by the approving authority:

1. The permittee shall defend, indemnify, and hold harmless the city or any of its boards, commissions, agents, officers, and employees from any claim, action or proceeding against the city, its boards, commission, agents, officers, or employees to attack, set aside, void, or annul, the approval of the project, or to hold the City liable in whole or in part as a result of the engineering, design, construction or operation of the facility. The City shall promptly notify the provider(s) of any such claim, action or proceeding if the city bears its own attorney’s fees and costs, and the city defends the action in good faith.

2. The permittee shall be strictly liable for interference caused by its facilities with city communications systems. The permittee shall be responsible for costs for determining the source of the interference, all costs associated with eliminating the interference (including but not limited to filtering, installing cavities, installing directional antennas, powering down systems, and engineering analysis), and all costs arising from third party claims against the city attributable to the interference.

Resolution No. 26-54 21-17

Page 11 of 27 ends

_____________________

3. Subsequent submittals for this project shall be in substantial compliance with the plans date-stamped received by the Planning Department on _____________. The project shall comply with all conditions of approval stipulated in the referral sheets attached to the agenda report for this project. In the event the project plans conflict with any condition of approval, the condition shall take precedence and revised plans shall be submitted and approved by the Planning Director prior to the Environmental Sustainability Department for plan check.

4. The permit and rights conferred in this approval shall not be effective until the permittee signs, notarizes and returns the Acceptance of Conditions Affidavit accepting the conditions set forth herein. The applicant shall file this form with the Planning Department within 30 days of this decision or prior to issuance of any development, conditional use, building, electrical or encroachment permit.

5. The applicant shall digitally submit a complete set of plans, including the items required in Condition No. 6 to the Planning Department for consistency review and approval prior to plan check and again prior to the issuance of any building or development permits.

6. The Notice of Decision (including the signed and notarized Acceptance of Conditions Affidavit) shall be copied in its entirety and placed directly onto a separate plan sheet(s) to be included in the development plans prior to submitting any development permits from the City of Malibu Environmental Sustainability Department and encroachment permit.

7. A development permit or conditional use permit, as applicable, shall be valid for a period of ten (10) years from issuance, unless pursuant to another provision of the Code or these conditions, it expires sooner or is terminated. At the end of ten (10) years from the date of issuance, such development or conditional use permit shall automatically expire, unless an extension or renewal has been granted. A person holding a development permit or conditional use permit must either (1) remove the facility within thirty (30) days following the permit’s expiration (provided that removal of support structure owned by City, a utility, or another entity authorized to maintain a support structure need not be removed, but must be restored to its prior condition, except as specifically permitted by the City); or (2) prior to expiration, submit an application to renew the permit, which application must, among all other requirements, demonstrate that the impact of the wireless facility cannot be Resolution No. 26-54 21-17

Page 12 of 27 ends

_____________________
reduced. The wireless facility must remain in place until it is acted upon by the City and all appeals from the City’s decision exhausted.

8. The installation and construction authorized by a permit shall be completed within three (3) years after its approval, or it will expire without further action by the City unless prior to the three (3) years the applicant submit an extension request and the City, in its sole discretion, grants a time extension for due cause. The installation and construction authorized by a permit shall conclude, including any necessary post-installation repairs and/or restoration to the property, within thirty (30) days following the day construction commenced. The permittee must provide written notice to City within ten (10) days after completing construction, and may not begin operations until all City and Fire Department (if applicable) inspections have been completed and the project is found to be consistent with the permit. The expiration date shall be suspended until an appeal and/or litigation regarding the subject permit is resolved.

9. The Planning Director may grant up to four one-year extensions of the timeline, in Condition 7 above, for completing the installation and construction authorized by a development or condition use permit, if the Planning Director finds that the conditions, including but not limited to changes in the wireless ordinance under which the permit approval was issued, have not significantly changed.

10. Any questions of intent or interpretation of any condition of approval will be resolved by the Planning Director upon written request of such interpretation.

11. All structures shall conform to the requirements of the Environmental Sustainability Department, City Public Works Department, FCC and Los Angeles County Fire Department
requirements, as applicable. Notwithstanding this review, all required permits, including but not limited to an encroachment permit from the City, shall be secured.

12. Minor changes to the approved plans or the conditions of approval may be approved by the Planning Director, provided such changes achieve substantially the same results and the project is still in compliance with the MMC. An application with all required materials and fees shall be required.

Resolution No. 26-54 21-17

Page 13 of 27 ends

_____________________
Cultural Resources

13. In the event that potentially important cultural resources are found in the course of geologic testing, work shall immediately cease until a qualified archaeologist can provide an evaluation of the nature and significance of the resources and until the Planning Director can review this information. Where, as a result of this evaluation, the Planning Director determines that the project may have an adverse impact on cultural resources, a Phase II Evaluation of cultural resources shall be required pursuant to MMC Section

17.54.040(D)(4)(b).

14. If human bone is discovered, the procedures described in Section 7050.5 of the California Health and Safety Code shall be followed.

These procedures require notification of the coroner. If the coroner determines that the remains are those of a Native American, the applicant shall notify the Native American Heritage Commission by phone within 24 hours. Following notification of the Native American Heritage Commission, the procedures described in Section 5097.94 and Section 5097.98 of the California Public Resources Code shall be followed.

