ATTACHMENT 3
Aviation Boulevard Missing Sidewalk Project
Budget and Expenditures Summary
BUDGET
Aviation Boulevard Missing Sidewalk Project (CIP Measure R ST20102)
$700,000.00
TOTAL BUDGET $700,000.00
EXPENDITURES
Design Services Agreement (Glenn A. Rick Engineering and Development Company, DBA Rick Engineering Company)
$179,149.00
TOTAL EXPENDITURES $179,149.00
BALANCE $520,851.00