Wireless Facility Conditions

15. All antennas shall meet the minimum siting distances to public/uncontrolled areas required for compliance with the FCC regulations and standards governing the environmental effects of radio frequency emissions. Permittee shall keep up-to-date on current information from the FCC in regards to maximum
permissible radio frequency exposure levels. In the event that the FCC changes its guidelines for human exposure to radio frequency, permittee shall, within 30 days after any such change, submit to the Planning Director a report prepared by a qualified engineer that demonstrates actual compliance with such changed guidelines. The Director may, at permittee’s sole cost, retain an independent consultant to evaluate the compliance report and any potential modifications to the permit necessary to conform to the FCC’s guidelines. Failure to submit the compliance report required under this condition, or failure to maintain compliance with the FCC’s guidelines for human exposure to radio frequency at all times shall constitute grounds for permit revocation.

16. All antennas shall be located so that any person walking adjacent to the transmitting surface of the antenna will be walking on a grade, which is a minimum of eight and one-half feet below the transmitting surface.

Resolution No. 26-54 21-17

Page 14 of 27 ends

_____________________

17. All antennas, equipment, and support structures shall be engineered and designed to prevent unauthorized climbing.

18. The wireless facility shall be erected, operated, and maintained in compliance with the general requirements set forth in the Standards and any specific requirements in the permit.

19. The antenna and electrical support equipment shall, at all times, be operated in a manner that conforms to the applicable health and safety standards, including those imposed by MMC Chapter 17.46 and this Resolution.

20. Wireless communications facilities and equipment must comply with the City’s noise ordinance in MMC 8.24, or any successor provisions, and prevent noise and sound from being plainly audible at a distance of fifty (50) feet from the facility or within ten (10) feet of any residence.

21. The Planning Director’s approval is required if a generator is to be placed onsite for temporary or permanent use.

22. All non-ground-mounted equipment associated with the application shall be located no lower than eight feet above grade or ground level on the monopole or support structure.

23. The City or its designee may enter onto the facility area to inspect the facility upon 48 hours prior notice to the permittee. The permittee shall cooperate with all inspections and may be present for any inspection of its facility by the City. The City reserves the right to enter or direct its designee to enter the facility and support, repair, disable, or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

The City shall make an effort to contact the permittee prior to disabling or removing any facility elements, but in any case, shall notify permittee within 24 hours of doing so.

24. Testing of any equipment shall take place on weekdays only, and only between the hours of 8:30 a.m. and 4:30 p.m., except that testing is prohibited on holidays that fall on a weekday. In addition, testing is prohibited on weekend days.

25. Permittee shall obtain and maintain throughout the term of the permit commercial general liability insurance with a limit of five million dollars ($5,000,000) per occurrence for bodily injury and property damage and six million dollars ($6,000,000) general aggregate including premises operations, contractual liability, Resolution No. 26-54 21-17

Page 15 of 27 ends

_____________________
personal injury, and products completed operations. The relevant policy(ies) shall name the City, its elected/appointed officials, commission members, officers, representatives, agents, and employees as additional insureds. A true and correct copy of the policy of insurance shall constitute proof of insurance required by this Subsection. Permittee shall use its best efforts to provide thirty (30) days’ prior notice to the City of to the cancellation or material modification of any applicable insurance policy. Failure to maintain insurance consistent with this Condition shall automatically void the permit, and the permittee shall immediately deenergize and remove the facility from operation. The policy shall not have a pollution or other exclusion which excludes injuries or damages from EMF/RF exposures.

26. Prior to issuance of a City permit or encroachment permit, the permittee shall file with the City, and shall maintain in good standing throughout the term of the approval, a performance bond or other surety or another form of security for the removal of the facility in the event that the use is abandoned or the permit expires, or is revoked, or is otherwise terminated. The security shall be in the amount equal to the cost of physically removing the facility and all related facilities and equipment on the site, based on the higher of two contractor’s quotes for removal that are provided by the permittee. The permittee shall reimburse the city for staff time associated with the processing and tracking of the bond, based on the hourly rate adopted by the City Council. Reimbursement shall be paid when the security is posted and during each administrative review.

27. Permittee shall not move, alter, temporarily relocate, change, or interfere with any existing structure, improvement, or property without the prior consent of the owner of that structure, improvement, or property. No structure, improvement, or property owned by the City shall be moved to accommodate a permitted activity or encroachment, unless the City determines that such movement will not adversely affect the City or any surrounding businesses or residents, and the Permittee pays all costs and expenses related to the relocation of the City's structure, improvement, or property. Prior to commencement of any work pursuant to any permit, the permittee shall provide the City with documentation establishing to the city's satisfaction that the permittee has the legal right to use or interfere with any other structure, improvement, or property to be affected by permittee's facilities.

Resolution No. 26-54 21-17

Page 16 of 27 ends

_____________________

28. No possessory interest is created by a Wireless Permit. However, to the extent that a possessory interest is deemed created by a governmental entity with taxation authority, permittee
acknowledges that City has given to permittee notice pursuant to California Revenue and Taxation Code Section 107.6 that the use or occupancy of any public property pursuant to a development or conditional use permit may create a possessory interest which may be subject to the payment of property taxes levied upon such interest. Permittee shall be solely liable for, and shall pay and discharge prior to delinquency, any and all possessory interact taxes or other taxes, fees, and assessments levied against permittee’s right to possession, occupancy, or use of any public property pursuant to any right of possession, occupancy, or use created by this development or conditional use permit.

29. If not already completed, permittee shall enter into the appropriate agreement with the City, as determined by the City, prior to constructing, attaching, or operating a facility on municipal infrastructure. This permit is not a substitute for such agreement.

30. If a facility is not operated for a continuous period of three (3) months, the Wireless Permit and any other permit or approval therefor shall be deemed abandoned and terminated automatically, unless before the end of the three (3) month period (i) the Director has determined that the facility has resumed operations, or (ii) the City has received an application to transfer the permit to another service provider. No later than ninety (90) days from the date the facility is determined to have ceased operation, or the permittee has notified the Director of its intent to vacate the site, the permittee shall remove all equipment and improvements associated with the use and shall restore the site to its original condition to the satisfaction of the Director. The permittee shall provide written verification of the removal of the facilities within thirty (30) days of the date the removal is completed. If the facility is not removed within thirty (30) days after the permit has been discontinued pursuant to this subsection, the site shall be deemed to be a nuisance, and the City may cause the facility to be removed at permittee’s expense or by calling any bond or other financial assurance to pay for removal. If there are two (2) or more users of a single facility or support structure, then this provision shall apply to the specific elements or parts thereof that were abandoned but will not be effective for the entirety thereof until all users cease use thereof.

31. In the event the City determines that it is necessary to take legal action to enforce any of these conditions, or to revoke a permit, and Resolution No. 26-54 21-17

Page 17 of 27 ends

_____________________
such legal action is taken, the permittee shall be required to pay any and all costs of such legal action, including reasonable attorney’s fees, incurred by the City, even if the matter is not prosecuted to a final judgment or is amicably resolved, unless the City otherwise agrees, in its complete discretion, to waive said fees or any part thereof.

32. Interference with city communications systems and other governmental emergency systems is prohibited. Further, no permits issued pursuant to this chapter of the City Code establish any guarantee or warranty that Licensee’s facility will be free from interference from city or third-party communication systems.

Construction

33. Installation hours shall be limited to Monday through Friday from 7:00 a.m. to 7:00 p.m. and Saturdays from 8:00 a.m. to 5:00 p.m. No installation activities shall be permitted on Sundays and Citydesignated holidays. The restricted work hours described in this condition do not apply to emergency maintenance necessary to protect health or property. The City of Malibu may issue a Stop Work Order if permittee violates this condition. Construction activities shall be conducted in compliance with, and abide by, all applicable safety codes and permit conditions.

34. All sites must be designed and build to the standards of ANSI/APCO Public Safety Grade Site Hardening Requirements, also referred to as “APCO ANSI 2.106.1-2019”.

Site Specific Conditions

35. In the event that the electric service provider does not currently offer an alternative metering option, the permittee shall remove the above-grade electric meter when such option becomes available.

Prior to removing the above-grade electric meter, the permittee shall apply for any encroachment and/or other ministerial permit(s) required to perform the removal. Upon removal, the permittee shall restore the affected area to its original condition that existed prior to installation of the equipment.

36. The permittee acknowledges that the City specifically includes conditions of approval related to (a) painting, coloring or finishing the equipment to match the monopole or support structure; (b) undergrounding all equipment to the extent possible; (c) installing equipment within shrouds, conduits and risers as concealment elements engineered and designed to integrate the wireless facility Resolution No. 26-54 21-17

Page 18 of 27 ends

_____________________
with the surrounding built and natural environment; and (d) specific structural, seismic, electrical, fire and operating/maintenance requirements. Any future modifications to the permittee’s wireless facility must maintain or improve all concealment elements and safety precautions.

37. Before the permittee submits any applications for construction, encroachment, excavation or other required permits in connection with this permit, the permittee must incorporate a true and correct copy of this permit, all conditions associated with this permit and any approved photo simulations into the project plans (collectively, the “Approved Plans”). The permittee must construct, install and operate the wireless facility in substantial compliance with the Approved Plans as determined by the Director or the Director’s designee. Any substantial or material alterations, modifications or other changes to the Approved Plans, whether requested by the permittee or required by other departments or public agencies with jurisdiction over the wireless facility, must be submitted in a written request subject to the Director’s prior review and approval, who may refer the request to the original approval authority if the Director finds that the requested alteration, modification or other change substantially deviates from the Approved Plans or implicates a significant or substantial land-use concern.

38. The permittee shall install and at all times maintain in good condition a “Network Operations Center Information” and “RF Caution” sign on the utility pole no less than three (3) feet below the antenna (measured from the top of the sign) and no less than nine (9) feet above the ground line (measured from the bottom of the sign). Signs required under this condition shall be installed so that a person can clearly see the sign as he or she approaches within three (3) feet of the antenna structure. If any person on or within the property is or may be exposed to emissions that exceed applicable FCC uncontrolled/general population limits at any time the sign shall expressly so state, and provide instructions on how persons can avoid any such exposure. The sign shall also include the name(s) of the facility owner(s), equipment owner(s) and operator(s)/carrier(s) of the antenna(s), property owner name, as well as emergency phone number(s) for all such parties. The sign shall not be lighted, unless applicable law, rule or regulation requires lighting. No signs or advertising devices other than required certification, warning, required seals or signage, other signage required by law, this Chapter, any City or applicable state code or the Los Angeles County Fire Department Chief or his or her designee shall be permitted. The sign shall be no larger than two (2) square feet.

Resolution No. 26-54 21-17

Page 19 of 27 ends

_____________________

39. The permittee shall ensure that all signage complies with FCC Office of Engineering and Technology Bulletin 65, CPUC General Order 95 or American National Standards Institute C95.2 for color, symbol, and content conventions. All such signage shall at all times provide a working local or toll-free telephone number to its network operations center, and such telephone number shall be able to reach a live person who can exert transmitter power-down control over this site as required by the FCC.

40. In the event that the FCC changes any of radio frequency signage requirements that are applicable to the project site approved herein or ANSI Z535.1, ANSI Z535.2, and ANSI C95.2 standards that are applicable to the project site approved herein are changed, the permittee, within 30 days of each such change, at its own cost and expense, shall replace the signage at the project site to comply with the current standards.

41. The permittee shall maintain the paint, color and finish of the facility in good condition at all times.

42. All improvements, including foundations, and appurtenant ground wires, shall be removed from the property and the site restored to its original pre-installation conditions within 90 days of cessation of operation or abandonment of the facility.

43. Build-Out Conditions.
a. Permittee shall not commence any excavation, construction, installation or other work on the project site until and unless it demonstrates to the City Public Works Department that the project complies with these Conditions along with all
applicable laws, regulations, codes and other rules related to public health and safety, including without limitation all applicable provisions in California Public Utilities
Commission General Order 95 and MMC Chapters 8.12,

8.24 and 15.08.
b. To the extent that a pole owner or any provision in the MMC or this resolution require greater or more restrictive
standards than California Public Utilities Commission
General Order 95, if applicable, those standards shall
control.

44. Permittee shall at all times maintain compliance with all applicable federal, State and local laws, regulations, ordinances and other rules, including Americans with Disabilities Act (ADA) requirements.

Resolution No. 26-54 21-17

Page 20 of 27 ends

_____________________

45. The permittee shall cooperate with all inspections. The City and its designees reserve the right to support, repair, disable or remove any elements of the facility in emergencies or when the facility threatens imminent harm to persons or property.

46. Permittee shall at all times maintain accurate contact information for all parties responsible for the facility, which shall include a phone number, street mailing address and email address for at least one natural person. All such contact information for responsible parties shall be provided to the Planning Department at the time of permit issuance and within one business day of permittee’s receipt of City staff’s written request.

47. Permittee shall undertake all reasonable efforts to avoid undue adverse impacts to adjacent properties and/or uses that may arise from the construction, operation, maintenance, modification and removal of the facility.

48. The site and the facility must be maintained in a neat and clean manner and in accordance with all approved plans and conditions of approval.

49. Permittee shall promptly remove any graffiti on the wireless facility at permittee’s sole expense within 48 hours after notice.

Prior to Operation

50. The applicant shall request a final Planning Department inspection and final building inspection by the City of Malibu Environmental Sustainability Department immediately after the wireless facility has been installed and prior to the commencement of services.

51. Within thirty (30) calendar days following the installation of any wireless communications facilities, the applicant shall provide to the Planning Department with a field report prepared by a qualified engineer verifying that the unit has been inspected, tested, and is operating in compliance with FCC standards. Specifically, the onsite post-installation radiofrequency (RF) emissions testing must demonstrate actual compliance with the FCC OET Bulletin 65 RF emissions safety guidelines for general population/uncontrolled RF exposure in all sectors. For this testing, the transmitter shall be operating at maximum operating power, and the testing shall occur outwards to a distance where the RF emissions no longer exceed the uncontrolled/general population limit. Such report and
documentation shall include the make and model (or other identifying information) of the unit tested, the date and time of the Resolution No. 26-54 21-17

Page 21 of 27 ends

_____________________
inspection, a certification that the unit is properly installed and working within applicable FCC limits, and a specific notation of the distance from the transmitter at which the emissions are equal to or less than the uncontrolled/general population limit.

52. The operation of the approved facility shall commence no later than one (1) month after the City completes its post-installation inspections of the facility, any issues with the facility are resolved, and the City receives the RF testing report required in the condition of approval above, or the development or conditional use permit will expire without further action by the City.

Fixed Conditions

53. Violation of any of the conditions of this approval shall be cause for revocation and termination of all rights thereunder.

Eligible Facilities Requests
All permits for an eligible facilities requests under MMC Chapter 17.46 shall be subject to the following conditions and all of the other conditions of approval placed on a Wireless Permit, unless modified by the approving authority:

54. Any permit granted in response to an application qualifying as an eligible facilities request shall be subject to the terms and conditions of the underlying permit.

55. The City’s grant or grant by operation of law of an eligible facilities request permit constitutes a federally-mandated modification to the underlying permit or approval for the subject tower or base station.

Notwithstanding any permit duration established in another permit condition, the City’s grant or grant by operation of law of a eligible facilities request permit will not extend the permit term for the underlying permit or any other underlying regulatory approval, and its term shall be coterminous with the underlying permit or other regulatory approval for the subject tower or base station.

56. The City’s grant or grant by operation of law of an eligible facilities request does not waive, and shall not be construed to waive, any standing by the City to challenge Section 6409(a) of the Spectrum Act, any FCC rules that interpret Section 6409(a) of the Spectrum Act, or any modification to Section 6409(a) of the Spectrum Act.

Resolution No. 26-54 21-17

Page 22 of 27 ends

_____________________
Small Cell Facilities
In addition to the other conditions of approval placed on a Wireless Permit, all permits for a small cell facility under MMC Chapter 17.46 shall be subject to the following additional condition, unless modified by the approving authority:

57. The City’s grant of a permit for a small cell facility request does not waive, and shall not be construed to waive, any standing by the city to challenge any FCC orders or rules related to small cell facilities, or any modification to those FCC orders or rules.

Basic Application Requirements for Permits Under MMC Chapter 17.46.

A. Generally. In addition to providing all required fees, all wireless telecommunication facility carriers or providers shall provide the information required by a separate application form published, and updated from time to time, by the City. If no such form is available, then the applicant must submit all documents, information, and any other materials necessary to allow the City to make required findings and ensure that the proposed facility will comply with applicable laws and not endanger the public health, safety, or welfare. Such information may include:

1. Contact information for:
a. Applicant and their representatives
b. Owner of proposed wireless communications facility
c. If different from facility owner, the identity of the person or entity responsible for operating the proposed wireless
facility
d. The property owner or owner of the structure on which the proposed wireless facility would be installed
e. Names, addresses, telephone numbers, and email addresses of anyone acting on behalf of the applicant with regard to the application;
f. The name, address and phone number of all persons that prepared or assisted in preparing the application and any required reports;
g. The postal address, parcel number, or utility pole identifier of the property;
h. The location of the schools, playgrounds and parks within 500 feet of the project site;
i. Local contact person for emergencies
j. Assessor’s Parcel Number

2. Purpose of new wireless communications facility or amendment

3. Type of Application (Select all that apply)
a. Eligible Facilities Request
b. Small Cell – Collocation
Resolution No. 26-54 21-17

Page 23 of 27 ends

_____________________
c. Small Cell – New Structure
d. Collocation (Non-Small Cell)
e. All Other Wireless Communications Facilities
f. Permit Renewal
g. Waiver

4. Letter of authorization signed by the property owner authorizing the applicant to submit and process the application, including executed copies of any leases, letters of agency, or proof of ownership, of private property involved in the project.

5. Authorizations, and Licenses

6. Provide previous approvals, if applicable, and Certificate of Completion. Site inspection fees may apply if a final inspection was never requested

7. Identify all other required permits and approvals for the subject facility.

8. Electrical and Structural Safety Information. The following engineering documents prepared under the responsible charge of and sealed by a California licensed Professional Engineer must be included in the application:
a. A short circuit and coordination study (“SCCS”) calculated pursuant to the IEEE 551-2006: Recommended Practice for Calculating AC Short-Circuit Currents in Industrial and Commercial Power Systems or the latest version of that
standard. The study must demonstrate the protection devices will ensure the equipment enclosure will not be breached.

The SCCS must include analysis of Voltage Transient
Surges due to contact of conductors of different voltages; b. A one-line diagram of the electrical system;
c. Voltage Drop & Load Flow Study;
d. Load Calculation;
e. Panel Directories;
f. A plot plan showing the location of the mounting structure including address, or structure designation, or GPS location on the front sheet;
g. A plot plan showing the location of the service disconnecting means; and
h. An elevation drawing of the equipment and the service disconnecting means.

9. Structural Safety Information. The structural/civil engineering documents prepared under the responsible charge of and sealed by a California licensed professional civil engineer.
a. Photo simulations, from at least three different angles, showing the pole and streetscape before and after
installation. In some cases, more than three different angles may be required;
Resolution No. 26-54 21-17

Page 24 of 27 ends

_____________________
b. The azimuth, size and center-line height location of all proposed and existing antenna(s) on the supporting
structure;
c. The number, type and model of the antenna(s) that will be used with a copy of the specification sheet;
d. The make, model, type and manufacturer of any tower
involved and a design plan stating the tower’s capacity to accommodate multiple users;
e. Site and Construction Plans. Complete and accurate plans, drawn to scale, signed, and sealed by a California-licensed engineer, land surveyor, and/or architect, which include the following items.
(1) A site plan and elevation drawings for the facility as existing and as proposed with all height and width
measurements explicitly stated.
(2) A site plan describing the proposed tower and
antenna(s) and all related fixtures, structures,
appurtenances and apparatus, including height above
pre-existing grade, materials, color and lighting;
(3) A depiction, with height and width measurements
explicitly stated, of all existing and proposed
transmission equipment.
(4) A depiction of all existing and proposed utility runs and points of contact.
(5) A depiction of the leased or licensed area of the site with all rights-of-way and easements for access and
utilities labeled in plan view.
f. Detailed map with locations of the poles or other property on which equipment is to be located, including specific pole identification number, if applicable, and the areas it will service;
g. Description as to why the desired location is superior to other similar locations, from a community perspective, including, but not limited to:
(1) Proximity to residential buildings and descriptions of efforts to prevent any blocking of views of
impressive scenes; and
(2) Written documentation demonstrating a good faith
effort to locate the proposed facility in the least
intrusive location in accordance with the location
requirements of this Resolution.
h. A description in writing and a visual rendering
demonstrating effective screening of all ground-mounted or roof-mounted equipment of the facility from view.

Resolution No. 26-54 21-17

Page 25 of 27 ends

_____________________
i. Color-coded carrier-generated RF Coverage (propagation) maps, at a scale no smaller than 1 inch (1”) to a quarter (1/4) mile with all appropriate legends, showing the coverage for the highest and lowest frequencies to be used by the facility.

Frequencies are to be stated numerically, not qualitatively.

Provide a represented value in dB of each colors it
specifically represents.
j. If the project involves, modifies or will use an existing facility or structure, a description of the type of structure (e.g., guyed, self-supporting lattice or monopole), and a report on the physical condition of the facility certified by a professional engineer licensed in the state of California. k. If the application is for a new tower, clear and convincing technical evidence by a carrier or wireless service provider justifying the total height of the proposed facility and the need for such to the exclusion of all reasonable alternatives.

Evidence in the form of propagation studies must include all modeling data and assumptions used to produce the studies at the requested height and should take into consideration the ability to collocate other carriers in the future.
l. A siting analysis which identifies other feasible locations within or outside the City which could serve the area
intended to be served by the facility, unless the applicant provides compelling technical reasons for providing fewer than the minimum.
m. An affirmation, under penalty of perjury, that the proposed installation will be FCC compliant, in that it will not cause members of the general public to be exposed to RF levels that exceed the emissions levels deemed safe by the FCC. A copy of the fully completed FCC form “A Local
Government Official’s Guide to Transmitting Antenna RF
Emission Safety: Rules, Procedures, and Practical Guidance:

Appendix A” titled “Optional Checklist for Determination of Whether a Facility is Categorically Excluded” for each frequency band of RF emissions to be transmitted from the proposed facility upon the approval of the application. All planned radio frequency emissions on all frequency bands must be shown on the Appendix A form(s) attached to the application. All planned radio frequency emissions are to be entered on each Appendix A form only in wattage units of “effective radiated power.”
n. A statement detailing the frequency, modulation and class of service of radio or other transmitting equipment;
o. A copy of the FCC license applicable for the intended use of the proposed facilities;
Resolution No. 26-54 21-17

Page 26 of 27 ends

_____________________
p. A HazMat Business Plan for all new generators, and any storage and/or use of hazardous materials during the project, to include:
i. A list of toxic substances that may develop during
arcing or fire that may impede fire suppression
efforts;
ii. A list of hazards that may develop during arcing or fire that may impede fire suppression efforts;
q. A demolition plan, if applicable.
r. A written statement of the applicant’s willingness to allow other carriers to co-locate on the proposed personal wireless service facility where technically and economically feasible and aesthetically desirable, subject to the qualification that colocation should not occur when public exposures from the resulting higher cumulative sources would exceed FCC
limits.
s. Such other information as the Director shall establish. t. A statement signed by a person with legal authority to bind the applicant attesting under penalty of perjury to the accuracy of the information provided in the application. If attester not an authorized employee of the applicant, then the attester must demonstrate that it is an authorized agent of the applicant, with lawful Power of Attorney from the applicant.

SECTION 10. Environmental Review.

This Resolution is not a project within the meaning of Section 15378 of the State of California Environmental Quality Act (CEQA) Guidelines, because it has no potential for resulting in physical change in the environment, directly or indirectly. The Resolution does not authorize any specific development or installation on any specific piece of property within the City’s boundaries.

Moreover, when and if an application for installation is submitted, the City will at that time conduct preliminary review of the application in accordance with CEQA. Alternatively, even if the Resolution is a “project” within the meaning of State CEQA Guidelines section 15378, the Resolution is exempt from CEQA on multiple grounds. First, the Resolution is exempt CEQA because the City Council’s adoption of the Resolution is covered by the general rule that CEQA applies only to projects which have the potential for causing a significant effect on the environment. (State CEQA Guidelines, § 15061(b)(3)). That is, approval of the Resolution will not result in the actual installation of any facilities in the City. In order to install a facility in accordance with this Resolution, the wireless provider would have to submit an application for installation of the wireless facility. At that time, the City will have specific and definite information regarding the facility to review in accordance with CEQA. And, in fact, the City will conduct preliminary review under CEQA at that time. Second, the Resolution is categorically exempt under CEQA Guidelines §§ 15307 and 15308 as an action taken by a regulatory agency, as authorized by local ordinance (MMC Chapter 17.46), to assure the protection of natural resources and the environment. The Resolution strengthens the City’s location and design Resolution No. 26-54 21-17

Page 27 of 27 ends

_____________________
standards for new wireless facilities. It does not weaken any existing standard and does not authorize any construction or development. The City’s wireless permitting process involves procedures for protection of the environment, including discretionary review of each application and coastal development permit review under the certified Local Coastal Program where applicable. None of the exceptions in CEQA Guidelines § 15300.2 applies.

Moreover, in the event that the Resolution is interpreted so as to permit installation of wireless communications facilities on a particular site, the installation would be exempt from CEQA review in accordance with either State CEQA Guidelines section 15302 (replacement or reconstruction), State CEQA Guidelines section 15303 (new construction or conversion of small structures), and/or State CEQA Guidelines section 15304 (minor alterations to land).

SECTION 11. This Resolution shall become effective immediately upon its passage and adoption.

SECTION 12. The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

PASSED, APPROVED, and ADOPTED this 12 13th day of July 2026 April 2021. ______________________________
BRUCE SILVERSTEIN, Mayor
ATTEST:
__________________________________
KELSEY PETTIJOHN, City Clerk
(seal)
APPROVED AS TO FORM:
__________________________________
TREVOR RUSIN, Interim City Attorney

ATTACHMENT
5

Page 1 of 4 ends

Agenda Item # 7.A.

Council Agenda Report
To: Mayor Silverstein and the Honorable Members of the City Council Prepared by: Joseph D. Irvin, City Manager
Date prepared: May 22, 2026 Meeting date: July 13, 2026 Subject: Letter of Support – Pier to Pier (Continued from June 8, 2026) RECOMMENDED ACTION: It is recommended that the City Council: 1) Consider submittal of a Letter of Support for Pier to Pier LLC’s California State Parks concession application at Malibu Pier; or 2) Provide additional direction to city staff.

FISCAL IMPACT: There is no fiscal impact associated with the recommended action.

STRATEGIC PLAN IMPLEMENTATION:

Goal 2: Drive Economic Recovery and Restore Lost Revenue.

Objective 2.1: Recover lost sales, hotel, and transaction tax revenue to pre-disaster levels to restore the city’s ability to deliver high quality services.

Strategy: Leverage public-private partnerships.

Economic Recovery Outreach Campaign: Utilize the city’s brand to attract visitors, investment, and residents through strategic outreach.

Goal 4: Improve Public Safety
Objective 4.2: Increase Wildfire Resiliency
Emergency Evacuation: Increase alert warning, and evacuation capabilities.

Goal 7: Explore New Opportunities for Educational, Cultural, and Recreational Establishments.

Objective 7.1: Deliver high quality public services and spaces for education, recreation, and culture.

DISCUSSION:

Pier to Pier LLC is a U.S. Coast Guard-approved, privately funded, coastal passenger ferry service operating in partnership with Harbor Breeze Cruises, a California-licensed vessel operator and led by Malibu residents including a Retired Rear Admiral of US Coast Guard and former Heal the Bay Board Members. Pier to Pier is proposing to launch a scheduled water transportation service, initially for events, then slowly adding daily routes, City Council Meeting
07-13-26
Item

7.A.

Page 2 of 4 ends

Agenda Item # 7.A.
connecting Malibu to already approved stops at Santa Monica, Marina del Rey, Redondo Harbor, San Pedro, and Long Beach, with fares of approximately $50 plus tax round trip on (2) 100 ft, 149 passenger, CARB compliant catamarans once a California State Parks Department of Parks and Recreation (DPR) agreement is in place.

Beyond transportation, this service has the potential to help advance five City of Malibu priorities:
(1) it provides economic recovery to local businesses without adding cars to PCH; (2) it creates a critical coastal evacuation corridor and emergency water-based escape route for residents during wildfire or PCH closure events — pending the State Parks agreement, CalOES can authorize the deployment of all available vessels in any declared emergency;
(3) it offers a practical transit alternative to visit Malibu, particularly vital during ongoing and planned PCH construction;
(4) allows Malibu to participate in LA28, as Pier to Pier can operate as official athlete transportation for Team USA from Pepperdine to their events, and (5) it creates a new funding pathway for Malibu Pier itself, as the concession structure positions Pier to Pier to contribute to pier maintenance, repair, and infrastructure improvements.

The Council’s Letter of Support carries meaningful weight in the State Parks concession review process and costs the City no direct funding commitment while potentially securing Malibu revenue through an embarkment tax and a permanent, Coast Guard-approved maritime safety and transportation asset at its own pier, while not invoking SB79.

Pier to Pier Funding
Approximately $60M in private funding has been pledged. Pier to Pier’s funding goal is $120M of private funding (for infrastructure upgrades and operations). This would fund approximately the first 18 months of service (Summer 2026 through December 2027).

In terms of public support, Sen. Ben Allen submitted a formal CA state budget line item in support for passenger ferry funding of $2 million annually. Pier to Pier, LLC is actively seeking and applying for federal and state transportation grants.

Page 3 of 4 ends

Agenda Item # 7.A.

Pier to Pier, LLC would eventually move toward a private-public partnership. Their general exit strategy is for the state to take over the Southern California regional passenger ferry system within an estimated five-year timeframe.

Pier to Pier Route
The initial “proposed” routes and 10 landings (or ferry and water taxi stops) are:
(1) Malibu,
(2) Santa Monica,
(3) Marina Del Rey,
(4) Redondo Beach,
(5) San Pedro,
(6) Long Beach – Belmont,
(7) Long Beach – Rainbow Harbor,
(8) Long Beach – Almeida,
(9) Long Beach – Queen Mary, and
(10) Long Beach – Amphitheater.

Public Transit and Parking
Pier to Pier, LLC is coordinating closely with LA Metro and the 134-bus line will be used.

They have private parking partners and have identified approximately 75-to-100 parking spaces for initial use.

Harbor Breeze Cruises
Harbor Breeze is identified as the global vessel operator partner. They have CA-licensed boat operators or captains. Their boats are CARB-compliant, carbon-neutral vessels.

Harbor Breeze has a 30-year maritime safety record, recently validated by USCG. Pier to Pier, LLC expects between two-and-four boats once daily operations are underway with approximately three stops-per-landing daily.

The safety of the service is a primary focus of Pier to Pier, LLC’s work. Moreover, the emergency utility of the boats is a goal, specifically, for evacuation service.

Pier to Pier “Proposed” Timeline
JUNE 2026: Inaugural ride scheduled for June 5 during U.S. Conference of Mayors in Long Beach.

JUNE/JULY 2026: Soft events launch scheduled for June and July during FIFA World Cup.

Page 4 of 4 ends

Agenda Item # 7.A.

FALL 2026: Continue weekend or event schedule, can extend based on Santa Monica Pier timing.

WINTER 2026-27: Coordination with City of Santa Monica in preparation for 10-day hosting pre-Super Bowl 2027 and then Pier to Pier Passengers for Ferry Service, thereafter.

For additional information pertaining to the Pier to Pier project, visit https://piertopier.org/.

ATTACHMENTS: Proposed Letter of Support
City of Malibu
23825 Stuart Ranch Road · Malibu, California · 90265-4861 Phone (310) 456-2489 · Fax (310) 456-3356 · www.malibucity.org \\MLB-ADMSCSRV\common\City Council Agendas\2026 Agendas\260713\_Word Versions\July 13_Item 7A_Pier to Pier\Pier to Pier Letter of Support.docx Recycled Paper
June 8, 2026
California Department of Parks and Recreation
Concession Program
Attn: Concessions Program Staff
715 P Street
Sacramento, CA 95814
Re: Letter of Support for Pier to Pier LLC Concessions Application at Malibu Pier Dear Review Committee,
On behalf of the City of Malibu, this letter provides support for Pier to Pier LLC’s proposed concession application for passenger ferry operations at Malibu Pier. The proposed coastal passenger ferry service presents an opportunity to advance several priorities important to our community.

The service has the potential to support Malibu’s ongoing economic recovery by bringing visitors and customers to local businesses without increasing vehicle traffic on Pacific Coast Highway (PCH). It offers a promising transportation alternative during current and planned corridor improvements and could help reduce congestion along one of the region’s most critical transportation corridors. Importantly, the project introduces a maritime component that could strengthen emergency preparedness and evacuation options during wildfire incidents, road closures, and other emergencies affecting PCH access. In addition, the proposal could create longterm support opportunities for maintenance and investment at Malibu Pier itself.

With approximately $60 million in private funding already pledged and State Senator Ben Allen’s formal budget support, Pier to Pier LLC has demonstrated the seriousness and resources needed to deliver. We respectfully urge the Department to consider this application and welcome the opportunity to discuss our support further.

Sincerely,
Bruce Silverstein
Mayor, City of Malibu

Page 1 of 1 ends

Agenda Item # 8.A.

Council Agenda Report
To: Mayor Silverstein and the Honorable Members of the City Council Prepared by: Christina Muñoz, Deputy City Clerk
Reviewed by: Kelsey Pettijohn, City Clerk
Approved by: Joseph D. Irvin, City Manager
Date prepared: June 24, 2026 Meeting date: July 13, 2026 Subject: Appointment of a City Council Representative to the Independent Cities Association (ICA) Board of Directors
RECOMMENDED ACTION: Appoint one City Councilmember to serve as the City of Malibu's representative on the Independent Cities Association (ICA) Board of Directors.

FISCAL IMPACT: There is no fiscal impact associated with the recommended action.

STRATEGIC PLAN IMPLEMENTATION: N/A.

DISCUSSION: The City of Malibu has recently joined the Independent Cities Association (ICA), a nonprofit 501(c)(3) organization representing nearly 40 independent cities throughout Southern California. ICA's mission is to empower independent elected officials through education, policy insight, and leadership development, while fostering collaboration on regional issues such as public safety, infrastructure, economic development, education, and intergovernmental relations.

As a member City, Malibu may appoint a City Councilmember to serve on the ICA Board of Directors; however, the appointment is optional. The Board provides leadership for the organization and represents the interests of its member cities. ICA also hosts two educational seminars annually and conducts in-person Board meetings several times throughout the year.

Staff recommends that the City Council appoint one City Councilmember to serve as the City's representative on the ICA Board of Directors.